Detailing : Exterior Wall Assemblies

Embed Size (px)

Citation preview

Page 1: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 1

D E T A I L I N G S E M I N A R

EXTERIOR WALL ASSEMBLIESp r e s e n t a t i o

n

Page 2: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 2

OUTLINE Exterior Wall Assemblies

Detailing Objectives

Thin-Stone Veneer

Cavity Wall : Brick on CMU

Page 3: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 3

Detailing ObjectivesDOB-1 : FIREDOB-2 : EARTHDOB-3 : WATERDOB-4 : AIR

DOB-5 : COSTDOB-6 : TIMEDOB-7 : SCOPE

FIRE

WATER

AIR EARTH

dryhot

wet cold

ELEMENTS

TIMECOST

SCOPE

Page 4: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 4

Thin-Stone Veneer PROJECTS :

St. Joseph Outpatient Center GE Healthcare Research Park Acuity

Page 5: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 5

Thin-Stone Veneer Panelized thin-stone veneer

wall panels Manufacturer : Biesanz Stone Co

Assembly includes 1-1/4” Winona Dolomite

Limestone Stone is held in place with threaded

studs Epoxy-anchored into back of stone

panels 6” welded structural stud frames

Page 6: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 6

Thin-Stone VeneerDOB-1 Fire (Thermal)

Conduction 4” Polyurethane Insulation Sprayed in stud cavity

Encapsulates metal studs R5 per inch = R20

Sprayed after panels are placed Monolithic installation (+)

Cannot be exposed : Fire hazard Ceiling plenum or Other occupied spaces

Must be covered by Gypsum Board or Sprayed-on fire resistive

coating

Page 7: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 7

Thin-Stone VeneerDOB-2 Earth (Solid) Panels : welded to

floor edge framing Edge framing

designed for deflection criteria : Panel to panel or Panel & window

system

Page 8: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 8

Thin-Stone VeneerDOB-3 Water (Liquids)

Barrier system No drainage cavity Water infiltration barrier

stone veneer epoxy joints sealant joints

Closed-cell polyurethane insulation helps to keep water out

of assembly Flashing placed :

under handset copings and window sills

at top of foundation wall

Page 9: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 9

Thin-Stone Veneer

Page 10: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 10

Thin-Stone VeneerDOB-4 Air (Vapor) Insulation acts as vapor

barrier Closed cell 3” or more thickness

DOB-5 Cost Comparable to precast Life cycle costs

Very good Very low maintenance

Sealant at panel joints Periodic replacement

Page 11: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 11

Thin-Stone VeneerDOB-6 Time Labor

Prefabricated panels Ease of installation

Panels can be large Building enclosure fast

All-weather construction Easily installed during winter

DOB-7 Scope Aesthetics

Natural stone product Mix of lights and darks Very high quality look

Coordination Similar to precast panels Shop drawings must be accurate Errors in the field

Pull epoxy-ed stone from panels : difficult

Page 12: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 12

Cavity Wall : Brick on CMU Project :

UW LaCrosse Residence Hall Project Scope

Occupancy : R-2 Construction Type : Type IIB

Need : Provide a building that meets

the Department of State Facilities (DSF) longevity requirements : 100 yr building

Concerns : Costs Solution :

Provide a century old building system Provide a brick/ block cavity rain

screen wall system

Page 13: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 13

DOB-1 : Fire (Thermal) Thermal Insulation

2” air space + 2” rigid insulation

Cavity Wall : Brick on CMU

Page 14: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 14

Cavity Wall : Brick on CMUDOB-2 : Earth (Solid) Movement : Materials

CMU/ Brick move/ contract at different rates

Page 15: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 15

Cavity Wall : Brick on CMUDOB-2 : Earth (Solid) Movement : Elements

Horizontal movement : Vertical control joints (24’ o.c.)

