Page 1: C ONSTRUCTION  R EPAIR M AINTENANCE

1

CCONSTRUCTION ONSTRUCTION

RREPAIREPAIR

MMAINTENANCEAINTENANCE

Donna SummersDonna SummersApril 10, 2013April 10, 2013ACE AcademyACE Academy

Page 2: C ONSTRUCTION  R EPAIR M AINTENANCE

2

My Contact Info

Donna Summers

NJDEP – Air Compliance & Enforcement

Southern Regional Office

856 – 614 – 3601

[email protected]

Page 3: C ONSTRUCTION  R EPAIR M AINTENANCE

3

Ground Rules

• Ask questions anytime

• CRM = Construction Repair Maintenance

• SOTA = State Of The Art

Page 4: C ONSTRUCTION  R EPAIR M AINTENANCE

4

CONSTRUCTION

Page 5: C ONSTRUCTION  R EPAIR M AINTENANCE

5

Page 6: C ONSTRUCTION  R EPAIR M AINTENANCE

6

Page 7: C ONSTRUCTION  R EPAIR M AINTENANCE

7http://www.nj.gov/dep/aqpp/permitguide/PermitApplicabilityConstSites.pdf

Construction Sites

January 6, 2010

Page 8: C ONSTRUCTION  R EPAIR M AINTENANCE

8

REPAIR

Page 9: C ONSTRUCTION  R EPAIR M AINTENANCE

9

Page 10: C ONSTRUCTION  R EPAIR M AINTENANCE

10

Page 11: C ONSTRUCTION  R EPAIR M AINTENANCE

11

Page 12: C ONSTRUCTION  R EPAIR M AINTENANCE

12

Page 13: C ONSTRUCTION  R EPAIR M AINTENANCE

13

MAINTENANCE

Page 14: C ONSTRUCTION  R EPAIR M AINTENANCE

14

Page 15: C ONSTRUCTION  R EPAIR M AINTENANCE

15

Page 16: C ONSTRUCTION  R EPAIR M AINTENANCE

16

Page 17: C ONSTRUCTION  R EPAIR M AINTENANCE

17

132 yr old Howland Croft Bldg Camden, NJ 6/6/11

Page 18: C ONSTRUCTION  R EPAIR M AINTENANCE

18

Page 19: C ONSTRUCTION  R EPAIR M AINTENANCE

19

TWO TYPES: Type 1 - Tool

• equip itself does the CRM work

• just a tool needed to directly do CRM work

• don’t normally need this equip• Not replacing anything…just an extra temporary “tool”

Page 20: C ONSTRUCTION  R EPAIR M AINTENANCE

20

TWO TYPES: Type 2 - Replacement

• equip replaces a source undergoing CRM • do normally use the equip• replacement source needed because of and during CRM

Page 21: C ONSTRUCTION  R EPAIR M AINTENANCE

21

COMPARISON OF TWO TYPES

• Equip itself does the CRM work

• Portable

• < 1 yr

• Emission limits: none

• No notification needed

• Equip replaces a source undergoing CRM

• Portable

• < 90 days

• Emission limits: <SOTA

• YES notification needed

Page 22: C ONSTRUCTION  R EPAIR M AINTENANCE

22

NOTIFICATION PROCESS

Page 23: C ONSTRUCTION  R EPAIR M AINTENANCE

23

NOTIFICATION

• Free

• 2x: before (due anytime) & after (due within 30 days)

• Electronic…..website

Page 24: C ONSTRUCTION  R EPAIR M AINTENANCE

24

Page 25: C ONSTRUCTION  R EPAIR M AINTENANCE

25

Page 26: C ONSTRUCTION  R EPAIR M AINTENANCE

26

Page 27: C ONSTRUCTION  R EPAIR M AINTENANCE

27

Remember: Notif Forms only apply to Type 2 (Temp Replacement Source)

Page 28: C ONSTRUCTION  R EPAIR M AINTENANCE

28

Page 29: C ONSTRUCTION  R EPAIR M AINTENANCE

29

Page 30: C ONSTRUCTION  R EPAIR M AINTENANCE

30

What info is needed for the INITIAL notif.

