Tank cleaning : oil sludgecontrol & homogenization with
P43 Jet Mixers
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
2/13
1
Blancon: a solutions oriented company
Blancon offers two approaches to hydrocarbon tank cleaning. These may be combined or
engaged separately depending on the specific tank conditions and client objectives.
Method A: Conditioning and fluidification of heavy sludge with waterbased, non-toxic, non surfactant Petromax formula: Heavy, solidsludges, including tank bottom cleaning, oil pits/ lagoons, sandy oil/slurry cleaning
Method B: Oil mixing and resuspension using P43 oil jet mixersfrom: Lighter sludges, sludges requiring re-suspension,general tank cleaning where sludges are not solid or the tankcontains a sufficient amount of good oil to be used in recirculationor new oil can be added to help the resuspension, as well as no veryhigh content of BS&Ws
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
3/13
2
Tank cleaning that necessitates only10 days of production down-timeAn example of tank de-sludging operation of a 70.000m3 floating roof flat bed tank with over 2.000 m3 sludge
Blancon offers a safe, fast and efficient method to remove unpumpable tank bottom sludges while
eliminating the high disposal costs by at clients request - recovering the previously unusableproduct for customers use
Complete mobility of our equipment allows us to respond to tank cleaning problems quickly in acost-effective way
Safety of plant, equipment and crews represent paramount priorities throughout our operations
All of our operators are trained to the highest standard to undertake any tank or vessel
cleaning operation
Equipment equipped to meet hazardous work area requirements
Non man entry
Blancon offers a complete desludging service available whenever the need may arise
to reduce your tank bottoms.
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
4/13
3
Blancons tank cleaning solution is broader and more extensive,and probably the fastest and safest method available
Sludge minimization De-sludging Tank cleaning Oil recovery
Blabo (Oreco)
COWS (Taiho)
GasTight (Hydrochem)
SuperMacs (3i) Phaser (3i)
Hydrodozer (Willacy)
Manual labor
Advanced, high volume
P43 jet mixers at up to800 m3/h/unit
Can convert 90% of theoriginal volume of sludge to
salable material
Heavy sludge mobilization
and tank bottom cleaning Remove all remaining and
tough sludge to prepare thetank for inspection and hot-
work
Advanced technology to
deliver the best level ofrecovery
Recover up to 99% ofhydrocarbons
Oil lagoons andand recovery
Up to 99% recovery
of oil from lagoonsand pits
Environmental cleanup and remediation
Blancon
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
5/13
4
High volume sludge reduction without man-entry
Blancon uses a proven system/Rotary Jet
Mixers P43 - Veolia that works by directinga submerged jet of crude oil across thebottom of the storage tank
Dissolves and re-suspends theaccumulated sludge throughout theoverhead oil
Fluid dynamically powered
Valuable hydrocarbons are re-suspended intothe crude oil and not wasted (up to 90-95% oilrecovery)
The shell-mounted system is designed to be
placed at the tank wall
Normally using the existing tank shell manwayfor mounting
The solution is suitable for all roof types(floating roof application requires the legs ofthe roof to be out of the main operatingstream)
Note: Veolia Environmental Services UK plc isthe owner of P43 technology made in UK
Blancon offers solutions for very heavy build-ups where jetting may not be optimal
as well as oil and sludge treatment and separation services
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
6/13
5
Methodology overview: 10 days down-timeAn example of tank de-sludging operation of a 70.000m3 floating roof flat bed tank with over 2.000 m3 sludge
Stage 1: Client bottoms tank
The tank is bottomed to allow access through themanway covers for the jet mixers.
Degassing: This operation should be carried outbefore our specialist operators arrive on site.
Samples of sludge are taken to measure the
percentage in BS&Ws (Bottom Sediment&Water) and the sludge profile is carried out
Day 1 & 2 : Site preparation & installation
The site is prepared and the jet mixers areinstalled in the tank, mounted on custom-mademanway covers.
Then the high-volume pumps are connected,ready for the de-sludging operation
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
7/13
6
Methodology overview (continued)
Days 3 & 4: Re-filling the tank
After a thorough check of the installation, the clientrefills the tank to a pre-determined level with lightcrude.
The crude oil has to be sampled and BS&W levelsare measured
Days 5 & 6 : The cleaning process putting
the hydrocarbons back into suspension
The specialist team set the de-sludging operation inprogress by re-circulating the light crude andpumping it back into the tank at 700M per hour perunit.
As the jet mixer units rotate slowly inside the tank,the jet of crude will sweep up the sludge cutting, re-suspending and homogenizing it in the overhead oilready for normal refining processes.
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
8/13
7
Methodology overview (continued)
Day 7: Re-suspension completed
The crude should now be homogenized, withsoluble hydrocarbons in suspension and readyfor processing. At this stage the tank is drainedto a holding tank and the effectiveness of theoperation assessed. If there is still a largeamount of solids not suspended the operation isrepeated but for a shorter period.
Day 8 : Equipment removed tank now
available for re-use
After removal of the Jets/shell mounted de-sludging equipment, any small amounts of (ifany) remaining residues can be handled byconventional methods.
Alternatively, the tank can be put straight back
into operation for storing crude.
A typical test with 2600 m3 sludge showed that after a 15h-
operation, 2300 m3 are re-suspended, whereas after a 30h-
operation up to 2500 m3 were re-suspended.
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
9/13
8
P43 Jet mixer and cleaning process scheme
P43 : Shell-mounted machine
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
10/13
9
-Installation for sludge control and homogeinization: 57 oil companies
-Companies that specify P43 as standard equipment: 14 companies in 6 countries
Some of the clients:
More than 600 tanks worldwide have been treated using this approach
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
11/13
10
Optional final full slop oil separation and treatment system overview
Note: Illustrative example. Actualconfiguration and units may change.
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
12/13
11
Oil processing, dewatering and recovery
Continuous processing of extracted slope, or contaminatedsoil, and separating it into its base components for disposal,or re-use
2 stage and 3 stage, including centrifuging
Separation of oil, water and inorganics
Reuse of hydrocarbons
Reduced slope volume
Minimal waste generated
Environmental remediation applications for oil-contaminatedsoils etc.
Provides a cleaner and more liquid free cake in a 3 phase separation process*
Offers cleaner oil free tanks in preparation for inspection and repairs
* As tested by US Filter on their dewatering equipment, yielded asignificantly drier cake. Instead of the usual 30% - 40% liquidcontent on the filter test, the conditioned slope yielded a result of17.5%
** Results may vary
< 1% Water in Oil Content
< 0,2% of Sediments in Oil**
8/6/2019 Blancon Sludge Re Suspension R2-P43-En
13/13
12
Calle La Resina 37,Nave 1128021 Madrid,Spain
www.blancon.net
(+34) 91.723.15.02
Blancon is a leading provider of industrial support, and maintenance
solutions, delivering premium quality, technology-based services
Our highly qualified, multi-craft personnel are ready to respond to our
customers needs 24-hours per day, 365 days per year
Blancon is headquartered in Madrid, Spain, and through highly mobile
service crews, works with our partners in Mexico and Libya to serve
markets throughout the world
Grupo SAPSAIndiana 260-835, Col. NpolesMxico, 03810 D.F.Mxico City, Mexico(+52) 55.5598 9851
Al Amaq Blancon Oil Field Services CoSalah City St, Hay Al Andalus GargareshTripoli, Libya(+218) 21.478.0498