Coal Mill Performance Questionnaire Corrected

Embed Size (px)

Citation preview

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    1/15

    PLANT

    LINE

    DESIGN DATA MILL1 MILL2

    COAL MILL TYPE Ball Mill Vertical Mill

    COAL MILL DESIGN CAPACITY 15 25 tph product

    POWER CONSUMPTION DESIGN (MILL ONLY) - 24.5 kWh/t

    FUEL ANALYSIS - AS PER DESIGNCV NA 4300 kcal/kg net adb

    ASH NA 32.7 % adb

    TOTAL MOISTURE NA 20(max) % asr

    INHERENT MOISTURE NA 3 % asr

    VM NA 25.5 % adb

    S NA 0.4 % adb

    Cl NA NA % adb

    HGI NA 50

    PRODUCT RESIDUE 90 um 12 12 %

    COAL MILL MOTOR POWER INSTALLED 405 365 kW

    COAL MILL GEARBOX POWER NA NA kW

    TABLE DIAMETER - 2 m

    BALL MILL DIAMETER 3 - m

    BALL MILL DRYING CHAMBER LENGTH 2.8 - m

    BALL MILL GRINDING CHAMBER LENGTH 4.4 - m

    SEPARATOR SUPPLIER FLS/L&T LNVT

    SEPARATOR TYPE Static LVT type

    MILL FILTER AREA TOTAL 340.34 1000 m2

    MILL FILTER AREA ACTIVE (OFFLINE CLEANING) - - m2

    MILL FAN DESIGN VOLUME 24600 84000 m3/hr

    Kiln coal dosing system capacity 14 tph

    Calciner coal dosing system capacity 20 tph

    Note:

    adb - air dried basis

    asr - as received

    ARASMETA CEMENT PLANT, INDIA

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    2/15

    PLANT

    LINE

    CURRENT OPERATION

    RAW MEAL

    Chloride %

    KFUI

    CLINKER CHEMISTRY

    S = SO3 %

    Na2O %

    K2O %

    Chloride %

    COAL MILL PERFORMANCE MILL 1 MILL 2

    PRODUCTION 15 27 tph product Actual for

    PRODUCT RESIDUE 90 UM 15.8 25.26 %

    PRODUCT RESIDUE 200 UM 1.92 2.5 %

    MILL POWER ABSORBED 371 276 kW

    POWER CONSUMPTION 36.0 26.0 kWh/t

    PRODUCT MOISTURE 1.85 1.14 %

    FUEL 1 PROPORTION 100 100 % total CV inputFUEL 2 PROPORTION 0 0 % total CV input

    FUEL ANALYSIS - CURRENT FUEL 1 FUEL 2

    CV 4888 4568 kcal/kg net adb

    ASH 30.36 34.06 % adb

    TOTAL MOISTURE - - % asr

    INHERENT MOISTURE 1.85 1.14 % asr

    VM 26.16 24.77 % adb

    S 0.3 0.3 % adb

    Cl 0.015 0.015 % adb

    HGI 68 69

    ALTERNATIVE FUEL NOT THRU MILLS % cv replacement

    KILN FEEDRATE VARIATION % tphCOAL FEED RATE VARIATIONS KILN % tph

    COAL FEED RATE VARIATIONS PC % tph

    BURNER MOMENTUM Nh/GJ

    AXIAL ALIGNMENT OF BURNER

    GAS ANALYSIS RELIABILTY

    GAS ANALYSIS KILN INLET %

    GAS ANALYSIS PC OUTLET %

    GAS ANALYSIS P/H OUTLET %SPLASH BOXES INSTALLED

    MEAL CURTAIN INSTALLED

    BLASTERS ON RISER AND HEARTH

    SILICON CARBIDE ON RISER AND HEARTH

    Yes

    -

    Yes

    No

    3.8

    20 mm down & 20mm

    towards feed

    70 to 80

    95 to 98

    95 to 98

    -

    3.0

    1.5 -1.6

    0.020 - 0.025

    +/- 10

    +/- 6

    ARASMETA CEMENT PLANT, INDIA

    0.012-0.02

    3 to 4

    0.6 - 0.8

    0.25 - 0.3

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    3/15

    002

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    4/15

    COAL MILL EXPLOSION PROTECTION& FIRE SUPPRESSION

    1 PREHEATER EXIT

    Preheater gas analys is

    Preheater exit gas analyser installed (y/n)

