Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
20-06-2018
1
Waste Management & Recycling
from DISTILLERY EFFLUENT
COMPANY : E.I.D PARRY (INDIA) LTD.
LOCATION : SIVAGANGA - TAMILNADUParticipant - 1 KM.Muthukaruppan – Deputy General Manager
Participant - 2 S.Senthilvelan - Senior Manager Process
Participant - 3 S.Muralidharan – Manager Engineering
CII - Environmental Best Practices Award 2018
Let us be the change
RECAP OF CONVENTIONAL SYSTEM SUGAR & DISTILLERY
2
&
SUGAR PROCESS SUGAR MOLASSES FERMENTATION
DISTILLATIONEVAPORATORINCINERATION BOILERTURBINE
ASH To KASH RO PLANT
560 KLPD185 TPD of Con
Spent wash
412 KLPD of condensate
192 KLPD spent less
Fly Ash
20-06-2018
2
Present practice:
The distillery is a largest red category industry which has the Conventional
effluent treatment system.
Effluent is rich in Nutrients like N, P & K and other micro nutrients
Conventional method of treating this effluent is mixing with press mud to
produce bio compost which is sold as a fertilizer as well as sold to cement
industries to use as alternative fuel & grinding agent.
Need for change:
With the above technology, we were permitted to operate the plant only
for 270 days a year and we were proposing to operate 365 days a year
To achieve ZLD with new a concept & technology
To create wealth from waste
NEED FOR THE PRACTICE
3
Distillery can operate 365 days
Zero Liquid Discharge
Creating waste to wealth in terms of Potash rich fertilizer
Converting the spent wash in to renewal energy through Incineration
Entire concentrated Spent wash fired in the incineration boiler at 60 Bx
Converting the fly Ash (Solid waste) into Fertilizer – Value added product
Converting the emitted C02 gas in to valuable liquid product form
Recycle & Reuse of the generated process condensate from Evaporation
including the spent lees(Distillation) back into fermentation to conserve
the ground water.
UNIQUENESS OF OUR DISTILLERY
4
20-06-2018
3
DISTILLERY EFFLUENT – SPENT WASH
INCINERATION
Fly Ash
Evaporation- MEE system
RO PLANT
Fermentation
POTASH FERTILIZER
METHODS ADOPTED IN OUR DISTILLERY UNITS
5
Recycle/Complete ZLD
Condensate Con Spent wash
PROJECT TANGIBLE BENEFIT - 17 Crores per AnnumBoiler Steam generation : 480 TPDActual Coal requirement : 120 TPD (1MT coal generate 4MT of steam)Input of Concentrated Spent Wash : 195 TPD (1MT CSW generate 1.8MT Steam)Steam from the Con Spent wash : 352 TPDCoal Savings by Con Spent wash : 88 TPDCoal savings per annum (300 Days) : 26400 Mt
Project title No.1 CONVERTING THE SPENT WASH INTO RENEWABLE ENERGY
M/s THERMAX has partner in this journey
Project Commencement date : 02nd May 2008
Completion date : 31st Jan 2009
WAY FORWARD – PROJECT IMPLEMENTATION
6
20-06-2018
4
PROJECT TANGIBLE BENEFIT - 2.50 Crores per Annum
Fly Ash generation : 26 TPD.CSW as binding agent : 10 TPD (55% solids @ 58–60 bx) Expected production per day : 35 TPD (6- 6.5 % moisture)
Project title No.2 FLY ASH (SOLID WASTE) INTO FERTILIZER – VAP
In house innovation - Rich in water soluble potash 20 to 22 %
Project Commencement date : 15th Jan 2010
Completion date : 12th Jan 2013
7
Value Added Product-KASH
Fly Ash as Waste from Boiler
Sweet Potash Granules as Product of Fertilizer
20-06-2018
5
Kash
• Boiler ash rich in Potash is sold as fertlizer.• Ash is granulated to a size of 2 mm to 6 mm and sold.• Survey conducted in various state and good feed back is obtained from the farmers.
Field Trial and Findings
20-06-2018
6
PROJECT TANGIBLE BENEFIT - 0.75 Crore per Annum
C02 generation per day : 25 TPD.
Expected C02 per annum :7500 TPA
Project title No.3 CAPTURING THE EMITTED C02 - VAP
Safe Environment - Avoid Carbon Emission – Liquid C02
Project Commencement date : 18th Jan 2017
Completion date : 26th Aug 2017
11
PROJECT TANGIBLE BENEFIT
Ground water savingsOf
530 KLPD
Project title No.4 RECYCLE - REUSE PROCESS CONDENSATE
Resource Conservation
Project Commencement date : 02nd May 2008
Completion date : 31st Jan 2009.
12
20-06-2018
7
13
Tangible benefits: Revenue generation from waste – Rs 20 cr Recovering Resources from Industrial Waste – Potash fertilizer Water and Air pollution are completely eliminated. Water recovery and recycle thereby reducing the ground water drawl.
Intangible benefits :
Reduction in Green house gas emission Organizational goals are achieved Reduce foreign exchange due to import of Potash Employment opportunities Environment Best Practices
TANGIBLE & INTANGIBLE BENEFIT
14
PRODUCT QUALITY
Govt of India – Fertilizer division – Fertilizer control order has listed this product as “Fly ASH (KASH) derived from Molasses”
Sl.No ParametersFCO
Norms(%)KASH G
Results(%)
1 Moisture < 4.79 < 5.05
2 Water Soluble Potash >14.70 >18-19.5
3 Total Nitrogen >1.66 >0.65
4 Total Phosphorus >0.39 0.4
20-06-2018
8
Highly appreciated
by PCB officials for our
success of new technology.
