1
Computer Systems Upgrade
Lindh, Lopez, and Williams
2
Status Summary
Conversion underway.Currently awaiting
computers for Sales/Mktg, two weeks overde.
Completion by year end, if last shipment of computers arrives on time.
3
Upgrade Completed
TelemarketingManagementShippingMail Room
4
Upgrade Underway
Client ServicesProductionQuality
AssuranceCatalog
5
Upgrade Pending
SalesMarketing
6
Attention Areas
Computers for Sales/Mktg are late in arriving.
Expansion of the Sales/Mktg area is still not completed.
7
More Areas Needing Attention
Rewiring wrong in Production department.
Additional labor to complete upgrade on time.
Upgrade cannot disrupt client service.
Training must be scheduled; contact.
8
Schedule
All departments upgraded by 10/16–Except Sales/Mktg
(11/20)Training begins
10/21–Call Barb x2132
Sales/Marketing training complete by 12/15
9
Areas Over Budget
Sales/Mktg upgrade
IS department overtime
Extra training sessions
10
Areas Under Budget
WiringNetwork server
systems Some software
upgrdes
11
Problems Resolved
Last week’s Internet outages solved
Email spam/virus detectors installed
Additional training weeks scheduled
12
Status By Monday On:
Computer shipments
Wiring installation
Sales/Mktg carpentry
IS Department overtime
13
Status Also Needed For:
Cost for temp workers
Departments completing upgrade
Training schedules