Upload
rolando-menear
View
307
Download
3
Embed Size (px)
Citation preview
1
Chapter 10
The Basics of Capital Budgeting
2
Topics Methods
NPV IRR, MIRR Payback, discounted payback EAS (EAA)
3
What is capital budgeting? Analysis of potential projects. Long-term decisions; involve large
expenditures.
4
Steps in Capital Budgeting Estimate cash flows (inflows &
outflows). Determine r = WACC for project. Evaluate
5
Capital Budgeting Project Categories
1. Replacement to continue profitable operations
2. Replacement to reduce costs3. Expansion of existing products or
markets4. Expansion into new
products/markets5. Contraction decisions6. Safety and/or environmental projects7. Mergers8. Other
6
Independent versus Mutually Exclusive Projects Projects are:
independent, if the cash flows of one are unaffected by the acceptance of the other.
mutually exclusive, if the cash flows of one can be adversely impacted by the acceptance of the other.
7
Net present value (NPV) rule
Accept project if
Net present value > 0
What is Net present value?
Net present value = Benefits minus Costs
8
How do we measure benefits & costs?
NPV = B – C =
N
ttt
N
ttt
r
COF
r
CIF
00 11
9
NPV: Sum of the PVs of All Cash Flows
Cost often is CF0 and is negative.
NPV = ΣN
t = 0
CFt
(1 + r)t
NPV = ΣN
t = 1
CFt
(1 + r)t– CF0
10
Cash Flows for Franchises
L and S
10 8060
0 1 2 310%L’s CFs:
-100.00
70 2050
0 1 2 310%S’s CFs:
-100.00
11
What’s Franchise L’s NPV?
10 8060
0 1 2 310%L’s CFs:
-100.00
9.09
49.59
60.1118.79 = NPVL NPVS = $19.98.
12
Calculator Solution: Enter Values in CF Register for L
-100
10
60
80
10
CF0
CF1
NPV
CF2
CF3
I = 18.78 = NPVL
13
Rationale for the NPV Method NPV = PV inflows – Cost
This is net gain in wealth, so accept project if NPV > 0.
Choose between mutually exclusive projects on basis of higher positive NPV. Adds most value.
14
Using NPV method, which franchise(s) should be accepted?
If Franchises S and L are mutually exclusive, accept S because NPVs > NPVL.
If S & L are independent, accept both; NPV > 0.
NPV is dependent on cost of capital.
15
Internal Rate of Return: IRR
0 1 2 3
CF0 CF1 CF2 CF3
Cost Inflows
IRR is the discount rate that forcesPV inflows = cost. This is the sameas forcing NPV = 0.
16
NPV: Enter r, Solve for NPV
= NPV ΣN
t = 0
CFt
(1 + r)t
17
IRR: Enter NPV = 0, Solve for IRR
= 0 ΣN
t = 0
CFt
(1 + IRR)t
IRR is an estimate of the project’s rate of return, so it is comparable to the YTM on a bond.
18
What’s Franchise L’s IRR?
10 8060
0 1 2 3IRR = ?
-100.00
PV3
PV2
PV1
0 = NPV Enter CFs, then press IRR: IRRL = 18.13%. IRRS = 23.56%.
19
Rationale for the IRR Method If IRR > WACC, then the project’s
rate of return is greater than its cost-- some return is left over to boost stockholders’ returns.
Example:WACC = 10%, IRR = 15%.
So this project adds extra return to shareholders.
20
Decisions on Franchises S and L per IRR
If S and L are independent, accept both: IRRS > r and IRRL > r.
If S and L are mutually exclusive, accept S because IRRS > IRRL.
IRR is not dependent on the cost of capital used.
r > IRRand NPV < 0.
Reject.
NPV ($)
r (%)IRR
IRR > rand NPV > 0
Accept.
NPV and IRR: No conflict for independent projects.
22
Reinvestment Rate Assumptions
NPV assumes reinvest at r (opportunity cost of capital).
IRR assumes reinvest at IRR. Reinvest at opportunity cost, r, is
more realistic, so NPV method is best. NPV should be used to choose between mutually exclusive projects.
23
Modified Internal Rate of Return (MIRR)
MIRR is the discount rate that causes the PV of a project’s terminal value (TV) to equal the PV of costs.
TV is found by compounding all inflows at WACC.
Thus, MIRR assumes cash inflows are reinvested at WACC.
24
10.0 80.060.0
0 1 2 310%
66.0 12.1
158.1
-100.010%
10%
TV inflows
-100.0PV outflows
MIRR for Franchise L: First, Find PV and TV (r = 10%)
25
MIRR = 16.5% 158.1
0 1 2 3
-100.0
TV inflowsPV outflows
MIRRL = 16.5%
$100 =
$158.1(1+MIRRL)3
Second, Find Discount Rate that Equates PV and TV
26
BAII: Step 1, Find PV of Inflows First, enter cash inflows in CF register:
CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80
Second, enter I = 10.
Third, find PV of inflows:Press NPV = 118.78
27
Step 2, Find TV of Inflows
Enter PV = -118.78, N = 3, I/YR = 10, PMT = 0.
