DEPNRMT-GT-T2-I-PS-13-0002 1 de 38Octubre 2013

EXECUTIVE MANAGEMENT OF NEW REFINERY PROJECT, ENHANCING AND TERMINALS

Terminal Storage and Shipment of Crude Araya TAECA

START MEETING PRESENTATION

Page 2: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 2 de 38Octubre 2013

CONTENTS

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

1.- Objective of the project

2.- Scope of the project

3.- Implementation Strategy

4.- PDVSA Organization

5.- Interaction with other organizations

6.- Information required to start the project

7.- Contract Administration

Overview

• Registration of providers PDVSA • Contract Administration• Modifications and / or changes in scope

• Acts and Guarantees

Page 3: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 3 de 38Octubre 2013

CONTENTS

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

Billing procedure

• Progress Report approved by the Project Management• Submission of monthly bills: Professional fees and reimbursable expenses• Reimbursable expenses

8.- Document Control

Overview Required Information Consortium Final submission of engineering products

9.- Quality Requirements

Requirements Information provided by the customer

Page 4: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 4 de 38Octubre 2013

CONTENTS

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

10. - Planning and Control Requirements Schedule TAECA Early Activities Work partition structure (E.P.T.) Milestones for measuring physical progress

11. - Other points. Delivery conceptual engineering Coordinating the development of the TDR concerning hiring open

book CPI

Page 5: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 5 de 38Octubre 2013

Design and construction of the infrastructure necessary for the receipt, storage and dispatch of Crude and Products:

Dcom upgraded crude 16 and 32/42 ° API FPO Decom preparing mixtures and for obtaining improved segregation between 22 and 26 ° API according to market requirements.

Components, intermediate streams and strategic refined products

OBJECTIVE OF THE PROJECT

Page 6: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 6 de 38Octubre 2013

Construction of Terminal Storage and Shipment of Crude Araya (TAECA), with all necessary facilities for the receipt, storage and dispatch of crude mixture, components, intermediate streams and refined products. The TAECA will consist of the following facilities:

Patio storage tanks for liquid products MMBls 72.8: DCOM 16, 22 and 26 ° API, Enhanced 32 and 42 ° API, refined products (Gasoline, Diesel, etc.) and components (Reformed, alkylate, naphtha, residual, among others).

Boarding platform with six charging stations for ships Suezmax and Aframax 160 200 MTPM MTPM Monobuoy five VLCC ship up to 300 MTPM type.

Administrative and operational buildings and industrial service requirements.

PROJECT SCOPE

Page 7: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 7 de 38Octubre 2013

The project will be developed in three phases:

Phase I: Start of operation in 2017 (*) to handle production of breeders

Petromacareo (176 MBD Enhanced oil 32 ° API) - Petrourica (64 MBD

Enhanced oil 32 ° API and MBD DCOM 312 16) and have the following facilities:

• Thirteen tanks: two Buoys (50-150 Mbls / h) administrative and

operational buildings, service systems, service dock

• Early onset Milestone: Site Preparation, 4 Mbls 750 tanks, 1 Monoboya

+ underwater pipe

IMPLEMENTATION STRATEGY

(*):Estas fechas están sujetas a revisión de acuerdo al plan de negocios de la corporación 2013-2019

Page 8: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 8 de 38Octubre 2013

Phase II: Implementation Start 2018 (*) to handle production of breeders

Petromiranda (92 MBD Enhanced oil 42 ° API and 340 MBD of DCOM 16) -

PetroCarabobo (58 MBD Enhanced oil 32 ° API and 316 MBD of DCOM 16) -

Petroindependencia (58 MBD Enhanced oil 32 ° API and 316 MBD of DCOM

16) and will feature the following facilities:

Seventeen tanks: a Platform of 6 posts, 3 monobuoys, Extension office

station and transfer pumps, systems services

Phase III: Implementation Start 2019 (*) at the request of C & S

Ninety-eight tanks

(*):Estas fechas están sujetas a revisión de acuerdo al plan de negocios de la corporación 2013-2019

IMPLEMENTATION STRATEGY

Page 9: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 9 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

