1. Contracts for Labour2. Contracts for Mechanical work3. Contracts for Civil work4. Contracts for Electrical work5. Contracts for Transport & employee services6. Contracts for Scrap Sale (Accounts Receivable)

Page 3: Contractor Evaluation[1]

CONTRACTORS FOR LABOURName AREA Cost Per month (Rs.) Approx Manpower Vehicles

Raghbir Singh & Company Power plant 1033273 75 13

Virsa Singh Raw material feeding 523773 20 4

Sunita Devi Finishing & Packing 420481 80

Chunchun Devi Truck loading, stiching, marking 41960070

White Fox Support Services Pvt. Ltd. Security service 41020730

Harkeval Singh Housekeeping, unloading & feeding soap stone 352234

35 1

Dharam Singh Copier packing, finishing house 25152030

Akbar Ali Depither work-Gangapur (Bagasse Material) 210579

12 7

Harjinder Singh Broke handling pm3, loader 205298 22 1

Jagtar Singh Broke handling pm4 166911 40

Madhya Uttar Pradesh Suraksha Guard Broke handling pm1 & 2 166401

32

Gurmukh Singh Pith shifting 157684 10 5

Mohd.Hanif Elephanta & lantanta grass cutting 12508910

Karan Singh Lime feeding 101539 8

Page 4: Contractor Evaluation[1]

CONTRACTORS FOR LABOUR

Chanderpal Singh Jhandu cutter 89699 12

Sundeep kumar Tractor trolley for recovery(sludge) 80486

8 4

Baldev Singh Loader in Yard 80349 4 2

Dilshad Hussain Loader in Yard 58000 1

Jagdev Singh Loader in Yard 58000 1

Malkit Singh Loader in Yard 55791 2 1

Davinder Singh Loader in Yard 51818 2 1

Nirmal Singh Loader in Yard 50390 2 1

Veer Singh Unloading lime, caustic, cement 4710515

Sikatar Singh Tractor trolley for screen reject 25000 1

Sarvottam Express Courier service (Kashipur to Delhi) 19671

Blazeflash courier Courier service-others 882

5161781 519 43

Name AREA Cost Per month (Rs.) Approx Manpower Vehicles

Page 5: Contractor Evaluation[1]

Note – Cost per month does not include the taxes

CONTRACTORS FOR LABOUR

Page 6: Contractor Evaluation[1]

CONTRACTORS FOR MECH WORK

Sr. Name Name

Total Amount ( Rs.) Against Submitted Bills( Apr to Dec)

1 Ahmad Hassan Contractor 2290966

2 Shiv shakti Enterprises 800822

3 MA Enterprise 658763

4 Om Sai Engineering & Fabricators 586321

5 Devender Kumar 397179

6 V.K.Enterprises 385392

7 Shareef Ahmed 297762

8 Vinayak Furniture 116791

9 Rudra Instuments 112316

10 G.S Driller 109344

11 Hamid Contractor 101430

12 Ras System 49000

13 Power Tech Engineers 41665

14 Kumar Pal 24786

15 Mahaveer Sanitary Store 24255

16 GulachiEngineers 11236

17 Sabir Hussain 10720

12015540

Page 7: Contractor Evaluation[1]

CONTRACTORS FOR MECH WORK

Note – Cost per month does not include the taxes

Page 8: Contractor Evaluation[1]

CONTRACTORS FOR CIVIL WORK

Sr. No. Name

Total Amount ( Rs.) Against Submitted Bills( Apr to Dec)

1 MH Construction Group 8704981

2 Om Prakash Associates 6167131

3 Hi Tech Cons. 4541688

4 Shri Pawan Kumar Verma 3611810

5 M.T.P Builders 3055114

6 Shilpa Associates Pvt. Ltd. 2089329

7 Sharp Construction Co. 439096

8 Deepesh Agarwal 363262

9 Target Engineering Works 72554

29044965

Page 9: Contractor Evaluation[1]

CONTRACTORS FOR CIVIL WORK

Note – Cost per month does not include the taxes

Page 10: Contractor Evaluation[1]

CONTRACTORS FOR ELECTRICAL WORK

Sr. No. Name Total Amount ( Rs.) Against Submitted Bills( Apr to Dec)

1 Supertech Service 81591

2 AbdulSalam 123397

3 Supreme Engineers 12348

217336

Page 11: Contractor Evaluation[1]

CONTRACTORS FOR EMPLOYEE SERVICES

Sr. No. Name Particular Cost Per month (Rs.)

1 Pavinder Singh Bus Service 55250

2 Inderjeet Singh Bus Service 55250

3Parmatma Canteen Service 45397

4Mahipal Singh Guest House 12500

5

Arti Badhwar & Anand Gopal Badhwar Guest House for GETs

10000

178397

Page 12: Contractor Evaluation[1]

ACTION ITEMS

1. In few contracts the area of work is not clearly mentioned.2. It has been observed that Raghbir Singh & Company is using only 1 no. JCB & 12 nos.

loader/ pusher/ trolley ,but, as per contract 2 nos. JCB & 11 nos. loader/ pusher/ trolley (Rs. 6 + 2 lakhs) are to be used. The party is raising the bill for the full amount. Since the power plant is managed with the existing only 1 no. JCB & 12 nos. loader/ pusher/ trolley so expected reduction of cost would be to the tune of Rs 1.75 lakhs/ month. It is also suggested to cross check the previous bills.

3. Presently it is observed that the attendance record is maintained at Time Office, based on that contractor’s bills are verified for labour rate work. It is suggested that the concerned user may maintain a separate register to have the over all attendance and accordingly deploy the manpower optimally.

4. Presently Gurmukh Singh provides 5 nos. tractor trolley for pith shifting, out of which 1 no. is kept as stand by. This stand by vehicle is redundant as in case of urgency one tractor trolley owned by SSPBML may be used. Presently SSPBML has 3 nos. tractor trolley used for material shifting.

5. Total 9 nos. Loaders are being used at Yard, out of which 2 nos. are owned by SSPBML & 7 nos. are provided by seven different contractors. It is suggested that if we can utilize the services of only one/two different contractors for 7 nos. loaders, then, we may get some rate discount based on the volume.

Page 13: Contractor Evaluation[1]

ACTION ITEMS

6. The condition of Tractor Trolley for screen rejects operating in Pulp Mill is not good.7. The contract of Virsa Singh is based on minimum pulp production of 3000 MT, In case

it goes below 3000MT the contract rate is to decided .8. For re-packing, re-stitching types of jobs HODs shall validate the party’s bill based on

which payment can be made.9. For any contract finalization the following guidelines may be considered - Up to Rs.10,000 /- (Single quotation) -Up to Rs.10,000 to 50,000/-( Min. two quotations) - Above 50,000/- ( Min. three quotations) Contract finalization with single party may be done with proper justification to

be mentioned in the work order. 10. Apart from contracts for labour , mechanical, civil, electrical and employee

services, contracts for scrap sales have been included which is attached in the excel sheet along with this presentation for ready reference.

Page 14: Contractor Evaluation[1]

Thank you