Upload
sameer-alam
View
1.060
Download
0
Embed Size (px)
Citation preview
Problem 1
Activity Predecessor SuccessorA - D,EB - FC - G,HD A FE A JF B,D JG C JH C II H -J E,F,G -
AOA Network
1
2
4
START
3
7
C
A
D
E
G
J
IBF
6
5
H
AON Network
START
A
C
D
B
G
E
F
H
ENDJ
I
Problem 2
Activity Predecessor Successora - c,fb - d,ec a hd b he b hf a ig b ih c,d,e ii f,g,h -
AOA Network
AON Network
In the AOA Network representation a dummy task has to be incorporated into the network to allow for two predecessors of the task e. No such requirement is found in the AON representation. It appears that an AON representation is much easier than AOA.
1
2
4
START
a
b
c
d
e
f
h
g
END
5
3
6
7
b
a
f
h
c
d
e
g
i
i
In the AOA Network representation a dummy task has to be incorporated into the network to allow for two predecessors of the task e. No such requirement is found in the AON representation. It appears that an AON representation is much easier than AOA.
Problem 7
Duration - 3 estimates
Activity Predecessora - 2 4 9b - 2 3 8c b 4 7 14d a 4 5 16e b 5 7 12f c,d 2 4 8g c,d 6 8 14h e,f 6 7 14i g,h 2 3 9
(a) Activity Variance S.D.a 4.50 1.361 1.17b 3.67 1.000 1.00c 7.67 2.778 1.67d 6.67 4.000 2.00e 7.50 1.361 1.17f 4.33 1.000 1.00g 8.67 1.778 1.33h 8.00 1.778 1.33I 3.83 1.361 1.17
(b) AOA Network
(c) Path Variance S.D.3.83 1-2-4-6-7 23.67 8.500 2.920.17 1-2-4-5-6-7 27.33 9.500 3.08
27.50 1-3-4-5-6-7 27.50 7.917 2.813.67 1-3-4-6-7 23.83 6.917 2.63
Optimistic (months)
Most Likely
(months)Pessimistic
(months)
Estimated Time
Estimated Time
2
3
4 6
5
1
a:4.50
b:3.67
d:6.67
c:7.67
e:7.50
f:4.33
g:8.67
h:8.00
i:3.83
4.50 1-3-5-6-7 23.00 5.500 2.35
(d) Due date D = 36Estimated time T = 27.50Standard Deviation 3 2.81Standard normal variate = 3.020979
99.87
(e) Probability of completion = 0.8Standard normal variate = 0.842Estimated time T = 2 27.33SD = 3.08Due date D = 29.93
(f)
(g)
Due date D = 36Estimated time T = 27.33Standard Deviation 3.08Standard normal variate = 2.811838
99.75
From the above table we see that the critical path is 1-2-4-5-6-7 and the nearly critical path is 1-3-4-5-6-7
Probability of completion in 40 months =
For reduction in the project duration, activities on the critical path can be reviewed for crashing options.The firm must investigate methods that enables it to reduce the variance of some of the activities on the critical path.
The probability of completion in 36 months, on the near critical path is :
Probability of completion in 36 months =
It is interesting to note that a near-critical path can potentially bring down the probability of completion compared to a critical path due to high path variance. Therefore the notion of an official critical path in PERT is not the same as in a CPM method.
What-if ??
Change the activity durations to assess the
impact
7
monthsmonths
%
months
months
monthsmonths
%
From the above table we see that the critical path is 1-2-4-5-6-7 and the nearly critical path is 1-3-4-5-6-7
This observation does not hold if you change the activity durations.
For reduction in the project duration, activities on the critical path can be reviewed for crashing options.The firm must investigate methods that enables it to reduce the variance of some of the activities on the critical path.
The probability of completion in 36 months, on the near
It is interesting to note that a near-critical path can potentially bring down the probability of completion compared to a critical path due to high path variance. Therefore the notion of an official critical path in PERT
Problem 8
Activity Predecessora - 6 5 10,000 15,000b - 4 3 12,000 14,000c a 5 n.a. 16,000 n.a.d b 3 n.a. 18,000 n.a.e c 4 2 11,000 17,000f d 4 2 24,000 32,000g c 4 3 12,000 18,000h d 9 6 50,000 68,000i e,f 2 n.a. 16,000 n.a.j g,h,i 3 2 10,000 11,000
Indirect cost for the project per week (Rs.) 6,000
AON Network
Activitya 6 5 10,000 15,000 1b 4 3 12,000 14,000 1c 5 n.a. 16,000 n.a. 0
Normal Duration (weeks)
Crash Duration (weeks)
Normal Cost (Rs.)
Crash Cost (Rs.)
We evaluate our options by the following table:
Normal Time (Weeks)
Crash Time (Weeks)
Normal Cost NC
(Rs.)
Crash Cost CC
(Rs.)
Max. Crashing (Weeks)
START
b
a:
d
c
h
f
g
e6 5
4 3
9
4
4
4
d 3 n.a. 18,000 n.a. 0e 4 2 11,000 17,000 2f 4 2 24,000 32,000 2g 4 3 12,000 18,000 1h 9 6 50,000 68,000 3i 2 n.a. 16,000 n.a. 0j 3 2 10,000 11,000 1
No.1 a,c,e,i,j None 0 179,000 202 a,c,e,i j 1 180,000 193 a,c,i e 2 186,000 174 c,i a 1 191,000 16
Therefore we find the optimum cost to be (Rs.)Savings obtained by crashing activities (Rs.)
Sum of the normal costs for all the activities in the above table constitutes the direct cost without crashing
The indirect cost is @ Rs. 6000 per week charged for the project duration of 20 weeks
Crashable Activities on Critical path
Activitiy Crashed
No. of weeks
crashedDirect Cost
Project Duration
PREVIOUS SOLUTION
What-if ??
50002000n.a.
Change the cost structure to assess the impact
Crashing Cost/week
i j FINISH
23
n.a.3000400060006000n.a.
1000
Indirect Cost Total Cost120,000 299,000114,000 294,000102,000 288,00096,000 287,000
287,00012,000
Sum of the normal costs for all the activities in the above table constitutes
The indirect cost is @ Rs. 6000 per week charged for the project duration of 20
NEXT SOLUTION