Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
49
CHAPTER 3 Transport Demand Forecast
3.1 Assumptions and Method of Demand Forecast
3.1.1 Overall Methodology
The demand forecast methodology is in line with the CoMTrans urban transport master plan. The CoMTrans master plan employed a four-step method which is empirically proven methodology with a number of applications in many countries. The flow of the analysis is shown in Figure 3.1.1
The initial input data to the demand forecast model is the population projection of the Western Province mentioned in Chapter 4 of the CoMTrans urban transport master plan, urban development projects and urban planning policies including transit-oriented development. Residential population, employed population and student population by income level are estimated by zone. These data are input to the trip generation model. Origin-destination (OD) tables by trip purpose and income level are estimated by the trip generation and distribution models developed for the Western Province.
As road traffic and public transport are closely related, these cross-relationships are taken into account in the demand forecast in addition to the conventional four-step modelling. For instance, bus travel speeds are dependent on the congestion level of roads. Slow travel speed of private motorised mode of transport can contribute to the modal shift to rail-based transport. Therefore, two stages of road assignment and two stages of transit (public transport) assignment are conducted to consider these relationships as shown in Figure 3.1.1.
As a monorail is a new transport mode for Sri Lanka, a Stated Preference (SP) survey was conducted. A stated preference survey is a survey method which requires respondents to indicate their preference in a certain fictive condition such as transport mode choice with a monorail system in the future. In contrast, a revealed preference (RP) survey collects actual choice results such as current mode of transportation.
RP-based modal choice models were developed to estimate the modal share without new policy interventions such as a modernised railway, BRT, monorail and electronic road pricing. The SP-based modal shift model was developed to estimate modal shift due to new policy interventions.
After the initial road and transit assignment; impedance tables, initial link travel speed and initial bus volume on the roads are estimated. These will be input to the second modal split and second road and transit assignment. Finally, link volumes and performance indicators are the final outputs of the assignment. Further detailed methodology of the demand forecast is available in the technical report of the CoMTrans master plan.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
50
Figure 3.1.1 Flow of Transport Demand Forecast
Estimation of Zonal Population
Output
Provincial Population Projection Residential, Student and
Employed Population by Zone Urban Planning Policy Intervention
Estimation of Trip Generation / Attraction
Estimation of Trip Distribution
Trip Generation/Attraction Model
Trip Generation/Attraction by income by purpose by zone
Trip Distribution Model OD by Trip Purpose by Income Group
Initial RP-Based Modal Split
Initial SP-Based Modal Split
RP-Based Modal Split Model Initial OD by Mode by Income without New Policies
Policy Framework of New Transits and TDM Initial OD by Mode by
Income with New Policies SP-Based Modal Split Model
Initial Road Assignment
Road Impedance by OD Pairs
Initial Bus Speed
Initial Transit Assignment
Road Network
Public Transport Network
Public Transport Impedance by OD Pairs
Bus Frequency
Input
Second RP-Based Modal Split
Second SP-Based Modal Split
Updated OD by Mode by Income without New Policies
Updated OD by Mode by Income with New Policies
Second Road Assignment
Link Volume and KPIs
Second Transit Assignment Link Volume, KPIs
RP-Based Modal Split Model
Policy Framework of New Transits and TDM
SP-Based Modal Split Model
Road Network
Public Transport Network
Process
Bus Speed
Source: CoMTrans
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
51
3.1.2 Origin-Destination Table Estimation
(1) Socio-Economic Framework
Population and gross regional domestic product (GRDP) projections are consistent with the CoMTrans urban transport master plan. The projected population for the Colombo Metropolitan Area (CMA) which is defined in the CoMTrans master plan is illustrated in Figure 3.1.2. Employed population and student population were also the same as the master plan estimation.
0
1,000,000
2,000,000
3,000,000
4,000,000
5,000,000
6,000,000
7,000,000
8,000,000
9,000,000
2001 2012 2015 2020 2025 2030 2035
Kalutara District
Gampaha District
Colombo District
Note: After 2015, the projected populations are shown in the High, Medium, and Low growth scenarios. Source: CoMTrans Study Team
Figure 3.1.2 Population Projections to 2035
GRDP assumptions utilised for the master plan as well as this feasibility study are summarised in Table 3.1.1. The IMF assumption is taken and the growth rate will gradually become lower after 2016 and drop to around 4% in 2035.
Table 3.1.1 Assumption of Gross Regional Domestic Products (GRDP) Growth
Year GDP Annual Growth Rate Note
2013 6.3% IMF Forecast
2014 6.7% IMF Forecast
2015-2017 6.7% Assumption
2018 6.5% IMF Forecast
2019-2020 6.5% Assumption
2012-2025 6.0% Assumption
2026-2030 5.0% Assumption
2031-2035 4.0% Assumption
Source: “World Economic Outlook - April 2013 - Hopes, Realities, Risks” by IMF
Source: CoMTrans Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
52
(2) Zone System
The western province was divided into a total of 462 traffic analysis zones (TAZs). Outside of Colombo Metropolitan Area (CMA), one divisional secretariat division (DSD) comprises 2-3 TAZs. TAZs in Colombo Municipal Council (CMC) are consistent with Grama Niladhari (GN) Administration Division in general except for large GNs which are divided into multiple TAZs. The balance DSDs, DSDs in CMA but outside of CMC, are composed of more than 3 TAZs depend on the size of the DSD and its development level.
The Port of Colombo, Bandaranaike International Airport, Ratmalana Airport and Katukunrunda Air force Base have separate traffic analysis zone codes. In addition, 10 arterial roads connecting the Western Province are coded as cordon TAZs.
(3) Origin-Destination Tables by Trip Purpose by Income Level
In the CoMTrans urban transport master plan, origin-destination (OD) tables by trip purpose by income level and by year were prepared. This feasibility study utilised the same OD tables. In the master plan study, trip generation/attraction regression models were developed. The socio-economic framework including residential, employed and student population by income level by TAZs were input as explanatory variables of the trip generation / attraction model for the 3 projection years of 2020, 2025 and 2035. Figure 3.1.3 presents the projected trip production. The trip distribution is estimated basically utilizing the current trip distribution pattern. For the planned development area, a gravity model was also utilised.
Source: CoMTrans Study Team
Figure 3.1.3 Person Trip Demand by Region: 2013 – 2035
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
53
(4) Modal Choice
Since the monorail, bus rapid transit (BRT) and modernised railway are completely new transport modes in Sri Lanka, special attention should be paid to the transport modal choice. Electronic road pricing (ERP) is also a currently non-existing policy option for CMA. In addition to the conventional revealed preference survey such as the Home Visit Survey (HVS) on travel behaviour, a stated preference survey was conducted to estimate modal shift from conventional mode of transport.
1) Revealed Preference Based Modal Choice Model Development
Based on the Home Visit Survey (HVS) results, mode choice models were developed using the discrete choice theory. A modal choice model using the discrete choice theory is a relatively stable modelling method in terms of space and time differences. Even though spatial location or time is not equal, individual choice of a certain group of people in a specific condition such as travel time and fare is empirically stable. With regard to the mathematical structure, a prevalent “multinomial logit model”, which can represent unique characteristics of each choice such as transportation mode, was employed for this study.
Four models were developed by trip purpose for home-based work purpose, home-based education purpose, home-based others purpose and non-home-based trips. Parameters were estimated by the maximum likelihood method utilizing the Home Visit Survey (HVS) results. Biogeme 2.3, an open source software for parameter estimation of discrete choice models developed by Prof. Bierlaire, M. of École polytechnique fédérale de Lausanne (Bierlaire, 2003), were utilised for parameter estimation.
Bierlaire, M. (2003). BIOGEME: A free package for the estimation of discrete choice models, Proceedings of the 3rd Swiss Transportation Research Conference, Ascona, Switzerland.
The list of explaining variables and estimated parameters of the Home-Based Work purpose trips are shown in Table 3.1.2, Table 3.1.3 and Table 3.1.4 as examples. Since the adjusted rho-square which indicates the fitness of a model was 0.365, it can be concluded that this model has enough accuracy for the mode choice analysis. Parameter estimation results of other models are described in the Technical Report on Transport Demand Forecast.
Table 3.1.2 Parameter Estimation Summary of Home-Based Work Purpose Model
Number of estimated parameters: 13
Number of observations: 39,210
Null log-likelihood: -50,173.551
Cte log-likelihood: -44,934.210
Init log-likelihood: -50,173.551
Final log-likelihood: -31,867.354
Likelihood ratio test: 36,612.394
Rho-square: 0.365
Adjusted rho-square: 0.365
Source: Technical Report on Demand Forecast, CoMTrans Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
54
Table 3.1.3 List of Variables and Parameter Estimation Results of Home-Based Work
Purpose Model
Name Value Std err t-test Notes
ASC_3W -0.827 0.0729 -11.33 Alternative specific constant for three wheelers
ASC_Car -1.81 0.0593 -30.47 Alternative specific constant for passenger cars
ASC_Mc -0.266 0.0577 -4.61 Alternative specific constant for motorcycles
ASC_NMT 0.00 fixed Alternative specific constant for non-motorised transport
ASC_Pub 0.626 0.0567 11.03 Alternative specific constant for public transport (Bus and Railway)
B_AvgInc 1.26 0.0222 56.72 Parameter of average monthly household income in 100,000 rupees
B_AvgPopD 0.511 0.0345 14.79 Parameter of average population density of origin and destination zones in persons per are (1 are = 100 m2)
B_Dist -0.301 0.00687 -43.81 Parameter of trip distance for non-motorised transport in km
B_Dist3W -0.159 0.00559 -28.35 Parameter of trip distance for three wheelers in km
B_DistMc -0.0354 0.00164 -21.63 Parameter of trip distance for motorcycles in km
B_HSRail 0.130 0.0346 3.76 Parameter of dummy variable of availability of high-service-level railway
B_LowInc 0.886 0.0507 17.48 Parameter of dummy variable of low household income group (less than 40,000 rupees)
B_RGT 0.246 0.0781 3.15 Parameter of ratio of generalised time (generalised time of private mode / generalised time of public transport)
B_Rrl2Rrl 0.415 0.0330 12.56 Parameter of dummy variable of non-CMA trip
Source: Technical Report on Demand Forecast, CoMTrans Study Team
Table 3.1.4 List of Alternatives and Utility Function of Home-Based-Work Purpose Model
Name Mode Specification
A1_Car Passenger Car ASC_Car * one + B_AvgInc * Avg_Inc3
A2_Mc Motorcycle ASC_Mc * one + B_Rrl2Rrl * Rrl2Rrl + B_DistMc * Distance
A3_3W Three Wheeler ASC_3W * one + B_Dist3W * Distance + B_AvgPopD * AvgPopD
A4_Pub Rail and Bus ASC_Pub * one + B_RGT * RGT + B_HSRail * RailRail
A5_NMT Non-motorised transport ASC_NMT * one + B_Dist * Distance + B_LowInc * LowInc
Note: Avg_Inc3 stands for average monthly household income in LKR 100,000. Distance stands for trip distance in km. RailRail is a dummy variable if both origin and destination zones are accessible to high-service- level railway.
