Concepts and Principles (2)

Embed Size (px)

Citation preview

  • 7/31/2019 Concepts and Principles (2)

    1/38

    Concepts and Principles of Distribution LossReduction

    T Raghunatha

    Joint Director

    Central Power Research Institute

    Bangalore

    Best practices in Distribution loss reduction

  • 7/31/2019 Concepts and Principles (2)

    2/38

    Installed

    Capacity=182689 MW

    T&D Losses:25.47 A &TC Losses: 28.44%

    Peak Shortage: 12.7%Per Capita Consumption : 733.54units

    IndianPower SceneIndian Power Scenario

  • 7/31/2019 Concepts and Principles (2)

    3/38

    Frequency fluctuations 2 HzVoltage fluctuations 10% - 40%

    Statistical non-availability About 200-800 hours per

    year

    Technical transmission

    and distribution losses

    Estimated 30% from 220

    kV to 220V

    Commercial losses >20%

    From a technical point of view the story was not different as

    reflected in the Grid performance.

    IndianPower SceneIndian Power Scenario

  • 7/31/2019 Concepts and Principles (2)

    4/38

    PERCENTAGE TRANSFORMATION, T&D

    TECHNICAL LOSSES IN DEVELOPING COUNTRIES

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    R

    EP.OFKOREA

    CHINA

    BARBADOS

    BELIZE

    THAILAND

    TUNISIA

    EL-SALVADOR

    FR

    ENCHGUIANA

    BRAZIL

    ZIMBABWE

    GUATEMALA

    PHILIPINES

    SRILANKA

    INDIA@

    PAKISTAN

    NICARAGUA

    HONDURAS

    MYANMAR

    %

    ... Where does India stand globally

  • 7/31/2019 Concepts and Principles (2)

    5/38

    Loss Scenario in India

    Sl No SystemSegment

    Existing% Level

    Target%Level

    Tolerable% Level

    1 Trs. System 4.5 2.00 3

    2 Sub Trs.System

    4.0 2.25 3

    3 Primary (HV)

    Distn

    7.0 3.00 5

    4 Secon (LV)

    Distn

    7.5 1.00 4

    5 Total 23% 8.25 15

  • 7/31/2019 Concepts and Principles (2)

    6/38

    ACS v/s ARRIndian

    Power Scene

    ACS ARR

    2001-02 246 181

    2002-03 238 195

    2003-04 239 203

    2004-05 254 209

    2005-06 258 221

    2006-07 276 227

  • 7/31/2019 Concepts and Principles (2)

    7/38

    All India T&D and AT&C Losses

    T&D Losses

    AT&C

    Losses

    2002-03 32.54 32.54

    2003-04 32.53 34.78

    2004-05 31.25 34.33

    2005-06 30.42 33.02

    2006-07 28.65 30.59

    2007-08 27.2 29.24

    2008-09 25.47 28.44

  • 7/31/2019 Concepts and Principles (2)

    8/38

    T&D and Revenue Loss

    The total of Technical and Commercial losses are

    called Distribution losses

    In addition to the above, revenue loss occurs on

    account of non realization of billed demand

  • 7/31/2019 Concepts and Principles (2)

    9/38

    Technical Losses

    Every element in a power systema linea transformer etc

    consume some energy while performing their expected duty.

    Cumulative energy consumed by all these elements

    constitute technical losses.

  • 7/31/2019 Concepts and Principles (2)

    10/38

    AT&C Losses

    Example:

    Units Input 100 MU Units sold 70 MU

    Losses 30 MU

    T&D Loss 30%

    If Revenue collections are

    90% of demand.

    Out of 70 MU of sales revenue

    is realized for 63 MU.

    AT & C losses are 37%.

