Aldrin Report

  • Upload
    rfernz

  • View
    225

  • Download
    0

Embed Size (px)

Citation preview

  • 8/12/2019 Aldrin Report

    1/12

    ABSTRACT

    Dredgings works have an important

    participation in any port or coastal

    work, being currently very related to

    the artificial feedings of beaches.

    His applications are nevertheless

    much more diverse, intervening for

    example in the conditioning of the

    funds, in the extraction of materials

    and in the securing of landfills. The

    used machinery acquires a special

    leading role in this type of works

    and is decisive in the final cost of

    the operation. There exists a great

    variety of dredging equipment,

    which differentiate principally in the

    way of realizing the excavation.

    2 OBJECT OF DREDGINGThe dredging is carried out to

    increase the depth of waterway, to

    provide sufficient draft for ship or

    vessel is the vertical linear

    immersion of ship floating in stable

    conditions safely. Navigable depth

    of water is draft added with vertical

    clearance at bottom of ship. If the

    navigable depth required for ship is

    greater than depth of water available

    at site (entrance and basin of

    harbour) ship cannot enter into the

    harbour. Hence the port authorities

    have to decide whether to lose the

    sea traffic, or modify the basin

    characteristics to be improved at a

    harbour is to increase the depth of

    water at required locations in basin

    by dredging.

    3 MAINTENANCE DREDGING

    Dredging is defined as excavation

    under water and is done by earth-

    moving machine called dredger.

    These machines are designed to

    increase the depth of water by

    removing the bed material under

    water surface.

    The dredging may either be capital

    dredging or maintenance grudging.

    In capital dredging, the required

    depth of water at a particular place is

    obtained and it is then maintenance

    regularly to have a convenient

    harbour. Thus, capital dredging

    indicates initial removal of material

  • 8/12/2019 Aldrin Report

    2/12

    and the material removed may be

    anything from rock to slit. In case of

    maintenance dredging, the depth of

    water is maintained by carrying out

    dredging operations periodically and

    it is quite clear that the material

    obtained during maintenance

    dredging will be in the form of fresh

    deposits such as sand and silt only.

    It may be noted that maintenance

    dredging is one of the important

    activity at all the harbours and there

    is no harbour worth the name where

    maintenance dredging is not

    required. It may be noted that ports

    havebeen shifted in the past simply

    because the harbour or the entrance

    to it got silted up.

    Similarly, many harbours have been

    abandoned because of difficulties

    involving the overcome of silting of

    harbour or for providing more depth

    of water to ships of big size.

    4 DREDGING METHODS

    Currently there are three methods of

    sediment removal for inland water

    bodies; excavation on the water

    body basin, excavation from

    shoreline, and hydraulic

    dredging. Each of these ideologies

    has their respective

    limitations. Lets take a moment to

    explore each method looking at the

    advantages and disadvantages of

    each approach.

    4.1 Dredging of the Water Body

    Basin

    This technique involves the draining

    of the entire water body, waiting for

    the basin to dry, then the employing

    of traditional heavy equipment

    (excavators). Once all dredging is

    complete, then the water body is

    refilled.

  • 8/12/2019 Aldrin Report

    3/12

    Fig.1 Dredging Of The Water BodyBasin

    4.2 Dredging from Shoreline

    This technique involves the use of

    long reach excavators or drag line

    cranes to reach out into the water

    basin and pull sediment onto shore.

    Once at shore the sediment is placed

    in trucks and moved to disposal site.Fig. 2 Dredging From Shoreline

    Fig. 3 Dredging From Shoreline

    4.3 Hydraulic Dredging

    This technique uses a barge that

    pumps a combination of sediment

    and water to a discharge site. The

    water then effectively drains fromthe discharge area (spoils pit or

    sediment bags) and then returns

    back to the body of water.

  • 8/12/2019 Aldrin Report

    4/12

    Fig.4 Hydraulic Dredging

    Fig.5 Hydraulic Dredging

    5 DREDGER

    A dredger is an earth-moving

    machine, which is designed to

    increase the depth of water by

    removing the bed materials under

    the surface.

    The choice of a dredger primarily

    depends on the nature of sea bed, i.e.

    whether it is of loose materials orrocks. It is therefore important to

    carry out the preliminary

    topographic, geological and

    submarine geophysical surveys to

    decide the nature of sea bed.

