LAPORAN KEMAJUAN MINGGUAN BIL.110 CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B CAWANGAN KERJA BANGUNAN AM, IBU PEJABAT JKR MALAYSIA 1 CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN FASA 3B MAKLUMAT PROJEK LOKASI : Tapak Parlimen, Kuala Lumpur KOMPONEN PROJEK : Blok Ahli Parlimen (MP) Dewan Serbaguna Link Bridge Gelanggang Tenis Pembesaran Pondok Pengawal Kerja-kerja Luar Service tunnel, Pintu & Pagar Berhias, Tapak Semaian & Pangkin Nurser, Jalan & Perparitan Pengalihan utiliti Force Main & Pump House KOS PROJEK : RM 200,700,000.00 (ATDA) KOS KONTRAK ASAL : RM 181,578,000.00 KOS KONTRAK SEMASA : RM 181,726,675.28 KAEDAH PELAKSANAAN : Konvensional JKR KAEDAH PEROLEHAN : Tender Terbuka KONTRAKTOR UTAMA : DKLS Construction Sdn Bhd TEMPOH PEMBINAAN : 39 Bulan TARIKH MILIK TAPAK : 28 September 2015 TARIKH SIAP ASAL : 27 Disember 2018 LANJUTAN MASA : TIADA KEMAJUAN KERJA KESELURUHAN SEHINGGA 25 JANUARI 2018* KEMAJUAN % JADUAL % SEBENAR BEZA Hari Awal (+) / Lewat (-) FIZIKAL 32.94 33.80 +0.86 -15 KEWANGAN 83,309,231 (45.83%) 77,761,057 (42.77%) 5,548,174 (-3.06%) (Berdasarkan Rujukan SKALA pada 25 Januari 2018 : 8 Hari Lewat) STATUS KEWANGAN BERAKHIR 19 JANUARI 2018 Bayaran kepada Kontraktor RM 51,922,733.07 (31.30%) Wang Jaminan Pelaksanaan : Belum Dilepaskan Wang Pendahuluan : RM 10,000,000.00 Bayaran Balik Wang Pendahuluan (Recoupment) : RM 4,957,369.32 Liquidated & Ascertained Damages (LAD) : RM 34,137.00 / hari *Berdasarkan Recovery CPM Terkini (14/12/2017)

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek... · kos kontrak asal : rm 181,578,000.00 kos kontrak semasa : rm 181,726,675.28 kaedah pelaksanaan : konvensional jkr kaedah

Embed Size (px)

Citation preview

Page 1: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek... · kos kontrak asal : rm 181,578,000.00 kos kontrak semasa : rm 181,726,675.28 kaedah pelaksanaan : konvensional jkr kaedah

LAPORAN KEMAJUAN MINGGUAN BIL.110

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

1

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN FASA 3B

MAKLUMAT PROJEK

LOKASI : Tapak Parlimen, Kuala Lumpur KOMPONEN PROJEK :

Blok Ahli Parlimen (MP)

Dewan Serbaguna

Link Bridge

Gelanggang Tenis

Pembesaran Pondok Pengawal

Kerja-kerja Luar Service tunnel, Pintu & Pagar Berhias, Tapak Semaian & Pangkin Nurser, Jalan & Perparitan Pengalihan utiliti Force Main & Pump House

KOS PROJEK : RM 200,700,000.00 (ATDA)

KOS KONTRAK ASAL : RM 181,578,000.00

KOS KONTRAK SEMASA : RM 181,726,675.28

KAEDAH PELAKSANAAN : Konvensional JKR

KAEDAH PEROLEHAN : Tender Terbuka

KONTRAKTOR UTAMA : DKLS Construction Sdn Bhd

TEMPOH PEMBINAAN : 39 Bulan

TARIKH MILIK TAPAK : 28 September 2015

TARIKH SIAP ASAL : 27 Disember 2018

LANJUTAN MASA : TIADA

KEMAJUAN KERJA KESELURUHAN SEHINGGA 25 JANUARI 2018*

KEMAJUAN % JADUAL % SEBENAR BEZA Hari Awal (+) /

Lewat (-)

