1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

Embed Size (px)

Citation preview

Page 1: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

1

International Construction Arbitration

John SavagePartner and Head of International Arbitration, Asia

December 13, 2007

Page 2: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

2

Outline of the Presentation

I. Introduction to International Construction Arbitration

II. Issues that Cause International Construction Disputes

III. Typical International Construction Claims

IV. Common Mechanisms for Resolving International Construction Disputes

V. Introduction to FIDIC and its Dispute Resolution Provisions

VI. Conduct of a Typical International Arbitration

VII. Investment Treaty Arbitration and Construction Disputes

VIII. Advice on Drafting International Construction Dispute Resolution Provisions

IX. Advice on Preparing for and Conducting International Construction Disputes

Page 3: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

3

I. Introduction to International Construction Arbitration (1)

Typical Features of International Construction Disputes (1)

• Technically complex, fact intensive: require technical experts as well as lawyers

• Often more than two parties, even in turnkey projects (involvement of subcontractors, suppliers, lenders, consultants, other contractors etc)

• Often more than one relevant contract (subcontracts, supply contracts, construction of other facilities on same project, offtake contracts, operation and maintenance etc)

• Parties of (sometimes many) different nationalities on the same job

• Site may be in another country altogether

Page 4: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

4

Typical Features of International Construction Disputes (2)

• Large sums in dispute, at least in absolute terms

• Project usually of long duration, with disputes emerging throughout

• English law often applies, or at least contracts often inspired by English law

• Use of standard form contracts (e.g. FIDIC contracts)

• Not a separate area of law, in English law at least (general contract and tort law apply in most cases), but specialised lawyers, judges and arbitrators in practice

I. Introduction to International Construction Arbitration (2)

Page 5: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

5

• Alleged interference by or deficiencies of Owner, such as:

− Lack of site possession

− Late approvals or instructions

− Changes in design/materials/specification

− Non payment

• Alleged deficiencies of Contractor, such as:

− Contractor design omissions and deficiencies

− Defective manufacture and construction

− Delayed performance (various causes attributable to contractor)

− Excessive cost, when contract price not fixed

II. Issues that Cause International Construction Disputes (1)

Page 6: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

6

• Third party events, such as:

−Adverse site conditions

−Adverse weather

−Material escalation

−Hostilities/strikes

−Changes in law

II. Issues that Cause International Construction Disputes (2)

Page 7: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

7

• Contractor usually claims one or more of the following:

− Compensation for extra work performed

− Compensation and/or schedule relief for acceleration, delay and/or disruption

− Payment and interest

− Blocking draw of performance bond

III. Typical International Construction Claims (1)

Page 8: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

8

• Owner usually claims one or more of the following:

− Damages (usually liquidated) for delay, or for poor performance (plant not at specification)

− Correction or compensation for defective work (under warranties)

− Draw on performance bond

III. Typical International Construction Claims (2)

Page 9: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

9

Non Binding Dispute Resolution Mechanisms

• Mediation

• Early Neutral Evaluation

Temporarily Binding Dispute Resolution Mechanisms

• Statutory Adjudication

• Dispute Boards

• Expert Determination (but can be final…?)

Binding Dispute Resolution Forms

• Arbitration

• Court Litigation

IV. Common Mechanisms for Resolving International Construction Disputes (1)

Page 10: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

10

Mediation (not binding)

− Process conducted by third party mediator

− Confidential

− Without prejudice

− Objective is to facilitate settlement of dispute by parties, not an evaluation

− Can be effective if parties committed to process, attendees have power to settle, and if mediator competent

IV. Common Mechanisms for Resolving International Construction Disputes (2)

Page 11: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

11

• Early Neutral Evaluation (not binding)

− An independent third party will give an evaluation of the dispute, like a one person Dispute Review Board

− Parties will then have a predetermined period of time for follow-up direct negotiation with the goal of reaching settlement

IV. Common Mechanisms for Resolving International Construction Disputes (3)

Page 12: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

12

• Statutory Adjudication (temporarily binding)

− Most important dispute resolution process in UK construction industry due to 1996 Construction Act

− The Act makes adjudication mandatory for an agreement which involves “construction operations” in England, Wales or Scotland

− Party can apply for adjudication “at any time”. Rapid procedure before an individual or a board, but must meet statutory conditions. Temporarily binding decision

− Speedy but needs a court system to enforce adjudication decisions

− Legislation has been adopted elsewhere, mainly in Commonwealth jurisdictions such as Australia, New Zealand, Singapore, Hong Kong

− Parties to international projects need to be aware that legislation may exist

IV. Common Mechanisms for Resolving International Construction Disputes (4)

Page 13: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

13

• Dispute Boards (temporarily binding)

− Procedure where a standing panel of 1 or 3 engineers/lawyers appointed at the outset of project, and visit the site 3 or 4 times a year to monitor progress and deal with potential problems

− When requested by the parties the Dispute Board conducts an informal hearing of the dispute and issues a recommendation or decision (depending on the contract). Decision temporarily binding, but can be challenged through arbitration or litigation

− FIDIC and ICC have their own Dispute Board procedures

IV. Common Mechanisms for Resolving International Construction Disputes (5)

Page 14: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

14

• Expert Determination (1) (temporarily binding?)

