52
Delivering School Construction Successfully Regardless of the Delivery Method Presented by: Doug Sitton, PE, LEED AP Sitton Construction Group

Delivering School Construction Successfully

  • Upload
    jessie

  • View
    30

  • Download
    1

Embed Size (px)

DESCRIPTION

Delivering School Construction Successfully. Regardless of the Delivery Method Presented by: Doug Sitton, PE, LEED AP Sitton Construction Group. - PowerPoint PPT Presentation

Citation preview

Page 1: Delivering School Construction Successfully

Delivering School Construction Successfully

Regardless of the Delivery Method

Presented by:

Doug Sitton, PE, LEED AP

Sitton Construction Group

Page 2: Delivering School Construction Successfully

What if you could spend less time, reduce the overall cost, and

eliminate most of the problems on your next construction project without reducing quantity or

quality?

Page 3: Delivering School Construction Successfully

Agenda

• Case Studies• Project Complexity• Bridging the Gaps• Keys to Success• Project Delivery• Additional Tips

Page 4: Delivering School Construction Successfully

Projects That Fell Short

What did the following projects all have in common that caused them to fall

short of expectations?

Page 5: Delivering School Construction Successfully

Project #1

• New High School• Design/bid/build with CM as Advisor• $45 million new construction• 20-month original schedule• 12 months late• 14% delay claims/change orders

Page 6: Delivering School Construction Successfully

Project #2

• University Student Rec Center• CM at Risk• $13 million new construction• 15-month original schedule• 12 months late

Page 7: Delivering School Construction Successfully

Project #3

• University Student Center• Design/bid/build – multiple prime• $14 million addition/renovation• 18-month original schedule• 12 months late

Page 8: Delivering School Construction Successfully

Project #4

• New College Classroom Building• Design/bid/build – multiple prime• $11 million new construction/addition• 21-month original schedule• 15 months late• 11% delay claims/change orders

Page 9: Delivering School Construction Successfully

What Was The Common Cause?

What did each of these projects have in common?

A. Under-qualified contractor(s) or CM

B. Under-qualified architect/engineer

C. Wrong delivery method

D. Unusually complex

E. Other

Page 10: Delivering School Construction Successfully

The Common Cause

What did each of these projects have in common?

The gaps that existed were not filled

Gaps are caused by complexity

Page 11: Delivering School Construction Successfully

Successful Case Study #1

• $60 million program • 2 new elementary schools• Various additions/renovations• Design/bid/build – single primes• Delivered in 16 months and under

budget

Page 12: Delivering School Construction Successfully

Successful Case Study #2

• $6 million program • Renovations to elementary and high

schools• D/B/B – single primes and PC• Saved $550,000 while adding in

quantity and quality

Page 13: Delivering School Construction Successfully

Project Complexity

Page 14: Delivering School Construction Successfully

Project Organizational Chart

Thousands of exchanges of info in different languages

• Owner• Funding sources• Design firms• Consultants • Contractors• Subcontractors• Utilities• Regulatory agencies• Manufacturers/vendors• Stakeholders

Page 15: Delivering School Construction Successfully

Design/Construction Complexity

Organizations

X

People

X

Processes

X

Technical

X

External Forces

Page 16: Delivering School Construction Successfully

Technical Complexity

• Systems:– Structural

– MEP/FP

– Security

– Data/telecommunications

– Furnishings and equipment

• Codes, soils, environmental, etc.• Project delivery• LEED• BIM

Page 17: Delivering School Construction Successfully

The Cost of Complexity

U. of I. Sues over Dorm's Big Cost Overrun

Cost Overruns at Prairie State Energy

SCHOOL BOARD TO MEET ON SCHOOL COST OVERRUNS

MetroLink Files Damage Suit Against Four Companies

Big Dig Cost Explodes To $22 Billion from Original $2.6 Billion

Page 18: Delivering School Construction Successfully

Complexity = Change Orders

Page 19: Delivering School Construction Successfully

Complexity = Change Orders

Page 20: Delivering School Construction Successfully

Gaps

Why Complexity Often Wins

Page 21: Delivering School Construction Successfully

Where Are The Gaps?

Between all project participants• Owner• Funding sources• Design firms• Consultants • Contractors• Subcontractors• Utilities• Regulatory agencies• Manufacturers/vendors• Stakeholders

Page 22: Delivering School Construction Successfully

What are the Gaps?

• Knowledge and experience• Priorities, goals and objectives• Roles, responsibilities and risk• Information and communication• Cultures and

personalities• Performance

and results

Page 23: Delivering School Construction Successfully

Bridging the Gaps

Page 24: Delivering School Construction Successfully

The Owner’s (District’s) Role

Build the bridges

Start with the 3 legs

The Owner is responsible for the

team of teams.

