15 August 2007 Bill Meyer Modularization Introduction William (Bill) Meyer - Director Project Execution Development Foster Wheeler USA Corporation Contact: 2020 Dairy Ashford Road, Houston, TX 77077 Ph. 281 597 3000 Direct 713 255 6089

Modularizationpresentationfor Hbr

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Modularization

Introduction

William (Bill) Meyer - Director Project Execution DevelopmentFoster Wheeler USA Corporation

Contact: 2020 Dairy Ashford Road, Houston, TX 77077Ph. 281 597 3000Direct 713 255 6089

Page 2: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

1. Modularization drivers

2. Module types

3. Installation methods

4. Engineering and Procurement impacts

5. Logistics

6. Module Fabrication

7. Critical success factors

Modularization

Turner Industries

Page 3: Modularizationpresentationfor Hbr

IntroductionTo

Foster Wheeler

Page 4: Modularizationpresentationfor Hbr

International Engineering Firm (EPC)International Engineering Firm (EPC)with over 100 Years of with over 100 Years of

Dedicated Services to the Dedicated Services to the Process and Energy IndustriesProcess and Energy Industries

Foster Wheeler

Page 5: Modularizationpresentationfor Hbr

A global business: over 10,500 highly skilled people

Reading

Milan

Houston

Singapore

CLINTON, NJ

Helsinki

Corporate CenterOperating Unit HQs and/or Main Engineering CentersRegional Engineering CentersSales/Local Service OfficesManufacturing Centers

A global network of high-quality resources, enabling us to deliver local service and local content, and to access local labor markets

Shanghai

Chennai

Foster Wheeler Operations

Page 6: Modularizationpresentationfor Hbr

FOSTER WHEELER LIMITEDFOSTER WHEELER LIMITED

FW Energy InternationalFW Energy InternationalFW Energy CorpFW Energy Corp.

ENGINEERINGAND

CONSTRUCTION

ENGINEERINGAND

CONSTRUCTION

FW USA Corp.FW USA Corp.FW Energy Limited FW Energy Limited -- U.K.U.K.FW Continental EuropeFW Continental EuropeFW Asia PacificFW Asia Pacific

ENERGYEQUIPMENTENERGY

EQUIPMENT

2006 Revenue: $2.8 Billion Backlog: $5.4 Billion2006 Revenue: $2.8 Billion Backlog: $5.4 Billion2006 Revenue: $2.8 Billion Backlog: $5.4 Billion

Foster Wheeler Corporate Overview

Page 7: Modularizationpresentationfor Hbr

RefiningPetrochemicalsChemicalsHydrogen / GTL / GasificationOil and Gas PowerPharmaceuticals and Fine ChemicalsBuild Own and Operate

Fired HeatersCoke Drum Unheading SystemsSteam GeneratorsBoilersCondensersSCR’s

ENGINEERING ENGINEERING & CONSTRUCTION & CONSTRUCTION SERVICESSERVICES(EPC or (EPC or EPCmEPCm))

EQUIPMENT EQUIPMENT SUPPLYSUPPLY

Foster Wheeler Services & Products

Page 8: Modularizationpresentationfor Hbr

Leader in Refinery Process Engineering

200+ Hydroprocessing Units200+ Crude Units200+ Vacuum Units80+ Catalytic Reforming Units100+ FCC Units80+ Cokers40+ Alkylation Units50+ Deasphalters20+ Catalytic Polymer Units30+ Aromatics units20+ Lube refineries50+ Hydrogen Plants80+ Sulfur Plants

Reactor Regenerator Assembly with UOP VSS Technology at Premcor FCCU, Memphis, TN

Page 9: Modularizationpresentationfor Hbr

Sriracha, Thailand

Singapore

Houston, Texas

Milan, Italy

Madrid, Spain

Perryville, New Jersey

Paris, France

Reading, U.K.