CoordinadorOffshore

( 1 N. Mayor)

Contratación

CONSORCIOEjecutor

Ingeniería Básica

Gerente del Proyecto (1 N. Mayor)

• Finanzas (finance)

• Jurídico (legal)

• RRHH (HR)

• PCP (PCP)

• Asuntos Públicos (Public Affairs)

• AIT (AIT)

• Servicios logísticos (logistics services)

• Administración de contratos(Contract Administration)

• Laboral• HDI Líder Planif. y

Control

Leader Planning. and

Control

Líder Eval. EconómicaLe

aLeader Eval.

economic

(1 N. Mayor)

Líder Procura

Procurement Leader

(1. Mayor)

Líder CalidadQuality Leader

(1 N. Mayor)

Líder SIHO – Ambiente

SIHO Leader - Environment

(1 N. Mayor) ( 1 N. Mayor)

- Mecánica (2)- Civil (2)- Instrumentación (1)- Electricidad (1)- Proceso (1)- Ambiente y Seg. (1)- Documentación (1)

Org. Apoyo Nacional

Consultora 9- Mecánica (3)- Civil (3)- Instrumentación (3)- Electricidad (2)- Proceso (2)- Ambiente y Seg. (2)- Documentación (1)

Org. Apoyo Internacional Consultora 17

PDVSA

Indirectos

Coordinado

r Onshore

( 1 N. Mayor) Ing. Mecánico

1 N.Mayor

Ing. Electric. 1 N.Mayor

Ing. Instrument.1 N.Mayor

C. Proyectos Offshore 1 N.Mayor

C. Proyectos Onshore

1 N.Mayor

INGENIARIA BASICA

FUERZA LABORAL

N.Mayor PDVSA 13

Consultora Internacional 17

Consultora Nacional 9

Total 39

ORGANIZACIÓN

Page 10: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 10 de 38Octubre 2013

PDV Marina

PDVSA

Industrial

PDVSA G

as

PDVSA

Div. Costa Afuera

MPPAT

MPP

TT

MPPA

Hidrocaribe

Corpoelec

CANTV

TAECA

Dae

woo

-STX

Ing.

Bás

ica

INTERRELACIÓN CON OTRAS ORGANIZACIONES

Page 11: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 11 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

INFORMATION REQUIRED AT THE START OF THE PROJECT

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

• CONCEPTUAL ENGINEERING

• STRUCTURE AND FORMAT OF PLANS AND DOCUMENTS

• PDVSA RULES AND PROCEDURES• EPT• MODEL MAKING PROGRESS

REPORT

• IMPLEMENTATION STRATEGY (ORGANIZATION)

• QUALITY PLAN

• PLAN A FOUR (4) WEEKS

• DETAILED PLANNING• ING.BASICA (Red Logic of precedence)

• CODED PRODUCT LIST INCLUDING ESTIMATED DATES REVISIONS FOR HOME,, DRAFT, REV.A, BY 0

• HISTOGRAM OF RESOURCES

• CURVES OF PHYSICAL AND FINANCIAL PROGRESS

• BUDGET DISAGGREGATED• REFUNDABLE COST:• Travel Expenses• Special Studies• others

• DISTRIBUTION MATRIX

• CV's• STAFF LIST, DETAILED BY DISCIPLINE,

RANKING, AND REMOVAL FROM DATE OF INCORPORATION, PLANNED HOURS

CONSORTIUM

PDVSA

Page 12: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 12 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

CONTRACT ADMINISTRATION

GENERAL

•Registration of providers PDVSA

•Contract Administration

•Modifications and / or changes in scope

Page 13: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 13 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

CONTRACT ADMINISTRATION

1. SEND TO A PRO-FORMA PDVSA (IN ORIGINAL AND COPY) ATTACHING THE MONTHLY REPORT APPROVED PDVSA.

4. GET INPUT SHEET AND THE ACCOMPANYING SERVICES INVOICE (ORIGINAL AND COPY) AND SEND TO PDVSA

PRESENTATION OF BILLS

2. RECEIVED, REVIEWS AND APPROVING THE PRO-FORMA

3. MAKES THE SERVICE ENTRY SHEET (HES) AND SEND TO CONSORTIUM

5. GET THE INVOICE AND SEND TO FINANCE FOR PAYMENT

PDVSACONSORTIUM DAEWOO- STX

PROFESSIONAL FEES

Page 14: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 14 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

