COST PLANNING AND

ESTIMATIONDaniel Ng

[email protected]

Page 2: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

Course outline

1. Overview of Cost Planning

2. Cost Planning Techniques

3. Approximate Estimating

4. Elemental Method

5. Cost Planning at Various Stages of Design

6. Resource Analysis

7. Cash Flow

8. Valuation

9. Final Accounts

Page 3: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

Teaching Scheme

DATE CHAPTER

11 April 2016 1. Overview of Cost Planning

13 April 2016 2. Cost Planning Techniques

3. Approximate Estimating

18 April 2016 4. Elemental Method

20 April 2016 5. Cost Planning at Various Stages of Design

25 April 2016 6. Resource Analysis

27 April 2016 7. Cash Flow

8. Valuation

3 May 2016 9. Final Accounts

7 May 2016 Exam

Page 4: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4. Elemental Method

4.1 Elemental Cost Analysis

4.2 Elemental Method

4.3 Building Economics and Cost Analysis

Page 5: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.1 Elemental Cost Analysis

Source: Elemental Standard Form of Cost Analysis Principles, Instructions, Elements and Definitions, 4th (NRM) Edition, 2012, Building Cost Information Service of RICS

Page 6: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

The forecast cost of each element can be calculated in two ways:-

• By general adjustments for each element on a similar building

• By measuring the approximate quantity of each element and applying a unit rate.

Page 7: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

Sources of cost data• In-house data • Cost database

• Cost analyses

• Project rates

• Published data • Government

• Institutions

• Journals and magazines

• Pricing books

• Market testing

Page 8: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

Affects on cost• Quantum • Economies of scale

• Availability

• Location • Regional variations

• Exchange rates

• Timing • Inflation

• Market conditions

• Quality

Page 9: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

Project A = Total cost for a bungalow at Holland Village is S$ 4 million, built in 2010 with total gross floor area of 2,000m2

How much for a project B – a bungalow at Jurong Island, to be built in 2015 with total gross floor area of 3,000m2?

Page 10: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental MethodProject A = Total cost for a bungalow at Holland Village is S$ 4 million, built in 2010 with total gross floor area of 2,000m2

How much for a project B – a bungalow at Jurong Island, to be built in 2015 with total gross floor area of 3,000m2?From BCA:

Adjust for time for construction: Cost x 2015 TPI divided by 2010 TPI

Page 11: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

Project A = Total cost for a bungalow at Holland Village is S$ 4 million, built in 2010 with total gross floor area of 2,000m2

How much for a project B – a bungalow at Jurong Island, to be built in 2015 with total gross floor area of 3,000m2?

Assuming it is 15% more expensive to construct at Jurong Island

Adjust for location for construction: Cost + 15%

Page 12: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

Project A = Total cost for a bungalow at Holland Village is S$ 4 million, built in 2010 with total gross floor area of 2,000m2

How much for a project B – a bungalow at Jurong Island, to be built in 2015 with total gross floor area of 3,000m2?

Answer

S$ 4 million / 2,000m2 x 3,000m2 x time x location

= 4,000,000 / 2,000 x 3,000 x 104/100 x 1.15

= S$ 7,176,000

Page 13: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

Elemental cost = Quantity x Unit Rate

Page 14: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.2 Elemental Method

Page 15: COST PLANNING AND ESTIMATION - Trent Global...Teaching Scheme DATE CHAPTER 11 April 2016 1. Overview of Cost Planning 13 April 2016 2. Cost Planning Techniques 3. Approximate Estimating

4.3 Building Economics and Cost Analysis

Design

economics• Assessment criteria • Site density

• Wall/floor ratio

• Floor area ratios e.g. net to gross

• Area efficiency e.g. M2 per bed

• Functional unit rate e.g. $ per

pupil

• Building height e.g. height to

eaves or storey height