    The study of such surveys will help

    in determining the following points:

    Actual volume of thedredged material

    Depth to be attained Length of dredged

    channels

    There has been considerable

    improvement in the dredging

    equipment of the present time and

    knowing the nature of sea bed and

    its characteristics, the most suitable

    type can be chosen or recommended.

  • 8/12/2019 Aldrin Report

    5/12

    The following are some of the

    modern types of mechanical dredges

    used in modern marine engineering

    practice.

    Dipper dredge Grapple dredge Continuous bucket

    elevator or Ladder

    dredge

    Hydraulic or Suctiondredge

    5.1 Dipper Dredge

    It consists of floating vessel strongly

    constructed carrying an include

    frame Ain the bow to hold the boom

    Bby guy wires. Through the middle

    of the boom runs a dripper stick,

    worked by a rack and pinion

    arrangement and to the end of which

    is rigidly attached the dipper bucket

    K, with a flap. A hoist cable is fixed

    to the bucket, to move it up or down.

    The vessel is fixed to the bed in

    position by means of three stakesduring the dredging operations. The

    boom B could be swing horizontally

    at the bow

    5.1.1 Operation:

    The hoist cable is released, to enable

    the bucket K to reach the bed when

    a continuous force is applied to the

    stick, through the rack and pinion

    forcing the teeth of the bucket to bite

    into the soil. The hoist cable is

    slowly pulled resulting in a cut being

    made in the bed. The hoisting is

    continued and the bucket K is

    hauled out of the water, the boom B

    is swing round to deposit the

    material in the bucket K, into any

    scow along side or on to any

    predetermined place, by opening the

    flap. The boom Bis swing back and

    the dipper is lowered, in preparation

    for the next cut.

    5.1.2 Advantages of dipper dredge:

    Easy maneuverable andhence, suitable for use in

  • 8/12/2019 Aldrin Report

    6/12

    confined spaces around docks

    and narrow channels.

    Very powerful and capable ofexcavating in hard soil for

    removal of boulders, and

    breaking up of heavy objects

    like old piles, cribs, etc. this

    type of dredge can dig in

    depths up to 15m of water and

    the dipper capacity varies

    from 1 to 4 m3 normally.

    These types of dredges of

    heavy capacities of about 12

    m3are in the Panama Canal.

    This type of dredger canexcavate and deposit it either

    on the blank or on a floating

    barrage.

    The dredger is very powerfuland capable of excavating in

    hard soil boulder beds and

    rocks, which break into largeheavy pieces.

    5.2 Grapple Dredge

    It consists of a hull, to the front of

    which are fixed a frame and a boom

    B. the frame is guyed back, by back

    legs. A grab bucket K is suspended

    by two cable lines HH called the

    opening and closing lines.

    The boom is fixed at the required

    elevation by means of a guy wire

    and arrangement to rotate through a

    horizontal angle on a pivot at the

    lower end. The bucket hoisting lines

    pass over two main sheaves fixed to

    the upper end of the boom B. the

    dredge is moored by the help of

    stakes fixed fore and aft.

    5.2.1 Operation:

    After positioning the dredge, a scow

    is brought alongside and tied fast to

    it, on the right side. The bucket is

    lowered to the bottom, where it bites

    the bed and fills itself. Then tension

    is put on the closing cable, which

    closes the bucket, hoists the load and

    swings the boom B horizontally to

    the right. When the boom B reaches

    over to the scow, the tensions in the

  • 8/12/2019 Aldrin Report

    7/12

    bucket and the boom B swings back

    to the digging position as before.

    The hull is generally 30 m to 60 m

    long and 15 m across, the booms

    being 15 m long. The capacity of the

    grab bucket ranges from 8 to 23 m3.

    5.2.2 Advantages of grapple dredge:

    This dredge is very efficient and

    suitable for dredging materials like

    sand, clay or mud, but not well for

    hard diggings. The bed dredged by a

    grab seldom be even and will exhibit

    pits and high spots.

    5.3 Continuous Bucket Elevator

    Or Ladder Dredge

    It consists of an endless chain of

    buckets, mounted and running round

    a ladder, formed in the middle of the

    bow of a floating vessel. The ladder

    could be is lowered of raised by the

    line N. The chain of buckets is

    operated, manually or mechanically

    by a big wheel E. the buckets are

    provided with pronged cutting

    edges.

