Business Communication Case Study

  • Upload
    -

  • View
    229

  • Download
    0

Embed Size (px)

Citation preview

  • 8/20/2019 Business Communication Case Study

    1/15

    ***

    A Report on

    PROJECT COMMUNICATION MANAGEMENT

    On Project Site of

    CRESCENT BAY, PAREL, MUMBAI

    Submitted to:

    Dr. (Mrs.) Kirti Rajhans

    Submitted By:

    Anshul Sharma AP14049

    Ashish Mishra AP14067

    Swapnil Gajghate AP14145

    Avinash Sharma AP14177

     Nikhil Bakane AP14189

  • 8/20/2019 Business Communication Case Study

    2/15

    ***

    Contents

    1.  Introduction

    2. 

    Current Status of the Project Communication

    Case: Communication Failure

    3. Communication Challenges

    4. Stakeholder Identification

    5. Change Management 

    Case: Resistance to Change

    6. 

    Risk Management 

    7.  Communication Management Plan

  • 8/20/2019 Business Communication Case Study

    3/15

    ***

    Introduction 

    The project discussed in this report is a residential project named CRESCENT BAY

    situated in Parel, Mumbai. It comprises of three towers including G+22, G+32, and

    G+ 21.

    The first tower is currently under progress on 8th floor and the second one is on 30th 

    floor. The third tower is under Handing-Over Process.

    The Client is L&T Realty, the real estate arm of the construction giant, L&T.

    The Contractor is L&T IF&BC.

    The project involved high end construction technology and the involvement of high

    end customers which increases the credibility of the project. The project has seen

    about 90% of flats got sold during the announcement of the project. This shows the

    company’s popularity in the market.

    This report deals in the communication pattern seen during the process. The current

    status of project communication is cited so as to make you visualize the actual

    scenario and then followed by the challenges involved. The stakeholder management

    is described with preparing a Power/Interest Grid. The Change Management was

    found to be an integral part of project communication which needs urgent attention

    on site. This is displayed with the messages followed by solutions. The Risk

    Management strategy involves the most important proactive approach in project

    communication to solve problems and gain successful project completion.

    There are two cases described to support the report in order to have a practical

    understanding of the bottlenecks and solutions to the same during the

    communication process.

  • 8/20/2019 Business Communication Case Study

    4/15

    ***

    Current Status of the Project Communication

    The communication pattern involved the reporting system, coordination between

    the active stakeholders and timely execution of payment process. The

    communication during the progress stage (execution) involves a high level of

    ambiguity. There the lower level management and the direct field engineers are

    involved in the process. The miscommunication and inefficient way of delivering

    the information was found to be the bottleneck.

    The right information was not being passed to the right person at the right time.

    This violates the basic against an effective project communication. There were

    cases where there had been conflicts which were just the effect of ineffective

    communication.

    The reporting was done from the junior level to the top most senior level. This

    whole scenario was understood and the result was found that here the process was

     better than the previous case. This was due to the involvement of top management

    in the loop.

    The co-ordination between the Client, contractor and the JV partner was an

    important part of communication. This involved coordination and proper planning

    so as to not cause any delay in the handing over process. It is estimated that

    generally there is a significant amount of delay during handing over process of a

     project. This is due to unnecessary causes which needs attention at the right time

    and need to be attended at the required time. The communication failure at thisstage will lead to significant delay in time and finally will lead to cost overruns.

    The JV partner is not informed for inspection time and schedule by the client

    which led to unnecessary delays. The contractor could not effectively manage in

    communicating the requirements during the process.

    There was a case when the JV partner was called for inspection along with client

    and there was a dispute related to not bringing the required document for the

     process. The JV partner accused the client of not communicating them about the

    same and the contractor was not aware of the situation. This led to complaint to the

    Project Head from the JV partner side.

    The billing process needs special attention while communicating the required

    documents and the information needs to be put at the right place or else it would

    lead to significant losses.

  • 8/20/2019 Business Communication Case Study

    5/15

    ***

    Project Review Meeting is a place where one can actually see the causes and

    effects of project communication failures. The boss is always ready to hit the

    accused harder and make him on his knees.

    This is the stage where there is organized communication as well as lot of

    interdependency involved.

    A diagrammatic view of the communication is shown below:

    Progress,Quality and

    SafetyReporting

    Co-ordinationbetween the Client,Contractor and JV

    Partner duringHanding Over

    Progress

    Timelyexecution of

    Billing Process

    Project ReviewMeetings

  • 8/20/2019 Business Communication Case Study

    6/15

    ***

    Case: Communication Failure

    Situation: Erection was under process for 12th floor at the G+22 Tower. The 10th 

    and 11th floor has been successfully completed. There was a particular wall panel

    which was erected for the 10th, 11th and 12th floor. It was 8days since the erection

    has been done. The site supervisor was dealing with day to day activities. The

    contractor ’s site engineer was involved in the supervision of the site execution and

    the client’s site engineer was monitoring the progress. During an internal quality

    audit it was found that the wall panel which was erected had not been grouted for

    the current floor and the two floors below.

    This is a serious quality issue which was communicated directly to the top

    management.

