The New Massachusetts Construction Prompt Pay Law
Special Thanks
2
Proud Corporate Sponsor
PanelistsJohn Romeo, Director, Capital Construction, Boston College
Nancy May, Vice President for Facilities, Northeastern University
Jeff DeMarco, Partner, Campanelli Companies
Charles Buuck, Senior Vice President, Turner Construction
Steve McDonald, President, Erland Construction
Mike Powers, Principal, Symmes Maini & McKee Associates
Deborah Griffin, Partner, Holland & Knight LLP
Robert Lizza, Partner, Hinckley, Allen & Snyder LLP
Tim Bonfatti, President, Compass Project Management
3
4
Brief History Of The Legislation After 1996 lien law reform, ASM pressed for limits
on pay-if-paid
Compromise negotiated between ASM and AGC/Mass passed by Legislature in 2004 – Governor Romney vetoed
2007 ASM added payment processing, change order processing, and right to suspend
Meanwhile, several states pass Prompt Pay statutes
5
Brief History Of The Legislation
ASM and AGC working groups met in 2008 and 2009
April 2010: ASM filed new, streamlined bill
July 8, 2010: House passed ASM bill
July 2010: AGC and ASM negotiated revisions following which AGC voted to “not oppose” amended bill
July 31, 2010 Senate passes amended bill; August 10, 2010 Governor Patrick signs into law
6
Contracts Affected Statute takes effect November 8, 2010
Applies to prime contracts signed on or after November 8, 2010 - Owners as well as contractors and subcontractors affected
Applies to all subcontracts of any tier under those prime contracts
Applies to all projects with prime contracts with an original value of $3 million or more, but not residential projects of 1-4 units
All contracts, subcontracts, purchase orders eligible for rights under Mass. lien law, Ch. 254
7
Law Addresses Five Main Issues In Payment Process
1. Limit on time for submission, review, and payment of requisitions
2. Limit on time for review and approval of change orders that increase the contract price
3. Effective prohibition of “pay-if-paid” clauses in subcontracts with two limited exceptions
4. Delayed dispute resolution process for rejection of requisitions and changes
5. Limit on forced continuation of work more than 30 days beyond due date of undisputed payment
8
Payment Process: c. 149, §29E(c)Every contract must provide reasonable timeperiods for submission, review and payment ofapplications for payment
“Reasonable” cannot exceed: Submission: 30 day limit on billing
intervals Review: Approval or rejection, in whole
or in part, within 15 days (7 days added to at each tier below the Owner)
Payment: 45 days from approval
9
Payment Process: c. 149, §29E(c)
Approval or Rejection Deadlines Can be no more than 15 days after submission for
action by owner Deadline for each tier below owner is 7 days
longer than for next tier above Must either approve or reject pay application, in
whole or in part Billing is “deemed” automatically approved if not
rejected by deadline Approval starts time interval for payment
10
Payment Process: c. 149, §29E(c)
Rejection of pay applications: Must be in writing Must explain “factual and contractual basis for
the rejection and must be certified as made in good faith”
No specified grounds for rejection in statute, so long as good faith basis
Contract, not statute, governs grounds for rejection
“Deemed” approval can be reversed by actual rejection per statute any time up to payment deadline
11
Change Orders: c. 149, §29E(d) Contract must state reasonable time period for
approval or rejection of any written request for price increase - cannot exceed 30 days
Time to approve or reject commences later of: submission of written request or start of performance of the extra work
Inaction by deadline is “deemed” approval Rejection can be for any contractually valid reason Rejection must be in writing, explain the factual and
contractual basis for the rejection, and be certified as made in good faith
Additional compensation can be billed in next regular pay application after approval
“Deemed” approval can be undone by rejection of change request before payment deadline
12
Pay-if-Paid: c. 149, §29E(e) Pay-if-Pay clause unenforceable except in
two narrow circumstances, which must be expressly stated in subcontract:
Non-performance by party seeking payment Person seeking payment must have been given
notice and opportunity to cure in accordance with contractual cure provisions, or 14 days if silent
Insolvency of third-party payor if upper tier payor is or becomes insolvent within 90