A third party with expertise in a particular field is asked to give a determination on a disputed issue in that field

− Generally used for a single issue or a handful of related issues, not a whole dispute

− Either technical, financial or contractual issues

− Flexible procedures, query if due process required

− Parties can choose to use ICC Rules for Expertise in their contract

− ICC International Centre for Expertise can administer the expert determination or act as appointing authority for the expert

IV. Common Mechanisms for Resolving International Construction Disputes (6)

Page 15: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

15

• Expert Determination (2) (temporarily binding?)

Difficulties with expert determination:

− Finality/recourse (is it an arbitral award capable of challenge?)

− Which dispute resolved by expert, which by arbitrators

− What to do with legal questions brought before expert

− Flexibility/vagueness of procedures

− Enforcement

IV. Common Mechanisms for Resolving International Construction Disputes (7)

Page 16: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

16

• Arbitration (1) (binding)

− Most international construction contracts specify arbitration as final resort if interim dispute resolution measures fail

− Arbitration generally preferred over court litigation (see later slides)

− Larger disputes usually involve 3 member tribunal

− Common to have use of tiered dispute resolution clauses, e.g. negotiation then arbitration, dispute board then arbitration etc.

IV. Common Mechanisms for Resolving International Construction Disputes (8)

Page 17: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

17

• Arbitration (2) (binding)

No institutions specialised in construction cases. Instead, we recommend usual top international arbitration institutions, such as:

− International Chamber of Commerce (ICC)

− London Court of International Arbitration (LCIA)

− Singapore International Arbitration Centre (SIAC)

− Hong Kong International Arbitration Centre (HKIAC)

− Beijing Arbitration Commission (BAC) or CIETAC for arbitration in China

(Note: leading institutions’ arbitration rules are largely similar)

IV. Common Mechanisms for Resolving International Construction Disputes (9)

Page 18: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

18

• Court litigation (binding)

− usually in the country of one or other party (not neutral)

− usually subject to one or more levels of appeal

− cost and duration can vary enormously from country to country

IV. Common Mechanisms for Resolving International Construction Disputes (10)

Page 19: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

19

• Neutrality: avoid home courts of other party

• Enforceability: arbitral awards much more enforceable across borders than court judgments, thanks to New York Convention

• Flexibility: parties can design, in their contract, their own dispute resolution mechanism

• Finality: no court or other review of the merits of an arbitral award

• Cost and time savings? As compared to which courts?

• Confidentiality?

Advantages of international arbitration over court litigation for internationaldisputes?

IV. Common Mechanisms for Resolving International Construction Disputes (11)

Page 20: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

20

Advantages of court litigation over international arbitration?

Joinder or consolidation available before courts without further party consent No 50-50 decisions in court. Perhaps, but is that what happens today in

arbitration? Lack of finality (review of merits available)? Courts can be less expensive and time-consuming? In Singapore, yes, but not

in India, for example

IV. Common Mechanisms for Resolving International Construction Disputes (12)

Page 21: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

21

What if we don’t include an arbitration clause in our contract?

• No arbitration clause in contract usually = no arbitration.

• But exceptions include:

− where parties agree to arbitration when dispute arises (rare)

− where party has grievance against state or state body, and there is investment treaty coverage (investment treaties usually allow arbitration without prior arbitration clause)

• Alternative to arbitration is either selection in contract of court(s) or, if no selection, court with jurisdiction by default

IV. Common Mechanisms for Resolving International Construction Disputes (13)

Page 22: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

22

What is FIDIC?