    Analysis: The situation arouse due to negligence and negative attitude carried by the

    site supervisor. This led to incomplete transfer of information to the Site engineer

    and this was carried forward the client side. This is a typical case of not having the

    communication in the right way at the right time and to the right person.

    The site supervisor could have saved this from happening if the information was

    immediately forwarded to his seniors and immediate action would have been taken.

    Response: The response to the situation was strict and led to both impact

     positively and negatively. The Contractor ’s site In-charge was given

    serious warning and was held responsible for the case. This gave a

    message to the project team to follow the company’s policy and meet the

    requirement s of the job.

  • 8/20/2019 Business Communication Case Study

    7/15

    ***

    Communication Challenges 

    Construction projects are complex and risky, requiring the active participation of all

    contributors. Cooperation and co-ordination of activities through interpersonal and

    group communication are essential in ensuring the project is completed successfully.

    Poor communication, lack of consultation and inadequate feedback are to be found

    as the root cause of defects in many constructed works. Poor co-ordination and

    communication of design information lead to design problems that cause design

    errors. Communication is the one aspect of the management of projects that pervades

    all others.

     

    The organization of human, financial and material resources: People are

    very unpredictable and as such, require different skills and competencies if

    they are to be managed effectively.

      A unique scope of work and specification: This demands that project

    managers generate a bespoken communication strategy for every project.

     

    Constraints of cost and time: Rapid and precise communication strategy is

    required.

      Quantitative and qualitative objectives: The PM needs to meet stakeholder

    needs and to communicate this effectively to them.

      The inter-dependence of project participants such as VP >PM >SR ENG>JU

    ENG.

       Need to respond to sudden changes in workload.

     

    The labour intensiveness of construction activity  – using of only regional

    language

      Jargon, semantics and the potential for misunderstandings-don’t have

    knowledge of symbols and technical meanings.

  • 8/20/2019 Business Communication Case Study

    8/15

    ***

     

    An ingrained male-dominated culture.

    Many problems concerning communication have been reported, with a focus on

    intra-supplier communication within the construction sector; demand-supply

    communication during the design phase; and communication between and within

    single demand and supply side parties, during whole the construction process.

    In our company, there was a confusion due to communication gap between engineers

    and supervisors as they were using local names for process such plumb, skirting

    activities. They referred to plumb to Olamba and skirting as Beda, which created a

    sense of ambiguity between engineers and supervisors.

    The communication between supervisors were in regional language. When

    supervisors were discussing the activities related problems, engineers find it difficult

    to understand.

    There was a communication gap between execution team and sales team. The

    execution team were not having any information related to carpet area and selling

    rates.

    The consultant visited site weekly .He found out the various technical flaws which

    were not communicated to quality department in time, flaws such as proper cover to

    reinforcement.

  • 8/20/2019 Business Communication Case Study

    9/15

    ***

    Stakeholder

    Internal

    Client

    Project Head

    Project Manager

    Line Managers

    Site Engineers

    Contractor

    Project Manager

    Line Managers

    Site Engineers

    Supervisor

    Foreman

    Sub Contractor Consultant

    Structural

    Architectural

    MEP

    External

    J V Partner

    Sponsors

    Supplier/Vendor

    Customer

    Govt. /Regulatory

    Bodies

    Public/ LocalBody

    1. Govt. Regulatory Body

    2. Consultant

    1.Client  – Project Head,Project Manager

    2. Vendor/Supplier

    3. Sponsors

    4. JV Partner

    1. Public

    2. Local Body

    1. Customer

    2. Contractor  – PM andTeam

    3. Sub- Contractor

    Stakeholder Identification

    Power / Interest Grid

    Interest 

         P    o    w    e    r

  • 8/20/2019 Business Communication Case Study

    10/15

    ***

    Change Management

    Messages about the change: -

    • 

    the current situation and the rationale for the change

    •  a vision of the organization after the change takes place

    •  the basics of what is changing, how it will change, and when it will change

    •  the expectation that change will happen and is not a choice

    •  status updates on the implementation of the change, including success stories

    Messages about how the change will impact the employee: -

    • 

    The impact of the change on the day-to-day activities of the employee

    (WIIFM –  What’s in it for me?) 

    •  Implications of the change on job security (Will I have a job?)

    •  Specific behaviors and activities expected from the employee, including

    support of the change

    •  Procedures for getting help and assistance during the change

    Aspects for Successful Communication - Change 

    o  Direct communications were seen as successful for conveying messages

    about the need for change, providing details about specific roles and

    expectations, describing the future state and answering specific questions.

    In addition to how the message was delivered, participants provided

    characteristics of communications that contributed to success.

    According to participants, successful communications were:• 

    honest –  “Honesty even when the consequences were possibly negative” 

    •  frequent and constant throughout the entire program

    •  consistent

    •  open, transparent and safe

  • 8/20/2019 Business Communication Case Study

    11/15

    ***

    Case: Resistance to Change

    All the planning engineers were well equipped in working with excel but at times

    certain reports needed to be generated on Gantt Chart which included proper

    sequence of work along with the durations and constrains (e.g. Must start on, mustend on, as soon as possible etc.)