days Notice of Contract filed before submitting first pay
application for on-site work Payor must diligently pursue all other reasonable
collection rights and remedies unless fruitless
13
Right to Seek Dispute Resolution
C. 149, §29E (c) and (d) limit contract provisions that require disputes for payment and changes to be reserved until end of project
Maximum mandatory delay or waiting period for commencing dispute resolution process is 60 days after rejection
Restriction applies ONLY to disputes over rejection of pay applications and rejections of additional compensation for changes
14
Right to Suspend Work for Overdue Payment: c. 149, §29E(f) Limits contract clauses requiring continued
performance despite nonpayment of undisputed requisitions
Provides statutory right to suspend work if approved payment over 30 days past due, unless non-payment is due to: Dispute over quality or quantity of the work or Default by the claimant after approval of the
overdue payment Exception available only where there is prior written
notice of the dispute or default and payment of all undisputed amounts
Key Issues that Impact the Owner-CM Relationship The Application for Payment Cycle
Change Order Processing
Contractors Protecting a “Pay-If-Paid” Clause
The Payment Cycle
The Subcontractors’ Bargain:Traded certainty of eventually being paid (i.e., no “paid-if-paid”) for extended commercial terms
22 days to approve at first tier 45 days for payment after approval 30 days to stop work for non-payment Total: 97 days from submission of pay
application
The Payment Cycle Impact on Subcontractor-Vendor
RelationshipFor lower tiered subs and suppliers the periods
are longer (7 days each tier)But, suppliers and manufactures are not likely to
be willing to change their commercial terms, e.g. “30 days net”
Will Owners adopt the PPA payment cycle as the new standard of “reasonableness?”
Will Subcontractors get squeezed between traditional vendors terms and the longer PPA payment cycle?
Change Order Processing Subcontractor Goal: To move the paper
Approval or rejection required w/in 30 daysAccess to dispute resolutionBilling in advance of formal change
But, many changes can be complex, involve multiple trades, and take months or longer to resolve.
Does the PPA disrupt productive change order management?
Does the PPA merely force project managers at all tiers to “do their job?”
Will large complex changes be broken up into smaller parts to meet PPA obligations?
20
Protecting a Pay-if-Paid Clause Potential increase in lien filings prior to
submittal of initial applications for payment Increased pressure on upper tier payors to
bond off or otherwise discharge lower tier lien filings
Increased use of lien prevention bonds Payor parties of any tier must balance
desire to retain limited “pay-if-paid” benefits against impact on client relations
22
Prompt Pay Best PracticesFrom Designer 1. Focus on pre-construction partnering meetings to set
designer/contractor/owner expectations for payment schedule,
review and approval.
2. Keep performing the comprehensive review of the “Pencil” monthly
requisition with the Contractor prior to submission of formal monthly
requisition.
3. Prioritize cost/schedule sensitive change requests as part of the
Change Order Review Process.
23
Prompt Pay Best PracticesFrom Owner 1. Reconsider when to start a Change Order? May tend to start them with
T&M at first
2. New contract language with GC
3. Pay closer attention to when invoices must be paid and who the ball is
with
4. Revise boilerplate contract language to include in RFPs when we go out
initially to bid capital projects
5. Consider the advantage/disadvantage of using the same boilerplate for
all projects, rather than differentiate at the $3 million threshold
6. Make sure the architect/design team is on board with a detailed process
for reviewing and approving change orders and make it mandatory for
discussion with the CM/GC at the beginning of every capital project
24
Prompt Pay Best PracticesFrom CM 1. Modify construction contract
2. Train Finance department
3. Train Project managers
4. Know the impact of the Prompt Pay Bill and educate your project
personnel-read, attend seminars, bring in legal counsel for training
5. Review and modify contract language (Owner Contracts & Sub
Contracts)
6. Prequalify all parties for financial capabilities (Owners, GC’s and Subs)
7. GC’s and Subs – Develop a corporate policy regarding filing Notices of
Contract
25
The New Massachusetts Construction Prompt Pay Law