    5.3.1 Operation:

    Each bucket cuts and brings up

    material to the top of the ladder as

    chain moves round, where each

    bucket inverts on descent and

    discharge its contents into special

    holds H-H. The vessel movesforward on completion of work at

    each section. The size of these

    vessels is about 60 m in length and

    15 m in width, having a draft of

    about 2.50 m to 3 m. these can be

    used for digging depths of 9 m to 12

    m. The average digging capacity of

    such a vessel is about 6000 m3 to

    7650 m3per day.

    5.3.2 Advantage of continuous

    bucket elevator or ladder dredge:

    This dredge is very suitable for

    handling coarse gravel or sand, hard

    clays and even soft or broken stone,

    at fairly good depths and beyond the

    reach of a dipper.

    5.4 Hydraulic Or Suction Dredge

  • 8/12/2019 Aldrin Report

    8/12

    It consists of a suction pipe, carrying

    at the lower end a cutter of some sort

    and having a universal joint at top.

    This pipe is supported on a ladder

    and held in position by an A frame

    mounted on the bow of the dredging

    vessel. The suction pipe is connected

    to a centrifugal pump located

    amidships having a long flexible

    delivery pipe discharging into

    hopper barges alongside the vessel

    itself or on to specially selected spot

    on shore, needing reclaiming or

    filling.

    5.4.1 Operation:

    The hull V carries the suction pipe

    on a ladder in the bow and the

    pumping machinery P is housed in

    the middle of the ship with its

    delivery pipe D discharging into

    hopper barges floating behind the

    dredging vessel. The cutter is

    suspended from a frame in front and

    the vessel is moored by anchors. The

    cutter rotates cuts and loosens the

    soil for quick and easy suction by

    the pump. The cutter up materials is

    well churned in the operation and

    mixed with water to facilitate

    suction.

    Sea going dredges of this type have

    a size varying from 45 m to 140 m

    in length and 9 m to 30 m in width.

    The dredging depths vary from 4.50

    m to 15 m. the machinery is

    operated either by stream power or

    electric power. The pump is a

    special type of dirt and rock brought

    out in dredging.

    5.4.2 AdvantagesOf Hydraulic Or

    Suction Dredge:

    This type of dredge is very effective

    in beds of sand, silt, mud and clay in

    open water and is an excellent

    machine to clear sand bars. If big

    boulders or tree stumps are meeting

    with, they will have to be lifted out

    before putting the cutter to work.

  • 8/12/2019 Aldrin Report

    9/12

    Gravel and soft rocks are easily

    reduced by the cutter.

    6 DISPOSAL OF DREDGEDMATERIAL

    Dredged materials are mainly

    disposed off in the following ways.

    Conveying out to sea anddeposited far from the siteof accumulation.

    Conveyed and deposited inswampy inland areas or

    adjacent to the shore to the

    reclamation of land.

    Disposal site selection for dredged

    material is one of the most important

    and challenging parts of planning a

    dredging project. The most common

    dredged material disposal methods

    are ocean placement, beach

    nourishment, confined disposal

    facilities (CDFs), flow-lane and

    within-banks placement, and capped

    disposal

    6.1 Ocean Placement

    Ocean Dredged Material Disposal

    Sites (ODMDS) are primarily used

    for material coming from inlets,

    coastal entrance bars, or main

    coastal navigation waterways.

    Typically, in ocean placement, a

    hopper dredge or towed barge sails

    to a designated area in the ocean,

    where the hull (bottom) of the vessel

    is opened. The dredged sediments

    drift to the bottom. Only clean

    dredged material may go to ocean

    sites.

    6.2 Beach Nourishment

    Beach nourishment is the placement

    of dredged material on or near the

    beach, usually to replenish an

    eroding beach or protect an eroding

    wetland. The dredged material is

    generally sand coming from inlets,

    coastal entrance bars, or main

    offshore waterways. Both hopper

    dredges and pipeline dredges can

    use beach nourishment sites. When

    hopper dredges place sand offshore

    along the beach, natural processes

  • 8/12/2019 Aldrin Report

    10/12

    carry it onto the beach over a long

    period of time. Only clean dredged

    material can be used for beach

    nourishment. This method of

    dredged material disposal is

    considered a beneficial use of

    dredged sands. It is used in coastal

    areas all around the country.