Foster Wheeler E&C Centers

North America 1,300United Kingdom 3,200Italy 1,200France 500Spain 650Singapore 400Thailand 600China 900Other worldwide 1,750+

Total 10,500+

Page 10: Modularizationpresentationfor Hbr

FW Houston presence since 1940sSince 1994, U.S. EPC Center for Oil & Gas, Refining, and Petrochemical ProjectsOffice space in 3 buildingsCapacity for over 1200 Engineering and Design StaffFully Integrated Design Systems (CAD) and Communications Technology

Foster Wheeler Houston Operations

Page 11: Modularizationpresentationfor Hbr

End market diversity of backlog

December 29, 2006Total: $5.4 billion

Backlog includes flow-through costs

29.0%

17.2%

32.0%

16.6%

3.2%2.0%

Oil & Gas

Refining

Chemicals

Power Equip. & Services

Pharmaceutical

Power Plant Ops, Other &Eliminations

Page 12: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

1. Modularization drivers

2. Module types

3. Installation methods

4. Engineering and Procurement impacts

Modularization

Page 13: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Modularization execution benefits:

1. Cost reductions 2. Schedule reductions3. Risk reductions

Modularization

Page 14: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Cost Downside

Increased cost of steelIncreased cost of shippingPotentially - increased cost of transport and installation

Modularization

Page 15: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Cost Downside

Increased cost of steelIncreased cost of shippingPotentially - increased cost of transport and installationIncreased cost of engineering

Modularization

Page 16: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Cost Upside

Move labor cost offsite to cheaper labor supplyReduce indirect costs (camp, construction supervision, consumables etc at the site rates)Improved productivity (weather, flexible workforce, site accessability etc)Reduced schedule - reduces construction indirects[Positive impact to NPV if revenue stream begins earlier]

Modularization

Page 17: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Cost BenefitsEconomic Productivity Factor

On-site Off-siteLabour Productivity 1.70 1.2

Composite Manhour cost $105.00 $55.00Relative manhour cost c/w Gulf Coast $178.50 $66.00

Economic productivity ratio 2.70 : 1

Modularization

Page 18: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Cost BenefitsEconomic Productivity Factor using Far East Yards

On-site Off-siteLabour Productivity 1.70 3.5

Composite Manhour cost $105.00 $12.10Relative manhour cost c/w Gulf Coast $178.50 $42.35

Economic productivity ratio 4.21 : 1

Modularization

Page 19: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

MODULE vs STICK COST DIFFERENTIALS

Modular versus Stick built costs

$0.0

$10.0

$20.0

$30.0

$40.0

$50.0$60.0

$70.0

$80.0

$90.0

$100.0

Modular Cost Stick built Cost

Installation cost ΔShipping cost ΔConst. Mngmt cost ΔFoundation cost ΔSteel cost ΔEngineering cost ΔCamp cost Δlabor cost

Savings

Milli

o ns

$

Modularization

Existing Project Data

(Note – All projects have different cost drivers )

Page 20: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Modular versus Stick built costs

$0.0

$20.0

$40.0

$60.0

$80.0

$100.0

$120.0

$140.0

Modular Cost Stick built Cost

Installation cost Δ

Shipping cost Δ

Steel cost Δ

Engineering cost Δ

Camp cost Δ

Labour cost

Modular versus Stick built costs

Modular Cost Stick built Cost

Installation cost Δ

Shipping cost Δ

Steel cost Δ

Engineering cost Δ

Camp cost Δ

Labour cost

Modular versus Stick built costs

Modular Cost Stick built Cost

Installation cost Δ

Shipping cost Δ

Steel cost Δ

Engineering cost Δ

Camp cost Δ

Labour cost

COST DRIVEN MODULAR PROJECT

SCHEDULE DRIVEN MODULAR PROJECT

COST DRIVEN STICK BUILT PROJECT

Modularization

Page 21: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Schedule benefits

Schedule benefits

Modularization

Page 22: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Modular

Stick Built

Schedule Comparison – Modular vs Stick Built

0

10

20

30

40

50

60

70

80

90

100

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

Duration - Months

Prog

ress

%

Order Placement Engineering ConstructionOrder Placement Engineering Construction

Return

Modularization

Page 23: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

1. Modularization drivers

2. Module types

3. Installation methods

4. Engineering and Procurement impacts

Modularization

Page 24: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module Types

1. Pre – Assembled Units (PAU’s)Multi disciplined modules including:- tagged and non tagged items, steel, piping, electrical,

instrumentation, fireproofing, insulation

Page 25: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module Types

1. Pre – Assembled Units (PAU’s)

Page 26: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module Types

1. Pre – Assembled Units (PAU’s)

Page 27: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module Types

1. Pre – Assembled Units (PAU’s)

Page 28: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module Types

2. Pre – Assembled Racks (PAR’s)Piping modules including:- steel, piping, electrical cable tray, fireproofing, insulation