    O2 measured (y/n)

    CO measured (y/n)

    Service factor of analyser >95% (y/n)

    2 COAL MILL

    Coal mill design pressure

    DCS system installed if not what type of control system

    Using hot gas from cooler,pre-heater or hot gas generator

    coal mi l l temperature moni tor ing

    coal mill exit thermocouple installed (y/n)

    Normal operating exit temperature

    Alarms configured for exit temperature

    First alarm level for coal mill exit temperature

    Second alarm level for coal mill exit temperature inlet thermocouples installed (y/n)

    Normal operating Inlet Temperature

    Alarms configured for inlet temperature

    First alarm level for mill inlet temperature Second alarm level for coal mill inlet temperature

    Temperature controlled by Recirculation damper (y/n)

    Automated shutdown for high high coal mill exit temperature (y/n)

    OXYGEN LEVEL at filter (%)

    Tramp metal detection installed

    Coal mil l explosio n rel ief

    Explosion relief installed on coal mill (y/n)

    Venting direction inside or outside building ?

    Position (e.g. on coal mill body in inlet or exit duct etc)

    Type of protection explosion flap, rupture panel

    Area of explosion flap, panel (m2)

    ANSWERS TO THIS QUESTIONNAIRE SHOULD BE ACCURATEAND SPECIFIC please add any comments you might feel of help atthe end of the questionnaire. If there is an area where the answer isnot know please state not known. Note cells are auto formated yes =green no = red

    Completion target date 10th October 2003

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    5/15

    Lifting/ breaking pressure of flap , panel

    Manufacturer of explosion relief

    Extra Venting fitted on duct from coal mill to filter (y/n)

    Venting direction inside or outside building ?

    3 COAL MILL BAG FILTER

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    6/15

    Bag filter design pressure

    Bag fi l ter temperature mon itor ing

    Inlet thermocouple fitted (y/n)

    Outlet thermocouple fitted (y/n)

    Differential temperature monitored and displayed (y/n)

    Position of probes (e.g. in filter or ducts)

    Typical differential temperature

    First alarm level of differential temperature

    Second alarm level of differential temperature

    Does second alarm trigger automatic shutdown (y/n)

    Temperature measured in bag filter bottom (y/n)

    Material discharge temperature of bag filter measured (y/n)

    Bag f i l ter Gas mo ni tor ing

    Bag filter gas exit analyser installed (y/n)Position inside filter or in exit duct

    CO measured (y/n)

    O2 measured (y/n)

    Normal operating level of CO ppm

    Normal operating level of O2 %

    First alarm level (O2 %)

    Second alarm level (O2%)

    First alarm level (CO ppm)

    Second alarm level (CO ppm)

    Do the second alarms for CO or O2 trigger an automatic shutdown

    Bag fi l ter level devices

    Any level devices installed in bag filter (y/n)position of level devices

    Any blockage devices fitted to filter discharge (y/n)

    Bag fi l ter isolat ion

    Fast acting isolation dampers installed outlet and inlet of filter (y/n)

    Bag f i l ter Explos ion pro tect ion

    Explosion relief installed on bag filter (y/n)

    Type of protection (self closing doors rupture panels etc)

    Area of explosion doors, panels (m2)Lifting/ breaking pressure of flap , panel

    Number of explosion doors panels etcPosition of doors panels (side venting etc)

