CERN Computer Centre Upgrade Project. Wayne Salter HEPiX November 2010. Overview. Current status of CERN Computer Centre (CC) Layout, powering and cooling Current issues and anomalies Aims of the upgrade project Proposed project Layout, powering and cooling Project schedule and status - PowerPoint PPT Presentation

Citation preview

Page 1: CERN Computer Centre Upgrade Project

Computing Facilities

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF

CERN Computer Centre Upgrade Project

Wayne SalterHEPiX November 2010

Page 2: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Overview

• Current status of CERN Computer Centre (CC)– Layout, powering and cooling

• Current issues and anomalies• Aims of the upgrade project• Proposed project

– Layout, powering and cooling• Project schedule and status• Summary

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 2

Page 3: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF CERN Computer Centre Overview• Designed and built in early 1970s• Fully refurbished around 2000

– Increased power and improved cooling• Nominal current capacity: 2.5MW (including

240kW of critical power)• Extended (usable) capacity: 2.9MW (including

340kW of critical power) forfeiting redundancy for all UPS systems

• On-going project to:– Increase the nominal capacity to 3.5MW/600kW

with N+1 redundancy– Address some issues/anomalies

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 3

Page 4: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Main Computer Room

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 4

Page 5: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Cold aisle is cold!

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 5

Page 6: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Current Status of CERN CC• Main computer room (1600m²)

– Air cooled racks– ~1.9MW

• ‘Vault’ (1400m²)– Mixture of air cooled and water cooled racks + tape robots– ~640kW

• Room for back up data in separate building (200m²)– Mainly tape robots with air cooling– ~ 30kW

• Two Telecoms rooms– CERN Internet Exchange Point (CIXP) ~ 10kW

• Two types of equipment both on UPS– Physics with a single power feed but no diesel backup– Critical with dual power feeds and diesel backup

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 6

Page 7: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Power and Cooling• 3 physics UPS, each with 4*400kvA modules + 1

critical UPS with 2*300kVA modules• Air cooled installations:

– IT & Telecoms equipment (capacity up to ~2.5MW), technical areas (mainly UPS rooms)... and offices

– (3+1) Chillers not secured by UPS nor diesel– Pumps and AHUs secured by diesel but not UPS– Water-tank for stored cooling capacity (a few mins)

• Water cooled installations:– For IT (physics) equipment (capacity up to 800kW)– (1+1) Chillers not secured by UPS nor diesel– Pumps secured by (physics) UPS– Water-tank for stored cooling capacity (~10 mins)

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 7

Page 8: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Current Issues and Anomalies• Cooling for critical UPS room insufficient• Mixing of critical and physics equipment

– Location and cooling• No cooling of CC when running on UPS and

insufficient stored cooling capacity when on diesel• Insufficient critical power available• Approaching the limit of available power for the

building• No redundancy for critical UPS• Usage of full ‘available’ 2.9MW implies loss of

redundancy for physics UPS• A/C of CC coupled to adjacent office building

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 8

Page 9: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Current Power Situation

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 9

IT Physics Equipment

IT Critical Equipment

Physics UPS(4*)

Diesel Generator

(N+1)

Critical UPS(2)

340kW340kW2.56MW

2.9MW

Normal Network

*N+1 redundancy sacrificed to achieve 2.9MW

Page 10: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Main Computer Room

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 10

Page 11: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Vault

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 11

Page 12: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 12

Backup Building

Page 13: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Primary Goals of the Upgrade Project

• Solve the cooling issue for the critical UPS room– New UPS systems in a different location

• Increase critical UPS capacity to 600kW• Increase overall power capacity to 3.5MW• Restore N+1 redundancy for both critical and

physics UPS systems• Secure cooling for critical equipment when

running on UPS and extend stored cooling capacity for physics when on diesel

• Decouple the A/C for CC from the adjacent office building

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 13

Page 14: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Power Requirements

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 14

IT Physics Equipment

IT Critical Equipment

Physics UPS(4+1)

Diesel Generator

(N+1)

Critical UPS(3+1)

600kW600kW2.9MW

3.5MW

Normal Network

Cooling forIT Critical

Equipment

Page 15: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Approach• Barn area of CC building to be converted to house:

– 3 Electrical rooms– An IT room with water cooled racks to house critical equipment

(up to 450kW)– New ventilation systems for the critical area of the main

computer room• New ventilation systems for the Telecoms rooms

will be installed in adjacent offices• A new partially sunken building for additional

chillers and a storage tank for the cooling of the critical areas

• An additional storage tank for extending the stored cooling capacity for physics equipment

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 15

Page 16: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Areas Affected

Presentation Title - 16

Barn

Reduced Critical AreaTelecoms Rooms

NewCVroom

Two newtransformers

Future expansion for Telecoms Rooms New AHUsNew AHUs

Page 17: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Layout - I

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 17

Page 18: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Layout - II

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 18

Page 19: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Layout - III

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 19

Page 20: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Layout - IV

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 20

Page 21: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Layout - V

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 21

Page 22: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Layout - VI

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 22

Page 23: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Layout - VII

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 23

Page 24: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Schedule and Status• All Market Surveys already launched• RFPs in process of being released• ‘Barn’ cleared of IT equipment end of

October• ‘Barn’ to be cleared of electrical and other

installations end of 2010• Adjudication of contracts at March FC• CE works to be completed July 2011• EL+CV installations Aug/2011-May/2012• Increased physics power available March

2012 and increased critical power June 2012 CERN Computer Centre Upgrade Project - HEPiX November 2010 - 24

Page 25: CERN Computer Centre Upgrade Project

CERN IT Department

CH-1211 Geneva 23

Switzerlandwww.cern.ch/

it

CF Summary

• CERN CC was not designed for today’s IT equipment

• Major upgrade already performed in 2000• Further upgrade in progress:

– To maximize the capacity of the CC– To resolve some outstanding issues

• Increased capacity to be available mid-2012• Last increase in capacity foreseen with today’s

technology• Other solutions will be required for any future

increases in required computing capacity

CERN Computer Centre Upgrade Project - HEPiX November 2010 - 25