Source: Technical Report on Demand Forecast, CoMTrans Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
55
2) Stated Preference Survey
The stated preference (SP) survey for monorail, bus rapid transit (BRT) and modernised railway as well as electronic road pricing (ERP) were conducted for the evaluation of new transport policies. Respondents to the SP survey were sampled from the respondents of the Home Visit Survey in 2013 who provided their phone number. A surveyor telephones a potential respondent and requests cooperation with the survey. After approval of the respondent, the surveyor made an appointment and visited the respondent for an interview survey. For the purpose of evaluating the proposed monorail project and modernised railway, respondents were sampled from areas roughly 1km from Malabe corridor where the monorail is proposed and Galle corridor where modernised railway and BRT are proposed. The survey was conducted in February and March, 2014. Total sample size was 1,146 individuals. The number of samples by current mode of transport is shown in Table 3.1.5. As one survey form contains several questions on the stated preference under different conditions, the sample size is large enough to develop discrete choice model.
Table 3.1.5 Sample Size of SP Survey by Current Mode of Transport and Corridor
Transport
Mode
Malabe
Corridor
Galle
Corridor
Total
Public 366 318 684
Motorcycle 99 87 186
Three Wheeler 23 52 75
Car 124 77 201
Total 612 534 1,146
Source: SKYTRAIN Study Team
Prior to beginning the interview survey, the surveyors explained details of the planned new modes of transport including the modernised railway, the bus rapid transit (BRT) and the monorail. For each transport mode, routes and station locations were described to the respondent with pictures of each transport mode. It was also explained that the coaches of these three transport modes will be clean, safe and air-conditioned. Headway is assumed at five minutes during peak hour and fifteen minutes during off-peak hour. It is assumed that paid parking facilities are provided nearby the monorail stations.
The survey form consists of the 3 sections below.
Section 1: General information relevant to the present trips made by the respondent. Two different questionnaires for this section were prepared: 1) Commuter; and 2) Non-Commuter.
Section 2: Mode choice behaviour under hypothetical situations in which different future transport systems are shown to the respondents based on the main modes of transport they use at present.
Section 3: General opinion.
In section 2, the surveyor told the respondent where the nearest station would be located. The surveyor asked the respondent about his potential access/egress transport modes, time and cost.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
56
Several levels of in-vehicle travel time of the new transport modes were tested for each respondent.
3) SP-Based Modal Shift Model Development
Modal shift from conventional mode of transport to new transport modes of monorail, BRT and modernised railway were surveyed in the abovementioned SP survey. After data input and data verification, modal shift models were developed. Seven models were developed by existing mode and policy options. Table 3.1.7 is a list of the developed models. Choice set is binary; an existing transport mode and a new transport mode. Thus, a Binary Probit model was employed.
Table 3.1.6 List of Modal Shift Model
Model Name Current Mode New Policy Option
Car-Mono Passenger Car Monorail
Car-Rail Passenger Car Modernised railway and BRT
Mc-Mono Motorcycle Monorail
Mc-Rail Motorcycle Modernised railway and BRT
3W-Mono Three Wheeler Monorail
3W-Rail Three Wheeler Modernised railway and BRT
Pub-Mono & Rail Public Transport Monorail, modernised railway and BRT
Source: Technical Report on Demand Forecast, CoMTrans Study Team
Example of parameter estimation of passenger car to monorail modal shift model is shown in Table 3.1.7 to Table 3.1.9.
Table 3.1.7 Parameter Estimation Summary of Car to Monorail Modal Shift Model
Model: Binary Probit
Number of estimated parameters: 11
Number of observations: 4,555
Null log-likelihood: -3,157.285
Cte log-likelihood: -2,951.434
Init log-likelihood: -3,157.285
Final log-likelihood: -2,298.848
Likelihood ratio test: 1,716.874
Rho-square: 0.272
Adjusted rho-square: 0.268
Source: Technical Report on Demand Forecast, CoMTrans Study Team
Note: This is an example of car to monorail modal shift model. Please refer the Technical Report on Demand Forecast of CoMTrans for other models.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
57
Table 3.1.8 List of Variables and Parameter Estimation Results of Car-Monorail Model
Name Value Std err t-test Notes
ASC_NEW 0.00 fixed Alternative specific constant for monorail
ASC_NOCHANGE 0.00 fixed Alternative specific constant for current mode
B_AGE -0.0180 0.00162 -11.09 Parameter of age
B_AvgEmpD 1.43 0.223 6.43 Parameter of average employed population density of origin and destination zones in persons/are (1 are = 100 m2)
B_AvgPopD 1.12 0.250 4.46 Parameter of average population density of origin and destination zones in persons/are (1 are = 100 m2)
B_COST -0.00680 0.000460 -14.78 Parameter of total fare of monorail in rupees
B_DTYPE_13 0.532 0.0663 8.02 Parameter of dummy variable of destination type (workplace or other company)
B_ERP -0.00880 0.000289 -30.43 Parameter of ERP price in Rupees
B_INCOME -2.95e-006 2.93e-007 -10.07 Parameter of average household income in Rupees
B_MaxEmpD -0.575 0.115 -4.99 Parameter of higher population density of origin or destination zones in persons/are (1 are = 100 m2)
B_MaxPopD -0.653 0.148 -4.42 Parameter of higher employed population density of origin or destination zones in persons/are (1 are = 100 m2)
B_RailOr -0.425 0.0538 -7.90 Parameter of dummy variable of high service railway (either origin or destination)
B_TIME -0.00316 0.00109 -2.91 Parameter of travel time in minutes
Source: Technical Report on Demand Forecast, CoMTrans Study Team
Note: This is an example of car to monorail modal shift model. Please refer the Technical Report on Demand Forecast of CoMTrans for other models.
Table 3.1.9 List of Alternatives and Utility Function of Car-Monorail Modal Shift Model
Name Mode Specification
A1_NEW New Transit Mode (Monorail)
ASC_NEW * one + B_TIME * TOTAL_T_NEW + B_COST * TOTAL_COST_NEW + B_AGE * AGE_HVS + B_DTYPE_13 * DEST_TYPE_1_3 + B_RailOr * RailOr + B_AvgPopD * AvgPopD + B_MaxPopD * MaxPopD + B_AvgEmpD * AvgEmpD + B_MaxEmpD * MaxEmpD + B_INCOME * INCOME
A2_NOCHANGE Current mode
ASC_NOCHANGE * one + B_TIME * TOTAL_TT_RP_ERP + B_ERP * ERP
Note: Total_T_New and Total_Cost_New stands for total travel time and cost including access and egress. AGE_HVS means age; Dest_Type_1_3 is a dummy variable of destination type. 1 if destination is workplace or other companies and 0 if not. TOTAL_TT_RP_ERP means total travel time in the case of the existing transport mode.
This is an example of car to monorail modal shift model. Please refer the Technical Report on Demand Forecast of CoMTrans for other models.
Source: Technical Report on Demand Forecast, CoMTrans Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
58
(5) Traffic Assignment
Assumptions and method of traffic assignment are shown in the sub-sections below.
1) Software and Estimation Procedure
The System for Traffic Demand Analysis (STRADA) is a Microsoft Windows based package; developed for which was started in 1993 by the Japan International Cooperation Agency (JICA) under the leadership of the Prof. Hideo Nakamura of Tokyo University with participation of some experts in the relevant fields.
In this traffic demand analysis, JICA STRADA version 3 is used for trip assignment of present transport demand and for the future forecast. STRADA is comprehensive, simple and cost effective software, which is also used by the Road Development Authority (RDA) in Sri Lanka.
User equilibrium assignment was utilised for road traffic assignment which is a prevalent and technically sound method based on Wardrop’s equal travel time principle. Iteration calculations were conducted by the Frank-Wolfe method until it reached convergence criteria. JICA STRADA’s Transit Assignment package was used for estimation of the public transport demand. As JICA STRADA’s transit assignment programme cannot estimate demand by income group in one assignment run, assignment was done by income group for public transport.
Although transit assignment and road traffic assignment are closely related, the methodologies of transit and road traffic assignment are different. For instance, while bus speed is dependent on road congestion level, road speed is dependent on frequency of bus operation. Therefore, iteration estimations of road-transit assignments are essential. In this study, 2 iterations of road-transit assignment were conducted considering resource availability and estimation time.