• FIDIC stands for Fédération Internationale des Ingénieurs-Conseils or International Federation of Consulting Engineers

• Formed in 1913, now a global organisation with members from 70 plus countries and secretariat based in Switzerland

• FIDIC Forms of Contract are widely used forms (i.e. model contracts) for engineering, construction, provision of mechanical and electrical works in international projects

• FIDIC introduced the concept of Dispute Board into its Orange Book contract in 1995

• In November 1996 FIDIC introduced the procedure into Clause 67 of its Red Book

V. Introduction to FIDIC and its Dispute Resolution Provisions (1)

Page 23: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

23

• In 1999, FIDIC revised its Forms of Contract

• The four FIDIC Forms of Contract are:

− Conditions of Contract for Construction (New Red Book)

− Conditions of Contract for Plant and Design-Build (New Yellow Book)

− Conditions of Contract for EPC Turnkey Projects (Silver Book)

− Short Form of Contract (Green Book)

(Note that FIDIC will be launching its Design, Build and Operate (DBO) Contract (Gold Book) in mid 2008)

Note that these are just model contracts. The parties are expected to adapt them to their own projects

V. Introduction to FIDIC and its Dispute Resolution Provisions (2)

Page 24: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

24

• FIDIC Dispute Resolution provision is set out in Clause 20 of the New Red, New Yellow and Silver Books

• Approach used by FIDIC is the Dispute Adjudication Board (DAB) which issues a decision, as opposed to Dispute Review Board which issues a recommendation

• The FIDIC DAB provisions apply whenever a FIDIC contract is used unless parties delete the provision

• FIDIC DAB decisions are immediately binding and parties are obliged to comply with the decision pending other stages of the dispute resolution procedure, e.g. revised by amicable settlement or arbitral award

• New Red (Construction Contract) and New Yellow (Plant and Design-Build Contract) Books provide for Engineer to act as adjudicator and DAB. Silver Book (EPC Contract) has no Engineer, so disputes under Silver Book must be handled by DAB.

V. Introduction to FIDIC and its Dispute Resolution Provisions (3)

Page 25: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

25

FIDIC Procedure for Contractor’s Claims

28 day Notice of Claim to Engineer

42 day “Fully Detailed Claim”to Engineer

“Final Claim” 28 days after end of effects

42 days after receipt of claim Engineer’s Response

Clause 3.5 Engineer to“Agree or Determine”

Clause 20.1

Contractor’s Claims

Clause 3.5Determinations

28 day Notice of Claim to Employer

42 day “Fully Detailed Claim”to Employer

“Final Claim” 28 days after end of effects

42 days after receipt of claim Employer’s Response

Clause 3.5 Employer to“Agree or Determine”

Given effect unlessContractor’s Notice of Dissatisfaction

14 days of receipt

New Red/Yellow Books Silver Book

Agreement/Determination given effect unless revised under Clause 20

V. Introduction to FIDIC and its Dispute Resolution Provisions (4)

Page 26: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

26

FIDIC Procedure for Contractor’s Claims

Reference to Dispute Adjudication Board (DAB) (1 or 3 people)

DAB Decision within 84 days of reference

“Amicable Settlement” stage

ICC Arbitration within 56 days after Notice of Dissatisfaction

Clause 20.2

Clause 20.4

Clause 20.5

Clause 20.6

No Notice of Dissatisfaction within 28 days of Decision

Notice of Dissatisfactionwithin 28 days after 84 days of reference

No DAB Decision within 84 days of reference

Notice of Dissatisfaction within 28 days of Decision

DAB Decision final and binding

V. Introduction to FIDIC and its Dispute Resolution Provisions (5)

Page 27: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

27

FIDIC Procedure for Employer’s Claims New Red/Yellow Books Silver Book

Employer or Engineer gives notice and particulars to Contractor

Employer gives notice and particulars to Contractor

Clause 3.5 Engineer to “Agree or Determine”

Clause 3.5 Employer to “Agree or Determine”

Clause 2.5Employer’s Claims

Clause 3.5Determinations

Reference to Dispute Adjudication Board (DAB) (1 or 3 people)

“Amicable Settlement” stage

ICC Arbitration within 56 days after Notice of Dissatisfaction

Clause 20.5

Clause 20.6

Clauses 20.2 and 20.4 (See previous diagram for full Clause 20.4 procedure)

Agreement/Determination given effect unless revised

under Clause 20

Given effect unlessContractor’s Notice of Dissatisfaction

14 days of receipt

V. Introduction to FIDIC and its Dispute Resolution Provisions (6)

Page 28: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

28

• Procedural Rules for DAB are set out in Annex to Dispute Adjudication Agreement

• DAB shall visit site at intervals of not more than 140 days but not less than 70 days at request of either Employer or Contractor

• DAB to use site visits to become and remain acquainted with progress of the Works and actual/potential problems or claims