FIZIKAL 32.94 33.80 +0.86 -15

KEWANGAN 83,309,231

(45.83%) 77,761,057

(42.77%) 5,548,174 (-3.06%)

(Berdasarkan Rujukan SKALA pada 25 Januari 2018 : 8 Hari Lewat)

STATUS KEWANGAN BERAKHIR 19 JANUARI 2018

Bayaran kepada Kontraktor RM 51,922,733.07 (31.30%)

Wang Jaminan Pelaksanaan : Belum Dilepaskan Wang Pendahuluan : RM 10,000,000.00

Bayaran Balik Wang Pendahuluan (Recoupment) : RM 4,957,369.32 Liquidated & Ascertained Damages (LAD) : RM 34,137.00 / hari

*Berdasarkan Recovery CPM Terkini (14/12/2017)

Page 2: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek... · kos kontrak asal : rm 181,578,000.00 kos kontrak semasa : rm 181,726,675.28 kaedah pelaksanaan : konvensional jkr kaedah

LAPORAN KEMAJUAN MINGGUAN BIL.110

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

2

KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 25 JANUARI 2018

ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN

PRELIMINARIES 5.66% 71.79 71.79 0

PILING WORKS 9.02% 100 100 0

BUILDING WORKS & INFRA STRUCTURE (36.67%)

BESMEN 3.57% 63.51 66.87 +3.36

BLOK MP 30.11% 40.55 48.13 +7.58

LINK BRIDGE 0.56% 10.29 10.16 -0.13

DEWAN SERBAGUNA 2.15% 30.30 25.46 -4.84

TAPAK SEMAIAN 0.12% 40.00 31.58 -8.42

TEMPAT LETAK BAS BERBUMBUNG

0.16% 0 0 0

INTERNAL SERVICES (PC SUMS) (32.98%)

Mechanical Works

AC System (PC Sums) 7.43% 10.23 12.52 -2.29

Fire Fighting (PC Sums) 1.55% 19.02 8.05 -10.97

Lift System (PC Sums) 1.24% 0 0 0

BAS (PC Sums) 1.24% 5.12 2.35 -2.77

Kitchen Equipments (PC Sums) 0.25% 22.84 8.65 -14.19

Electrical Works

Electrical Installation (PC Sums) 10.09% 17.5 18.6 +1.1

ELV (PC Sums) 8.29% 22.74 26.2 +3.46

ICT (PC Sums) 2.91% 26.94 14.19 -12.75

EXTERNAL WORKS (5.14%)

Site Preparation & Earthworks 0.57% 100 100 0

SI & Geotechnical I&M 0.19% 100 100 0

Roadworks 0.09% 0 0 0

Surface Water Drainage 0.82% 8.16 0 -8.16

Permanent Water Reticulation 0.06% 0 0 0

Temporary Water Reticulation 0.12% 100 100 0

Sewerage 0.28% 52.44 48.78 -3.66

Turfing 0.06% 20.0 0 -20.0

Fencing & Gates 0.23% 0 0 0

Infra Works for Electrical 0.05% 44 0 -44.0

Terowong Utiliti 0.08% 100 100 0

Page 3: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek... · kos kontrak asal : rm 181,578,000.00 kos kontrak semasa : rm 181,726,675.28 kaedah pelaksanaan : konvensional jkr kaedah

LAPORAN KEMAJUAN MINGGUAN BIL.110

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

3

KEMAJUAN KERJA SEMASA DI TAPAK SEHINGGA 25 JANUARI 2018

ITEM WEIGHTAGE % PLANNING % ACTUAL %BEZA SEBAB-SEBAB KELEWATAN

RE Wall System 1.86% 100 97.14 -2.86

Trench for Mechanical Pipes 0.09% 0 0 0

External Staircases 0.01% 0 0 0

OTHERS (10.53%)

