7793250 Cpm Pert Example

  • Upload
    harnav5

  • View
    43

  • Download
    4

Embed Size (px)

DESCRIPTION

Cpm Pert Example

Citation preview

  • 5/26/2018 7793250 Cpm Pert Example

    1/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-1

    Network Planning MethodsExample PERT &CPM : Saint

    Pauls Hospital

  • 5/26/2018 7793250 Cpm Pert Example

    2/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-2

    Terms Used in Project Management

    Activity : A certain amount of work or task required in the

    project

    Activity duration: In CPM the best estimate of time to

    complete an activity . In PERT the expected time or

    average time to complete an activity

    Critical activity: An activity that has no room for schedule

    slippages: if it slips the entire the entire project completion

    will slip. An activity with zero slack

  • 5/26/2018 7793250 Cpm Pert Example

    3/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-3

    Critical path: The chain of critical activities for the project

    .The longest path through the network

    Dummy activity:An activity that consumes no time butshows precedence among activities

    Earliest finish (EF):The earliest that an activity can finish

    from the beginning of the project

    Earliest start ( ES):The earliest that an activity can start

    from the beginning of the project

  • 5/26/2018 7793250 Cpm Pert Example

    4/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-4

    Event :A beginning , a completion point ,or amilestone accomplishment within the project . Anactivity begins and ends with events

    Latest finish (LF) : The latest that an activity can finishfrom the beginning of the project

    Latest start (LS):The latest that an activity can start fromthe beginning of the project

    Most likely time ( t m): The time for completing theactivity that is is the consensus best estimate, used inPERT

  • 5/26/2018 7793250 Cpm Pert Example

    5/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-5

    Optimistic Time(to): The time for completing an activity ifall goes well : used in PERT

    Pessimistic Time(tp): The time for completing an activityif bad luck is encountered : used in PERT

    Predecessor activity: An activity that must occur beforeanother activity .

    Slack: The amount of time that an activity or group ofactivities can slip without causing a delay in thecompletion of the project

    Successor activity: An activity that must occur after

    another activity

  • 5/26/2018 7793250 Cpm Pert Example

    6/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-6

    Conventions used in drawing network diagrams

    (Arrows & Circles )

    Activity on Arrow (AOA): The activities are denoted byArrows and events are denoted by circles

    Activity on Node(AON): Activities are denoted bycircles(or nodes) and the precedence relation ships

    between activities are indicated by arrows

  • 5/26/2018 7793250 Cpm Pert Example

    7/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-7

    Relationship between activities

    Project duration

    Critical path Slack for noncritical activities

    Crashing (cost / time trade-offs)

    Resource usage

    PERT / CPMNetwork planning methods that generate:

  • 5/26/2018 7793250 Cpm Pert Example

    8/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-8

    St. Pauls Hospital

    ImmediateActivity Description Predecessor(s)

    A Select administrative and medical staff.

    B Select site and do site survey.

    C Select equipment.D Prepare final construction plans and layout.

    E Bring utilities to the site.

    F Interview applicants and fill positions in nursing,

    support staff, maintenance, and security.

    G Purchase and take delivery of equipment.H Construct the hospital.

    I Develop an information system.

    J Install the equipment.

    K Train nurses and support staff.

    AB

    B

    A

    CD

    A

    E,G,H

    F,I,J

  • 5/26/2018 7793250 Cpm Pert Example

    9/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-9

    St. Pauls Hospital

    ImmediateActivity Description Predecessor(s)

    A Select administrative and medical staff.

    B Select site and do site survey.

    C Select equipment.D Prepare final construction plans and layout.

    E Bring utilities to the site.

    F Interview applicants and fill positions in nursing,

    support staff, maintenance, and security.

    G Purchase and take delivery of equipment.H Construct the hospital.

    I Develop an information system.

    J Install the equipment.

    K Train nurses and support staff.

    AB

    B

    A

    CD

    A

    E,G,H

    F,I,J

    AON Network

    FinishStart

    A

    B

    C

    D

    E

    F

    G

    H

    I

    J

    K

  • 5/26/2018 7793250 Cpm Pert Example

    10/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-10

    St. Pauls Hospital

    ImmediateActivity Description Predecessor(s)

    A Select administrative and medical staff.

    B Select site and do site survey.

    C Select equipment.D Prepare final construction plans and layout.

    E Bring utilities to the site.

    F Interview applicants and fill positions in nursing,

    support staff, maintenance, and security.

    G Purchase and take delivery of equipment.H Construct the hospital.

    I Develop an information system.

    J Install the equipment.

    K Train nurses and support staff.

    AB

    B

    A

    CD

    A

    E,G,H

    F,I,J

    Completion Time

    FinishStart

    K

    9

    I

    15

    F

    10

    C

    10

    D10

    E

    24

    G

    35

    H40

    J4

    A

    12

    B9

  • 5/26/2018 7793250 Cpm Pert Example

    11/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-11

    St. Pauls Hospital

    ImmediateActivity Description Predecessor(s)

    A Select administrative and medical staff.

    B Select site and do site survey.

    C Select equipment.D Prepare final construction plans and layout.

    E Bring utilities to the site.

    F Interview applicants and fill positions in nursing,

    support staff, maintenance, and security.

    G Purchase and take delivery of equipment.H Construct the hospital.

    I Develop an information system.

    J Install the equipment.

    K Train nurses and support staff.

