Barracuda

Brazil

Caratinga

The Largest Offshore Project Ever Awarded to a Single Contractor, at the time.

Client: Petroleo Brasileiro (Petrobras)/Barracuda & Caratinga Leasing Company (BCLCO)

Location: Campos Basin, Offshore Brazil

Scope: Engineering (Detailed Design), Procurement, Construction, Project Management, Installation, Commissioning, Start-up, Operations Support

Status: Barracuda Completed 2004; Caratinga Completed 2005

Details:• The Barracuda and Caratinga Fields are located in the Campos basin offshore Brazil in

deepwater.

• Water depth: 2,950 - 3,445 feet (900 - 1,050 meters)

• The EPIC contract included the construction of the wells; fabrication and installation of flowline and risers; and the construction and installation of two floating, production, stor-age and offloading vessels (FPSOs).

• FPSO Storage capacity: 2,000,000 bbl each

• FPSO Production capacity: 150,000 bopd and 210 mmscfd gas each

• Hulls were converted in Brazil and Singapore

Highlights:• Reinvigorated local fabrication facilities and capabilities

Barracuda & Caratinga

FPSOs

CaratingaBarracuda