2) Assumptions for Traffic Assignment
Value of time
Value of time is specified by income group as shown in Table 3.1.10. Mean household income was estimated by the Home Visit Survey Results and adjusted by the Household Income and Expenditure Survey 2012/2013. The value was converted to the worker’s time value. Although averaged time value by purpose is used for economic analysis, worker’s time value was used for the transport demand forecast. According to experience in other countries, time value of transport mode and route choice is higher than their salary per unit of time.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
59
Table 3.1.10 Value of Time for Traffic Assignment
Income
Level
Mean
Household
Income (Rs.)
Avg. No. of
Workers in
Household
Monthly
Working
Hours
Social
Security
Cost
Worker’s Time
Value (Rs./h)
Low 24,009 1.20 140 30% 186
Middle 56,810 1.72 140 30% 307
High 186,164 1.90 140 30% 909
All 70,366 1.36 140 30% 479
Note: “Avg.” stands for “average”.
Source: CoMTrans Study Team
Passenger Car Unit (PCU)
Passenger car unit by major category of vehicles are listed in Table 3.1.11. The values are adopted from the road geometric design standards of the Road Development Authority.
Table 3.1.11 Passenger Car Units for Traffic Assignment
Car 1.0
Motorcycle 0.4
Three Wheeler 0.8
Bus 1.8
Medium Truck 1.7
Large Truck 2.8
Container Trailer 4.0
Source: Geometric Design Standards of Roads, RDA, 1998
Average Number of Passengers
Average number of passengers was also estimated from various types of surveys and are summarised in Table 3.1.12.
Table 3.1.12 Average Number of Passengers for Traffic Assignment
Car 1.71
Motorcycle 1.22
3 Wheeler 1.42
Bus 38.8
Truck 2.2
Source: Car, Motorcycle and 3 Wheeler; CoMTrans Home Visit Survey, 2013 Bus: CoMTrans Screen Line Survey, 2013 Truck: CoMTrans Cordon Line Survey, 2013
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
60
Daily Traffic and Peak Hour Traffic
Traffic assignment was conducted on a daily basis taking data availability and accuracy into consideration. After the daily traffic assignment, peak-hour values were estimated by multiplying daily volume by the peak-hour ratio. The peak-hour ratio is generally estimated by dividing peak one hour passenger volume by daily passenger volume. Figure 3.1.4 shows the hourly fluctuation of trip generation at trip destination in the Western Province. A clear peak is observed at 7-8 AM in the morning. The peak hour ratio of bus passengers in the Malabe Corridor is also estimated in the range of approximately fourteen to seventeen percent according to the screen line survey of CoMTrans Project conducted in 2013. In general, bus passenger peak hour ratio is lower than railway due to the constraints of road capacity. The hourly fluctuation of passenger demand estimation for monorail is assumed as Figure 3.1.5 taking the abovementioned aspects into consideration.
0
500
1000
1500
2000
2500
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
No
. o
f T
rip
s ('
00
0)
Hour of Day
Home to Work Home to School Home to Other Work to Home
School to Home Other to Home Non-Home-Based
Source: CoMTrans Home Visit Survey
Figure 3.1.4 Hourly Fluctuation of Trip Generation by Purpose at Trip Destination
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
61
Source: SKYTRAIN Study Team
Figure 3.1.5 Assumed Hourly Fluctuation of Passenger Demand for Monorail
3.1.3 Transport Network
The transport network setting is based on the public transport intensive scenario of the CoMTrans master plan. The network is prepared for 2013, 2020, 2025 and 2035. Details of the network condition of the public transport network and road network are mentioned in the sub-section below.
(1) Public Transport Network
Modernised railway, monorail, bus rapid transit (BRT), bus priority system and conventional bus service are simulated in the traffic assignment network as shown in Table 3.1.13. The Intensive Public Transport Development scenario was employed for the traffic assignment.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
62
Table 3.1.13 List of Projects Included in the Public Transport Assignment Network
Sub
Sector
Project ID Project Name 2020 2025 2035
TDM TM-ERP Electric Road Pricing (CMC)
BRT BRT-1 Moratuwa – Kelaniya* √ √ √
BRT-1 Wellawatta – Kirillapone - (Baseline) √ √ √
BRT-1 Kelaniya-(Kandy Road)-Kadawata √ √ √
BRT-1 Fort – Negombo and Katunayake √ √ √
BRT-2 Middle Ring Road √ √
Monorail RT-NT1 Line 1 (East West Line) (Malabe – Battaramulla – Town Hall – Fort – Kotahena)
√ √ √
RT-NT2 Line 2 (North - South Line) (Kollupitiya – Town Hall)
√ √ √
RT-NT3 and 4 Borella- Kirillapone-Homagama √
Railway RL-M1 to M5 Tentative signal improvement √ √
RL-M1 to M5 Electrification, Signal improvement, Procurement of Electric Cars
√
Note: * 2020 and 2025 are from Moratuwa - Kelaniya
Source: CoMTrans Study Team
Fares of public transport modes including bus, modernised railway, bus rapid transit (BRT) and monorail are assumed to be the same as current normal bus fares considering the policy of the Ministry of Transport. Low fare can attract more passengers compared with higher fare conditions during the initial stages while revenues from public transport will be limited. It also should be noted that low fare can be affordable to the poverty group. Current bus and railway fare structures are shown in Figure 3.1.6 and Figure 3.1.7.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
63
0
20
40
60
80
100
120
140
0 5 10 15 20 25 30 35 40
Railway 1st Class
Railway 2nd Class
Railway 3rd Class
Distance (km)
Far
e (R
s.)
Source: Sri Lanka Railways
Figure 3.1.6 Railway Fare Setting in Sri Lanka Railways
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
0 10 20 30 40
Fare
(R
upee
s)
Distance (km)
Normal
Semi-Luxury
Luxury
Source: National Transport Commission, Annual Fare Revision of 14 February 2012
Figure 3.1.7 Fares of Buses by Distance by Class in Sri Lanka
Service levels of public transport, which are represented by travel speed, frequency and congestion level in the transit assignment, are summarised in Table 3.1.14. It is assumed that service level will be improved due to the projects proposed in the master plan.
Fare
(L
KR
) Fa
re (
LK
R)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
64
Table 3.1.14 Service Level of Public Transport by Mode
Item Bus Modernised
Railway
BRT Monorail
Frequency Dependent on demand Dependent on demand
Initial setting is 1 - 6 trains per hour
Dependent on demand
Initial setting is 4 - 6 trains per hour
Dependent on demand
Initial setting is 6 - 30 trains per hour
Capacity* 60 passengers per vehicle (average of medium and large buses)
2,000 passengers per one train set
180 passengers per bus (articulated bus)
800 passengers per one train set
Speed 80% of road speed, maximum speed is 20km/h
50 km/h for express service
35 km/h for local service
23 km/h for intra city routes
25 km/h for suburban routes
30 km/h for Line 1
25 km/h for Line 2
Note: *100% capacity is seating capacity plus comfortable standing passenger capacity. Standing passengers can hold a hand strap or a hand rail.
Source: CoMTrans Study Team
(2) Road Network
The road network setting is also in line with the intensive public transport development scenario. Several expressways and arterial roads are assumed to be completed based on the proposal of the master plan. The road network settings are summarised in Table 3.1.15.
Table 3.1.15 List of Projects Included in the Road Assignment Network
Sub Sector Project ID Project Name 2020 2025 2035
Arterial
Roads
RD-RN3 Base Line Extension √ √
RD-RN4 Marine Drive Extension * √ √
RD-RN2 Middle Ring Road √ √
RD-RN1,5,6,7and 8
Major Arterial Roads √ √
RD-RN9,10 Minor Arterial Roads * √ √
Urban Expressways RD-EX1 Kelani-Borella-Kirillapone- √ √
RD-EX3 Port Access √ √ √
Note * partially completed. Details are in the CoMTrans urban transport master plan
Source: CoMTrans Study Team
Capacity, toll and speed settings of expressways are summarised in Table 3.1.16.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
65
Table 3.1.16 Toll Setting of the Road Assignment Network
Operation
Year
Expressway Toll Rate
Rs/km
Car
Toll Rate
Rs/km
Truck
Velocity
(km/h)
Capacity
(PCU/both
directions/ day)
2012 Southern Expressway (SE) 4.20 15.60 100 72,000
2013 Colombo-Katunayake (CKE) 13.60 27.10 80 60,000
2013 Outer Circular Highway (OCH or Outer Circular Expressway) (Kottawa – Kothalawala)
9.10 27.27 100 72,000
2020 Outer Circular Highway (OCH or Outer Circular Expressway) (balance section)
9.10 27.27 100 72,000
2035 Northern Expressway (NE) 4.20 15.60 100 72,000
2020 Port Expressway 13.60 27.10 60 50,000
2025 Horana Expressway (proposed by CoMTrans)
13.60 27.10 60
(From Kottawa- Nugegoda 80km/h)
60,000
Source: CoMTrans Study Team
Capacities and speeds settings of roads are summarised in Table 3.1.17. The capacity and velocity of the road network were determined by the results of the screen line survey and travel speed survey. The traffic count surveys of the screen line surveys were conducted during January – March 2013. A travel speed survey utilizing the global positioning system (GPS) was conducted with roughly 200 vehicles including taxies, passenger cars, school vans, office transport and trucks in the same duration. Therefore, some survey vehicles of the travel speed survey pass traffic count survey points. By matching traffic count survey data and travel speed survey data, scatter graphs of quantity – velocity distributions were prepared. An example of traffic volume – capacity graph is shown in Figure 3.1.8.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
66
Table 3.1.17 Capacity and Velocity Settings Arterial Roads for Road Assignment
Road Type Capacity
(pcu/2dir/day)
Velocity
(km/h)
6 Lane Urban 61,000 60
6 Lane (Suburban) 79,000 60
4 Lane (Urban, Non-CMC) 40,000 45
4 Lane (Suburban) 52,000 50
2 Lane (Urban) 17,000 35
2 Lane (Suburban) 22,000 45
2 Lane (Street) 10,000 30
5 Lane (Urban, One way) 51,000 60
4 Lane (Urban, One way) 41,000 60
3 Lane (Urban, One way) 30,500 60
2 Lane (Urban, One way) 20,000 45
1 Lane (Urban, One way) 8,000 35
Note: Capacity of roads in the CMC was reduced to 70% considering interference by intersections and parked vehicles.