Press FV = 158.10 = FV of inflows.
28
Step 3, Find PV of Outflows
For this problem, there is only one outflow, CF0 = -100, so the PV of outflows is -100.
For other problems there may be negative cash flows for several years, and you must find the present value for all negative cash flows.
29
Step 4, Find “IRR” of TV of Inflows and PV of Outflows
Enter FV = 158.10, PV = -100, PMT = 0, N = 3.
Press I/YR = 16.50% = MIRR.
30
Why use MIRR versus IRR?
MIRR correctly assumes reinvestment at opportunity cost = WACC. MIRR also avoids the problem of multiple IRRs.
Managers like rate of return comparisons, and MIRR is better for this than IRR.
31
Apply NPV, IRR Assume a discount rate of 11%. Compute
the NPV, IRR and decide whether the project should be accepted or rejected.
Project
C0 C1 C2 C3 C4 C5
T=0 T=1 T=2 T=3 T=4 T=5
A -1000 400 400 400 500 500
Verify that NPV = 603.58, IRR = 31.79%,
Since NPV>0, IRR>11%, accept the project
32
Conceptual problem: NPV and IRR Consider a project with an initial outflow at
time 0 and positive cash flows in all subsequent years. As the discount rate is decreased the _____________.
A. IRR remains constant while the NPV increases.B. IRR decreases while the NPV remains constant.C. IRR increases while the NPV remains constant.D. IRR remains constant while the NPV decreases.E. IRR decreases while the NPV decreases.
33
Computational problem: NPV and IRR
You are attempting to reconstruct a project analysis of a co-worker who was fired. You have found the following information:
The IRR is 12%. The project life is 4 years. The initial cost is $20,000. In years 1, 3 and 4 you will receive cash
inflows of $6,000. You know there will be a cash flow in year 2,
but the amount is not in the file. The appropriate discount rate is 10%. What is the NPV of the project?
34
Condition 1: Cash inflows occur before cash outflows
Thus far, we have considered projects with normal cash flows, (i.e., a single cash outflow in year 0 followed by cash inflows in all future years).
With normal cash flows, IRR works fine. However, if you have cash inflow first,
followed by cash outflow, then IRR will be negative.
Result: You cannot use IRR to make the accept/reject decision.
Use NPV to get the correct decision.
35
Condition 2: Cash flows change signs more than once
Consider the following project cash flows: t = 0, -$400, t = 1, $2,500, t = 2, -$3,000. Suppose that the company’s cost of capital is 70 percent.
NPV = $32.53. The project is, acceptable. There are two IRR’s for this project: 61.98%,
363%. Look at the NPV profile (next slide). When there are multiple IRRs, the IRR
method loses meaning and is NOT appropriate.
However, the NPV method still gives the correct accept/reject decision.
36
What is the payback period?
The number of years required to recover a project’s cost,
or how long does it take to get the business’s money back?
37
Payback for Franchise L
10 8060
0 1 2 3
-100
=
CFt
Cumulative -100 -90 -30 50
PaybackL 2 + $30/$80 = 2.375 years
0
2.4
38
Payback for Franchise S
70 2050
0 1 2 3
-100CFt
Cumulative -100 -30 20 40
PaybackS 1 + $30/$50 = 1.6 years
0
1.6
=
39
Applying the PBP criterion
Compute the payback periods for the following two projects.
Project C0 C1 C2 C3 C4 C5
A -9000 2000 3000 4000 5000 6000
B -11000 2000 3000 4000 5000 6000
Verify that PBP for A = 3 years, PBP for B = 3.4 years (assume cash flows occur evenly throughout the year)
40
NPV + PBP Problem Bantam Industries is considering a project
which has the following cash flows:Year Cash flow
0 ? 1 $2,000 2 $3,000 3 $3,000 4 $1,500
The project has a payback period of 2 years. The firm's cost of capital is 12%.
What is the project's net present value?Verify that NPV = 2,265.91
41
Strengths and Weaknesses of Payback Strengths:
Provides an indication of a project’s risk.
Easy to calculate and understand. Weaknesses:
Ignores the TVM. Ignores CFs occurring after the
payback period.
42
PBP does not consider cash flows after the critical number
Project C0 C1 C2 C3
A -1000 500 510 10
B -1000 0 0 99,000,000
A firm uses two years as the critical number for the payback period.
This firm is faced with two projects whose cash flows are:
According to the payback rule, project A will be accepted and B will be rejected.
But, if you consider all cash flows, including those after 2 years, then project B is more attractive.
43
10 8060
0 1 2 3
CFt
Cumulative -100 -90.91 -41.32 18.79
Discountedpayback 2 + $41.32/$60.11 = 2.7 yrs
PVCFt -100
-100
10%
9.09 49.59 60.11
=
Recover investment + capital costs in 2.7 yrs.
Discounted Payback: Uses Discounted CFs
44
Example of discounted payback period criterion Example: Suppose that the discount rate is 10
percent. Project A has the following cash flows and discounted cash flows. Find A’s discounted PBP.