    AT & C is abbreviation for Aggregate Technical& Commercial Loss

  • 7/31/2019 Concepts and Principles (2)

    11/3815

    LOSSES DEPENDS IN ANY SYSTEM ON

    Pattern of Energy Used

    Intensity of Load Demand

    Load Density

    Capability and configurations of T & D system

  • 7/31/2019 Concepts and Principles (2)

    12/3817

    State-wise T&D Loss (%)

  • 7/31/2019 Concepts and Principles (2)

    13/38

    19

    AT & C Loss

    Loss in Revenue due to Non Realization of Billed Demand

    Input EnergyEnergy Realized x 100Input Energy

    or

    1Billing Efficiency x Collection Efficiency

    Energy Realized = Units Billed x Collection Efficiency

    Technical Loss + Commercial Loss + Revenue Loss due to Non

    Realization of total Billed Demand

    Ex: Units Input = 100MU Units Input = 100MU

    Units (Output) Sold = 70 MU Units Realized = 63 MU,

    (90% of 70 MU)T & D Loss = 30 MU AT & C Loss = 37 MU

  • 7/31/2019 Concepts and Principles (2)

    14/38

    Causes for Technical Losses

    Wrong location of DTCs

    DTCs are not located centrally and farthest consumersface low voltages

    For every 10% voltage drop losses increase by 21% andfor every 20% voltage drop losses increase by 44%

    DTCs to be relocated at load center to minimise losses

  • 7/31/2019 Concepts and Principles (2)

    15/38

    Causes for Technical Losses

    Over rated DTCs

    Under loaded DTCs are a source for high avoidable

    Iron losses

    Taking village as a unit the loads can be readjusted

    among all DTCs in the village for optimal use of

    installed capacity

  • 7/31/2019 Concepts and Principles (2)

    16/38

    Causes for Technical Losses

    Low voltage pockets

    Where as the permissible LT voltage variations are +/-

    6% the voltages at some points go below 10% and in some

    cases even more

    Full load current drawn by motors go up by 15% for

    every 10% drop in voltage

    On load tap changers are not made use of due to certaininhibitions

  • 7/31/2019 Concepts and Principles (2)

    17/38

    Causes for Technical Losses

    Low power factor In majority of Distribution circuits the pf is between 0.65

    & 0.75

    Low pf contributes to high distribution losses

    When shunt capacitors of adequate rating are fixed atload end, experiments showed

    10% Improvement in voltage

    20% reduction in current

    6% overall reduction in energy

  • 7/31/2019 Concepts and Principles (2)

    18/38

    Causes for Technical Losses

    Bad workmanship

    Bad joints are a source of power loss

    Proper jointing techniques should be adopted for firm

    connection

    Connections at line jumpers, transformer bushingrods, drop-out fuses, isolators, LT switch etc shall beperiodically inspected.

    Timely replacement of deteriorated wires, worn outclamps etc

  • 7/31/2019 Concepts and Principles (2)

    19/38

    Inadequate conductor size.

    Main consideration for selection of conductor is voltagedrop

    Approved voltage regulation in distribution lines is +/-8% for 11kV and +/-6 % for LT .

    Current carrying capacity at ambient temperatures is also

    a consideration. Voltage regulation is

    (ES-ER)/ ER

    ES - Sending end voltage

    ER - Receiving end voltage

  • 7/31/2019 Concepts and Principles (2)

    20/38

    Standards for 11kV Lines

    Length of 11kV line corresponding to different loads

    Size of

    conductor

    kVA-km for

    8% voltage

    drop at 0.8pf

    Max of

    length of

    line (km)

    Load that

    can be

    connected

    (kW)

    Rabbit 10,650 30 355

    Weasel 7,200 20 360

    Squirrel 5,120 15 341

    The figures are for a conductor temperature of 600C. For a conductor

    Temperature of 500C, the above figures shall be about 3% higher and for a

    temperature of 700

    C about 3% lower.

  • 7/31/2019 Concepts and Principles (2)

    21/38

    Standards for LT Lines

    Length of 415V line corresponding to different loads

    Size of

    conductor

    kVA-km for 6%

    voltage drop at

    0.8pf

    Max of length

    of line (km)

    Load that

    can be

    connected

    (kW)

    Rabbit 11.76 1.6 7.35

    Weasel 7.86 1.0 4.86

    The figures are for a conductor temperature of 600C. For a conductor

    Temperature of 500C, the above figures shall be about 3% higher and for a

    temperature of 700C about 3% lower.

