44
DRILLED SHAFT / BORED IN PILE INSTALLATION New Brunswick Fitness & Wellness Plaza New Brunswick, NJ Presentation to: ADSC Northeast Chapter Holiday Inn, Clark, NJ November 30 th , 2012 Presentation by: Jeffrey B. Ayres Moretrench American Corporation

ADSC Presentation - 11.30.12

Embed Size (px)

Citation preview

Page 1: ADSC Presentation - 11.30.12

DRILLED SHAFT / BORED IN PILE INSTALLATION

New Brunswick Fitness & Wellness PlazaNew Brunswick, NJ

Presentation to:ADSC Northeast Chapter

Holiday Inn, Clark, NJNovember 30th, 2012

Presentation by:Jeffrey B. Ayres

Moretrench American Corporation

Page 2: ADSC Presentation - 11.30.12

PROJECT OVERVIEW

• Proposed Construction:• Fitness Center• Supermarket• Parking Garage

• Owner• City of New Brunswick

• General Contractor• Joseph Jingoli & Sons,

Inc.• Structural Engineer

• PS&S• Foundation Contractor

• Moretrench

Page 3: ADSC Presentation - 11.30.12

PROJECT OVERVIEW

• Scheduling / Coordination• Difficult Schedule• No relief in schedule

when schedule slid• Additional subs added

when schedule slid

Page 4: ADSC Presentation - 11.30.12

MTAC CONTRACT WORK – DRILLED SHAFTS

• 77 Total Drilled Shafts• Provide support for

new column loads• 39 @ 3’ diameter

• Reinforcing dowels • 38 @ 6’ diameter

• Reinforcing dowels• Anchor bolts

(precast connection)

• Average drill length: 30’

Page 5: ADSC Presentation - 11.30.12

DRILL RIG (DRILLED SHAFTS)

• Soilmec SR-65• Hydraulic Rotary Rig• 22,500 mm (~74’) mast

• Equipped with:• Self Handling Counterweight• Kelly Drilling System• Drilling Mate System

• Actively monitor drill depth, crowd pressure, mast verticality, pump pressures, and more

Page 6: ADSC Presentation - 11.30.12

DRILL RIG (DRILLED SHAFTS)

• Bottom of Mast Clearance• Cable system feed on back of mast• Enough clearance for casing

“spinner”

WHY SOILMEC?

Page 7: ADSC Presentation - 11.30.12

MTAC CONTRACT WORK – BIP’s

• 246 Bored In Piles (BIP’s)• Provide support for new

slab• 18” Diameter• 6 x #6 reinforcing cage

substituted with #18 grade 75 threadbar

• Average drill length: 20’

Page 8: ADSC Presentation - 11.30.12

DRILLING EQUIPMENT (BIP)

• Bauer RTG RG 19 T• Universal Piling Rig• Up to 78’ Mast Height

• Equipped with:• PIR (Pile Installation

Recorder)• Actively monitor drill

depth, grout volume per 5’ increment, and more

Page 9: ADSC Presentation - 11.30.12

MATERIAL / EQUIPMENT SUPPLIERS

• Soilmec SR-65• American Equipment & Fabrication,

East Providence, RI • Bauer RTG RG 19T

• Moretrench owned, purchased from Posillico, Inc.

• Temporary Casing• Favor Steel & Fabricating,

Bessemer, AL• Drill Tooling

• Jeffrey Machine, Birmingham, AL• Concrete

• Clayton Concrete, Edison, NJ• Rebar

• Barker Steel, Avenel, NJ

Page 10: ADSC Presentation - 11.30.12

LOGISTICS

Page 11: ADSC Presentation - 11.30.12

LOGISTICAL ISSUES

• Existing Overhead Powerlines• Existing Robert Wood Johnson (RWJ) Building• Existing Utilities• Northeast Regional Amtrak Line

Page 12: ADSC Presentation - 11.30.12

EXISTING OVERHEAD POWERLINES

Page 13: ADSC Presentation - 11.30.12

EXISTING OVERHEAD POWERLINES

Page 14: ADSC Presentation - 11.30.12

EXISTING OVERHEAD POWERLINES

Page 15: ADSC Presentation - 11.30.12

EXISTING OVERHEAD POWERLINES

Page 16: ADSC Presentation - 11.30.12

RWJ BUILDING DEMOLITION

Existing RWJ Building

Page 17: ADSC Presentation - 11.30.12

RWJ BUILDING DEMOLITION

Page 18: ADSC Presentation - 11.30.12

RWJ BUILDING DEMOLITION

Mobilized prior to demolition

22 caissons unavailable during demolition

Obstructions / Utilities encountered beneath building footprint while drilling

Page 19: ADSC Presentation - 11.30.12

RWJ BUILDING DEMOLITION

Page 20: ADSC Presentation - 11.30.12

EXISTING / NEW UTILITIES

Page 21: ADSC Presentation - 11.30.12

AMTRAK PROXIMITY

• Required to be 15’ minimum between mast & edge of Amtrak line

Page 22: ADSC Presentation - 11.30.12

DRILLED SHAFTS

Page 23: ADSC Presentation - 11.30.12

DRILLING PROCEDURE (3’ DRILLED SHAFTS)