Project A C0 C1 C2 C3
Cash flow -9000 3000 6000 9000
Discounted cash flow 2727 4959 6762
Verify that discounted payback period = 2.194 years
45
Normal vs. Nonnormal Cash Flows Normal Cash Flow Project:
Cost (negative CF) followed by a series of positive cash inflows.
One change of signs. Nonnormal Cash Flow Project:
Two or more changes of signs. Most common: Cost (negative CF), then
string of positive CFs, then cost to close project.
For example, nuclear power plant or strip mine.
46
0 1 2
-800,000 5,000,000 -5,000,000
PV outflows @ 10% = -4,932,231.40.
TV inflows @ 10% = 5,500,000.00.
MIRR = 5.6%
When There are Nonnormal CFs and More than One IRR, Use MIRR
47
If the two projects have different lifespan, then…
48
S and L are Mutually Exclusive, r = 10%
0 1 2 3 4
S: -100
L: -100
60
33.5
60
33.5 33.5 33.5
Note: CFs shown in $ Thousands
49
NPVL > NPVS, but is L better?
S LCF0 -100 -100
CF1 60 33.5
NJ 2 4
I/YR 10 10
NPV 4.132 6.190
50
Method 1:mPut Projects on Common Basis Note that Franchise S could be
repeated after 2 years to generate additional profits.
Use replacement chain to put on common life.
51
Replacement Chain Approach (000s)Franchise S with Replication
NPV = $7.547.
0 1 2 3 4
S: -100 60 -100 60
60-100 -40
6060
6060
52
Method 2:Equivalent annual series (EAS) or Equivalent Annual Annuity (EAA)
When projects are mutually exclusive but have unequal lives
a. We construct the equivalent annual series (EAS) of each project and
b. We choose the project with the highest EAS A project’s EAS is the payment on an
annuity whose life is the same as that of the project and whose present value, using the discount rate of the project, is equal to the project’s NPV.
53
Equivalent Annual Annuity Approach (EAA) Convert the PV into a stream of
annuity payments with the same PV.
S: N=2, I/YR=10, PV=-4.132, FV = 0. Solve for PMT = EAAS = $2.38.
L: N=4, I/YR=10, PV=-6.190, FV = 0. Solve for PMT = EAAL = $1.95.
S has higher EAA, so it is a better project.
54
Calculating EAS
Consider Projects J & K, with the following cash flows. The discount rate is 10%.
Project C0 C1 C2 C3 C4
J -12000 6000 6000 6000
K -18000 7000 7000 7000 7000
55
EAS for Project J To compute Project J’s EAS, do the following: Compute Project J’s NPV
• Verify that NPV(J) = $2,921.11 Find the payment on the 3-year (life of project J)
annuity whose PV is equal to $2,921.11. Enter the following values:N=3, I/Y=10, PV=-2921.11, FV=0, Then CPT, PMT.PMT = 1,174.62, which is Project J’s EAS. So, finding EAS is nothing more than finding the
payment of an annuity.
56
EAS for Project K Verify that Project K’s NPV= $4,189.06 Find the payment on the 4-year (life of
project K) annuity whose PV is equal to $ 4,189.06.
Enter the following values:N=4, I/Y=10, PV=- 4,189.06, FV=0, Then CPT,
PMT.PMT = 1,321.53, which is Project K’s EAS. Recall that Project J’s EAS=1174.62 So, choose Project K since it has the higher
EAS.
57
Another application of EAA
We can use the EAA concept to choose between two machines that do the same job but have different costs and lives.
Consider the following problem.
58
Problem Suppose that your firm is trying to
decide between two machines, that will do the same job. Machine A costs $90,000, will last for ten years and will require operating costs of $5,000 per year. At the end of ten years it will be scrapped for $10,000. Machine B costs $60,000, will last for seven years and will require operating costs of $6,000 per year. At the end of seven years it will be scrapped for $5,000. Which is a better machine? (discount rate is 10 percent)
59
Step 1: compute the PV of the costs of each machine
PV of costs (A) = $90,000 + PV of $5,000 annuity for ten
years - PV of the scrap (at t = 10) value of $10,000
= 90000 + 30722.84 – 3855.43 = $116,867.41
PV of costs (B)= $60,000 + PV of $6,000 annuity for seven
years - PV of the scrap (at t = 7) value of $5,000
= $60,000 + $29,210.51 - $2,565.79 =$86,644.72
60
Step 2: compute equivalent annual cost (EAC) series of each machine
The equivalent annual cost series is the payment of an annuity that has the same present value as the PV of the machine’s cost.
EAC of machine A, EAC(A): N = 10, I/Y = 10, PV = -116867.41, FV = 0. Then
CPT, PMT. This yields EAC(A) = $19,019.63. EAC of machine B, EAC(B): N = 7, I/Y = 10, PV = -86644.72, FV = 0. Then
CPT, PMT. This yields EAC(B) = $17,797.30. Choose machine B because it has the lower cost.
Homework Assignment
Problems: 1,2,3,4,5,6,7,9,11,13(a,b,c),16,17,21(a,b,c,d)
61