Vertical movement : Horizontal shelf angles

Every two floors or 30’ brick heights

Page 16: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 16

Cavity Wall : Brick on CMUDOB-2 : Earth (Solid) Structural Support : Dead load bearing

system Openings < 6’ : Bond beams Openings > 6’ : Engineered steel lintels

Page 17: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 17

DOB-3 : Water (Liquids) Sealant Joints and Gaskets

Provide flashing at all horizontal interruptions in a wall.

Opening Heads Opening Sills Shelf angles Foundations

Drain & Weep Water drained from cavity thru

a series of weeps. Do not use rope weeps. Need to provide vents at top of

cavity (similar to weeps only located at top of cavity.

Vents help equalize cavity pressure

Provide air movements to help dry cavity out.

Cavity Wall : Brick on CMU

Page 18: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 18

DOB-3 : Water (Liquids) Rainscreen Assembly

Cavity wall system utilizes the rain screen principal to control water

Water Allowed to penetrate the

outer layer Directed out of the cavity

thru the use of flashing + counter flashing systems

Sprayed on Air & Moisture Barrier utilize to control air & moisture vapor penetration

Cavity Wall : Brick on CMU

Page 19: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 19

DOB-3 : Water (Liquids) : Window Sills

Cavity Wall : Brick on CMU

Page 20: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 20

DOB-3 : Water (Liquids) : Window Heads Openings < 6’ : Bond beams Openings > 6’ : Engineered steel lintels

Cavity Wall : Brick on CMU

Page 21: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 21

DOB-3 : Water (Liquids) FlashingCavity Wall : Brick on CMU

Page 22: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 22

DOB-3 : Water (Liquids) : Window Jambs

Cavity Wall : Brick on CMU

Page 23: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 23

DOB-3 : Water (Liquids) : CopingCavity Wall : Brick on CMU

Page 24: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 24

DOB-3 : Water (Liquids) : Low Roof & Parapet

Cavity Wall : Brick on CMU

Page 25: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 25

DOB-3 : Water (Liquids) : Coping/ Roof

Cavity Wall : Brick on CMU

Page 26: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 26

Cavity Wall : Brick on CMUDOB-4 : Air (Vapor) Water Vapor

Air Barrier Placement : Critical Warm side : CW

insulation Cavity

Keep Clean : Critical 1” Minimum 2” Preferred

Page 27: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 27

Cavity Wall : Brick on CMUDOB-5 : Cost Life-Cycle Issues

Cavity Wall : 4” face brick 2” air space 2” rigid insulation 8” CMU

Time tested assembly Over century old Research performance

sources : numerous Material Costs $28-

$36 / s.f.

Page 28: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 28

Cavity Wall : Brick on CMUDOB-6 : Time Expected Life

100 year building assembly Life-Cycle:

Maintenance : Minimal Sealant/ tuck pointing

Efficient Use of Const Materials Labor intensive

Built one block/ brick at a time Refining the Detail Critical : Specify a mock-up panel

Show wall system components and openings Used to review finished work Provides objective comments/ concerns

All-Weather Construction Majority of winter construction cost (65-

75%) Temporary heat and protection of masonry Keep project moving

Pride of Craftsmanship Craftsmanship intensive

Parts That Are Easy To Handle Installation is easy.

Page 29: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 29

Cavity Wall : Brick on CMUDOB-7 : Scope Aesthetics

Natural materials+organic : from the earth

Different colors/ textures/ bricks/ bonding

Patterns can provide interest in a project Timeless Features : Never goes out of

style Coordination : S + MEP

Critical for any recessed component. Electrical requires conduit/ boxes to be

set with wall. Do not install pipes inside cavity wall. Need to create pipe chases on warm side

of wall.

Page 30: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 30

Cavity Wall : Brick on CMUDOB-7 : Scope Forgiving Details : Dimensional

Tolerances Maintain an 8” building module to

minimize cutting All openings need to be kept on 8”

module also

Page 31: Detailing : Exterior Wall Assemblies

eu:a eppstein uhen architects 31

ConclusionQuestions???