Gelanggang Tenis G1 0.12% 0 0 0

Pondok Pengawal G2 0.19% 40.57 9.9 -30.67

Built-in Furnitures 0.88% 0 0 0

Loose Furnitures 0.58% 0 0 0

Office Furnitures 1.46% 0 0 0

Landschapping Works 0.29% 0 0 0

Interior Design 2.04% 0 0 0

Acoustic Works 0.35% 0 0 0

Forensic Works 0.15% 100 100 0

Equipment at Gymnasium 0.09% 0 0 0

Equipment at Sauna Room 0.09% 0 0 0

Signages 0.26% 0 0 0

Energy Efficiency 0.23% 100 100 0

Rainwater Harvesting System 0.12% 0 0 0

Pump House & Force Main 1.75% 13.38 8.99 -4.39

OSD Pond 1.17% 45.24 41.26 -3.98

Relocation of Services & Utility 0.18% 100 100 0

BWIC 0.58%

KESELURUHAN 100.00% 32.94% 33.80% +0.86%

Page 4: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek... · kos kontrak asal : rm 181,578,000.00 kos kontrak semasa : rm 181,726,675.28 kaedah pelaksanaan : konvensional jkr kaedah

LAPORAN KEMAJUAN MINGGUAN BIL.110

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

4

AKTIVITI SEMASA DI TAPAK

1. BlOK MP

Kerja Struktur - Pemasangan Hollow Core Slab Aras 3 dan Aras 4 - Kerja konkrit Topping Aras 3 & Aras 4 - Pemasangan Steel Beam Aras 4 & Aras Lift Motor Room Level - Pemasangan formwork untuk flat roof aras 4

Kerja Arkitek - Brickwork Aras 1 dan 2 - Kerja plastering Aras Tanah dan Aras 1

Kerja Mekanikal - Pemasangan Internal sanitary fitting di Aras 3 - Pemasangan fire fighting pipe Aras Basemen, Aras Tanah dan Aras 1 - Pemasangan Aircond Ducting Aras Basemen, Aras Tanah, Aras 1 dan Aras 2

Kerja Elektrikal - Pemasangan cable tray dan conduit Aras Basement, Aras Tanah, Aras 1, Aras 2, Aras 3

2. BLOK DEWAN SERBAGUNA

Brickwork

3. RE Retaining Wall

Kerja-kerja cascade drain dan berm drain

4. Internal Sewerage

Kerja pembinaan jajaran MH8 – MH 11

5. External Sewerage (Force Main & Pump House)

Pipe jacking jajaran MH 11 – MH 13

Pemasangan hoarding untuk pembinaan rumah pam

Page 5: CADANGAN MENAIKTARAF DAN MEMBAIKPULIH … projek... · kos kontrak asal : rm 181,578,000.00 kos kontrak semasa : rm 181,726,675.28 kaedah pelaksanaan : konvensional jkr kaedah

LAPORAN KEMAJUAN MINGGUAN BIL.110

CADANGAN MENAIKTARAF DAN MEMBAIKPULIH BANGUNAN PARLIMEN MALAYSIA FASA 3B

C A W A N G A N K E R J A B A N G U N A N A M , I B U P E J A B A T J K R M A L A Y S I A

5

ISU-ISU/MASALAH SEMASA

1. KEKURANGAN PEKERJA

Kontraktor mengalami masalah untuk mengambil pekerja yang mempunyai Kad Hijau CIDB. Semua pekerja yang bekerja di tapak projek Parlimen diwajibkan mempunyai Kad Hijau CIDB.

2. KELEWATAN KERJA TANAH

Kerja tanah tergendala akibat kawasan yang terhad dan keadaan hujan yang kerap menyebabkan tanah

di tapak tidak boleh digunakan sementara sehingga ia kering sepenuhnya.

3. HALANGAN VALVE SYABAS

Kerja-kerja reprofiling cerun tergendala akibat kewujudan valve paip SYABAS di atas cerun. Perbincangan

dengan pihak Syabas telah diadakan dan urusan dokumentasi untuk kerja pengalihan valve dan paip

sedang diuruskan.

4. WAKTU BEKERJA YANG TERHAD BAGI KERJA-KERJA EXTERNAL SEWERAGE

Waktu kerja yang diluluskan oleh DBKL hanya dari 10.00 pm ke 5.00 am sahaja bagi kerja-kerja external

sewerage (sepanjang Jalan Parlimen dari pintu masuk Parlimen sehingga Padang Merbok).