Bimini Airport Runway BHM CO. LTD Background The development of Bimini Bay Resort will bring with it significant growth in visitors in the future. Made up of three islands, North Bimini, South Bimini and East Bimini, Bimini is the closest point in the Bahamas to the USA. The airport is situated on the South Island, with Bimini Bay Resort, the Port and the majority of the amenities located on the North Island. Movement between the islands is only possible by boat. To accommodate the anticipated growth in visitors to Bimini, the infrastructure needed significant improvements, including an extension to the existing runway to accommodate larger planes. Project Description BHM was appointed as Main Contractor to undertake significant improvements to the airport’s existing airside infrastructure. The project included the extension of the existing runway by 1,000ft, increasing the area of the existing apron by nearly 200% and the construction of a new taxi-way onto the runway to supplement the existing. The whole project required BHM to undertake bulk earthworks, grading and HMA paving. Runway extension and Apron expansion Client: OPAC Ltd, Bimini Bay Resort Services Provided Risk Management Value Engineering 1,000 foot runway extension Increased apron capacity and additional taxiway Asphalt mix design including quality assurance services Benefits to Customer Economic benefit achieved for the Bimini Economy new runway and apron ensures greater airlift capacity in terms of quantity and size of planes Zero accidents / incidents during project ensuring high levels of safety and security Minimal disruption caused as works carried out to suit current airport operations Integrated team working with the Client and the airport operators www.bhm.construction

Biini Airport Runway - bhm.construction · • Management of construction • Risk management • Value engineering • Design management of surfacing materials • Dedicated mixing

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Biini Airport Runway - bhm.construction · • Management of construction • Risk management • Value engineering • Design management of surfacing materials • Dedicated mixing

BHM branding - February 2014

Bimini Airport RunwayBHM CO. LTD

Background

The development of Bimini Bay Resort will bring with it significant growth in visitors in the future. Made up of three islands, North Bimini, South Bimini and East Bimini, Bimini is the closest point in the Bahamas to the USA. The airport is situated on the South Island, with Bimini Bay Resort, the Port and the majority of the amenities located on the North Island. Movement between the islands is only possible by boat. To accommodate the anticipated growth in visitors to Bimini, the infrastructure needed significant improvements, including an extension to the existing runway to accommodate larger planes.

Project Description

BHM was appointed as Main Contractor to undertake significant improvements to the airport’s existing airside infrastructure. The project included the extension of the existing runway by 1,000ft, increasing the area of the existing apron by nearly 200% and the construction of a new taxi-way onto the runway to supplement the existing. The whole project required BHM to undertake bulk earthworks, grading and HMA paving.

Runway extension and Apron expansion Client: OPAC Ltd, Bimini Bay Resort

Services Provided• Risk Management• Value Engineering• 1,000 foot runway extension

• Increased apron capacity andadditional taxiway

• Asphalt mix design including qualityassurance services

Benefits to Customer• Economic benefit achieved for the

Bimini Economy• new runway and apron ensures greater

airlift capacity in terms of quantity andsize of planes

• Zero accidents / incidents during projectensuring high levels of safety and security

• Minimal disruption caused as workscarried out to suit current airport operations

• Integrated team working with the Client and the airport operators

www.bhm.construction

Page 2: Biini Airport Runway - bhm.construction · • Management of construction • Risk management • Value engineering • Design management of surfacing materials • Dedicated mixing

BHM branding - February 2014

Lynden Pindling International AirportBHM CO. LTD

Expansion of existing International AirportClient: Nassau Airport Development Company

Services Provided• Management of construction• Risk management• Value engineering• Design management of surfacing materials• Dedicated mixing plant,• Pavers and ancillary equipment• Liaison with all stakeholders• Consideration of local environment

and neighbours

Benefits to Customer• Safety and security within airside

and public environments• On-site impact kept to a minimum

on operational airport• Working to tight time frames to suit airport operations• Integrated team working with the Client and airport operators• Close working relationship with other contractors on site• Accelerated construction programme• Staged completion and early access for Client and other contractors fit out• Ability to accommodate design changes during construction• Innovative solutions

BackgroundNamed after Sir Lynden Pindling, the first Prime Minister of the Commonwealth of The Bahamas, the airport sits just west of Nassau. The expansion of the airport was essential to attract and accommodate up to 5 million passengers annually and become one of the top world-class airports in North America.

With US pre-clearance facility, the airport offers Americans and transit passengers to and from the United States, who will make up 80% of passengers in the future, the added advantage of transitioning through US Customs and Immigration before leaving The Bahamas.

The expansion of the airport was undertaken in three stages. Stage One - US Departures Terminal. Stage Two - construction of a new International Arrivals Terminal and Pier. Stage Three - the construction of a new International Departures Terminal, together with a new Domestic Terminal.