Source: CoMTrans Study Team
0
10
20
30
40
50
60
0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000
Ve
loci
ty (
km
/h)
Traffic Volume per Direction (PCU per hour)
Source: CoMTrans Study Team
Figure 3.1.8 Example of Traffic Volume – Capacity Scattered Graph (4-lane Suburban
Roads)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
67
In addition, LKR 200 per direction per vehicle was charged to the vehicles which cross the boundary of Colombo Municipal Council (CMC) as an electronic road pricing (ERP).
3.2 Results of Demand Forecast
Based on the methodology and assumptions described in section 3.1, a traffic assignment was conducted. The estimated results of the transport demand for the monorail are summarised in Table 3.2.1. Daily passengers and passenger kilometres are expected to drastically increase by 2035 due to urban development projects along the corridor and improvement of public transport network.
Table 3.2.1 Summary of Demand Forecast Result
Indicator 2020 2025 2035
PPHPD of Line 1
Peak passenger per hour per direction at max. section
7,800
at Union Place – National Hospital
9,200
at Union Place – National Hospital
16,800
at National Hospital – Punci Borella
PPHPD of Line 2
1,300
at Dharmapala Mawatha –
National Hospital
1,500
at Dharmapala Mawatha –
National Hospital
4,100
at Dharmapala Mawatha –
National Hospital
Daily Passengers
in total monorail network
307,000 379,000 700,000
Daily Passenger-kilometres
in total monorail network
1,190,000 1,480,000 2,840,000
Source: CoMTrans Study Team
Sectional daily passenger volume of public transport in 2020, 25 and 35 are illustrated in Figure 3.2.1, Figure 3.2.2 and Figure 3.2.3 respectively.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
68
Note: Numbers are daily both direction sectional passengers in 1,000s. Source: SKYTRAIN Study Team
Figure 3.2.1 Daily Sectional Passengers of Public Transport in 2020 (Stage 1)
Note: Numbers are daily both direction sectional passengers in 1,000s. Source: SKYTRAIN Study Team
Figure 3.2.2 Daily Sectional Passengers of Public Transport in 2025 (Stage 1)
4
9
194
156
195
169
159
170
190
193
2
16
7475
78
48
35
87
34
86
91
27
28
68
84
81
80
79
102
76
78
16
79
74
47
39
85
94
44
98
86
91
102
43
88
66
89
103
104
57
68
100
106
125
82
34
43
85
41
53
42
BRT Monorail Railway Bus
7
116
92
67
78
104
69
56
129
1
14
636254
59
42
30
57
68
66
6987
22
36
50
64 60
6859
30
14
64
37
17
91
84
103
46
100
57
40
54
74
6866
42
81
34
67
47
100
31
14
BRT Monorail Railway Bus
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
69
Note: Numbers are daily both direction sectional passengers in 1,000s. Source: CoMTrans Study Team
Figure 3.2.3 Daily Sectional Passengers of Public Transport in 2035 (Stage 1)
Based on the estimated daily passenger volume, peak hour sectional passenger volume was estimated assuming eighteen percent peak ratio as mentioned in the subsection 3.1.2 (5) 2). Peak hour traffic volumes in 2020, 2025 and 2035 are shown in Figure 3.2.4, Figure 3.2.5 and Figure 3.2.6 respectively.
WTC
Fort
Malabe
Borella
Kotahena
Maradana
Town Hall
RajagiriyaKollupitiya Lumbini Temple
Punchi Borella
Sebastian Canal
Bandaranayake Mw
Palan Thuna Junc.
1300
5600
4800
5300
3800
2700
5100
6100
5900
62007800
2000
3200
5800 5400
2700
5600
1300
5300
5800
4500
5500
6200
Source: SKYTRAIN Study Team
Figure 3.2.4 Peak Hour Passenger Volume per Direction in 2020 (Stage 1)
282
21
23
18
27
259
223
289
251
227
243
286
284
45
68
64
28
122133174
53
60
46
170
148
183
157
186
156
175
132179
153
68
170
73
100
60
72
146
80
167
75
16893
169
138
98
143
149
223
222
192
104
217
163
162
120
100
75
BRT Monorail Railway Bus
IT Park
National Hospital
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
70
WTC
Fort
Malabe
Borella
Kotahena
Maradana
Town Hall
Rajagiriya
Kollupitiya Lumbini Temple
Punchi Borella
Sebastian Canal
Bandaranayake Mw
Palan Thuna Junc.
1500
67006800
7000
4300
3200
7800
3000
81009200
2400
6100
7500
7300
7200
7100
7000
6700
1500
6800
7100
2500
73007800
Source: SKYTRAIN Study Team
Figure 3.2.5 Peak Hour Passenger Volume per Direction in 2025 (Stage 1)
WTC
Fort
Malabe
Borella
Kotahena
Maradana
Town Hall
Rajagiriya
Kollupitiya Lumbini Temple
Punchi Borella
Sebastian Canal
Bandaranayake Mw
Palan Thuna Junc.
4100
1100012000
15700
6100
5700
25004700
5400
10500
15300
13300
14100
16800
14000
15800
13000
16100
13800
10700
6100
15300
16400
11900
Source: SKYTRAIN Study Team
Figure 3.2.6 Peak Hour Passenger Volume per Direction in 2035 (Stage 1)
Boarding and alighting passenger volume by station and sectional passenger volume during peak hour in 2020, 2025 and 2035 are shown in Figure 3.2.7, Figure 3.2.8 and Figure 3.2.9, respectively.
IT Park
National Hospital
IT Park
National Hospital
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
71
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Ko
tah
en
a
Arm
ou
r S
tre
et
Se
ba
stia
n C
an
al
Ma
rad
an
a
Tra
nsp
ort
Ce
ntr
e
Fo
rt
WT
C
Sla
ve
Isl
an
d
Un
ion
Pla
ce
Na
tio
na
l H
osp
ita
l
Pu
nch
i B
ore
lla
Bo
rell
a
Co
tta
Ro
ad
We
lik
ad
a
Ra
jag
iriy
a
Diy
aw
an
na
La
ke
Se
thsi
rip
ay
a
Ba
tta
ram
ull
a
Pa
lan
Th
un
a
Ro
be
rt G
un
aw
ard
en
a…
Lum
bin
i T
em
ple
Ta
lah
en
a
Ma
lab
e
IT P
ark
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Kot
ahen
a
Arm
our
Stre
et
Seba
stia
n C
anal
Mar
adan
a
Tra
nspo
rt C
entr
e
Fort
WT
C
Slav
e Is
land
Uni
on P
lace
Nat
iona
l Hos
pita
l
Punc
hi B
orel
la
Bor
ella
Cot
ta R
oad
Wel
ikad
a
Raj
agir
iya
Diy
awan
na L
ake
Seth
siri
paya
Bat
tara
mul
la
Pala
n T
huna
Rob
ert…
Lum
bini
Tem
ple
Tal
ahen
a
Mal
abe
IT P
ark
Alighting
Boarding
Section Volume
Passengers per hour per direction
Source: SKYTRAIN Study Team
Note: “Robert…” is “Robert Gunawardena Mawatha” station.
Figure 3.2.7 Peak Hour Passenger Loading by Station in 2020 (Stage 1)
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Ko
tah
en
a
Arm
ou
r S
tre
et
Se
ba
stia
n C
an
al
Ma
rad
an
a
Tra
nsp
ort
Ce
ntr
e
Fo
rt
WT
C
Sla
ve
Isl
an
d
Un
ion
Pla
ce
Na
tio
na
l H
osp
ita
l
Pu
nch
i B
ore
lla
Bo
rell
a
Co
tta
Ro
ad
We
lik
ad
a
Ra
jag
iriy
a
Diy
aw
an
na
La
ke
Se
thsi
rip
ay
a
Ba
tta
ram
ull
a
Pa
lan
Th
un
a
Ro
be
rt G
un
aw
ard
en
a…
Lum
bin
i T
em
ple
Ta
lah
en
a
Ma
lab
e
IT P
ark
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Kot
ahen
a
Arm
our
Stre
et
Seba
stia
n C
anal
Mar
adan
a
Tra
nspo
rt C
entr
e
Fort
WT
C
Slav
e Is
land
Uni
on P
lace
Nat
iona
l Hos
pita
l
Punc
hi B
orel
la
Bor
ella
Cot
ta R
oad
Wel
ikad
a
Raj
agir
iya
Diy
awan
na L
ake
Seth
siri
paya
Bat
tara
mul
la
Pala
n T
huna
Rob
ert…
Lum
bini
Tem
ple
Tal
ahen
a
Mal
abe
IT P
ark
Alighting
Boarding
Section Volume
Passengers per hour per direction
Source: SKYTRAIN Study Team
Note: “Robert…” is “Robert Gunawardena Mawatha” station.