    As the contractor had to abide by the requirements of client. The contract introduced

    MSP i.e. Microsoft projects into their work so steadily the work force came up with

    some issues when change was being implemented into the work culture.

    Some of the resistances were as follows on the individual level

    Habitual with all the work on excel as it solved most of the issues on tracking and

    monitors.

    Fear of unknown like some were afraid to work with complex commands and how

    to defend them.

    All this took the shape of group inertia.

    Due to this all the workshops arranged saw poor engagement when it came to

    working on the software

    At the very end with the change management saw the intervention of the projectmanager then work force was willing to accept it at a better level than expected due

    to the following things he did

    Motivating the change so as to diversify their reach on project, explaining the

    requirement of the current economic condition and also induction of positive fear to

     perform as they may get left out with primitive skills.

    Creating a vision of change and convincing them that this Change will initiate

    clarification of goals and seeing through the allocation of resources and developing

    alternative techniques to works to be done.

    Explaining the takeaway for employees with respect to knowledge and skill

  • 8/20/2019 Business Communication Case Study

    12/15

    ***

    Learning from this study is that

      Active participation of the management people or even a in-charge will do

    wonders

      Proper Negotiation and Manipulation can help both the parties (employees

    and project manager) involved achieve their profits at individual level

    collectively leading to the organisational good.

      Change has to be initiated slowly and has to be made understood and bring in

    to the work culture

  • 8/20/2019 Business Communication Case Study

    13/15

    ***

    Risk Management

      Explaining in detail the nature of a risk, how it may affect your project, and

    how you estimated the likelihood of its occurrence. The risks that are

    associated with time overrun like penalty, overheads were discussed.

      All the variances which were calculated by planning department were

    communicated to the execution team so that they can take remedial measures

    accordingly at the right time.

      Encouraging people to think and talk about risks, meetings were

    conducted every 15  – 20 days that included client, contractor, sub-contractor

    and consultant. DELPHI and Brainstorming methods were used to find out

    and mitigate the risks.

      Maintaining a risk register in which all the risk related data is documented;

    this is referred throughout the duration of the project.

      Telling people the current chances that certain risks will occur, how

    you’re minimizing the chances of problems, and how they can reduce the

    chances of negative consequences.

    Delphi Technique:

    The Delphi method is a structured communication technique or method, originally

    developed as a systematic, interactive forecasting method which relies on a panel of

    experts. The experts answer questionnaires in two or more rounds. After each round,a facilitator or change agent provides an anonymous summary of the experts’

    forecasts from the previous round as well as the reasons they provided for their

     judgments. Thus, experts are encouraged to revise their earlier answers in light of

    the replies of other members of their panel. It is believed that during this process the

  • 8/20/2019 Business Communication Case Study

    14/15

    ***

    range of the answers will decrease and the group will converge towards the "correct"

    answer. Finally, the process is stopped after a predefined stop criterion (e.g. number

    of rounds, achievement of consensus, and stability of results and the mean or median

    scores of the final rounds determine the results.

    Delphi is based on the principle that forecasts (or decisions) from a structured group

    of individuals are more accurate than those from unstructured groups. The technique

    can also be adapted for use in face-to-face meetings, and is then called mini-Delphi

    or Estimate-Talk-Estimate (ETE). Delphi has been widely used for business

    forecasting and has certain advantages over another structured forecasting approach,

     prediction markets.

    Brainstorming Technique:

    Brainstorming is a group creativity technique by which efforts are made to find a

    conclusion for a specific problem by gathering a list of ideas spontaneously

    contributed by its members. The term was popularized by Alex Faickney Osborn in

    the 1953 book Applied Imagination. Osborn claimed that brainstorming was more

    effective than individuals working alone in generating ideas, although more recent

    research has questioned this conclusion. Today, the term is used as a catch all for all

    group ideation sessions.

  • 8/20/2019 Business Communication Case Study

    15/15

    ***

    Communication Management Plan 

    Nature of

    Communicati

    on

    From To Purpose Frequenc

    y

    Delivery

    media

    Contractor

    related

    document

    submission

    Contractors Client Document

    register/Recor 

    ds

    At the

    start of the

     project

    Hard copy

    submission

    Project update Contractors Client / JV

     partner

    Project

     progress

    update

    Daily Email/Telepho

    ne

    Design change

    intimation

    Client/Archite

    ct

    Contractors Design

    change

    implementatio

    n

    When

    received

    Verbal update,

    Email, Memos

    Issues Contractors Client Major site

    issues

    resolution

    requests

    As needed Email

    Request for

    information

    Contractors Architect/P

    MC

    Design query

    resolution

    As needed Email

    Contractor

    invoices

    Contractors Client Invoice

    certification

    and payment

    Monthly/

    As needed

    Email, Hard

    copy

    submission

    Site

    instructions

    Client/Archite

    ct

    Contractors Minor query

    resolution

    As needed Verbal, site

    instruction

     book

    Handover

    documents

    Contractors JV Partner/

    Client

    Records,

    O&M

    manuals

    At the end

    of project

    Hard copy

    submission