CONTRACT ADMINISTRATION

1.-REFUNDABLE FEES BEFORE EXECUTION MUST BE PRE-APPROVED BY PDVSA

2. - SEND TO A PRO-FORMA PDVSA (IN ORIGINAL AND COPY) WITH ORIGINAL MEDIA AND EXPENDITURE AUTHORIZATION PDVSA

5.-RECEIVED SERVICE ENTRY SHEET AND ATTACHED TO THE INVOICE (ORIGINAL AND COPY) AND SEND TO PDVSA

PRESENTATION OF BILLS

3. - GET, REVIEWS AND APPROVING THE PRO-FORMA

4. - MAKES THE SERVICE ENTRY SHEET (HES) AND SEND TO CONSORTIUM

6. - GET THE INVOICE AND SEND TO FINANCE FOR PAYMENT

PDVSACONSORTIUM

EXPENSES REFUNDABLE

Page 15: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 15 de 38Octubre 2013

General

The exchange of technical information will be handled by transmittal, which shall be issued by discipline.

The technical consultations were held through the use of email.

The shipping of products, should be using the code PDVSA, according to the latest list of approved products.

The issue of digital files must include the transmittal and the product delivered, the latter in native and PDF version.

For the final delivery of engineering products loins, covers and indexes, folders and CD's, must be submitted for evaluation and approval of the quality area, prior to its release for final delivery, according to the structure and format DEPNRMT-GA-11-I-EF-10-0004, Rev. 1

The products to be delivered in the final book, in digital PDF version must include the covers with their respective signatures.

DOCUMENTATION

Page 16: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 16 de 38Octubre 2013

DOCUMENTATION

Required Information Consortium

ADMINISTRATIVE INFORMATION

Matrix distribution of information, which must be delivered to PDVSA before starting the process of information exchange.

TECHNICAL INFORMATION

Final list of engineering products encoded. Matrix distribution of information, which must be delivered to

PDVSA, along with the list of engineering products encoded Rev.0, before starting the process of information exchange.

Implementing an information exchange platform. (FTP, server, system, other)

Page 17: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 17 de 38Octubre 2013

DOCUMENTATION

Final Delivery Engineered Products

The CONSORTIUM shall deliver to the end of the project:

Three (3) digital copies on CDs.

One (1) printed original copy of the final issuance of Basic Engineering.

One (1) copy printout of the final issuance of Basic Engineering.

Page 18: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 18 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

1. Issue a "Quality Plan" project specific.

2. Deliver a "Plan Design and Development" project specific.

3. Send the Management Area Customer Quality formats of engineering products (documents and drawings), for review and approval.

4. Presenting the Management Area Customer Quality index to organize the final documentation of engineering products (documents and drawings), for review and approval.

5. Send the Management Area Customer Quality covers models (folders, CD or DVD) and folders loin final documentation of engineering products (documents and drawings), for review and approval.

Page 19: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 19 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

1. Prepare the "Quality Plan" according to ISO 9001:2008 and the document "DEPNRMT-GA-11-I-EF-10-0001: Structure and Format for Preparation of the Quality Plan for External Entity" , which must declare the Management System Quality, Management Responsibility, Resource Management, Product Realization and Measurement, Analysis and Improvement.

2. Append Quality Plan Mandatory procedures of ISO 9001:2008.

3. Deliver draft Quality Plan 21 days after the meeting calendars boot or 21 calendar days after the start of the project.

Page 20: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 20 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

4. The results of the review of the Quality Plan will be documented in the "Results of Review Quality Plan" and its approval is subject to the result to cast the assessment associated with the record.

5. The Quality Plan will be frozen on the Rev. B, to reflect changes that may arise during project implementation. The Customer will be issued when the Rev. 0.

