1. Software Process Models (Sommerville Chapters 4, 17, 19, 12.4)

A software process model is a standardised format for •  planning •  organising, and •  running a development project.

1

Page 2: 1. Software Process Models - KTH | V¤lkommen till KTH

Hundreds of different models exist and are used, but many are minor variations on a small number of basic models.

In this section we:

•  survey the important basic models, and •  consider how to choose between them.

2

Page 3: 1. Software Process Models - KTH | V¤lkommen till KTH

1.1. Planning with Models SE projects usually live with a fixed financial budget. (An exception is maintainance?)

Additionally, time-to-market places a strong time constraint.

There will be other project constraints such as staff.

3

Page 4: 1. Software Process Models - KTH | V¤lkommen till KTH

Project constraints

money

time Computing resources

staff

Specialist technical staff

management

Support e.g. sales

Examples of Project Constraints 4

Page 5: 1. Software Process Models - KTH | V¤lkommen till KTH

Project planning is the art of scheduling/constraint solving the project parameters, along various dimensions:

time, money, staff … in order to optimise: •  project risk [low] (see later) •  profit [high] •  customer satisfaction [high] •  worker satisfaction [high] •  long/short-term company goals

5

Page 6: 1. Software Process Models - KTH | V¤lkommen till KTH

Questions:

1.  What are project parameters?

2. Are there good patterns of organisation that we could copy?

6

Page 7: 1. Software Process Models - KTH | V¤lkommen till KTH

Project parameters describe the whole project, but we must at least describe: •  resources needed

(people, money, equipment, etc) •  dependency & timing of work

(flow graph, work packages) •  rate of delivery (reports, code, etc)

It is impossible to measure rate of progress except with reference to a plan.

7

Page 8: 1. Software Process Models - KTH | V¤lkommen till KTH

In addition to project members, the following may need access to parts of the project plan:

•  Management •  Customers •  Subcontractors (outsourcing) •  Suppliers (e.g. licenses, strategic partners) •  Investors (long term investment) •  Banks (short term cash)

8

Page 9: 1. Software Process Models - KTH | V¤lkommen till KTH

1.2. Project Visibility

Unlike other engineers (e.g. civil, electronic, chemical … etc.) software engineers do not produce anything physical.

It is inherently difficult to monitor an SE project due to lack of visibility.

9

Page 10: 1. Software Process Models - KTH | V¤lkommen till KTH

This means that SE projects must produce

additional deliverables (artifacts)

which are visible, such as: •  Design documents/ prototypes •  Reports •  Project/status meetings •  Client surveys (e.g. satisfaction level)

10

Page 11: 1. Software Process Models - KTH | V¤lkommen till KTH

1.3. What is a Software Process Model?

Definition. A (software/system) process model is a description of the sequence of activities carried out in an SE project, and the relative order of these activities.

11

Page 12: 1. Software Process Models - KTH | V¤lkommen till KTH

It provides a fixed generic framework that can be tailored to a specific project. Project specific parameters will include: •  Size, (person-years) •  Budget, •  Duration.

project plan = process model + project parameters

12

Page 13: 1. Software Process Models - KTH | V¤lkommen till KTH

There are hundreds of different process models to choose from, e.g: •  waterfall, •  code-and-fix •  spiral •  rapid prototyping •  unified process (UP) •  agile methods, extreme programming (XP) •  COTS … But most are minor variations on a small number of basic models.

13

Page 14: 1. Software Process Models - KTH | V¤lkommen till KTH

By changing the process model, we can improve and/or tradeoff:

•  Development speed (time to market) •  Product quality •  Project visibility •  Administrative overhead •  Risk exposure •  Customer relations, etc, etc.

14

Page 15: 1. Software Process Models - KTH | V¤lkommen till KTH

Normally, a process model covers the entire lifetime of a product.

From birth of a commercial idea to final de-installation of last release

i.e. The three main phases: •  design, •  build, •  maintain. (50% of IT activity goes here!)

15

Page 16: 1. Software Process Models - KTH | V¤lkommen till KTH

We can sometimes combine process models e.g. 1.  waterfall inside evolutionary – onboard shuttle

software 2. Evolutionary inside waterfall – e.g. GUI

prototyping

We can also evolve the process model together with the product to account for product maturity, e.g. rapid prototyping → waterfall

16

Page 17: 1. Software Process Models - KTH | V¤lkommen till KTH

1.4. The Waterfall Model

•  The waterfall model is the classic process model – it is widely known, understood and used.