• DAB to produce a report after each site visit

• DAB may conduct hearings and request exchange of statements

• DAB can adopt an inquisitorial procedure and refuse admission to hearings or grant audience to any persons other than parties’ representatives

• DAB can open up, review and revise any certificate, decision, determination, instruction, opinion or valuation of the Engineer

V. Introduction to FIDIC and its Dispute Resolution Provisions (7)

Page 29: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

29

A Typical ICC Arbitration Procedure

Application forInterimRelief

Request forArbitration

Answer to Requestand Filing of

Counterclaims

HearingsPost-HearingSubmissions

Exchange of Written

Submissions

Constitution ofArbitral Tribunal

Terms of Referenceand Procedural

Timetable

Limited Discovery(Exchange ofDocuments)

Final Award & Costs Typical duration: 15-24 months

VI. Conduct of a Typical International Arbitration (1)

Page 30: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

30

Four phases of the typical international arbitration

• Introductory phase: exchange of outline initial submissions and constitution of tribunal.

• Written phase: exchange of longer written pleadings and evidence.

• Hearing phase: witness hearings and hearings of argument.

• Award phase: arbitrators deliberate and draft their award.

VI. Conduct of a Typical International Arbitration (2)

Page 31: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

31

General remarks about international arbitration procedure

• Often an international hybrid of common and civil law procedures.

• Examples: IBA guidelines on evidence and conflicts.

• More informal than courts (no wigs, advocates usually sit)…

• … but equally adversarial.

• Often fascinating and difficult cultural clashes (e.g. document production, preparation of witnesses…).

VI. Conduct of a Typical International Arbitration (3)

Page 32: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

32

International arbitration personnel

• Worldwide arbitration community/mafia. Centred in Europe, especially France, Switzerland and the UK. Paris probably still the headquarters of international arbitration (seat of the ICC). But now a growing pool of international arbitrators from Asia and based in Asia.

• Increasingly two groups: arbitrators (older, academics, barristers, and in boutique firms) and counsel (younger, in larger firms). The former often graduate from the latter. Some overlap between the two groups.

• Case for specialisation: arbitration procedures and personnel increasingly distinct from those of local courts. What you know and who you know are both important.

VI. Conduct of a Typical International Arbitration (4)

Page 33: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

33

• If the owner in an international construction project is a sovereign state instead of a private company, a contractor with a claim may be able to start investment treaty arbitration instead of following contractual dispute resolution procedures

• Or if state interferes with a contractor’s project with a private owner, contractor may still have a claim against the state under an investment treaty

• Typical claims under investment treaties are based on interference by the state in the project, including by action of the legislature, the courts, local government, tax authorities etc

• Investment treaty arbitration can be better than “normal” arbitration as it gives access to neutral, offshore proceedings, and international law remedies that may not be available under contract or in the courts

• Can be very powerful, especially as China has concluded over 100 BITs, with new (and effective) second generation treaties now replacing first generation (less effective) treaties

VII. Investment Treaty Arbitration and Construction Disputes (1)

Page 34: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

34

• An investment treaty is an agreement concluded by two or more states to promote and protect investment by investors of those states in the territory of other states party to the treaty. Example:

State XInvestment

TreatyChina

Chinese

Investor State X

Investment

Protection

and

Promotion

State X

Investor

Investment

Protection

and

Promotion

China

VII. Investment Treaty Arbitration and Construction Disputes (2)

Page 35: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

35

• BITs cover investments by an investor of one country in the territory of the other country

• “ Investor of a Contracting State” is usually defined to include:

− Individuals who are nationals of the State; and

− Companies organised under the laws of the State

• Indirectly controlled investments are often covered

• “Investment” is usually broadly defined to include any kind of asset, which can include any claim to money or to performance under contract

• So definition of covered investment is very wide, far beyond traditional conception

VII. Investment Treaty Arbitration and Construction Disputes (3)

Page 36: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

36

• Question – are construction projects considered an “investment” in the context of investment treaty arbitration?

• See Salini v Morocco (2001) – two Italian contractors filed for ICSID arbitration against Morocco over a dispute arising under a contract for construction of a highway. The contract provided for resolution of disputes in domestic courts. Claimants alleged that Morocco’s failure to pay was a violation of the “fair and equitable treatment and protection against indirect expropriation” in the Morocco-Italy BIT. Morocco raised jurisdictional objection that dispute was not in relation to investment under Art. 25(1) of ICSID Convention and Art 1 of the Morocco-Italy BIT.

• Held: Contract for construction of a highway was an investment under both treaties. Tribunal upheld jurisdiction over the investors' claims.