6. Prepare the Design and Development Plan based on the requirements given by the customer in the document "DEPNRMT-GA-11-I-EF-10-0002: Structure and Format for Preparation of the Design and Development Plan Generated by External Entity ".

Page 21: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 21 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

7. Prepare the "Design and Development Plan," indicating the activities and stages under review, verification and validation of the design must indicate the reference documents, declare approval levels for each product design indicating who the that issue, review and approve engineering products.

8. Append the signature roster of personnel assigned to the project for Engineering Disciplines, indicating average signature and signature respectively.

9. The Design and Development Plan will be frozen on the Rev. B, to reflect changes that may arise during project implementation. The Customer will be issued when the Rev. 0.

Page 22: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 22 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

10. The results of the review of the Design and Development Plan will be documented in the "Results of Review of the Design and Development Plan" and its approval is subject to the result to cast the assessment associated with the record.

11. The Client will make two (02) or audits deemed necessary during project implementation (A to 45% and the other 70%).

12. The program and audit plan will be given to the consultant, 21 days after frozen Plans Design Quality and Development.

Page 23: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 23 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

13. If the Quality Plan and the Design and Development Plan are frozen for the first two months of project implementation, the client reserves the right to conduct audits that it considers appropriate. Additionally, the Customer will issue a new nonconformity report.

14. Issue engineered products in the various reviews on native and PDF.

15. Send revisions (Rev. A, Rev. B, Rev.0) engineering products in the English language, once approved by the Customer shall be translated into Spanish. Except for the documents (XX), which will be issued in Spanish.

Page 24: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 24 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

16. Engineered products will be discussed only in PDF.

17. Deliver the Rev. 0 of engineering products in English and Spanish.

18. Send the Management Area Customer Quality formats of documents and drawings for review and approval, before starting with the issuance of engineering products.

19. Engineered products that do not meet the requirements and criteria to be approved as a Rev. A, Rev. B, Rev.0, will be rejected and will not be given the physical and financial progress.

Page 25: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 25 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Requirements

20. Engineered products provide physical and financial progress in the Rev. A, Rev. B, Rev.0, once approved by Customer review.

21. Engineering products issued on Friday will start the day review from Monday.

Page 26: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 26 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Information provided by the customer

1. Plans Formats: A0, A1, A2, A3 and A4.

2. Templates: Paper Engineering and Quality Plan Design and Development

Plan.

3. DEPNRMT-GA-11-I-EF-09-0002, "Structure and Format for the Engineering

Document Preparation Generated by External Entity".

4. DEPNRMT-GA-11-I-EF-10-0001, "Structure and Format for Preparation of

the Quality Plan for External Entity".

5. DEPNRMT-GA-11-I-EF-10-0002, "Structure and Format for Preparation of

the Design and Development Plan Generated by External Entity".

Page 27: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 27 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Information provided by the customer

6. DEPNRMT-GA-11-I-EF-10-0004, "Structure and Format for the Issue of

Engineering Products and Electronic Physical Environment Generated by

External Entity".

7. DEPNRMT-GA-11-I-DR-11-0001. "Guidelines for the Application of

Standards, Decrees, Laws and Official Gazettes in Engineering

Development".

8. Organizational structure and staff signature log of the Client.

Page 28: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 28 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Information provided by the customer

9. Forms:

Plan Design and Development

Signature Roster Project Staff,

Reviews Summary Revision of Engineered Products

Outcome of Review Quality Plan and

Outcome of Review Plan Design and Development.

Page 29: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 29 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

QUALITY

Information provided by the customer

10. Standards:

L-E-4.7. "Structure, Content and Format for Preparation of Engineering

Drawings PDVSA"

PIC-1-1-03. "Structure and Content of Documents Product Developed

as a Capital Investment Project (CIP)" and

PIC-01-03-05. "Coding Projects and Documents".

Page 30: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 30 de 38Octubre 2013

PLANNING AND MANAGEMENT

Requirements

•The Consortium will provide, for approval of PDVSA, within no more than fifteen (15) days after the signing of the minutes of beginning the following documentation planning and control:

•Plan to four (4) weeks.