•  In some respect, waterfall is the ”common sense” approach.

•  R.W. Royce, Managing the Development of Large Software Systems: Concepts and Techniques, Proc. IEEE Westcon, IEEE Press, 1970.

17

Page 18: 1. Software Process Models - KTH | V¤lkommen till KTH

User Requirements

Software Requirements

Architecture Design

Detailed design & Coding

Testing

Delivery

The Waterfall Workflow

Time

User Requirements Document

Software Requirements Document

Architectural Design Document

Detailed Design & Code

phase output

”Swimming upstream”

18

Page 19: 1. Software Process Models - KTH | V¤lkommen till KTH

Advantages 1.  Easy to understand and implement. 2.  Widely used and known (in theory!) 3.  Fits other engineering process models: civil, mech etc. 4.  Reinforces good habits: define-before- design, design-

before-code 8.  Identifies deliverables and milestones 9.  Document driven: People leave, documents don’t

Published documentation standards: URD, SRD, … etc. , e.g. ESA PSS-05.

10.  Works well on large/mature products and weak teams.

19

Page 20: 1. Software Process Models - KTH | V¤lkommen till KTH

Disadvantages I 1.  Doesn’t reflect iterative nature of exploratory

development. 2.  Sometimes unrealistic to expect accurate requirements

early in a project 3.  Software is delivered late, delays discovery of serious

errors. 4.  No inherent risk management 5.  Difficult and expensive to change decisions, ”swimming

upstream”. 6.  Significant administrative overhead, costly for small

teams and projects. 20

Page 21: 1. Software Process Models - KTH | V¤lkommen till KTH

1.5. Code-and-Fix

This model starts with an informal general product idea and just develops code until a product is ”ready” (or money or time runs out). Work is in random order.

Corresponds with no plan! (Hacking!)

21

Page 22: 1. Software Process Models - KTH | V¤lkommen till KTH

Advantages

1.  No administrative overhead 2.  Signs of progress (code) early. 3.  Low expertise, anyone can use it! 4.  Useful for small “proof of concept”

projects, e.g. as part of risk reduction.

22

Page 23: 1. Software Process Models - KTH | V¤lkommen till KTH

Disadvantages

1.  Dangerous! 1.  No visibility/control 2.  No resource planning 3.  No deadlines 4.  Mistakes hard to detect/correct

2. Impossible for large projects, communication breakdown, chaos.

23

Page 24: 1. Software Process Models - KTH | V¤lkommen till KTH

1.6. Evolutionary Development Types

Type 1: Exploratory Development: customer assisted development that evolves a product from ignorance to insight, starting from core, well understood components (e.g. GUI?)

Type 2: Throwaway Prototyping: customer assisted development that evolves requirements from ignorance to insight by means of lightweight disposable prototypes.

24

Page 25: 1. Software Process Models - KTH | V¤lkommen till KTH

1.7. Type 1: Spiral Model Extends waterfall model by adding iteration to explore /manage risk

Project risk is a moving target. Natural to progress a project cyclically in four step phases 1.  Consider alternative scenarios, constraints 2.  Identify and resolve risks 3.  Execute the phase 4.  Plan next phase: e.g. user req, software req, architecture

… then goto 1 25

Page 26: 1. Software Process Models - KTH | V¤lkommen till KTH

In 1988 Boehm developed the spiral model as an iterative model which includes risk analysis and risk management.

Key idea: on each iteration identify and solve the sub-problems with the highest risk.

26

Page 27: 1. Software Process Models - KTH | V¤lkommen till KTH

Cumulative cost Evaluate alternatives, Identify & resolve risks

Develop & verify next-level product

Plan next phase

Determine objectives, alternatives & constraints

Review & commitment

Prototypes Phase1 Phase2 Phase3

Operational Prototype Start

End

Requirements plan

Development plan

Integration & Test plan

Requirements validation

Design, Validation & Verification

Detailed design

Coding

Unit & Integration Testing

Acceptance Testing

Concept Of Operation

C.f. Sommerville Figure 4.5

27

Page 28: 1. Software Process Models - KTH | V¤lkommen till KTH

Advantages

1.  Realism: the model accurately reflects the iterative nature of software development on projects with unclear requirements

2.  Flexible: incoporates the advantages of the waterfall and evolutionary methods

3.  Comprehensive model decreases risk 4.  Good project visibility.

28

Page 29: 1. Software Process Models - KTH | V¤lkommen till KTH

Disadvantages

1.  Needs technical expertise in risk analysis and risk management to work well.

2.  Model is poorly understood by non-technical management, hence not so widely used

3.  Complicated model, needs competent professional management. High administrative overhead.

29

Page 30: 1. Software Process Models - KTH | V¤lkommen till KTH

1.8. Type 2: Rapid Prototyping

Key idea: Customers are non-technical and usually don’t know what they want.