    4 PULVERIZED FUEL STORAGE

    Fuel storage design pressure

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    7/15

    Pulverized fuel Storage si lo gas monitor ing

    Number of storage silos

    Capacity of silos /s (t)

    CO analyser installed on individual silo/s (y/n)

    Pulverized fuel Storage si lo temperature mon itor ing

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    8/15

    Thermocouples installed in silo/s (y/n)

    Number of measuring points

    Position of points ( silo bottom, body, top etc)

    First alarm level

    Second alarm levelAny other temperature monitoring devices installed (describe)

    pulv erized fuel storage si lo/s explo sion p rotect ion

    Explosion relief installed on silos (y/n)

    Type of protection (self closing doors rupture panels etc)

    Number of explosion doors panels etc

    Area of explosion flap, panel (m2)

    Lifting/ breaking pressure of flap , panel5 RAW COAL STORAGE HOPPER IF INSTALLED (PRIOR TO MILL)

    Fire suppression system installed (y/n)

    Temperature monitoring for hopper

    Explosion vents installed (y/n)CO monitoring installed (y/n)

    6 OPERATOR TRAINING

    Have operators had training on fire suppression techniques

    7 DOCUMENTATION

    Is there a written procedure in case of fire or suspected fire on the coal mill system

    Are there any written procedures covering general house keeping in coal grinding area

    Any formal training attend (with suppliers Atc etc)

    8 SYSTEM GENERAL

    Is there a cleaning schedule for the coal plant area (y/n)

    Have earthing straps been installed and tested on all conveying pipes (y/n)

    Is there any horizontal ducting in the system

    9 FIRE SUPPRESSION SYSTEM

    Date installed

    Manufacturer

    Type of suppression used

    CO2 (gas)

    CO2 (liquid & gas)

    N2

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    9/15

    Storage capacity

    Storage in bulk or bottles

    Refill delivery time from time of order (hrs)

    Deliver capacity (M3/hr)

    Available discharge areas (coal mill, filter, silos others etc)

    Any alternative or secondary system used

    Automatic raw meal blanket system installed

    Any explosion suppression system fitted ( dry powder or other)

    What areas have explosion the suppression system installed

    10

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    10/15

    COAL MILL EXPLOSION PROTECTION& FIRE SUPPRESSION

    1 PREHEATER EXIT

    Preheater gas analys is

    Preheater exit gas analyser installed (y/n)

    O2 measured (y/n)

    CO measured (y/n)

    Service factor of analyser >95% (y/n)

    2 COAL MILL

    Coal mill design pressure (bar)

    DCS system installed if not what type of control system

    Using hot gas from cooler,pre-heater or hot gas generator

    coal mi l l temperature moni tor ing

    coal mill exit thermocouple installed (y/n)

    Normal operating exit temperature

    Alarms configured for exit temperature

    First alarm level for coal mill exit temperature Second alarm level for coal mill exit temperature

    inlet thermocouples installed (y/n)Normal operating Inlet Temperature

    Alarms configured for inlet temperature

    First alarm level for mill inlet temperature Second alarm level for coal mill exit temperature

    Temperature controlled by Recirculation damper (y/n)

    Automated shutdown for high high coal mill exit temperature (y/n)

    OXYGEN LEVEL at filter (%)

    Tramp metal detection installed

    Coal mil l explosio n rel ief

    Explosion relief installed on coal mill (y/n)

    Venting direction inside or outside building ?

    Position (e.g. on coal mill body in inlet or exit duct etc)

    Type of protection explosion flap, rupture panel

    Area of explosion flap, panel (m2)

    Lifting/ breaking pressure of flap , panel

    ANSWERS TO THIS QUESTIONNAIRE SHOULD BE ACCURATEAND SPECIFIC please add any comments you might feel of help at theend of the questionnaire. If there is an area where the answer is notknow please state not known. Note cel ls are auto fo rmatedyes = green no = red.