First Distillery to Obtain
MOEF clearance for operating
Plant for 365 Days in a Year.
ECONOMICAL BENEFIT - KASH
15
Introduction of new technology for converting Ash in to Granule form for Ease field Application
KASH Granule Production cost SheetS.No Description Cost Rs/Ton
Variable cost1 Packing & Stitching Cost (50 Kg Bags) 300.002 Loading Cost 60.003 Stitiching cost 4.004 Diesel for Tractors 25.00
Total-Variable Cost per MT 389.00Fixed cost
1 Tractor Rent-2 Nos 75.002 JCB rental charges 35.003 Depreciation of equipments 14.004 R&M-SS Line & Others(Electrical Maintanence) 75.005 Supervisor salary 25.006 Admin & Miscell. Exp- Safety ,stationery etc 5.50
Total -Fixed Cost per MT 229.50
Total cost of Production Rs per Ton 618.50Selling price Rs Per Ton 3000Net Relaisation [Profit] Rs per Ton 2,381.50Expected production per Annum-Tons 10500Revenue Generation Per Annum in Lac 250.06
REPLICATION POTENTIAL WITHIN THE SECTOR
We have already replicated this in other unit which is located in
Rajashree Sugars, BannariAmman Sugars, TN.
16
Best Distillery Award in the case of ZLD system has bagged during 2015-16 in SISSTA
We have already replicated this in our other unit which is located in Haliyal, Karanataka.
PCB instructed to implement the technology as its proven one for ZLD system.
20-06-2018
9
CHALLENGES FACED & OVERCOME METHODOLOGY
17
S.No CHALLENGES OVERCOME METHODOLOGY1 Boiler Run Days:
- Boiler was operated only 20-25 days due to chocking of ash in the coils
Primary super heater coil pitch was increased from 90mm to 103 mm Secondary super heater coil pitch was increased from 100mm to 117mm.
2 Boiler coil chocking:- Incinerated ash started to deposit in the coils leads to
blocking of flue gas path
Introduced soot blower system in the flue gas path to eliminate the ash deposition in the coils
3 Struggling in Bag filter(emission level):- Actual flow gas flow 65000 Cum is higher than
estimated flow45000, the installed 2 modules was notsufficient to handle the volume
- Supplied oven Bags was not tolerating the nature of flyash, resulted in escaping of the particulate matter
Additional 2 modules has been placed par alley to handle the quantity of the flue gas.
Imported PTFE bags are replaced and meet the norms of PCB
4 Erosion of Boiler Air Nozzle:- Top of the Air nozzle(SS 446) are eroded due to the
nature of spent wash incinerated resulted in improperfiring
Hard facing done in the top of the air nozzle to withstand the erosion
5 Installation of standby Evaporation system:- On improving the boiler run days, problem faced in the
MEE system, where it is run for 20 days only
Standby evaporator bodies only placed with common utility system to continue
6 Plate failures in Pre Heating system:- Pitting's are developed in the supplied plates of the
PHE and holes are created due to recycling ofcondensate contains chlorides resulted in product loss
Plates has been replaced with titanium coated SS 304 materials
National Bench mark/ standardsBench Mark / Standards - Environmental Parameter
Water:• No effluent is let out, the generated effluent is
concentrated in MEE / incinerated in boiler.• The generated condensate in the evaporation is
being used for molasses dilution.• Monitoring of BOD/COD is not applicable ,hence
total ZLD is achieved in the case of liquid front.
Emission:• The incinerated flue gas passed through properly
installed APC ( Bag filters).• Online Monitoring system is installed and same has
been connected to SPSB/CBCP portal.• The norms are well within,
Pollutants Unit Norms Actual
SPM Micro G/M3 100 35-45
SO2 Micro G/M4 80 20-25
NO2 Micro G/M4 80 30-35
Energy:• On power, VFD are installed achieved best
consumption of 0.57 Kw/lit against the design of 0.6 Kw/lit. ( Savings - 5.55 Lakh units – Rs 1.10 Cr )
• On Fuel, coal reduction is achieved by operation fine tuning and emission is controlled.
Carbon:• The generated CO2 is captured and converted in to
liquid form/ carbon emission avoided on environmental front.
Toxicity:• The hazardous waste- Turbine oil is disposed
through authorized TNPCB vendor by obtained license from TNPCB
20-06-2018
10
Best Practices- Design Vs Actual
S.no Description Units Design Actual
1. Coal Consumption Air fuel ratio adjusted. Coil pitch increased
Tons/Day 75 42
2 Boiler run days Modification done in the coil pitch
Day 25 65
3 Power consumption Introduction of VFD in heavy duty pumps. Logic control system introduced for auto mode
operation
Kw per lIt 0.6 0.57
4 Impure spirit production: Fine tuning of the operation/based on the
analysis report part of the impure spirit is recycled.
Fetches additional main product and obtained margin of Rs 134900 per day.
No customer complaints
% 6.5 0.95
Future Focus…
Our Future Focus
Predictive & Preventive Maintenance
Value added products
Developing product with Yeast Sludge rich in protein
Improving Efficiency
CapacityEnhancement
74 KLPD
20-06-2018
11
Our Journey Continues For Excellence…
As a