Upload
jeffrey-b-ayres-pe
View
45
Download
2
Embed Size (px)
Citation preview
DRILLED SHAFT / BORED IN PILE INSTALLATION
New Brunswick Fitness & Wellness PlazaNew Brunswick, NJ
Presentation to:ADSC Northeast Chapter
Holiday Inn, Clark, NJNovember 30th, 2012
Presentation by:Jeffrey B. Ayres
Moretrench American Corporation
PROJECT OVERVIEW
• Proposed Construction:• Fitness Center• Supermarket• Parking Garage
• Owner• City of New Brunswick
• General Contractor• Joseph Jingoli & Sons,
Inc.• Structural Engineer
• PS&S• Foundation Contractor
• Moretrench
PROJECT OVERVIEW
• Scheduling / Coordination• Difficult Schedule• No relief in schedule
when schedule slid• Additional subs added
when schedule slid
MTAC CONTRACT WORK – DRILLED SHAFTS
• 77 Total Drilled Shafts• Provide support for
new column loads• 39 @ 3’ diameter
• Reinforcing dowels • 38 @ 6’ diameter
• Reinforcing dowels• Anchor bolts
(precast connection)
• Average drill length: 30’
DRILL RIG (DRILLED SHAFTS)
• Soilmec SR-65• Hydraulic Rotary Rig• 22,500 mm (~74’) mast
• Equipped with:• Self Handling Counterweight• Kelly Drilling System• Drilling Mate System
• Actively monitor drill depth, crowd pressure, mast verticality, pump pressures, and more
DRILL RIG (DRILLED SHAFTS)
• Bottom of Mast Clearance• Cable system feed on back of mast• Enough clearance for casing
“spinner”
WHY SOILMEC?
MTAC CONTRACT WORK – BIP’s
• 246 Bored In Piles (BIP’s)• Provide support for new
slab• 18” Diameter• 6 x #6 reinforcing cage
substituted with #18 grade 75 threadbar
• Average drill length: 20’
DRILLING EQUIPMENT (BIP)
• Bauer RTG RG 19 T• Universal Piling Rig• Up to 78’ Mast Height
• Equipped with:• PIR (Pile Installation
Recorder)• Actively monitor drill
depth, grout volume per 5’ increment, and more
MATERIAL / EQUIPMENT SUPPLIERS
• Soilmec SR-65• American Equipment & Fabrication,
East Providence, RI • Bauer RTG RG 19T
• Moretrench owned, purchased from Posillico, Inc.
• Temporary Casing• Favor Steel & Fabricating,
Bessemer, AL• Drill Tooling
• Jeffrey Machine, Birmingham, AL• Concrete
• Clayton Concrete, Edison, NJ• Rebar
• Barker Steel, Avenel, NJ
LOGISTICS
LOGISTICAL ISSUES
• Existing Overhead Powerlines• Existing Robert Wood Johnson (RWJ) Building• Existing Utilities• Northeast Regional Amtrak Line
EXISTING OVERHEAD POWERLINES
EXISTING OVERHEAD POWERLINES
EXISTING OVERHEAD POWERLINES
EXISTING OVERHEAD POWERLINES
RWJ BUILDING DEMOLITION
Existing RWJ Building
RWJ BUILDING DEMOLITION
RWJ BUILDING DEMOLITION
Mobilized prior to demolition
22 caissons unavailable during demolition
Obstructions / Utilities encountered beneath building footprint while drilling
RWJ BUILDING DEMOLITION
EXISTING / NEW UTILITIES
AMTRAK PROXIMITY
• Required to be 15’ minimum between mast & edge of Amtrak line
DRILLED SHAFTS
DRILLING PROCEDURE (3’ DRILLED SHAFTS)
• 48” diameter starter can for top 5’
• 42” diameter “inner” can to top of rock
• Socketed into weathered shale
• Visual inspection performed by PS&S
DRILLING PROCEDURE (6’ DRILLED SHAFTS)
• 87” diameter starter can for top 5’
• 78” diameter “inner” can to top of rock
• Socketed into weathered shale
• Visual inspection performed by PS&S
6’ DRILL TOOLING
3’ DRILL TOOLING
Soilmec equipped to switch between both 3’ and 6’ diameter tooling easily
REINFORCING CAGE / CONCRETE
• 26 x #11 bars per 6’ caisson• 10 x #9 bars per 3’ caisson• Cage placed with drill rig or crane
REINFORCING CAGE / CONCRETE
• Top of reinforcing cage @ 3” below top of caisson (minimum coverage of reinforcement)
• Water removal (hydraulic pump) & shallow depth permitted end dumping of concrete
DOWELS
• Issues Faced:• All 77 caissons received either dowels or anchor bolts
• Connection to grade beam, column, etc.• Drilling grade consistent at ~ elevation 47• Top of caisson elevation varied from elevation 47 to elevation 40• Drilling / epoxying dowels into 6’ shafts was not permitted
• Solutions:• “Wet-Set” dowels for 6’ shafts using premade wooden templates• Drill / epoxy any remaining dowels once top of caisson is exposed
DOWELS
• More than a dozen different dowel patterns• Up to 7’ depth below drilling grade (worst case scenario)
DOWELS
ANCHOR BOLTS
• Issues Faced:• Anchor Bolt location and embedment in top of drilled shafts were
critical, with nearly negligible tolerances• Solution:
• Per the engineer, pour shaft concrete 3’ below top of caisson (cold joint).
• Place 6’ corrugated pipe around top of shaft• Set template at correct elevation and plan location• Pour remainder of concrete• Monitor location of template before, during, and after pour
ANCHOR BOLTS
• Left: 6’ Diameter Caisson with Concrete 2’-3’ low• Right: 6’ Diameter Corrugated Pipe
ANCHOR BOLTS
• Left: Typical Anchor Bolt Template• Right: Placement of Anchor Bolt Template at exact elevation prior to
pour
ANCHOR BOLTS
ANCHOR BOLTS
ANCHOR BOLTS
ANCHOR BOLTS
• Left: Finished Anchor Bolt Shaft• Right: Precast Column @ Anchor Bolt Shaft
BORED IN PILES (BIP’s)
DRILLING PROCEDURE (BORED IN PILES)
• 18” Diameter Continuous Flight Hollow Stem Auger• Advanced 5’ below top of first rock encountered or to auger refusal
• <1’ / minute • Once tip reached, sand-cement grout pumped through auger• 115% of theoretical volume (measured by PIR & stroke count)• Slow positive rotation maintained during withdrawal
DRILLING PROCEDURE (BORED IN PILES)
• Upon grouting completion, pile top protector placed into hole (left picture)
• Top of Pile (grout) elevation reached by removing excess grout from top• #18 Grade 75 Threadbar installed full length (right) along with 4 x #4
bars with 90 degree bends• Average Production – 15 to 20 / DAY
BEFORE
AFTER
NEW BRUNSWICK WELLNESS PLAZA
QUESTIONS?