Rapid prototyping emphasises requirements analysis and validation, also called: •  customer oriented development, •  evolutionary prototyping

30

Page 31: 1. Software Process Models - KTH | V¤lkommen till KTH

Requirements Capture

Quick Design

Build Prototype

Customer Evaluation of Prototype

Engineer Final Product

The Rapid Prototype Workflow

Iterate

31

Page 32: 1. Software Process Models - KTH | V¤lkommen till KTH

Advantages

1.  Reduces risk of incorrect user requirements 2.  Good where requirements are changing/

uncommitted 3.  Regular visible progress aids management 4.  Supports early product marketing

32

Page 33: 1. Software Process Models - KTH | V¤lkommen till KTH

Disadvantages I

1.  An unstable/badly implemented prototype often becomes the final product. (Migration to a type 1 process!)

2.  Requires extensive customer collaboration –  Costs customers time/money –  Needs committed customers –  Difficult to finish if customer withdraws –  May be too customer specific, no broad

market 33

Page 34: 1. Software Process Models - KTH | V¤lkommen till KTH

Disadvantages II

3. Difficult to know how long project will last

4. Easy to fall back into code-and-fix without proper requirements analysis, design, customer evaluation and feedback.

34

Page 35: 1. Software Process Models - KTH | V¤lkommen till KTH

1.9. Type 1: Agile Software Processes

Need for an adaptive process model suited to changes in: •  User requirements •  Customer business models •  Technology •  In-house environment

De-emphasise documentation, esp. URD! Emphasise change management e.g. reverse engineering design! Examples include XP, Scrum, Agile modeling etc

35

Page 36: 1. Software Process Models - KTH | V¤lkommen till KTH

1.9.1. Agile Principles (C.f Sommerville Fig 17.3)

•  Incremental delivery of software •  Continuous collaboration with customer •  Embrace change •  Value participants and their interaction •  Simplicity in code,

36

Page 37: 1. Software Process Models - KTH | V¤lkommen till KTH

1.9.2. XP Release Cycle

Select release stories

Evaluate system

Breakdown stories to tasks

Plan release

Develop/ Integrate/ Test code

Release code

For a sample story see Sommerville Figure 17.6 Same as use-case? 37

Page 38: 1. Software Process Models - KTH | V¤lkommen till KTH

1.9.3. XP Practices (Summary) 1.  Incremental planning 2.  Small releases 3.  Simple design 4.  Programming in pairs (egoless programming, see 7.) 5.  Test-driven development 6.  Software refactoring (needs UML?) 7.  Collective ownership: metaphors, standards, code 8.  Continuous integration 9.  Sustainable pace (No overtime!) 10. On-site customer!

38

Page 39: 1. Software Process Models - KTH | V¤lkommen till KTH

Advantages

1.  Lightweight methods suit small-medium size projects

2.  Produces good team cohesion 3.  Emphasises final product 4.  Iterative 5.  Test-based approach to requirements and

quality assurance

39

Page 40: 1. Software Process Models - KTH | V¤lkommen till KTH

Disadvantages

1.  Difficult to scale up to large projects where documentation is essential

2.  Needs experience and skill if not to degenerate into code-and-fix

3.  Programming pairs is costly (but see productivity literature)

4.  Test case construction is a difficult and specialised skill.

40

Page 41: 1. Software Process Models - KTH | V¤lkommen till KTH

1.10. Rational Unified Process (RUP)

•  Hybrid model inspired by UML and Unified Software Development Process.

•  A generic component-based process? •  Three views on the process

– Dynamic view: RUP phases – Static view: RUP activities – Practise view: RUP best-practise

41

Page 42: 1. Software Process Models - KTH | V¤lkommen till KTH

Details

•  Lifetime of a software product in cycles: •  Birth, childhood, adulthood, old-age,

death. •  Identify product maturity stages •  Each project iteration cycle is a phase,

culiminating in a new release (c.f. Spiral model)

42

Page 43: 1. Software Process Models - KTH | V¤lkommen till KTH

Inception Elaboration

Construction Transition

UP process – RUP phase workflow (drawn as a UML Statechart!)