Figure 3.2.8 Peak Hour Passenger Loading by Station in 2025 (Stage 1)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
72
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Ko
tah
en
a
Arm
ou
r S
tre
et
Se
ba
stia
n C
an
al
Ma
rad
an
a
Tra
nsp
ort
Ce
ntr
e
Fo
rt
WT
C
Sla
ve
Isl
an
d
Un
ion
Pla
ce
Na
tio
na
l H
osp
ita
l
Pu
nch
i B
ore
lla
Bo
rell
a
Co
tta
Ro
ad
We
lik
ad
a
Ra
jag
iriy
a
Diy
aw
an
na
La
ke
Se
thsi
rip
ay
a
Ba
tta
ram
ull
a
Pa
lan
Th
un
a
Ro
be
rt G
un
aw
ard
en
a…
Lum
bin
i T
em
ple
Ta
lah
en
a
Ma
lab
e
IT P
ark
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
Kot
ahen
a
Arm
our
Stre
et
Seba
stia
n C
anal
Mar
adan
a
Tra
nspo
rt C
entr
e
Fort
WT
C
Slav
e Is
land
Uni
on P
lace
Nat
iona
l Hos
pita
l
Punc
hi B
orel
la
Bor
ella
Cot
ta R
oad
Wel
ikad
a
Raj
agir
iya
Diy
awan
na L
ake
Seth
siri
paya
Bat
tara
mul
la
Pala
n T
huna
Rob
ert…
Lum
bini
Tem
ple
Tal
ahen
a
Mal
abe
IT P
ark
Alighting
Boarding
Section Volume
Passengers per hour per direction
Source: SKYTRAIN Study Team
Note: “Robert…” is “Robert Gunawardena Mawatha” station.
Figure 3.2.9 Peak Hour Passenger Loading by Station in 2035 (Stage 1)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
73
CHAPTER 4 Route Alignment and Station Locations
4.1 Criteria for Route Planning
The alignment of the monorail is in line with the proposal of the CoMTrans urban transport master
plans mentioned in Chapter 2. From this chapter, detailed alignments and station locations are
discussed in accordance with the technical aspects
The eastern part of route 1 is along with the Malabe Corridor as there is no transit line at this
moment. The Malabe corridor has the highest vehicle demand among the seven corridors
radiating from the Colombo Municipal Council (CMC). In addition, high population growth is
expected due to urban development projects and residential development projects along the
corridor such as universities, hospitals, government offices and residential areas.
The monorail is, therefore, expected to function as a catalyst to promote use of public transport
aiming alleviation of traffic congestion improvement of mobility of the area and economic growth
of the corridors and Colombo Metropolitan Area.
The line starts from Malabe of which the depot is located via Malabe, Battaramulla, Borella,
National Hospital, Fort, Maradana, Mattakuliya and reaches Kelaniya.While the Stage 1 of the
monorail stops at Kotahena, the line is expected to extend toward Kelaniya in the Stage 2 through
Mattakuliya.
Route alignment and station location is proposed in compliance with the following table.
Table 4.1.1 Criteria of Route Alignment and Station Location
Item Policy
Radius
The minimum horizontal curve radius shall be R=60m.
The station platform shall be installed in a straight section as much as
possible. In the case of a curving section, the minimum curve radius
shall be more than R=300m.
Longitudinal gradient The steepest gradient shall be less than 60‰.
Points of attention regarding
station layout
The station spacing shall be designed to be 0.5~1km in the urban areas
and 1~1.5km in suburban areas.
On selection of station location, the degree to which a station is close to
other transportation systems, major roads, and facilities with high
customer attraction capacity, shall be considered.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
74
4.2 Alternatives Analysis on Route Alignment and Station Locations
The route alignment and the station location are basically proposed in compliance with the above
criteria. However, several locations with particular features, such as accessibility to facilities
with high customer attraction, construction cost and restrictions on alignment, are examined
individually with alternative options.
In this section, alternative options and a comparative study for the alignment of the below stations
and sections are described.
• WTC Station
• National Hospital Station~Borella Station
• Borella Station~Welikada Station
• Sethshiripaya Station~IT Park Station
• North section (Armour Street Station ~ Kelaniya Station , MMC Station)
• Line 2
• Kollupitiya Station
Source: SKYTRAIN Study Team
Figure 4.2.1 General Route Alignment
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
75
4.2.1 World Trade Centre (WTC) Area
(1) Summary
Regarding the selection of WTC Station, this study selected Option 1 as the optimum plan because
it shortens the whole route length and required travel time, but it has issues regarding the
constructability.
Option 2 has the advantage of better accessibility to the World Trade Centre but it obstructs the
private land and lengthens the route.
Table 4.2.1 List of Examined Options
Name Concept
Shorter Route length option
(Option 1) The station is located at east side to shorten the route length.
WTC adjoining option
(Option 2)
The station is located as close as possible to the WTC for the
improvement of customer convenience.
Source: SKYTRAIN Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
76
So
urc
e: S
KY
TR
AIN
Stu
dy T
eam
Figure 4.2.2 WTC Route O
ptions
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
77
(2) Shorter route length plan (Option 1)
In contrast to Option 2, Option 1
gives the shortening of route
length top priority. For that
purpose, the station is located
over a road adjacent to SLR on
the east side of the WTC.
Although the route length can be
330m shorter than Option 2, it
has an issue on constructability
because monorail piers may
obstruct a road bridge across the
SLR southeast of the station.
(3) WTC adjoining plan (Option 2)
Option 2 places the station
adjacent to and as close as
possible to the WTC. To secure
a length of straight section, the
station is located at a straight
section on the west side of the
crossing with SLR.
The station and the route partially
cross the road section and have to
pass over the private land.
Therefore, consultation about the
development plan of the
surrounding area is required.
It has an advantage regarding
constructability since the
grade-separated crossing with
SLR east of the station has no
impact on the road bridge.
The result of comparative study and drawings are shown in the next section.
Source: SKYTRAIN Study Team
Figure 4.2.4 Planned WTC Station Location of Option 2
Source: SKYTRAIN Study Team
Figure 4.2.3 Planned WTC Station Location of Option 1
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
78
(4) Comparison table and map of WTC station location plan
Table 4.2.2 Comparison between WTC Station Location Options
Issues Option 1 Option 2
The distance to the
WTC
(Customer
Convenience)
The distance between the WTC and the
station is far, which worsens customer
convenience. The WTC is about approx.
300m away from the proposed station
location.
The distance between the WTC and the
station is close, which improves customer
convenience. The WTC is about approx.
190m away from the proposed station
location.
△ ○
Impact on the private
land
Coordination with the
development plan
There is no impact on private land
basically.
A part of the station and the route corridor
is out of the road section and passes
through private land. The coordination
with the development plan of the
surrounding area is required.
○ △
Impact on the route
length
The line length becomes shorter than
Option 2 by approx. 330m.
The route length becomes longer than
Option 1 by approx.330m.
○ ×
Construction Cost
Although the route is shorter, a road
bridge at the crossing with SLR needs to
be renovated, which increases total
construction cost.
The longer route increases the
construction cost. Because the corridor
passes through private land, land
acquisition is necessary.
△ ×
Crossing over SLR
(Constructability)
It causes difficulty for the installation of
piers near the crossing over SLR on the
south side of the WTC station. The pier
construction has an impact on the existing
road, and the road bridge crossing over
SLR needs to be renovated. Therefore,
additional cost would be incurred.
It is easy and feasible to construct piers
near the crossing over SLR on east side of
the WTC.
△ ○
Evaluation ○ △
Source: SKYTRAIN Study Team
Note: △○: Good/Desirable, : Fair, ×: Less Desirable
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
79
Source: SKYTRAIN Study Team
Figure 4.2.5 WTC Station Location Option 1
Source: SKYTRAIN Study Team
Figure 4.2.6 WTC Station Location Option 2
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
80
4.2.2 Sections between National Hospital and Borella
(1) Summary
The Option 1 which passes through Punchi Borella is selected because there are many hospitals
along National Hospital- Borella route. Although the space for monorail corridor is limited at
the section near National Hospital at the moment, more space can be secured following the
renewal plan of National Hospital.
The Option 2 is the shortest route connecting National Hospital with Borella, however, alignment
is constrained due to some narrow places on the existing road.
Table 4.2.3 List of Examined Options for National Hospital ~ Borella Section
Option Concept
Northern Route
(Option 1)
This route begins from Town Hall intersection, passing through the
National Hospital, and reaches Borella via Punchi Borella.
In regard of passenger demand, this is a critical route since there are
many hospitals and schools along it.
Southern Route
(Option 2)
This is the shortest route from the Town Hall intersection toward
Borella. Comparing the Option 1, this route takes advantages of route
length and construction cost, however, alignment is constrained due to
some narrow places on the existing road.
Source: SKYTRAIN Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
81
So
urc
e: S
KY
TR
AIN
Stu
dy T
eam
Figure 4.2.7 Route Plan for Section between National Hospital St. and Borella St.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
82
(2) Northern Route (Option 1)
This route begins from the intersection at the Town Hall area, pass through the National Hospital,
and reaches Borella via Punchi
Borella. In regard to passenger
demand, this is a critical route
since there are many hospitals
and schools along this corridor.
Although the space for monorail
corridor is limited at the section
near National Hospital at the
moment, space can be secured
following the renewal plan of
National Hospital. Punchi
Borella Station is located in the
middle of this section.
Source: SKYTRAIN Study Team
Figure 4.2.8 National Hospital Station Location (Option 1)
(3) Northern Route (Option 2)
In contrast to Option 1, this is the shortest route from the Town Hall area to Borella.
Comparing with Option 1, this route is more preferable in term of commercial speed and
construction cost because it can be 400m shorter and there is no station in the middle.
However, it is not convenient for
passengers to access National
Hospital, which has negative
impacts on ridership.
In addition, this route is inferior
from the demand side. The
surrounding area is used for
residence, and there are neither
intermediate stations nor major
facilities with high customer
attraction.
The result of comparative
analysis and drawings are
summarised in the next section.
Source: SKYTRAIN Study Team
Figure 4.2.9 National Hospital Station Location (Option 2)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
83
(4) Comparison Table and Map of National Hospital Station ~ Borella Station Section
Table 4.2.4 Comparison between Options for National Hospital St. ~ Borella St. Section
Issues Option 1 Option 2
Train operation
Commercial speed is lower due to
longer length and existence of a strict
curve and an intermediate station.