• 48” diameter starter can for top 5’

• 42” diameter “inner” can to top of rock

• Socketed into weathered shale

• Visual inspection performed by PS&S

Page 24: ADSC Presentation - 11.30.12

DRILLING PROCEDURE (6’ DRILLED SHAFTS)

• 87” diameter starter can for top 5’

• 78” diameter “inner” can to top of rock

• Socketed into weathered shale

• Visual inspection performed by PS&S

Page 25: ADSC Presentation - 11.30.12

6’ DRILL TOOLING

Page 26: ADSC Presentation - 11.30.12

3’ DRILL TOOLING

Soilmec equipped to switch between both 3’ and 6’ diameter tooling easily

Page 27: ADSC Presentation - 11.30.12

REINFORCING CAGE / CONCRETE

• 26 x #11 bars per 6’ caisson• 10 x #9 bars per 3’ caisson• Cage placed with drill rig or crane

Page 28: ADSC Presentation - 11.30.12

REINFORCING CAGE / CONCRETE

• Top of reinforcing cage @ 3” below top of caisson (minimum coverage of reinforcement)

• Water removal (hydraulic pump) & shallow depth permitted end dumping of concrete

Page 29: ADSC Presentation - 11.30.12

DOWELS

• Issues Faced:• All 77 caissons received either dowels or anchor bolts

• Connection to grade beam, column, etc.• Drilling grade consistent at ~ elevation 47• Top of caisson elevation varied from elevation 47 to elevation 40• Drilling / epoxying dowels into 6’ shafts was not permitted

• Solutions:• “Wet-Set” dowels for 6’ shafts using premade wooden templates• Drill / epoxy any remaining dowels once top of caisson is exposed

Page 30: ADSC Presentation - 11.30.12

DOWELS

• More than a dozen different dowel patterns• Up to 7’ depth below drilling grade (worst case scenario)

Page 31: ADSC Presentation - 11.30.12

DOWELS

Page 32: ADSC Presentation - 11.30.12

ANCHOR BOLTS

• Issues Faced:• Anchor Bolt location and embedment in top of drilled shafts were

critical, with nearly negligible tolerances• Solution:

• Per the engineer, pour shaft concrete 3’ below top of caisson (cold joint).

• Place 6’ corrugated pipe around top of shaft• Set template at correct elevation and plan location• Pour remainder of concrete• Monitor location of template before, during, and after pour

Page 33: ADSC Presentation - 11.30.12

ANCHOR BOLTS

• Left: 6’ Diameter Caisson with Concrete 2’-3’ low• Right: 6’ Diameter Corrugated Pipe

Page 34: ADSC Presentation - 11.30.12

ANCHOR BOLTS

• Left: Typical Anchor Bolt Template• Right: Placement of Anchor Bolt Template at exact elevation prior to

pour

Page 35: ADSC Presentation - 11.30.12

ANCHOR BOLTS

Page 36: ADSC Presentation - 11.30.12

ANCHOR BOLTS

Page 37: ADSC Presentation - 11.30.12

ANCHOR BOLTS

Page 38: ADSC Presentation - 11.30.12

ANCHOR BOLTS

• Left: Finished Anchor Bolt Shaft• Right: Precast Column @ Anchor Bolt Shaft

Page 39: ADSC Presentation - 11.30.12

BORED IN PILES (BIP’s)

Page 40: ADSC Presentation - 11.30.12

DRILLING PROCEDURE (BORED IN PILES)

• 18” Diameter Continuous Flight Hollow Stem Auger• Advanced 5’ below top of first rock encountered or to auger refusal

• <1’ / minute • Once tip reached, sand-cement grout pumped through auger• 115% of theoretical volume (measured by PIR & stroke count)• Slow positive rotation maintained during withdrawal

Page 41: ADSC Presentation - 11.30.12

DRILLING PROCEDURE (BORED IN PILES)

• Upon grouting completion, pile top protector placed into hole (left picture)

• Top of Pile (grout) elevation reached by removing excess grout from top• #18 Grade 75 Threadbar installed full length (right) along with 4 x #4

bars with 90 degree bends• Average Production – 15 to 20 / DAY

Page 42: ADSC Presentation - 11.30.12

BEFORE

Page 43: ADSC Presentation - 11.30.12

AFTER

Page 44: ADSC Presentation - 11.30.12

NEW BRUNSWICK WELLNESS PLAZA

QUESTIONS?