Upload
harnav5
View
43
Download
4
Tags:
Embed Size (px)
DESCRIPTION
Cpm Pert Example
Citation preview
5/26/2018 7793250 Cpm Pert Example
1/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-1
Network Planning MethodsExample PERT &CPM : Saint
Pauls Hospital
5/26/2018 7793250 Cpm Pert Example
2/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-2
Terms Used in Project Management
Activity : A certain amount of work or task required in the
project
Activity duration: In CPM the best estimate of time to
complete an activity . In PERT the expected time or
average time to complete an activity
Critical activity: An activity that has no room for schedule
slippages: if it slips the entire the entire project completion
will slip. An activity with zero slack
5/26/2018 7793250 Cpm Pert Example
3/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-3
Critical path: The chain of critical activities for the project
.The longest path through the network
Dummy activity:An activity that consumes no time butshows precedence among activities
Earliest finish (EF):The earliest that an activity can finish
from the beginning of the project
Earliest start ( ES):The earliest that an activity can start
from the beginning of the project
5/26/2018 7793250 Cpm Pert Example
4/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-4
Event :A beginning , a completion point ,or amilestone accomplishment within the project . Anactivity begins and ends with events
Latest finish (LF) : The latest that an activity can finishfrom the beginning of the project
Latest start (LS):The latest that an activity can start fromthe beginning of the project
Most likely time ( t m): The time for completing theactivity that is is the consensus best estimate, used inPERT
5/26/2018 7793250 Cpm Pert Example
5/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-5
Optimistic Time(to): The time for completing an activity ifall goes well : used in PERT
Pessimistic Time(tp): The time for completing an activityif bad luck is encountered : used in PERT
Predecessor activity: An activity that must occur beforeanother activity .
Slack: The amount of time that an activity or group ofactivities can slip without causing a delay in thecompletion of the project
Successor activity: An activity that must occur after
another activity
5/26/2018 7793250 Cpm Pert Example
6/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-6
Conventions used in drawing network diagrams
(Arrows & Circles )
Activity on Arrow (AOA): The activities are denoted byArrows and events are denoted by circles
Activity on Node(AON): Activities are denoted bycircles(or nodes) and the precedence relation ships
between activities are indicated by arrows
5/26/2018 7793250 Cpm Pert Example
7/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-7
Relationship between activities
Project duration
Critical path Slack for noncritical activities
Crashing (cost / time trade-offs)
Resource usage
PERT / CPMNetwork planning methods that generate:
5/26/2018 7793250 Cpm Pert Example
8/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-8
St. Pauls Hospital
ImmediateActivity Description Predecessor(s)
A Select administrative and medical staff.
B Select site and do site survey.
C Select equipment.D Prepare final construction plans and layout.
E Bring utilities to the site.
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.H Construct the hospital.
I Develop an information system.
J Install the equipment.
K Train nurses and support staff.
AB
B
A
CD
A
E,G,H
F,I,J
5/26/2018 7793250 Cpm Pert Example
9/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-9
St. Pauls Hospital
ImmediateActivity Description Predecessor(s)
A Select administrative and medical staff.
B Select site and do site survey.
C Select equipment.D Prepare final construction plans and layout.
E Bring utilities to the site.
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.H Construct the hospital.
I Develop an information system.
J Install the equipment.
K Train nurses and support staff.
AB
B
A
CD
A
E,G,H
F,I,J
AON Network
FinishStart
A
B
C
D
E
F
G
H
I
J
K
5/26/2018 7793250 Cpm Pert Example
10/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-10
St. Pauls Hospital
ImmediateActivity Description Predecessor(s)
A Select administrative and medical staff.
B Select site and do site survey.
C Select equipment.D Prepare final construction plans and layout.
E Bring utilities to the site.
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.H Construct the hospital.
I Develop an information system.
J Install the equipment.
K Train nurses and support staff.
AB
B
A
CD
A
E,G,H
F,I,J
Completion Time
FinishStart
K
9
I
15
F
10
C
10
D10
E
24
G
35
H40
J4
A
12
B9
5/26/2018 7793250 Cpm Pert Example
11/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-11
St. Pauls Hospital
ImmediateActivity Description Predecessor(s)
A Select administrative and medical staff.
B Select site and do site survey.
C Select equipment.D Prepare final construction plans and layout.
E Bring utilities to the site.
F Interview applicants and fill positions in nursing,
support staff, maintenance, and security.
G Purchase and take delivery of equipment.H Construct the hospital.
I Develop an information system.
J Install the equipment.
K Train nurses and support staff.