The route is shorter and there is no tight
curve in the section.
× ○
Impact on the
private land
Less private houses would be affected
compared to Option 2 since this route
go through hospital complex of which
land is owned by public.
Several private houses might be affected
by stations
○ △
Route length 400 m longer than Option 2. 400 m shorter than Option 1
△ ○
Constructability
The existing road inside National
Hospital is too narrow but it will be
possible to introduce monorail after the
renewal of this hospital.
The alignment is constrained due to
some narrow places on the existing road.
The construction of station is possible
but the placement of escalators,
stairways is difficult.
○ ×
Cost
Higher cost than Option 2 due to longer
route and more stations.
Lower cost than Option 1
△ ○
Convenience
It is convenience from the point of view
of better accessibility for passengers
since there are intermediate stations,
hospitals and schools along the route.
Not convenient for passengers due to
considerable distance to hospitals.
○ ×
Evaluation ○ △
Source: SKYTRAIN Study Team
Note: △○: Good/Desirable, : Fair, ×: Less Desirable
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
84
Source: SKYTRAIN Study Team
Figure 4.2.11 Option 2 of National Hospital Station ~ Borella Station Section
Source: SKYTRAIN Study Team
Figure 4.2.10 Option 1 for National Hospital Station ~ Borella Station Section
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
85
4.2.3 Sections between Borella and Welikada
(1) Summary
Comparing to Option1, Option 2 requires higher investment because the route length is approx.
220m longer with its additional detour toward the south. Moreover, the trains have to slow down
because a tight curve is inserted in the middle between stations. Therefore, Option 2 represents
considerable challenges in the improvement of commercial speed. In consideration of
accessibility to SLR at the intermediate station (tentative name: Devi Balika Station), Option 1 is
better than Option 2. Therefore, Option 1 is selected for this section.
Table 4.2.5 List of Examined Options for Borella ~ Welikada Section
Option Concept
North Route
(Option1)
Option 1 is the shortest route plan. The route begins in Borella
Station, passing through SLR Cotta Road station and reaches Welikada
Station.
South Route
(Option2)
Option 2 is the route plan arranged on the south side of Borella station.
It passes through the north side of Borella General Cemetery before
reaching Welikada station. It is an alternate plan if the route plan of
Option 1 cannot avoid the Bo Tree on Borella street.
Source: SKYTRAIN Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
86
So
urc
e: S
KY
TR
AIN
Stu
dy T
eam
Figure 4.2.12 Route Plans for Borella Station ~ W
elikada Station Section
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
87
(2) North Route Plan (Option 1)
In the vicinity of intersection at Borella station, there is an important Bo Tree near the centre of
road section
Because the impact on the Bo Tree must be avoided, and an underpass is being constructed near
this tree, monorail piers must be arranged to avoid it. This causes difficulty in locating the
structures. For better transfer to
SLR, a station is located here since
the route crosses near Cotta Road
station of SLR Although the SLR
trains stop at this station several times
a day at present, this option is
proposed with consideration to the
future increase in the train frequency.
From Cotta Road station, the
monorail route follows the existing
road and terminates at Welkada
Station.
Source: SKYTRAIN Study Team
Figure 4.2.13 The Bo Tree near the Borella Station
(3) South Route Plan (Option 2)
Option 2 is an alternate plan if the Bo Tree near Borella Station cannot be avoided.
From the intersection near Borella station, the route turns south along BaseLine Road, passing
through A0 road, and then proceeds along the north of Borella General Cemetery until connecting
to the same alignment as Option 1. The intermediate station is located near the intersection with
SLR station (tentative name: Devi
Balika Station).
Although the alignment crosses over
the SLR line, there is no SLR station
nearby at present. Cotta Road
station of SLR is not so far; therefore,
the construction of a transfer station
is not realistic. The distance
between the existing Cotta Road
station and the Devi Balika Station is
approx.300m. It is possible to
transfer between monorail and SLR,
but the accessibility is low.
Source: SKYTRAIN Study Team
Figure 4.2.14 Baseline Road Intersection
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
88
(4) Comparison table and Map of the Section between Borella Station and Welikada Station
Table 4.2.6 Comparison between Options for Borella St. ~ Welikada Section
Issues Option1 Option2
Impacts on Train
Operation
The route is shorter than Option 2, and no
tight curve is inserted in the middle
between stations. Therefore, it takes
advantages of commercial speed.
The route is longer than Option 1, and a
tight curve must be inserted in the middle
between Borella station and Devi Balika
Station. More journey time is required as
the commercial speed is lower.
○ ×
Impact on the
private land
Road is wide enough to accommodate
Monorail system.
Several private houses would be affected at
the intersection between Base Line Road
and A0 Road.
○ ×
Route length
The route is approx. 220m shorter than
Option 2.
The route is approx. 220m longer than
Option 1.
△ ×
Constructability・Feasibility
The issue on alignment is the evasion of the
Bo Tree near Borella station. Option 1
can be feasible if the route passes through
the bus terminal site at the north of the
Important Tree.
Although a minimum curve is inserted at
the intersection between Base Line Road
and A0 Road, it is still necessary to acquire
land for the monorail corridor in case of
normal horizontal double track alignment.
The land acquisition can be avoided by
using a two-layer structure in which one
track is above the other track to reduce the
corridor width. But when considering the
longitudinal slope, Borella station must be
a two-layer structure as well, which implies
challenges in both construction and
landscape.
This option remains in case avoidance of
the BoTree in Option 1 is impossible.
△ △
Cost Lower construction cost Higher construction cost
○ △
Accessibility
Cotta Road is adjacent to the SLR’s station,
so the passenger accessibility is higher.
However, the train frequency of the SLR is
low, so the demand for transfer is not
significant.
The passenger accessibility is fair. While
the Cotta Road station is 300m away from
the planned monorail station, accessibility
to Castle Maternity Hospital is high.
○ △
Selected Option ○ ×
Source: SKYTRAIN Study Team
△Note: ○: Good/Desirable, : Fair, ×: Less Desirable
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
89
Source: SKYTRAIN Study Team
Figure 4.2.16 Option 2 for Borella ~ Welikada Section
Source: SKYTRAIN Study Team
Figure 4.2.15 Option 1 of Borella ~ Welikada Section
1
2
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
90
4.2.4 Sections between Sethshiripaya and Malabe
(1) Summary of Result
The construction cost is higher in Option 1 because the route is 950m longer. In Option 2, it is
necessary to widen the existing road to construct stations. Additionally, Option 2 does not have
potential to capture high ridership along Malabe Road. Option 1 may have more ridership
because there will be transfer of various governmental bodies along its corridor.
Therefore, Option 1 is selected because it is easier to secure space for monorail line and higher
ridership is expected. However, the route passes through military lands, so consultation is
required to obtain approval.
Table 4.2.7 List of Examined Options for Sethshiripaya ~ Malabe Section
Option Concept
South Route
(Option1)
This route turns south at Sethsiripaya along Pannipitiya Road, and then
trends north at Palan Thuna Station. After passing Robert Gunawadena
Mw Station, the route returns to Malabe Road before reaching IT Park. In
future, various governmental bodies shall be transferred to Robert
Gunawadena Mw Station.
North Route
(Option2)
This route proceeds from Sethshiripaya along Malabe Road until reaching
IT Park.
Source: SKYTRAIN Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
91
So
urc
e: S
KY
TR
AIN
Stu
dy T
eam
Figure 4.2.17 Sethshiripaya Station ~ IT Park Station Section
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
92
(2) South Route (Option 1)
This route turns south at Sethsiripaya along Pannipitiya Road, and then trends north at Palan
Thuna Station. After passing Robert Gunawadena Mw Station to where various governmental
bodies shall be transferred, the route returns to Malabe Road near Lumbini Temple Station before
reaching IT Park. Although space for monorail is slightly narrow at Sethshiripaya- Palan Thuna
section, sufficient space is available for other sections. Because this route passes through the
land owned by Air Force at northern side of Buttaramulla intersection, it is necessary to have
further discussion about this issue.
Although the route in Option 1 is 950m longer than in Option 2, its ridership is expected to be
better because there will be transfer of various governmental bodies to the areas near Palan Thuna
and Robert Gunawadena Mw Station.
(3) North Route (Option 2)
This route proceeds from Sethshiripaya along Malabe Road before reaching IT Park. Comparing
to Option 1, this route is 950m shorter but space for station is more difficult to secure because
Malabe Road is not wide enough.
On adoption of this route, it is
necessary to widen this road;
otherwise, there are various
challenges with the existing road.
There are several small shops on the
road, but the density of population
in residential areas around the road
is not high, which causes
disadvantages in term of ridership.
Source: SKYTRAIN Study Team
Figure 4.2.18 Option 2 Malabe Road
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
93
(4) Comparison Table and Map of the Section between Sethshiripaya Station and IT Park
Station
Table 4.2.8 Comparison between Options for Sethshiripaya ~ IT Park Section
Issues Option 1 Option 2
Impacts on train
operation
More train journeys are required due to
950m longer route.
Route length is short, but there are many
tight curves, which decrease overall
commercial speed.
△ △
Impact on the private
land
This route avoids narrow road sections
and require less land acquisition of
private land
The roads is too narrow and impact of land
acquisition is significant.
○ ×
Route length Longer than in Option 2 by 950m Shorter than in Option 1 by 950m
△ ○
Constructability
Sufficient space for monorail can be
secured, however, this route passes
through the land owned by Air Force at
northern side of Buttaramulla
intersection, it is necessary to have
further discussion about this issue.
During construction, negative impact on
traffic is expected due to lack of space in
some sections. Particularly, the road is too
narrow to construct station that widening the
road is necessary.