  • 7/31/2019 Concepts and Principles (2)

    22/38

    44

    Way to reduce Technical Losses

    By proper planning of system configuration by using

    Computer Analysis, LT Lines (Radialy laid) can be

    reduced & HT can be increased

    Running Express Lines for bifurcation & load sharing

    Adding Additional DTCs to Network based on load

    growth & locating them near load centers

    Judicious selection of DT matching with Maximum

    KVA Demand @ good pf

  • 7/31/2019 Concepts and Principles (2)

    23/38

    45

    Use of On load Tap Changers in Power Transformer atHigh Voltage 66/11Kv substation

    To compensate for the voltage drop at transformer

    terminal resulting in poor regulation

    Providing switched capacitors & Automatic

    voltage regulators on 11 Kv feeders

    Use of Off load Tap Changers in DTCs to

    compensate Voltage drop due to Agriculturalpump sets, which may draw more current and

    hence double line losses

    Way to reduce Technical Losses

  • 7/31/2019 Concepts and Principles (2)

    24/38

    i) 11 kV Lines

    PF KVA Current Line Losses

    Kw

    Before 0.7 428 38.9 27.2

    After 1.0 300 27.2 13.4

    46

    Improving PF by Series and Shunt Capacitors installed at33/11 kV Secondary Side of Power Transformer

    ii) LT Lines

    Optimum Rating of Capacitor Bank = 2/3rd of KVAR requirement of that

    distribution Network

    Optimum Location: 2/3rd Length of Main Distributor from transformer

    end

    Way to reduce Technical Losses

  • 7/31/2019 Concepts and Principles (2)

    25/38

    47

    1) Use of Best Possible Workmanship

    2) Use of Minimum joints and proper techniques like PG

    Clamps and Wedge Clamps

    3) Avoiding Loose connections to Transformer bushing

    stem, Dropout Fuse, Isolator, LT Fuse Kit to preventsparking and heating of contacts

    4) Periodical inspection of all joints/connections

    5) Replacement of deteriorated wires/services/Materials

    timely to avoid any cause of Leaking and Loss of Power

    6) Adhering to O & m Schedule for all equipments /

    Switchgears

    7) Outsourcing and franchising of feeders/Substations

    Way to reduce Technical Losses

  • 7/31/2019 Concepts and Principles (2)

    26/38

    System Planning to reduce Technical losses

    Develop SLD for all 11kV Feeders

    Collect feeder loadings Calculate the Technical losses for all feeders

    Categorize the feeders on their loading and loss levels

    Suggest the improvement required for each feeder

    Prioritize the feeders based on the benefit to cost ratio To start with pick high loss/heavily loaded feeders and

    execute improvement work on them

    Have an improvement investment plan for at least 3 to 5

    years up front and cover all feeders.

  • 7/31/2019 Concepts and Principles (2)

    27/38

    Comparison of 11kV & LT line Losses

    Contrary to popular belief, HT line losses in rural 11kVfeeders are often higher than LT line losses.

    Currents stepped up by a factor of 25 in a 11000/433Vtransformer, does not necessarily imply larger LT losses.

    Losses depends on how many DTCs exist and how many

    LT feeders are taken out directly from the secondary ofthe transformer.

    Let us assume there are n number of DTCs ,

    An average two feeders directly come out of thesecondary of the Transformers.

    Let I be the 11kV line current.For simplicity

    assume that the loads are the same and branch out equally,then the branch currents on the LTs are 25I/2n

  • 7/31/2019 Concepts and Principles (2)

    28/38

    Comparison of 11kV & LT line Losses

    The primary and secondary conductors are of the samecross-section and the LT to HT ratio 4:1,

    HT and LT line losses are equal, when

    [I x 25/2n]2 x 4R = I2R,

    Then, n=25

    This indicates that the LT and 11kV line losses will beapproximately same when the number of TCs is 25

    With 2 LT Circuits on DTC Secondary, for n>25, LTlosses would be less than HT losses.

  • 7/31/2019 Concepts and Principles (2)

    29/38

    If the secondary current flows only in one LT feeder fromeach DTC, the equation will be modified into[I x 25/n]2 x 4R = I2R, where n=50

    And for n>50, the LT losses would be less than HT losses.