43

Page 44: 1. Software Process Models - KTH | V¤lkommen till KTH

RUP Phases Phases are goal directed and yield deliverables: •  Inception – Establish the business case. Identify

external entities (actors, systems). Estimate ROI. •  Elaboration – Understand problem domain.

Establish architecture, and consider design tradeoffs. Identify project risks. Estimate and schedule project. Decide on build vs. buy.

•  Construction – Design, program and test. Components are bought and integrated.

•  Transition – release a mature version and deploy in real world.

44

Page 45: 1. Software Process Models - KTH | V¤lkommen till KTH

RUP Workflows

•  RUP separates what and when into two orthogonal process views.

•  When modeled by phases •  What modeled by workflows (c.f. Sommerville

Figure 4.13) •  Any workflows can be active in any phases. •  Anything that instantiates the following diagram is

an instance of RUP!! •  An agile instantiation exists (Larman 2002)

45

Page 46: 1. Software Process Models - KTH | V¤lkommen till KTH

Unified Process: SoftwareProcess

Cycle

Phase

Iteration

Artifact

Workflow

Project Management

Environment

Requirements

Analysis/ Design

Implementation

Testing

Deployment

*

*

Inception

Elaboration

Construction

Transition

*

*

4

Product

releases

Business Modeling

46

Page 47: 1. Software Process Models - KTH | V¤lkommen till KTH

RUP Practise View

1.  Develop software iteratively 2.  Manage requirements 3.  Use component-based architectures 4.  Visually model software 5.  Verify software quality 6.  Control software changes

47

Page 48: 1. Software Process Models - KTH | V¤lkommen till KTH

Use Case Model

Analysis Model

Design Model

Deployment Model

Implementation Model

Test Model

specified by realised by

deployed by implemented by

verified by

4. Visually model software = UML Model-based Development

UML class diagram!

48

Page 49: 1. Software Process Models - KTH | V¤lkommen till KTH

Advantages/ Disadvantages

•  Difficult to judge without knowing the actual chosen instantiation of the RUP

•  Unique use of the UML philosophy of SE.

•  Can be as good/better than any other process

•  Also as bad/worse than …

49

Page 50: 1. Software Process Models - KTH | V¤lkommen till KTH

1.11. COTS

•  COTS = Commercial Off-The-Shelf software

•  Integrate a solution from existing commercial software components using minimal software plumbing

•  All projects seek some software re-use – Holy Grail of SE

•  See also Sommerville Chapter 19. 50

Page 51: 1. Software Process Models - KTH | V¤lkommen till KTH

Possible Approaches 1.  Third-party vendors: component libraries, Java beans, 2.  Integration solutions: CORBA, MS COM+, Enterprise

Java Beans, software frameworks … 3.  Good software engineering: application generators

(Yacc, Lex … Sommerville 18.3), generic programming (types, polymorphism etc)

4.  Commercial finished packages: databases, spread sheets, word processors, web browsers, etc.

5.  Design to open source interfaces: e.g. XML, ISO standards, etc.

51

Page 52: 1. Software Process Models - KTH | V¤lkommen till KTH

Distributed COTS: Web Service Providers

•  Integration of web-services: third party service providers using (XML-based?) service models:

•  JINI – extension of Java for service discovery •  SOAP (Simple Object Access Protocol) •  WSDL (Web Services Description Language) •  UDDI (Universal Description, Discovery and

Integration)

52

Page 53: 1. Software Process Models - KTH | V¤lkommen till KTH

Advantages

1.  Fast, cheap solution 2.  Explore solutions with existing products

(c.f. your project work!) 3.  May give all the basic functionality 4.  Well defined integration project, easy to

run. 5.  Open to outsourcing (c.f. Point 4) 6.  Build strategic supplier partnerships

53

Page 54: 1. Software Process Models - KTH | V¤lkommen till KTH

Disadvantages

1.  Limited functionality/ compromise/ requirements drift.

2.  Component identification can be tricky – mistakes occur!

3.  Licensing problems: freeware, shareware, etc. 4.  Customer lock-in: license fees, maintainance

fees, upgrades … 5.  Compatibility issues/loss of control:

1.  Between components (doesn’t start!) 2.  During maintenance (suddenly stops!)