32
1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

Embed Size (px)

Citation preview

Page 1: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

1

Chapter 4

DISCOUNTING AND ALTERNATIVE INVESTMENT

CRITERIA

Page 2: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

2

Contents

• Discounting

• Alernative Investment Criteria

- Net Present Value Criteria

- Benefit-Cost Ratio Criteria

- Pay Back Period Criteria

- Internal Rate of Return Criteria

Page 3: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

3

1.1 Discounting and Compounding

• Same amount of money "today" and "in future" do not have the same value.

• Finding the “today” value of a future amount is DISCOUNTING.

• Finding the “future” value a current amount is COMPOUNDING.

Page 4: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

4

1.1 Discounting and Compounding(cont’d)

An investment of $1, with a discount rate = r

Value Value Present After One Year Present After n-Years B/(1+r) B B/(1+r)n B

r is the discount rate 1/(1+r) is the discount factor (1+r) is the compound factor

Ex: Present value of 250$ for 10 years at 6% discount rate 4PV = $250/ (1+0.06)10

PV = $250/ 1.79= $139.6 or $250* 1/(1+0.06)10 = 139.6

Page 5: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

5

Example of Discounting

Year 0 1 2 3 4

Net Cash Flow -1000 200 300 350 1440

25.676)1.1(

1440

)1.1(

350

)1.1(

300

1.1

2001000NPV

4320

1.0

88.743)1.1(

1440

)1.1(

350

1.1

300200)1.1(1000NPV

321

1.0

26.818)1.1(

1440

)1.1(

350300)1.1(200)1.1(1000NPV

2122

1.0

Page 6: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

6

1.1Discounting and Compounding(cont’d)

• Discounting Net Benefits

- the period (number of years)

- the size of the discount (r)

NPVr0= (B0-C0)/(1+r)0 + (B1-C1)/(1+r)1 +---+

(Bn-Cn)/(1+r)n

Page 7: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

7

1.1Discounting and Compounding(cont’d)

In ranking projects, the particular point in time to which all the net benefits in each period are discounted does not matter.

Instead of discounting all the net benefit flows to the initial year (year 0), they can be dicounted to year “k” NPV at year k will be a constant multiple of NPV in year 0. It will be multiplied with (1+r). This will not change the ranks of the projects, as all projects’ NPVs in year 0 will be multiplied with the same constant (1+r).

Page 8: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

8

Items Year 0 1 2 3 4 5

1. Benefits 3247 4571 3525 2339

2. Costs 5000 2121 1000 1000 1000 1000

3. Net Benefits -5000 -2121 +2247 +3571 +2525 +1339

4. Discount Factor at 6% 1.000 0.943 0.890 0.840 0.792 0.747

5. Net Present value = 1000 -5000 -2000 +2000 +3000 +2000 +1000

2)06.01(

1

4)06.01(

2525

Table 4-1. Calculating the present value

of net benefits from an investment project

1)06.01(

1

Page 9: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

9

1.2 Variable Discount Rate

• Discount rates may vary through time.

• Funds may be very scarce at the beginning of the project and the discount rates may be very high.

• This will fall in the following years as the supply and demand for funds return to normal

Page 10: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

10

1.2 Variable Discount Rates

• Adjustment of Cost of Funds Through Time

0 1 2 3 4 5

r0r1r2r3

r4r5

r *4

r *3

r *2

r *1

r *0

If funds currently are abnormally scarce

Normal or historical average cost of funds

If funds currently are abnormally abundant

Years from present period

1/(1+r1), 1/[(1+r1)(1+r2)] & 1/[(1+r1)(1+r2)(1+r3)]

•For variable discount rates r1, r2, & r3 in years 1, 2, and 3, the discount factors

are, respectively, as follows:

Page 11: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

11

1.3 Factors Affecting the Discount Rates for Public Projects

• Discount rate for a private investment is the weighted average of:– Rate of return from the sale of equity– The cost of borrowed funds Discount rate for a public sector investment is the

Economic Opportunity Cost of Capital (EOCK). This rate reflects the opportunity forgone for not using the funds in an alternative public project. It considers the lost opportunity for the whole economy. It reflects the true cost of the resources (funds) used.