    Completion target date 10th October 2003

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    11/15

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    12/15

    Bag filter design pressure

    Bag fi l ter temperature mon itor ing

    Inlet thermocouple fitted (y/n)

    Outlet thermocouple fitted (y/n)

    Differential temperature monitored and displayed (y/n)

    Position of probes (e.g. in filter or ducts)

    Typical differential temperature

    First alarm level of differential temperature

    Second alarm level of differential temperature

    Does second alarm trigger automatic shutdown (y/n)

    Temperature measured in bag filter bottom (y/n)

    Material discharge temperature of bag filter measured (y/n)

    Bag f i l ter Gas mo ni tor ing

    Bag filter gas exit analyser installed (y/n)Position inside filter or in exit duct

    CO measured (y/n)

    O2 measured (y/n)

    Normal operating level of CO ppm

    Normal operating level of O2 %

    First alarm level (O2 %)

    Second alarm level (O2%)

    First alarm level (CO ppm)

    Second alarm level (CO ppm)

    Do the second alarms for CO or O2 trigger an automatic shutdown

    Bag fi l ter level devices

    Any level devices installed in bag filter (y/n)position of level devices

    Any blockage devices fitted to filter discharge (y/n)

    Bag fi l ter isolat ion

    Fast acting isolation dampers installed outlet and inlet of filter (y/n)

    Bag f i l ter Explos ion pro tect ion

    Explosion relief installed on bag filter (y/n)

    Type of protection (self closing doors rupture panels etc)

    Area of explosion doors, panels (m2)Lifting/ breaking pressure of flap , panel

    Number of explosion doors panels etcPosition of doors panels (side venting etc)

    4 PULVERIZED FUEL STORAGE

    Fuel storage design pressure

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    13/15

    Pulverized fuel Storage si lo gas monitor ing

    Number of storage silos

    Capacity of silos /s (t)

    CO analyser installed on individual silo/s (y/n)

    Pulverized fuel Storage si lo temperature mon itor ing

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    14/15

    Thermocouples installed in silo/s (y/n)

    Number of measuring points

    Position of points ( silo bottom, body, top etc)

    First alarm level

    Second alarm levelAny other temperature monitoring devices installed (describe)

    pulv erized fuel storage si lo/s explo sion p rotect ion

    Explosion relief installed on silos (y/n)

    Type of protection (self closing doors rupture panels etc)

    Number of explosion doors panels etc

    Area of explosion flap, panel (m2)

    Lifting/ breaking pressure of flap , panel5 RAW COAL STORAGE HOPPER IF INSTALLED (PRIOR TO MILL)

    Fire suppression system installed (y/n)

    Temperature monitoring for hopper

    Explosion vents installed (y/n)CO monitoring installed (y/n)

    6 OPERATOR TRAINING

    Have operators had training on fire suppression techniques

    7 DOCUMENTATION

    Is there a written procedure in case of fire or suspected fire on the coal mill system

    Are there any written procedures covering general house keeping in coal grinding area

    Any formal training attend (with suppliers Atc etc)

    8 SYSTEM GENERAL

    Is there a cleaning schedule for the coal plant area (y/n)

    Have earthing straps been installed and tested on all conveying pipes (y/n)

    Is there any horizontal ducting in the system

    9 FIRE SUPPRESSION SYSTEM

    Date installed

    Manufacturer

    Type of suppression used

    CO2 (gas)

    CO2 (liquid & gas)

    N2

  • 8/12/2019 Coal Mill Performance Questionnaire Corrected

    15/15

    Storage capacity kg

    Storage in bulk or bottles

    Refill delivery time from time of order (hrs)

    Deliver capacity (M3/hr)Available discharge areas (coal mill, filter, silos others etc)

    Any alternative or secondary system used

    Automatic raw meal blanket system installed

    Any explosion suppression system fitted ( dry powder or other)

    What areas have explosion the suppression system installed

    10