    In Rural 11kV feeders,Inmost cases two or more LT feeders branch out of thesecondary of the transformer.

    Rural feeders often have more than 50 TCs,

    Hence in majority of rural feeders LT line losses arelikely to be less than HT losses.

    In Urban feeders, however, the number of TCs aresignificantly less and the reverse would be true.

    Comparison of 11kV & LT line Losses

  • 7/31/2019 Concepts and Principles (2)

    30/38

    Commercial Losses.

    Occur on Account of

    Non performing meters

    Under performing meters

    Meters not read

    Application of lower multiplication factors

    Defects in CT/PT circuitry

    Pilferage by manipulation

    Theft by direct tapping etc.

    W t R d C i l L

  • 7/31/2019 Concepts and Principles (2)

    31/38

    Way to Reduce Commercial Losses.

    DTC wise energy audit

    Use quality meters

    Strengthen Vigilance squad

    Proper consumer indexing

    Computerized billing

  • 7/31/2019 Concepts and Principles (2)

    32/38

    54

    1) Accurate Metering

    2) Use of appropriate range of meter w.r.t connected load

    3) ETV meters with TOD, tamper proof data and Remote

    reading facility for HT and High valued services

    4) Energy Meters housed on a separate Box sealed and

    inaccessible to consumer

    5) Multicore PVC Cable used for Service Mains

    6) Providing potentials link inside body of Energy Meterrather than inside thermal cover

    Way to Reduce Commercial Losses.

    d l

  • 7/31/2019 Concepts and Principles (2)

    33/38

    55

    1) Integrated of MBC software along with CAT & MAT

    softwares to improve collection efficiency and easy

    implementation of A. T. Law

    2) Eradication of theft by implementation of ATL and

    constant intensive inspection by vigilance squad

    3) Implementation of IT measures as BEST PRACTICES

    adopted by DISCOMs

    4) Outsourcing & Franchising of Meter, Billing and

    collection and Energy Auditing and Accounting

    Way to Reduce Commercial Losses.

  • 7/31/2019 Concepts and Principles (2)

    34/38

    Anti Power Theft Initiatives

    56

    Vigilance Activity has been intensified to reducecommercial losses

    11 Police Stations are functioning

    Special Courts at District Headquarters have been set upexclusively for speedy disposal of Electricity related cases

    Apart from Vigilance Inspections by O & M staff havebeen intensified

    Periodical and surprise inspections are being carried out

    Meter Testing Division and Vigilance wing

  • 7/31/2019 Concepts and Principles (2)

    35/38

    MILESTONES ACHIEVED

    57

    ESCOMs has achieved the following milestones during the last two yearsMilestones:

    Any Time Payment Kiosk

    Transformer Information Management System

    Business Plan (07 -10)

    Training to ESCOM Personal

    Real Time Remote Automatic Meter Reading (RRAMR) Rural Load Management System

    DTC wise Energy Audit

    Modernization of Central Complaint system

    Energy Saving Initiatives ( Demand Side Management)

    Insurance Cover

    Customer Interaction Meets

    Grama Vidyuth Pratinidhi

    Prepaid Metering on Experimental basis

  • 7/31/2019 Concepts and Principles (2)

    36/38

    Conclusions

    58

    Reduction in AT & C loss calls for

    DTC wise Energy Audit

    System Improvement works

    LT Reconductoring works Rural Load management System

    Introducing HVDS System of distributions

    APDRP Works

    Rating and Calibration of installations on a regular basis

    Reducing the overloaded conditions of existing DTCs byestablishing new DTCs at Load centers

    C l i

  • 7/31/2019 Concepts and Principles (2)

    37/38

    59

    Bringing in fresh investments both long term capitaland working capital

    Reduction of political interference in day to dayworking

    Bringing effective regulatory Mechanisms

    Bringing Competition both at generation anddistribution levels

    Strict enactment of Antitheft Law in accordance withElectricity act 2003

    IT initiatives in Power Sector

    Professional Management and change in work culturein Power Sector

    Conclusions

  • 7/31/2019 Concepts and Principles (2)

    38/38

    THANK YOU