EOCK is taken as 12% by the World Bank for developing countries.

Page 12: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

12

1.3 Factors Affecting the Discount Rates for Public Projects (con’t)

• If significant market distortions exits i.e. domestic distortions (taxes and subsidies), and external distortions (tariffs and subsidies for exports), the market price of inputs and outputs of the projects do not reflect the true costs of the resources. Their economic (shadow) prices should be used in public projects.

• For public sector projects, economic analysis (rather than financial analysis) is more relevant. Economic analysis uses the EOCK (rather than the discount rate) and the economic values (rather than the market prices).

Page 13: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

13

1.3 Factors Affecting the Discount Rates for Public Projects (con’t)

Financial Analysis Economic Analysis

* Financial discount rates * EOCK

* Market prices * Economic values

* More relevant to private sector * More rel. to public sector

* Owner’s and banker’s point of view * Economy point of view

Page 14: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

14

2. Alternative Investment Criteria

First Criterion: Net Present Value (NPV)• What does net present value mean?• Measures change in wealth• Use as a decision criterion to answer following:

a. When to reject projects?

b. Select project (s) under a budget constraint?

c. Compare mutually exclusive projects?

Page 15: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

15

2.1 Net Present Value Criterion

a. When to Reject Projects?Rule: “Do not accept any project unless it generates a

positive net present value when discounted by the opportunity cost of funds”

Examples:Project A: Present Value Costs $1 million, NPV + $70,000Project B: Present Value Costs $5 million, NPV - $50,000Project C: Present Value Costs $2 million, NPV + $100,000Project D: Present Value Costs $3 million, NPV - $25,000Result:

Only projects A and C are acceptable. The country is made worse off if projects B and D are undertaken.

Page 16: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

16

2.1 Net Present Value Criterion (Cont’d)

b. When You Have a Budget Constraint?Rule: “Within the limit of a fixed budget, choose that subset of the

available projects which maximizes the net present value”Example:If budget constraint is $4 million and 4 projects with positive NPV:Project E: Costs $1 million, NPV + $60,000Project F: Costs $3 million, NPV + $400,000Project G: Costs $2 million, NPV + $150,000Project H: Costs $2 million, NPV + $225,000Result: Combinations FG and FH are impossible, as they cost too much. EG

and EH are within the budget, but are dominated by the combination EF, which has a total NPV of $460,000. GH is also possible, but its NPV of $375,000 is not as high as EF.

Page 17: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

17

2.1 Net Present Value Criterion (Cont’d)

c. When You Need to Compare Mutually Exclusive Projects?

Rule: “In a situation where there is no budget constraint but a project must be chosen from mutually exclusive alternatives, we should always choose the alternative that generates the largest net present value”

Example:Assume that we must make a choice between the following three mutually exclusive projects:

Project I: PV costs $1.0 million, NPV $300,000Project J: PV costs $4.0 million, NPV $700,000Projects K: PV costs $1.5 million, NPV $600,000Result:Projects J should be chosen because it has the largest NPV.

Page 18: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

18

2.1 Net Present Value Criterion (Cont’d)

Constraints of Using NPV• NPV, not only tells you whether the project will be

accepted or rejected but also gives you the present value of the surplus or the deficit of the project. This is an advantage for NPV.

• If the life periods of the strickly alternative projects are not the same, adjustments have to be made, so that the projects will be compared for the same lenght of lives.

• It is not correct to compare the NPV of a gas turbine plant with a life of 10 years, to a coal plant with a life of 30 years. Their lenght of lives should be equated by repeating the gas plant for three times.