AB
B
A
CD
A
E,G,H
F,I,J
Completion Time
FinishStart
K
9
I
15
F
10
C
10
D
10
E
24
G
35
H
40
J
4
A
12
B
9
Path Expected Time (wks)
A-I-K 36
A-F-K 31
A-C-G-J-K 70
B-D-H-J-K 72
B-E-J-K 46
Critical
Path
5/26/2018 7793250 Cpm Pert Example
12/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-12
Critical Path
The longest path in the network Defines the shortest time project can be completed
Critical path activity delay project delay
5/26/2018 7793250 Cpm Pert Example
13/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-13
Begin at starting event and work forward
ES is earliest start
ES = 0 for starting activities
ES = Maximum EF of allpredecessors for
non-starting activities
EF is earliest finish EF = ES + Activity time
Earliest Start and Earliest Finish
ES
LS
EF
LF
Activity
Name
Activity
Duration
5/26/2018 7793250 Cpm Pert Example
14/24 2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-14
A
12
K
9
C
10
G
35
J
4
H
40
B
9
D
10
E
24
I
15
F
10
FinishStart
Earliest Start / Earliest Finish
5/26/2018 7793250 Cpm Pert Example
15/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-15
Earliest Start / Earliest Finish
Finish
Earliest start time Earliest finish time
A
12
K
9
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 72
22 57
59 6319 59
9 33
0 9 9 19
12 22
Critical
path
Start
5/26/2018 7793250 Cpm Pert Example
16/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-16
Begin at ending event and work backward
LF is latest finish
LF = Maximum EF for
ending activities LF = Minimum LS of all
successors for
non-ending activities
LS is latest start
LS = LFActivity time
Latest Start and Latest Finish
ES
LS
EF
LF
Activity
Name
Activity
Duration
5/26/2018 7793250 Cpm Pert Example
17/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-17
Latest Start / Latest Finish
A
12
K
9
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 72
22 57
59 6319 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 72
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Latest start time Latest finish time
Critical
path
FinishStart
What do you
notice aboutES/LS & EF/LF?
5/26/2018 7793250 Cpm Pert Example
18/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-18
Activity Slack Analysis
A
12
K
9
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 72
22 57
59 6319 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 72
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Latest start time Latest finish time
Critical
path
FinishStartSlackK= 63 63 = 0
or
SlackK= 72 72 = 0
Slack = LS
ES
or
Slack = LFEF
5/26/2018 7793250 Cpm Pert Example
19/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-19
Activity Slack Analysis
A
12
K
9
C
10
G
35
J
4
H
40
B
9
D
10
E
24
0 12
I
15
F
10
12 27
12 22 63 72
22 57
59 6319 59
9 33
0 9 9 19
12 22
48 63
2 14 53 63 63 72
14 24 24 59
0 9 9 19 19 59
35 59
59 63
Latest start time Latest finish time
Critical
path
FinishStart
Node Duration ES LS Slack
A 12 0 2 2
B 9 0 0 0
C 10 12 14 2
D 10 9 9 0
E 24 9 35 26F 10 12 53 41
G 35 22 24 2
H 40 19 19 0
I 15 12 48 36
J 4 59 59 0K 6 63 63 0
Activity slack = maximum delay time
Critical path activities have zero slack
5/26/2018 7793250 Cpm Pert Example
20/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-20
Activity Slack
How much would we like to reduce
the time for activity B?
C
15
5 20
10 25
A
5
0 5
0 5 FinishStart
B
20
5 25
5 25D
10
25 35
25 35
5/26/2018 7793250 Cpm Pert Example
21/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-21
3 activity time estimates
Optimistic times (a)
Most-likely time (m)
Pessimistic time (b)
Follow beta distribution Expected time: t = (a+ 4m+ b) / 6
Variance of times: v= (b- a)2/ 6
Expected project time:T = sum of critical path activity times, t
Project variance:V = sum of critical path activity variances
Activity Times & Project Times
5/26/2018 7793250 Cpm Pert Example
22/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-22
Completion Time for Noncritical Activities
Variability of times for activities on non-criticalpaths must be considered when determining
the probability of finishing in a specified time.
Variation in non-critical activity may causechange in critical path.
5/26/2018 7793250 Cpm Pert Example
23/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-23
Cost / Time Trade-offs
Most activities can be done faster if youpay more money
Work overtime / hire more people /
rent extra equipment / incentive contracts
PERT / CPM have the ability to crash
a scheduleto shorten activity time in a network
to reduce project completion time.
5/26/2018 7793250 Cpm Pert Example
24/24
2004 by Prentice Hall, Inc., Upper Saddle River, N.J. 074583-24
Cost / Time Relationship
8000
7000
6000
5000
4000
3000
0
Directcost(dollars)
Crash cost
Normal cost
| | | | | |
5 6 7 8 9 10 11
Crashtime Normaltime
Activity B