Project DescriptionBHM contracted by Nassau Airport Development Company for the construction of airside and landside civil engineering works • Taxiway widening and surfacing for aprons• Pier B apron surfacing and concrete drive bridge pads• Widening culvert, installation of drainage and utilities• Airfield lighting, elevated LED Edge and taxiway lighting• Full construction including utilities, drainage, surfacing,

lighting & landscaping for:-▪ Long, short term and rental car parking area;▪ Taxi, bus and limousine holding areas;

www.bhm.construction

Page 3: Biini Airport Runway - bhm.construction · • Management of construction • Risk management • Value engineering • Design management of surfacing materials • Dedicated mixing

BHM branding - February 2014

Marsh Harbour RunwayBHM CO. LTD

Construction of new parallel runwayClient: Ministry for Public Works and Transport, Bahamas

Services Provided• Risk management• Value engineering• Construction of a new 6100 feet

jet runway• Conversion of original runway into

a jet way• Runway and taxiway electrical works

Benefits to Customer• Economic benefit achieved for

the Abaco economy.

• New scheme ensured compliance withthe International Civil AviationOrganisation requirements.

• Safety and security within airside and public environments

• On-site impact kept to a minimum on an operational airport

• Working to tight time frames to suit airport operations

• Integrated team working with the Client and airport operators

• Close working relationship with other contractors on site

BackgroundAbaco has around 90,000 visitors every year; Marsh Harbour Airport is the second busiest airport in the country and one of the busiest airports in the entire Caribbean region. The building of the new Marsh Harbour airport terminal, air traffic control tower and fire/crash rescue facility and new runway was designed to enhance Marsh Harbour Airport’s capacity to provide quality service to the growing number of Abaco residents and visitors.

Project DescriptionBHM was appointed as a major specialist subcontractor to support and collaborate with the main contractor FES Construction. The project included the construction of a new parallel runway, including site clearance, bulk earthworks, HMA paving, runway lighting, signage and approach lighting. It also required the rehabilitation and extension of the existing runway and associated taxiway links.

www.bhm.construction

Page 4: Biini Airport Runway - bhm.construction · • Management of construction • Risk management • Value engineering • Design management of surfacing materials • Dedicated mixing

BHM branding - February 2014

Norman’s Cay Runway BHM CO. LTD

Construction of New Runway, Apron and MarinaClient: Exuma Resort Developers Limited

Services Provided• Design and build project, progressing

initial contract design• Construction of a new runway,

4,700 feet long• Excavation of a marina• Reclamation of Ocean for runway extension• Environmental monitoring• Value Engineering• Logistic support during construction.

Benefits to Customer• Completion of the runway, aircraft parking apron, shore protection, fencing, roads and marina• New scheme will ensure compliance with International Civil Aviation Organisation airfield requirements• Ability to accommodate design progression and changes during construction• Able to satisfy the requirements of Bahamas Environment, Science and Technology Commission• Phasing of the project to maintain the operation of the existing runway.

BackgroundThe existing Norman’s Cay Airstrip was in poor condition and only 3,000 feet long; the airfield did not comply with international regulations for flight operations.

The client is intending to develop an upscale resort and luxury housing on the Cay and wished to upgrade the airfield so that it could become a point of entry into the Bahamas. A marina was also to be developed for the use of the residents and guests.

Project DescriptionBHM was appointed main contractor for the runway and marina works. The project includes the excavation of a marina which provides fill for the bulk earthworks for a new runway built partially on reclaimed land. Also included in the project are surface dressing, shore protection, sand seal road, fencing and traffic marking works. Due to the environmentally sensitive nature of the surroundings, inclusive of a National Marine reserve, a high degree of environmental compliance was established on the project.

www.bhm.construction

Page 5: Biini Airport Runway - bhm.construction · • Management of construction • Risk management • Value engineering • Design management of surfacing materials • Dedicated mixing

BHM branding - February 2014

Marsh Harbour International AirportBHM CO. LTD

Background

As part of wider infrastructure upgrades on Abaco Island, BHM completed the contract for the rehabilitation of North Abaco Settlement Roads over a distance of 33 miles.

Project Description

Our scope of works included:

• Bulk Earthworks

• Shaping and grading

• Traffic management to ensure works carried out safely

• Edge treatment and making good of existing surface

• New chip and sand seal roads construction

• Thermoplastic road markings

TitleClient: Name

Services Provided

• Value Engineering

• Risk Management

• onstruction management

• Traffic management

• Ashpalt Design

Benefits to Customer

• Single point of contact for client

• Works planned to minimize impacton road users

• High standards of quality andsafety management

• In house plant and materials

• Employment of skilled local workforce

www.bhm.construction

DATA SHEETUNDER CONSTRUCTION