Page 19: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

19

It is a widely used by the analysts. Should be very careful,

otherwise incorrect and misleading decisions can be made.Benefit-Cost Ratio (R) = Present Value Benefits/Present

Value CostsBasic rule: If benefit-cost ratio (R) >1, then the project should be undertaken.Problems?Sometimes it is not possible to rank projects with the Benefit-Cost

Ratio• Mutually exclusive projects of different sizes• Mutually exclusive projects and recurrent costs subtracted out of

benefits or benefits reported gross of operating costs• Not necessarily true that RA>RB that project “A” is better

2.2 Benefit-Cost Ratio

Page 20: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

20

2.2 Benefit-Cost Ratio (Cont’d)First Problem:

The Benefit-Cost Ratio Does Not Adjust for Mutually Exclusive Projects of Different Sizes.

For example:Project A: PV0of Costs = $5.0 M, PV0 of Benefits = $7.0 M

NPVA = $2.0 M RA = 7/5 = 1.4

Project B: PV0 of Costs = $20.0 M, PV0 of Benefits = $24.0 M

NPVB = $4.0 M RB = 24/20 = 1.2

According to the Benefit-Cost Ratio criterion, project A should be chosen over project B because RA>RB, but the NPV of project B is greater than the NPV of project A.

So, project B should be chosen

Page 21: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

21

2.2. Benefit-Cost Ratio (Cont’d)Second Problem:

The Benefit-Cost Ratio Does Not Adjust for Mutually Exclusive Projects where the Costs are treated in different ways.

Project A Project BPV of gross benefits 2,000 2,000PV of operating Costs 500 1,800PV of capital costs 1,200 100

1. B/C Ratio (Operating costs netted out of the benefits) RA = (2000-500)/1200 = 1.15 RB = (2000-1800)/100 = 2.0Project B is preferred to Project A (RB > RA ).

2. B/C Ratio (Operating costs added to capital costs) RA = 2000/(1200+500)= 1.18 RB = 2000/(1800+100) = 1.05 Project A is preferred to Project B (RA > RB ).

NPV of a project is not sensetive to the way the acountants treat costs. Thus NPV is far more reliable than B/C ratio as a criterion for project selection.

Conclusion: The Benefit-Cost Ratio CANNOT be used to rank projects

Page 22: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

22

2.3 Pay-Out or Pay-Back Period It is widely used criterion as it is very easy to apply.

Unfortunately it can give misleading results especially in cases of investment with a long life.

In a simplest form, it measures the number of years it will take for the undiscounted net benefits (positive net cash flow) to repay the investment. If the number is greater than an arbitrary chosen year, the project is accepted.

In more sophisticated form, it divides the discounted net benefits over a given year with the discounted investment costs. If the number is greater than 1, the project is accepted. One assumes that after the chosen net benefits are so uncertain (war and political inability) that they can be neglected. This assumption is not realistic in cases of bridges and roads, etc.

Page 23: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

23

2.3 Pay-Out or Pay-Back Period

• Project with shortest payback period is preferred

by this criteria

There is no reason to expect that quick yielding projects are superior to long term invetments.

Page 24: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

24

Figure 4.2 Comparison of Two Projects With Differing Lives Using Pay-Out Period Criterion

Bt - CtBa

Bb

ta

tb

Ca = Cb Payout period for project a

Payout period for project b

0

Time

Page 25: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

25

2.3 Pay-Out or Pay-Back Period (Cont’d)

• In such situations pay-back period criterion gives

wrong recommendation for choice among

investments.

• Assumes all benefits that are produced by in longer

life project have an expected value of zero after the

pay-out period.

• The criteria may be useful when project subject to

high level of political risk.

Page 26: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

26

2.4 Internal Rate of Return Criterion

• IRR is the discount rate (K) at which the present value of benefits are just equal to the present value of costs for the particular project.....(IRR= k) wkich equates the net benefits tı zero.