    AB

    B

    A

    CD

    A

    E,G,H

    F,I,J

    Completion Time

    FinishStart

    K

    9

    I

    15

    F

    10

    C

    10

    D

    10

    E

    24

    G

    35

    H

    40

    J

    4

    A

    12

    B

    9

    Path Expected Time (wks)

    A-I-K 36

    A-F-K 31

    A-C-G-J-K 70

    B-D-H-J-K 72

    B-E-J-K 46

    Critical

    Path

  • 5/26/2018 7793250 Cpm Pert Example

    12/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-12

    Critical Path

    The longest path in the network Defines the shortest time project can be completed

    Critical path activity delay project delay

  • 5/26/2018 7793250 Cpm Pert Example

    13/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-13

    Begin at starting event and work forward

    ES is earliest start

    ES = 0 for starting activities

    ES = Maximum EF of allpredecessors for

    non-starting activities

    EF is earliest finish EF = ES + Activity time

    Earliest Start and Earliest Finish

    ES

    LS

    EF

    LF

    Activity

    Name

    Activity

    Duration

  • 5/26/2018 7793250 Cpm Pert Example

    14/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-14

    A

    12

    K

    9

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    I

    15

    F

    10

    FinishStart

    Earliest Start / Earliest Finish

  • 5/26/2018 7793250 Cpm Pert Example

    15/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-15

    Earliest Start / Earliest Finish

    Finish

    Earliest start time Earliest finish time

    A

    12

    K

    9

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    0 12

    I

    15

    F

    10

    12 27

    12 22 63 72

    22 57

    59 6319 59

    9 33

    0 9 9 19

    12 22

    Critical

    path

    Start

  • 5/26/2018 7793250 Cpm Pert Example

    16/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-16

    Begin at ending event and work backward

    LF is latest finish

    LF = Maximum EF for

    ending activities LF = Minimum LS of all

    successors for

    non-ending activities

    LS is latest start

    LS = LFActivity time

    Latest Start and Latest Finish

    ES

    LS

    EF

    LF

    Activity

    Name

    Activity

    Duration

  • 5/26/2018 7793250 Cpm Pert Example

    17/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-17

    Latest Start / Latest Finish

    A

    12

    K

    9

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    0 12

    I

    15

    F

    10

    12 27

    12 22 63 72

    22 57

    59 6319 59

    9 33

    0 9 9 19

    12 22

    48 63

    2 14 53 63 63 72

    14 24 24 59

    0 9 9 19 19 59

    35 59

    59 63

    Latest start time Latest finish time

    Critical

    path

    FinishStart

    What do you

    notice aboutES/LS & EF/LF?

  • 5/26/2018 7793250 Cpm Pert Example

    18/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-18

    Activity Slack Analysis

    A

    12

    K

    9

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    0 12

    I

    15

    F

    10

    12 27

    12 22 63 72

    22 57

    59 6319 59

    9 33

    0 9 9 19

    12 22

    48 63

    2 14 53 63 63 72

    14 24 24 59

    0 9 9 19 19 59

    35 59

    59 63

    Latest start time Latest finish time

    Critical

    path

    FinishStartSlackK= 63 63 = 0

    or

    SlackK= 72 72 = 0

    Slack = LS

    ES

    or

    Slack = LFEF

  • 5/26/2018 7793250 Cpm Pert Example

    19/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-19

    Activity Slack Analysis

    A

    12

    K

    9

    C

    10

    G

    35

    J

    4

    H

    40

    B

    9

    D

    10

    E

    24

    0 12

    I

    15

    F

    10

    12 27

    12 22 63 72

    22 57

    59 6319 59

    9 33

    0 9 9 19

    12 22

    48 63

    2 14 53 63 63 72

    14 24 24 59

    0 9 9 19 19 59

    35 59

    59 63

    Latest start time Latest finish time

    Critical

    path

    FinishStart

    Node Duration ES LS Slack

    A 12 0 2 2

    B 9 0 0 0

    C 10 12 14 2

    D 10 9 9 0

    E 24 9 35 26F 10 12 53 41

    G 35 22 24 2

    H 40 19 19 0

    I 15 12 48 36

    J 4 59 59 0K 6 63 63 0

    Activity slack = maximum delay time

    Critical path activities have zero slack

  • 5/26/2018 7793250 Cpm Pert Example

    20/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-20

    Activity Slack

    How much would we like to reduce

    the time for activity B?

    C

    15

    5 20

    10 25

    A

    5

    0 5

    0 5 FinishStart

    B

    20

    5 25

    5 25D

    10

    25 35

    25 35

  • 5/26/2018 7793250 Cpm Pert Example

    21/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-21

    3 activity time estimates

    Optimistic times (a)

    Most-likely time (m)

    Pessimistic time (b)

    Follow beta distribution Expected time: t = (a+ 4m+ b) / 6

    Variance of times: v= (b- a)2/ 6

    Expected project time:T = sum of critical path activity times, t

    Project variance:V = sum of critical path activity variances

    Activity Times & Project Times

  • 5/26/2018 7793250 Cpm Pert Example

    22/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-22

    Completion Time for Noncritical Activities

    Variability of times for activities on non-criticalpaths must be considered when determining

    the probability of finishing in a specified time.

    Variation in non-critical activity may causechange in critical path.

  • 5/26/2018 7793250 Cpm Pert Example

    23/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-23

    Cost / Time Trade-offs

    Most activities can be done faster if youpay more money

    Work overtime / hire more people /

    rent extra equipment / incentive contracts

    PERT / CPM have the ability to crash

    a scheduleto shorten activity time in a network

    to reduce project completion time.

  • 5/26/2018 7793250 Cpm Pert Example

    24/24

    2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-24

    Cost / Time Relationship

    8000

    7000

    6000

    5000

    4000

    3000

    0

    Directcost(dollars)

    Crash cost

    Normal cost

    | | | | | |

    5 6 7 8 9 10 11

    Crashtime Normaltime

    Activity B