VII. Investment Treaty Arbitration and Construction Disputes (4)

Page 37: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

37

• See also R.F.C.C. v Morocco, Bayindir v Pakistan (both highway construction projects), Impregilo v Pakistan (construction of a dam) and Saipem v Bangladesh (pipeline construction project)

• In all cases, the construction projects were held to be investments covered by investment treaty in question and the ICSID Convention. The contractors could therefore all proceed with their claims in neutral, offshore international arbitration regardless of the dispute resolution provision in their contract

• So, if you have a dispute with a state or state agency, think about investment treaty arbitration even if you have an arbitration or litigation clause in your contract, or even if you have no contract

VII. Investment Treaty Arbitration and Construction Disputes (5)

Page 38: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

38

• Consider interim dispute resolution mechanism, as can be advantageous to contractors

• Final mechanism should be arbitration in most cases

• Resist temptation to overdraft, keep dispute resolution provisions simple: use model institutional clauses or standard form contracts (easily available online) as the basis

• Caution with carve-out clauses, e.g. sending some disputes to court/expert and the rest to arbitration

VIII. Advice on Drafting International Construction Dispute Resolution Provisions (1)

Page 39: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

39

• Resist temptation to limit pool of arbitrators, e.g. by requiring arbitrator to have esoteric experience

• Don’t forget the governing law clause; and if you are using a standard form contract, choose governing law that is compatible with the contract

• Consider consolidation/joinder for supplier/subcontractor contracts

• If consolidation/joinder impossible, try to get the dispute resolution clauses as similar as possible, e.g. same arbitration rules, governing law provisions

VIII. Advice on Drafting International Construction Dispute Resolution Provisions (2)

Page 40: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

40

• Ideally, make sure that dispute resolution clauses in performance bonds are identical with main contract dispute resolution provisions

• No language stating that contractor must wait until after completion before commencing final dispute resolution proceedings

• Ask for courts or (more realistically) arbitration in your home jurisdiction as a starting point

• Agree to an arbitration friendly place of arbitration if home jurisdiction not available, e.g. Hong Kong, Singapore, London, Paris

• If in doubt, seek specialist advice

• Keep enforcement considerations in mind, e.g. location of other party’s assets

VIII. Advice on Drafting International Construction Dispute Resolution Provisions (3)

Page 41: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

41

• For China-related arbitration, consider:

− That PRC Arbitration Law is currently interpreted by many as not permitting in China either ad hoc arbitration or arbitration administered by institutions based outside China

− Specifying that arbitration administered by selected institution, rather than merely referring to selected arbitration rules

− Providing for appointment of arbitrators other than those on the institution’s panel

− Providing that sole/presiding arbitrator not being the same nationality as the parties

− Avoiding two languages (e.g. English and Chinese) as the languages of the arbitration: keep it to only one language

VIII. Advice on Drafting International Construction Dispute Resolution Provisions (4)

Page 42: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

42

• Before a dispute arises:

− Establish sound, dedicated policies and procedures for correspondence, other documentation and claims handling

− Keep supporting documents and contemporaneous evidence well, e.g. diaries, photographs, maps, drawings (preferably electronically)

− Maintain a set of programmes which are regularly updated throughout the course of the project so that the delay experts will be able to prepare their report in the event of a delay claim

IX. Advice on Preparing for and Conducting International Construction Disputes (1)

Page 43: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

43

• When a dispute arises:

− Keep a close eye on notice provisions and other conditions precedent to claims in your contract, and time limitations for bringing claims and defences

− Gather facts and seek legal and expert advice early

− Take care in what you write and don’t write to the opposing party (do protest, don’t make unintended concessions)

− Evaluate chances of success early, and act upon that evaluation

− Carefully explore all settlement options, especially ADR (e.g. mediation)

− Look at exposure of performance bonds

IX. Advice on Preparing for and Conducting International Construction Disputes (2)

Page 44: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

44

• During arbitration or litigation:

− Set up dedicated internal team to maximise efficiency and minimise disruption to project

− Work with specialist external lawyers, arbitrators and experts,

− Work together with your external team, don’t just let them get on with it

− Prepare and monitor realistic litigation budgets

− Get management commitment to ensure cooperation of project participants

− Always keep settlement and ADR possibilities in mind

IX. Advice on Preparing for and Conducting International Construction Disputes (3)

Page 45: 1 International Construction Arbitration John Savage Partner and Head of International Arbitration, Asia December 13, 2007

45

John SavageShearman & Sterling LLP6 Battery Road, #25-03Singapore 049909

Tel : +65 6230 3008Fax : +65 6230 3899Email : [email protected] : www.shearman.com

Contact Information