• Contact info

• PI#

• Permit # E# U# of source being replaced

• Start date / expected duration

• Project description

• Equipment specs of source being brought onsite

make / model / serial #

size (BTU, kw)

fuel consumption rates (gal/hr, etc)

Page 31: C ONSTRUCTION  R EPAIR M AINTENANCE

31

What info is needed for the FINAL notif.

• Contact info

• PI#

• ACTUAL start/end dates, total duration

• Quantity emissions

Tons/yr

Must be reported in Emission Statements (sub21)

6 pollutants: TSP PM-10

NOx CO

SO2 VOC

Page 32: C ONSTRUCTION  R EPAIR M AINTENANCE

32

Page 33: C ONSTRUCTION  R EPAIR M AINTENANCE

33

3 Regional Enforcement Office

• Northern – Ph # 973- 656- 4444Bergen, Essex, Hudson, Hunterdon, Morris, Passaic, Somerset, Sussex, Union, Warren

• Central – Ph # 609- 292- 3187Mercer, Middlesex, Monmouth, Burlington, Ocean

• Southern – Ph # 856- 614- 3601Atlantic, Camden, Cumberland, Cape May, Gloucester, Salem

Page 34: C ONSTRUCTION  R EPAIR M AINTENANCE

34

Speculative use does NOT qualify for CRMex bringing onsite backup generators as part of storm

preparation efforts, just in case the power goes out during a weather event

Page 35: C ONSTRUCTION  R EPAIR M AINTENANCE

FAQ

35

Page 36: C ONSTRUCTION  R EPAIR M AINTENANCE

36

Q: What if 90 days isn’t long enough?

A: - 90 day limit can’t be extended via CRM

- Will be handled on case-by-case basis

- May result in enforcement action

Page 37: C ONSTRUCTION  R EPAIR M AINTENANCE

37

Q: Can I move the equipment around?

A: Can not move the equipment on & off site in order to circumvent the 90 day rule

CAN move the equipment around different areas of your property for a TOTAL of 90 days (NOT 90 days at each area)

Page 38: C ONSTRUCTION  R EPAIR M AINTENANCE

38

Page 39: C ONSTRUCTION  R EPAIR M AINTENANCE

39

Q: What is a Replacement Source?

A: Need NOT be an exact duplicate

Must be similar in design, function & purpose

ex) a boiler replaced by a boiler

Even a nat gas boiler replaced by an oil- fired boiler can be ok.

Page 40: C ONSTRUCTION  R EPAIR M AINTENANCE

40

Make every

reasonable effort

to minimize emissions

Page 41: C ONSTRUCTION  R EPAIR M AINTENANCE

41

Page 42: C ONSTRUCTION  R EPAIR M AINTENANCE

42

Page 43: C ONSTRUCTION  R EPAIR M AINTENANCE

43

For example:

- Rent clean equip from reputable dealers

- Use clean fuel

- Don’t run more than necessary

- Be responsible

Page 44: C ONSTRUCTION  R EPAIR M AINTENANCE

44

Page 45: C ONSTRUCTION  R EPAIR M AINTENANCE

45

Page 46: C ONSTRUCTION  R EPAIR M AINTENANCE

46

Make every

reasonable effort

to minimize emissions

Page 47: C ONSTRUCTION  R EPAIR M AINTENANCE

ONLINE RESOURCES

47

Page 48: C ONSTRUCTION  R EPAIR M AINTENANCE

48

- Construction Repair and Maintenance www.nj.gov/dep/aqpp

- Permit Applicability at Construction Sites Permitting Guidance

- Temporary Equipment

Page 49: C ONSTRUCTION  R EPAIR M AINTENANCE

49

SOTA

www.nj.gov/dep/aqppSOTA: ton/yr limits only…..no hourly limits

Page 50: C ONSTRUCTION  R EPAIR M AINTENANCE

50

Another option for Title V facilities only - Operating Permit General Provision #17

must meet a through h…. Max 90 days, owner must permit the equip, fac must comply with that permit, keep records, meet all state/federal regs, etc

Page 51: C ONSTRUCTION  R EPAIR M AINTENANCE

51