Site built steel or concrete

columns

Page 29: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module Types

2. Pre – Assembled Racks (PAR’s)

Page 30: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module Types

2. Pre – Assembled Racks (PAR’s)

Page 31: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

BHPBilliton – Module Types

3. Vendor Assembled Units (VAU’s)PAU’s assembled by a vendor

Page 32: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

BHPBilliton – Module Types

3. Vendor Assembled Units (VAU’s)

Page 33: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

4. Vendor Package Units (VPU’s)Complete packages purchased from a vendor

Module Types

Page 34: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

5. Remote Instrument Buildings (RIB’s) Sub-stations etc

Module Types

Page 35: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

5. Remote Instrument Buildings (RIB’s) Sub-stations etc

Module Types

Page 36: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

1. Modularization drivers

2. Module types

3. Installation methods

4. Engineering and Procurement impacts

Modularization

Page 37: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Installation Methods

Crane Installation

Page 38: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Installation Methods

Strand Jack Installation

Page 39: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Installation Methods

Transporter Installation

Page 40: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Installation Methods

Transporter Installation

Page 41: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Installation Methods

Transporter Installation

Page 42: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Installation Methods

Jack-down Installation

Page 43: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

1. Modularization drivers

2. Module types

3. Installation methods

4. Engineering and Procurement impacts

Modularization

Page 44: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Planning is Critical for Modular Projects

Page 45: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Differences can includeLocation of pumps

PAR 02/03

PAR 04/05

PAU 01

PAU 02

PAU 03 PAU 05

VAU 02

etail above

Modular

Stick built

E & P Impacts

Page 46: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Differences can includePipe track to pipe rack

E & P Impacts

Page 47: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Differences can includePipe track to pipe rack

Easy Install Easy Ship

E & P Impacts

Page 48: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Differences can includePipe track to pipe rack

Additional clearance can be provided

where required

E & P Impacts

Page 49: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Piping design file layoutLink files for pipe stressingSplit files for quantity takeoff and procurement

Page 50: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Site based Loads, Clearances and Critical Dimensions

Crane loadsModule clearancesCrane clearancesFoundations toleave low etc

Page 51: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Installation Methods

Transporter Installation

Page 52: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

Fabrication yard supports

Page 53: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

Transporting in theModule yard

Page 54: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Module yards

Page 55: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

Sea acceleration forcesduring shipment

Page 56: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

Sea acceleration forcesduring shipment

Page 57: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Type of ship – RO-RO, LO-LO, H/L

E & P Impacts

Page 58: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

Transporting on site

Page 59: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

1. Pre – Assembled Units (PAU’s)

E & P Impacts

Page 60: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Logistics and therefore loads imposed is project specific

E & P Impacts

Page 61: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

Installing on site

Page 62: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

In-situ on foundations

Page 63: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Procurement ComplexityNumber of delivery locations impact ordering and material tracking

EquipmentDeliveries

Material Logistics for theStick-Built Project

Install

Dock

Truck

Page 64: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Procurement Complexity

Truck

Materialyard

Dock

Transport

Install

Material Logistics for themodularized Project

Truck

Truck

Install

Module Fabrication Yard

EquipmentDeliveries

Port

ModuleDeliveries

Loadout

to ship

Bulk Materials and minor equipment

Modules andmajor equipment

Page 65: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

– Potential to ship stick built materials in “dead space” on HL ships

E & P Impacts

Page 66: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Page 67: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

E & P Impacts

Loads applied to Modules

Page 68: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

1. Modularization drivers

2. Module types

3. Installation methods

4. Engineering and Procurement impacts

Modularization

Page 69: Modularizationpresentationfor Hbr

15 August 2007Bill Meyer

Critical Success Factors include:Experienced team with tried and proven systems

Modularization CSF’s

Client / Project # Modules

Goro Nickel Project 625

Singapore Aromatics 213

TARP, Thailand (2X strategy) 65

Celanese, Singapore 25

ExxonMobil LSADO Altona (FEL) 13

SINCOR (FWUSA Shop) 10

Clark/Premcor, Texas 12

Shell, Deer Park, Texas 14

Mobil Coryton, UK 53

Statoil, Norway (1980s) 205