•Red precedence logic, structured under the EFA approved.

•List of engineering products encoded, with their relative weights, including planned dates for revisions A, B and 0.

•Resource histogram

•Curves of physical and financial progress

•Detailed budget of reimbursable expenses (travel expenses, special studies, etc..)

Page 31: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 31 de 38Octubre 2013

PLANNING AND MANAGEMENT

Requirements

•The Consortium will develop and deliver monthly to review and approval of PDVSA the following reports:

• Monthly physical progress

• Cost Monthly

•After approval of the Consortium PDVSA issue supports the invoicing of the period presented.

•There will be a monthly meeting coordination and monitoring of engineering.

Page 32: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 32 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

PLANNING AND MANAGEMENT

General Schedule TAECA

I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV

Ing. Básica 12

Estudios Especiales 10Tramite Ambiental 9.5

Procura LTE 28

Preparación del Sitio 16

Area de Almacenamiento (Productos de la Faja)

21

Area de Muelles 20Arranque Fase Temprana

Arranque 3

Area de Almacenamiento (Productos de la Faja)

20

Area de Muelles 24

Arranque 3

Area de Almacenamiento (Producción propia de PDVSA y

Productos Estratégicos)31

Arranque 3

Leyenda:

20192014 2015 2016ÁREAS PROYECTO FASES

D (M)

TERMINAL DE ALMACENAMIENTO Y EMBARQUE DE

CRUDOS DE ARAYA (TAECA)

IPC FASE I

IPC FASE II

IPC FASE III

2017 20182013

Inicio Contratación Arranque IPC Hitos Ingeniería Básica Estudios Epeciales Procura de Largo Tiempo de

Entrega

Page 33: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 33 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

PLANNING AND MANAGEMENT

Early Activities

Hiring the following Special Studies

•Geophysicist at Sea

•Metoceanico

•Marine traffic

•Sedimentation and Erosion on the Coast

•Sea Geotechnical

•Road Impact

•Environmental Impact

•Land Survey

•Bathymetry

•Soil Resistivity

•Geotechnical in Inland Area

•Hydraulic and Hydrological

•Seismic Hazard

Page 34: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 34 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

PLANNING AND CONTROL

Early Activities

Hiring Process for Special Studies

PDVSAPDVSA

1. Reviewed, updated and gives the scope for hiring each of the studies

3. Prompts respective bids.

5. Check the offers and presents PDVSA report results for company selection

7. Hire through reimbursable expenses approved for the IB

CONSORCIO

2. Approves the different scopes

3. Provides business name

6. Select company

8. Authorizes the execution of expenditure

Page 35: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 35 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

PLANNING AND CONTROL

Labour Partition Structure (E.P.T)

Page 36: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 36 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

PLANNING AND CONTROL

Labour Partition Structure (E.P.T)

Page 37: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 37 de 38Octubre 2013

Dirección Ejecutiva de Proyectos de Nuevas Refinerías, Mejoradores y Terminales

PLANNING AND CONTROL

MilestonesApproved Progress

%

Nº Description Parcial Acumulado1 Búsqueda de

información Al recopilar la información requerida 10 10

2 Calculo, diseño y borrador de planos y documentos

Emisión de borrador de planos (dibujo) y/o documentos y/o documentos (transcripción)

35 45

3 Emisión para comentarios

Recibido, y aprobado por el Líder de disciplina para comentarios (Emisión A)

25 70

4 Incorporación de comentarios

Incorporación de comentarios y documento firmado por el Líder de disciplina (Emisión B)

20 90

5 Aprobación final Incorporación de comentarios finales y documento firmado por el Gerente del proyecto (Emisión 0)

10 100

Milestones for Measurement of Physical Progress

Page 38: Presentaciones taeca kom 영문

DEPNRMT-GT-T2-I-PS-13-0002 38 de 38Octubre 2013

OTHER ITEMS

• Delivery conceptual engineering

• Coordinating the development of the TDR concerning hiring open book CPI