    6.3 Confined Disposal Facilities

    (CDFs)

    In Confined Disposal Facilities

    (CDFs), dredged material is placed

    behind dikes, which contain and

    isolate it from the surrounding

    environment. There are three types

    of CDFs: Upland, Shoreline, and

    Island. A mixture of dredged

    material and water is pumped into an

    area that is divided into several

    smaller areas, called cells. As the

    water moves between the cells, itslows, the dredged material settles

    out, and finally, clean water is

    discharged from the site. The

    difference in the three types of CDFs

    is their location. Upland CDFs are

    on land, above the line of high waterand out of wetland areas. Shoreline

    CDFs are constructed over the sea or

    lake bottom and are attached to the

    shoreline on at least one side. Island

    CDFs are constructed offshore, but

    in relatively shallow water.

    6.4 Flow-lane and Within-banks

    Placement

    Some waterways are in high-energy

    river systems with rapidly flowing

    water and strong currents. The

    energy of the water causes shoals

    made of coarse sand to form, move

    along the bottom, and re-form

    relatively quickly. In these systems,

    flow-lane or within-banks disposal

    may be used.

    6.5Capped Disposal

    Sometimes, but not often, dredged

    material is contaminated with

    metals, chemicals, or other

    substances. If the contamination is

    bad enough, it might be harmful to

    the environment to put the material

    in a typical in-water site or a typical

    CDF. In these cases special handling

  • 8/12/2019 Aldrin Report

    11/12

    will be used to prevent the

    contaminants from re-entering the

    environment during dredging and

    disposal.

    7 ENVIRONMENTAL

    IMPACTS

    Dredging can create disturbance

    to aquatic ecosystems, often with

    adverse impacts. In addition, dredge

    spoils may contain toxic chemicals

    that may have an adverse effect on

    the disposal area; furthermore, the

    process of dredging often dislodges

    chemicals residing

    in benthic substrates and injects

    them into the water column.

    The activity of dredging can create

    the following principal impacts to

    the environment:

    Release of toxic chemicals(including heavy

    metals and PCB) from

    bottom sediments into

    the water column.

    Short term increasesin turbidity, which can affect

    aquatic species metabolism

    and interfere with spawning.

    Secondary effects from watercolumn contamination of

    uptake of heavy

    metals, DDT and other

    persistent organic toxins,

    via food chain uptake and

    subsequent concentrations of

    these toxins in

    higher organisms including

    humans.

    Secondary impactsto marsh productivity

    from sedimentation

    Tertiary impactsto avifauna which

    may prey upon contaminated

    aquatic organisms

    Secondary impacts to aquaticand benthic

    organisms' metabolism andmortality

    Possible contamination ofdredge spoils sites

    8 LIMITATIONS OF

    DREDGING

    Can be very expensive

  • 8/12/2019 Aldrin Report

    12/12

    Need a disposal site Need large nearby

    handling area

    May be significantresiduals

    May need to over-dredge and remove

    debris

    May be significantlosses to resuspension or

    volatilization

    May be difficult to meetState WQS

    May be disruption tocommunity

    9 CONCLUSION

    Dredging is necessary for the ships

    to entering into the harbour. For

    entering, the depth of water

    available at the harbour must be

    greater than the navigable depth

    required for the ship. By discussing

    Dredging in harbour, we got the

    importance of dredging in harbour,

    method and disposal of dredged

    materials and clear idea about what

    types of dredging should be used in

    different situation and area.

    REFERENCE

    http://www.wikipedia.org http://www.dredging.com http://www.dscdredging.com http://www.vmi-dredges.com http://www.pla.co.uk R. Sreenivasan (2005),

    Harbour Dock and Tunnel

    Engineering.

    Environmental SolutionsLimited (2001).

    Environmental Impact

    Assessment: Port Antonio

    Yacht Club and Marina

    Project. Report submitted to

    Port Authority of Jamaica,

    Kingston, Jamaica.

    H.P.Oza & G.H.Oza (2005).Dock and Harbour

    Engineering