× ×
Cost
Higher cost due to longer route. Although the route is shorter, huge capital
expenditure associated with road widening
is required.
△ ×
Ridership
Ridership is expected to be better
because various government buildings
are moved to the area along the route.
Density of population in residential areas
around the road is not high, which is
disadvantageous in term of demand.
○ ×
Evaluation △ ×
Source: SKYTRAIN Study Team
Note: △○: Good/Desirable, : Fair, ×: Less Desirable
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
94
So
urc
e: S
KY
TR
AIN
Stu
dy T
eam
Figure 4.2.19 Option 1 Alignment for Sethshiripaya ~ IT Park Section
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
95
So
urc
e: S
KY
TR
AIN
Stu
dy T
eam
Figure 4.2.20 Option 2 Alignment for Sethshiripaya ~ IT Park Section
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
96
4.2.5 North Section between Armour Street and Kelaniya
(1) Summary
For the Armour Street Station – Kelaniya Station section, four route options are proposed.
Although most parts of the section are in the Stage-2, which is not the section for the construction
of Stage-1, alternative route options were examined.
Among them, Option 1 was recommended as the areas along the Option 1 are populated areas
which do not have enough public transport services. It is expected that the monorail system
expand the areas served by public transport system. .
However, the existing road at Kotahena- Mattakuliya section is too narrow for the monorail
corridor that road widening and land acquisition are necessary. For the Stage-2, further
examinations are to be required.
Table 4.2.9 List of Examined Options for Armour Street ~ Kelaniya Sectoin
Name Concept
Option 1
(via Mattakkuliya)
This alignment passes through Armour Street Station, Kotahena station
before heading north along the coast. After passing through
Mattakkuliya, it crosses Kelani River and terminates at MMC station
which is about 1km from northeast of Kelaniya Station of SLR. The
accessibility to SLR will be possible if a new station of SLR is
constructed at MMC.
Armour Street Station ~ MMC Station: 8.0km
Option 2
(via Negombo)
From Armour Street Station, the route follows Prince of Wales Ave,
crossing Kelani River via JFB (Japanese Friendship Bridge), and
proceeds to MMC. This route passes in between Option 1 route and
SLR line.
Armour Street Station ~ MMC Station: 6.5km
Option 3
(via 4th Mile Post)
From Armour Street Station to JFB, the route follows the same path as
in Option 2, but after crossing Kelani River, it proceeds along Kandy
Road and then reaches MMC after passing Kelaniya Station of SLR.
Armour Street Station ~ MMC Station: 6.3km
Option 4
(via Mattakkuliya and
terminating at Kelaniya)
The route follows the same path as in Option 1 except that the terminus
station is Kelaniya.
Armour Street Station ~ Kelaniya Station: 7.4km
Source: SKYTRAIN Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
97
Source: SKYTRAIN Study Team
Figure 4.2.21 North Section Alignment Map
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
98
(2) Option 1 (via Mattakkuliya)
From Armour Street Station, this alignment passes through Kotahena station before heading north
along the coast. After passing through Mattakkuliya, it crosses Kelani River and terminates at
MMC station which is about 1km from northeast of Kelaniya Station of SLR. The route length
is around 8km which is the longest among the four proposed routes.
However, the existing road at
Kotahena- Mattakkuliya section is
too narrow for monorail stations that
road widening is necessary.
There is road widening plan
undertaken separately. Once the
widening is completed, the
introduction of the monorail is
possible.
Source: SKYTRAIN Study Team
Figure 4.2.22 The Road near Mattakkuliya
(3) Option 2 (via Negombo)
From Armour Street Station, the
route follows Prince of Wales Ave,
crossing Kelani River by JFB
(Japanese Friendship Bridge), and
proceeds to MMC. This route
passes in between Option 1 route and
SRL line.
Density of population along this
route is lower than in Option 1,
which has negative impact on
ridership. However, route length
and journey time can be shortened.
As a result, the average operation
speed becomes faster than Option 1.
Source: SKYTRAIN Study Team
Figure 4.2.23 The Road near JFB (Japanese Friendship Bridge)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
99
(4) Option 3 (via 4th Mile Post)
From Armour Street Station to JFB, the route follows the same path as in Option 2, but after
crossing Kelani River, it proceeds along Kandy Road and then reaches MMC after passing
Kelaniya Station of SLR.
This route enables accessibility to
SLR at Kelaniya Station, which is
not possible in Option 2. It also
takes advantages of construction
cost as the route length is about
6.3km, which is the shortest among
four options.
From the north of JFB, the route
follows the Kandy Road, which is
spacious enough for construct
monorail. Nevertheless, it is
necessary to acquire land to avoid a
road bridge at intersection with SLR.
Source: SKYTRAIN Study Team
Figure 4.2.24 Road Bridge near Kandy Road
(5) Option 4 (via Mattakkuliya, and terminating at Kelaniya)
This route basically follows the
same path as the Option 1 except
that the terminus station is
Kelaniya. In contrast to Option 1
which connection to MMC is the
main purpose, this option takes the
connection with SLR as the first
priority.
Because the Kandy Road crosses
SLR line at right angles, it is
difficult to extend the monorail line
in the future.
Source: SKYTRAIN Study Team
Figure 4.2.25 Kandy Road in front of Kelaniya Station
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
100
(6) Comparison table and Map of the Section between Armour Street ~ Kelaniya Sectoin
Table 4.2.10 Comparison between Options for Armour Street ~ Kelaniya Sectoin
Source: SKYTRAIN Study Team
Note: △○: Good/Desirable, : Fair, ×: Less Desirable
* Although the impact on the private land is big, the option 1 is recommended as the areas are not covered by public
transport system at present. The section is mainly in the Stage-2 of the monorail system, therefore further examinations are required.
Issues Option 1 Option 2 Option 3 Option 4
Impact on train
operation
Longer journey from Armour Street Station to MMC Station due to longer route and more intermediate stations. Consequently, more journeys and number of vehicles are required.
Number of intermediate stations: 8 (north of Armour Street St)
The route is shorter, yet short interval between stations decrease commercial speed.
Number of intermediate stations: 7 (north of Armour Street St)
Shorter journey time and decrease in train numbers due to shorter route and less number of stations.
Number of intermediate stations: 6 (north of Armour Street St)
Longer journey time due to longer route and more stations. Number of intermediate stations: 8 (north of Armour Street St)
× △ ○ ×
Impact on the private
land
More than 200 householders would be resettled.
Land acquisition is limited to area for stations
Land acquisition is limited to area for stations
More than 200 householders would be resettled.
× △ △ ×
Route length
Armour Street Station ~ MMC Station
8.0km
(the longest route)
Armour Street Station ~ MMC Station : 6.5km
Armour Street St ~ MMC Station: 6.3km
(the shortage route)
Armour Street Station ~
Kelaniya Station: 7.4km
× ○ ○ △
Constructability
The existing road at Kotahena- Mattakkuliya section is too narrow for monorail stations. Additionally traffic shall be badly affected during construction. Therefore, road widening is necessary.
Space is available for monorail corridor. There is no difficulty with the constructability.
Crossing with the road bridge near Kelaniya Station is the most problematic issue. Land acquisition is necessary.
The existing road at Kotahena- Mattakkuliya section is too narrow for monorail stations. Additionally traffic shall be badly affected during construction. Therefore, road widening is necessary.
× ○ △ ×
Cost
Higher capital expenditure is expected because of longer route. In addition, this route has to cross the wide part of Kelani river.
Shorter route decreases construction cost. This route has to cross the river, but the width of the river on the route is not wide.
Shorter route and less number of stations decrease construction cost. This route has to cross the river, but the width of the river on the route is not wide.
This option is basically similar to Option 1, in which higher construction cost is necessary.
× △ ○ ×
Ridership
High ridership is expected as the routes passes through populated areas
Ridership is low as population density along the corridor is low.
Ridership is low as population density along the corridor is low.
High ridership is expected as the routes passes through populated areas
○ × × ○
Connectivity with
MMC, SLR
Transfer to SLR will be convenient if a new SLR station is added at MMC.
Transfer to SLR will be convenient if a new SLR station is added at MMC.
Transfer to SLR is possible at both Kelaniya and MMC
Transfer to SLR is possible only at Kelaniya, which is inconvenient for bus passengers.
△ △ ○ △
Evaluation ○ * △ △ ×
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
101
Source: SKYTRAIN Study Team
Figure 4.2.26 North Section (Option 1)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
102
Source: SKYTRAIN Study Team
Figure 4.2.27 North Section (Option 2)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
103
Source: SKYTRAIN Study Team
Figure 4.2.28 North Section (Option 3)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
104
Source: SKYTRAIN Study Team
Figure 4.2.29 North Section (Option 4)
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
105
4.2.6 Route Alignment of Line 2
(1) Summary
Since the alignment of Line 2 has considerable impacts on Line 1, this study analyses three
options considering the connectivity between those two lines.
The Option 1, which connects Kollupitiya Station with National Hospital St., is selected as the
most feasible option. In both Option 2 and Option 3, it is necessary to build Line 2 to be
grade-separated with Line 1. Those higher structures have negative impacts on landscape.
This result places importance on the scenery since there are many historic buildings in the vicinity
of National Hospital St. (Town Hall area) where Line 1 connects to Line 2.
Table 4.2.11 List of Examined Options for Line 2
Option Concept
Option 1
Kollupitiya Station~National
Hospital Station
Monorail station is located on Galle Road in the vinicity of SLR
Kollupitiya Station. After passing Dharmapala Mawatha Station, the
route arrives National Hospital Station which is adjacent to Town Hall
area.
Option 2
Kollupitiya Station ~
Sebastian Canal Station
The route begins at Kollupitiya Station of SLR, intersects with Line 1
(multi-level crossing) near Town Hall area and reaches Sebastian
Canal Station.