• NPVr 0 = 0 = (B0 - C0 ) + (B1 – C1 )/((1+k)1 + (B2 – C2 ) / (1+k)2

Bt - Ct

(1 + K)t

Note: the IRR is a mathematical concept, not an economic or financial criterion

Common uses of IRR:

(a). If the IRR is larger than the cost of funds then the project should be undertaken

(b). Often the IRR is used to rank mutually exclusive projects. The highest IRR project should be chosen

• An advantage of the IRR is that it only uses information from the project• Another advantage of IRR is that it does not require the calculation of EOCK. With

NPV one has to calculate the EOCK in the economic analysis.

t

i=0= 0

Page 27: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

27

2.4 Difficulties With the Internal Rate of Return Criterion

First Difficulty: Multiple rates of return for project

Solution 1: K = 100%; NPV= -100 + 300/(1+1) + -200/(1+1)2 = 0

Solution 2: K = 0%; NPV= -100+300/(1+0)+-200/(1+0)2 = 0

+300

Bt - Ct

-200-100

Time

Page 28: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

28

1. For Single Projects If the net cash flow is negative in the initial year

(due to initial investment) but all positive in the following years, then IRR has a unique solution i.e. One solution

If negative net cash flows take place after the negative net cash flow in intial year, we cannot have a unique solution for the IRR. You will have two values for IRR (figure 4.3)

If there is a large negative benefit in the final year of the project, there will not be a unique solution for IRR again.

2.4.1 Difficulties With the Internal Rate of Return Criterion

(IRR Makes Misleading Choice under following conditions)

Page 29: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

29

Figure 4.3 Time Profiles of the Incremental Net Cash Flows for Various Types of Projects

+

-

Bt - Ct

+

-

Bt - Ct

time

time

Page 30: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

30

Second difficulty: Projects of different sizes and also strict alternatives

Year 0 1 2 3 ... ... ҐProject A -2,000 +600 +600 +600 +600 +600 +600

Project B -20,000 +4,000 +4,000 +4,000 +4,000 +4,000 +4,000

NPV and IRR provide different Conclusions:Opportunity cost of funds = 10%

NPV : 600/0.10 - 2,000 = 6,000 - 2,000 = 4,000

NPV : 4,000/0.10 - 20,000 = 40,000 - 20,000 = 20,000

Hence, NPV > NPV

IRRA : 600/K A - 2,000 = 0 or K A = 0.30

IRRB : 4,000/K B - 20,000 = 0 or K B = 0.20

Hence, K A>KB

0B

0A

0B

0A

2.4.2 Difficulties With The Internal Rate of Return Criterion (Cont’d)

Page 31: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

31

2.4.3 Difficulties With The Internal Rate of Return Criterion (Cont’d)

Third difficulty:Projects of different lengths of life and strict alternatives

Opportunity cost of funds = 8%Project A: Investment costs = 1,000 in year 0

Benefits = 3,200 in year 5

Project B: Investment costs = 1,000 in year 0

Benefits = 5,200 in year 10

NPV : -1,000 + 3,200/(1.08) 5 = 1,177.86

NPV : -1,000 + 5,200/(1.08)10= 1,408.60

Hence, NPV > NPV

IRRA : -1,000 + 3,200/(1+KA)5 = 0 which implies that KA = 0.262

IRRB : -1,000 + 5,200/(1+KB)10 = 0 which implies that KB = 0.179

Hence, KA>KB

0B

0A

0B

0A

Page 32: 1 Chapter 4 DISCOUNTING AND ALTERNATIVE INVESTMENT CRITERIA

32

Fourth difficulty: Same project but started at different times

Project A: Investment costs = 1,000 in year 0

Benefits = 1,500 in year 1

Project B: Investment costs = 1,000 in year 5

Benefits = 1,600 in year 6

NPV A : -1,000 + 1,500/(1.08) = 388.88

NPV B : -1,000/(1.08) 5 + 1,600/(1.08) 6 = 327.68

Hence, NPV > NPV

IRR A : -1,000 + 1,500/(1+K A) = 0 which implies that KA= 0.5

IRRB : -1,000/(1+K B) 5 + 1,600/(1+K B) 6 = 0 which implies that KB = 0.6

Hence, K B >KA

0B

0A

2.4.4 Difficulties With The Internal Rate of Return Criterion (Cont’d)