Tracks are connected directly at Sebastian Canal Station while
passengers have to transfer at National Hospital St. to change between
Line 1 and Line 2.
Option 3
Kollupitiya Station ~
Transport Centre Station
The route begins at Kollupitiya Station of SLR, intersects with Line 1
(multi-level crossing) near Town Hall and reaches Transport Centre
Station.
In Option 2, because road width for Sebastian Canal Station is just
enough for the station, the arrangement of station is extremely difficult.
In comparison with Option 2, available land piece of SLR can be used
instead of private land acquisition.
Source: SKYTRAIN Study Team
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
106
Source: SKYTRAIN Study Team
Figure 4.2.30 Line 2 Route Alternatives
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
107
(2) Option 1 (Kollupitiya Station~National Hospital Station)
Monorail station is located on Galle Road in the vinicity of SLR Kollupitiya Station. After
passing Dharmapala Mawatha Station, the route arrives National Hospital Station which is
adjacent to Town Hall area. The line can be easily extended to Bambalapitya in case of
extension. The Kollupitiya monorail station is located on Galle Road which is 200m far from
Kollupitiya station of SLR, it is therefore necessary to build pedestrian deck between the two
stations to improve passenger convenience.
The route shall connect with Line 1 at National Hospital Station. In order to decrease height of
structures, two lines are connected on the same grade.
In order to decrease station section, platform of Line 2 (one side, one track) connects with
platform of Line 1 (separated platform, two sides, 3 tracks) at different level.
Source: SKYTRAIN Study Team
Figure 4.2.31 Line2 - Track arrangement at National Hospital Station
In contrast to Option 2 and Option 3, the route of Option 1 ends at National Hospital St. and does
not connect with Maradana Station of SLR. Because Maradana is an important hub, as an
alternative, Line 1 trends south at Transport Centre Station to connect with Maradana Station then
turn back to Sebastian Canal Station.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
108
Source: SKYTRAIN Study Team
Figure 4.2.32 Transport Centre St. ~ Sebastian Canal St. Line1 Route
(3) Option 2 (Kollupitiya Station - Sebastian Canal Station)
The route begins at Kollupitiya Station of SLR, intersects with Line 1 (multi-level crossing) near
National Hospital St. and reaches Sebastian Canal Station. Tracks are connected directly at
Sebastian Canal Station while passengers have to transfer at National Hospital St. to change
between Line 1 and Line 2.
In contrast to Option 1, the route in Option 2 starts from Kollupitiya Station and keeps stretching
toward the north side of National Hospital St. passing through Maradana Station then connects
with Line 1 at Sebastian Canal Station. For direct operation with Line 1, there are two proposals
of station layouts: Two-layer platform, and Horizontal partition platform. In Two-layer platform
proposal, height of station has negative impact on landscape. Therefore, Horizontal partition
platform is adopted.
The connection between Line 1 and Line 2 is proposed mainly for purpose of dead-head
operation; hence single connecting track shall be planned. Because the station of each line is
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
109
separated from each other, these two stations are linked by pedestrian deck.
At the multi-level intersection at National Hospital St. between Line 1 and Line 2, it is
necessary to mitigate height of monorail beam with surrounding landscape.
Source: SKYTRAIN Study Team
Figure 4.2.33 Sebastian Canal Station: Image of Two-layer Platform
Source: SKYTRAIN Study Team
Figure 4.2.34 Sebastian Canal St
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
110
(4) Option 3 (Kollupitiya Station ~ Transport Centre Station)
In Option 2, because road width for Sebastian Canal Station is too narrow, the arrangement of
station is extremely difficult. Therefore, land acquisition is necessary. To avoid land
acquisition, Option 3 proposes the connecting with Line 1 at Kesalwaththa Station. Because land
of SLR and public school is available nearby Kesewaththa intersection, land acquisition from
private owner is not necessary.
The connection between Line 1 and Line 2 at Transport Centre Station is proposed mainly for
purpose of dead head operation; hence single connecting track shall be placed. Because the
station of each line is separated from each other, these two stations are linked by pedestrian deck.
Source: SKYTRAIN Study Team
Figure 4.2.35 Transport Centre Station
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
111
(5) Comparison table and Map between Options
Table 4.2.12 Comparison between Options for Line 2
Issues Option1 Option2 Option 3
Landscape
Better landscape – as there
is no multi-level
intersection.
Due to multi-level
intersection, higher
monorail beam at National
Hospital St. may cause
discomfort and negative
impacts on landscape and
surrounding historical
buildings.
Due to multi-level
intersection, higher
monorail beam at Town Hall
may cause discomfort and
negative impacts on
landscape and surrounding
historical buildings.
○ × ×
Impact on the
private land
No outstanding issue No outstanding issue No outstanding issue
○ ○ ○
Route length
2.1km
Option 1 is the shortest
route and cost saving can be
expected.
4.0km
Almost 2 times longer than
Option 1
4.0km
Almost 2 times longer than
Option 1
△ △ △
Constructabil
ity
No outstanding issue Because arrangement of
piers at the intersection
between Line 1 and Line 2
at National Hospital St. is
complicated, impact to road
traffic is expected.
Road section at Sebastian
Canal Station is narrow that
placement of stairs is
difficult
Because arrangement of
piers at the intersection
between Line 1 and Line 2
at National Hospital St. is
complicated, impact to road
traffic is expected.
Near Transport Centre
intersection, there is Bo Tree
in the corridor. It can be
avoided to some extent but
cutting some of its branches
may be necessary.
○ × △
Cost
Less capital expenditure as
its structures are less
complicated than other
options.
More capital expenditure- as
there are large-scale
structures such as piers at
intersection
More capital expenditure- as
there are large scale
structures such as piers at
intersection
○ △ △
Evaluation ○ × ×
Source: SKYTRAIN Study Team
Note: ○: Good/Desirable, △: Fair, ×: Less Desirable
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
112
Source: SKYTRAIN Study Team
Figure 4.2.36 Line 2 - Option 1
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
113
Source: SKYTRAIN Study Team
Figure 4.2.37 Line 2 -Option 2
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
114
Source: SKYTRAIN Study Team
Figure 4.2.38 Line2 – Option 3
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
115
4.2.7 Location of Kollupitiya Station
(1) Summary
Option 1 is selected for Kollupitiya Station because the line can easily extended to Bambalapitya
in the future.
In Option 1, Galle Road is large enough for monorail station and line extension to the south is
simpler. Though Option 2 offers better accessibility to SLR’s station, space for monorail station
is relatively smaller. Future line extension is also more difficult because the line ending is
adjacent to the sea.
In the selection of the station location, regarding the extension in the future and available space for
construction, the Option 1 is selected.
Table 4.2.13 List of Examined Options for Kollupitiya Station
Name Concept
Location On Galle Road
(Option1)
Monorail station is located on Galle Road for future extension to
Bambalapitya.
Location in front of SLR railway
station (Option2)
Monorail station is located in front of SLR’s station for convenience
to access SLR.
Source: SKYTRAIN Study Team
Source: SKYTRAIN Study Team
Figure 4.2.39 Options for Kollupitiya Station
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
116
(2) Location on Galle Road Option
The monorail station is located on Galle Road which is 200m far from Kollupitiya station of SLR.
This road section is relatively wide for construction of monorails station. The line can be easily
extended along Galle Road in case of extension.
The line curves to the east at the intersection close to the north side of the station (National
Hospital direction). If turnout is installed at this side, there will not be enough straight length.
If the station is moved to the south, distance to SLR’s station shall increase. The turnout is,
therefore, installed at the south of the station so that train can turn back using the lead track.
Since there is approximately 200m distance to the SLR railway station, it is recommended to build
a pedestrian deck in order to improve the convenience of the transit passenger transferring
between monorail line and SLR.
(3) Location in front of SLR railway station
The monorail station is located close to SLR’s Kollupitiya Station. Since the road section for the
station is not wide enough and straight length for turnout is limited, island-typed station with
single track is appropriate. However, train operation with high frequency becomes difficult.
Moreover, line extension is not easy because the west side of the station is close to the sea.
Single track platform also causes difficulty for extension. It is further required to consult with
SLR because part of the monorail station is located above the SLR line.
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
117
(4) Details of comparative study
Table 4.2.14 Comparison between Options for Kollupitiya Station
Issue Option1 Option2
Future extension
Extension to Bambalapitya is
simpler due to its location on Galle
Road
Future extension is difficult because
station is adjacent to the sea and station
platform has only single track.
○ ×
Distance to SLR station
(Passenger convenience)
Longer distance to SLR Kollupitiya
station lower passenger
convenience. Direct distance to the
SLR station is 200m. It is
recommended to build a pedestrian
deck in order to improve the
convenience of transit passengers.
Higher convenience to transit
passengers because the monorail station
is close to SLR Kollupitiya Station.
△ ○
Impact on private land
No effect on private land No effect on private land, however,
consultation with SRL is necessary as
part of the monorail station is located
above the SLR line.
○ △
Route length
Route length to station centre is
almost the same as Option 2.
However, because turnout and lead
track is required, the route is longer
by 200m
Route length to the station centre is
almost the same as Option 1.
△ ○
Cost
Longer route and bigger station
increase construction cost.
Shorter route and single track platform
decrease construction cost.
× ○
Track arrangement
Not any issues. Allocation of turnout is difficult due to
lack of straight section. Dual track
platform station is not feasible.
○ ×
Evaluation ○ △
Source: SKYTRAIN Study Team
Note: ○: Good/Desirable, △: Fair, ×: Less Desirable
Preparatory Survey for New Integrated Urban Public Transport System Introduction Project
Final Report
118
Source: SKYTRAIN Study Team
Figure 4.2.41 Option 2 for Kollupitiya Station
Source: SKYTRAIN Study Team
Figure 4.2.40 Option 1 for Kollupitiya Station