Page 25: Delivering School Construction Successfully

The Owner’s Role

• Financing/budget/costs• Project delivery method• Requirements/program/operations/objectives• Property/surveys/utilities/environmental/soils• Existing conditions/testing• Schedule• Permits• Furniture/Fixtures/Equipment• Voice/Data/Security• Move management• Reviews/decisions

Page 26: Delivering School Construction Successfully

The Owner’s Role

• Procurement and performance– Architect/engineer– Consultants– Contractors– Construction manager– Performance contractor

• Dispute resolution

Page 27: Delivering School Construction Successfully

The Owner’s Required Expertise

Bridge building:• Improve all contracts• Manage and improve

everyone’s performance• Facilitate collaboration and teamwork• Streamline and improve the delivery of

planning, design and construction

Page 28: Delivering School Construction Successfully

Who Wins When The Owner Has Sufficient Resources?

Everyone!

Two Options: Win-Win or Lose-Lose

Page 29: Delivering School Construction Successfully

Minimize the Owner’s Role?

• Avoid paying for expertise?

Any expertise should more than pay for itself

• Hand it off to the Architect, CM or PC?

Time, focus, qualifications, conflicts

Page 30: Delivering School Construction Successfully

Keys to Success

10 Pieces to the Successful Project Puzzle

Page 31: Delivering School Construction Successfully

10 Pieces to the Project Puzzle

1. Identify Owner’s Expertise

2. Establish Goals and Objectives

3. Maximize Competition for Selection

4. Negotiate Effective Contracts

5. Place Right People in Right Roles

6. Plan Ahead

7. Establish Effective Processes

8. Set Performance Metrics

9. Apply Cost-Effective Technology

10. Lead and Manage Proactively

Page 32: Delivering School Construction Successfully

Solve It at the Beginning

.

Page 33: Delivering School Construction Successfully

Project Delivery

Methods and Myths

Page 34: Delivering School Construction Successfully

Project Delivery Methods

• Design/Bid/Build – Single Prime• Design/Bid/Build – Multiple Prime or

CM• Construction Manager at Risk• Performance Contracting

Page 35: Delivering School Construction Successfully

Design/Bid/Build – Single Prime

• Owner contracts with a design team• Design team provides design and

produces bid/construction documents• Project is bid to single general

contractor• Low responsive, responsible bidder

selected

Page 36: Delivering School Construction Successfully

Design/Bid/Build – Multiple Prime

Same as Single Prime except:• Project is bid in multiple packages• Low responsive, responsible bidders

selected• Multiple primes “assigned” to general

contractor as coordinating contractor

Page 37: Delivering School Construction Successfully

General Contractor as CMa

Same as Multiple Prime except: • Owner contracts with a CM• CM participates in design phase• Owner is at risk and holds all contracts

– no “assignments”• Typically many more contracts

Page 38: Delivering School Construction Successfully

General Contractor as CM at Risk

Same as GC as CMa except:• GC holds the contracts and is at risk

Page 39: Delivering School Construction Successfully

Performance Contracting

• Same as Design-Build except: • For energy savings improvements• ESCO provides:

– Financing

– Guaranteed energy savings

Page 40: Delivering School Construction Successfully

Which Method . . .

Can be completed in the least amount of time?

Requires the least amount of District time to oversee?

Takes the least amount of District expertise to manage?

Has the fewest change orders?

Involves the least risk for the District?

Provides the highest overall value for the District?

Design/Bid/Build – single prime Design/Bid/Build – multiple prime or CMa Construction Manager at Risk Performance Contracting It depends

Page 41: Delivering School Construction Successfully

Which Method . . .

Can be completed in the least amount of time?

Requires the least amount of District time to oversee?

Takes the least amount of District expertise to manage?

Has the fewest change orders?

Involves the least risk for the District?

Provides the highest overall value for the District?

Design/Bid/Build – single prime Design/Bid/Build – multiple prime or CMa Construction Manager at Risk Performance Contracting It depends

Page 42: Delivering School Construction Successfully

It Depends

• Every method:– Has positives and negatives, has

succeeded and failed– Is complex, just in a different way– Can be fast-tracked– Should never be used “as is”– Should be tailored to the specific client,

project, and local/current market

• Customization and management matter most, not the method

Page 43: Delivering School Construction Successfully

Selecting Project Delivery

Consider:• Most common, best understood• Experience and knowledge of:

architect, engineers, contractors

Don’t consider:• Time – overall or District’s• Change orders• Risk

These are customization considerations

Page 44: Delivering School Construction Successfully

Additional Tips for Success

Page 45: Delivering School Construction Successfully

Minimizing Owner’s Time Invested

• Have the right level of expertise• Invest the time early• Avoid gaps

More time here

Page 46: Delivering School Construction Successfully

Pick Any Two

• The Project

Management

Triangle

• Why not have all three?• Low quality often adds cost and time• Quality design can reduce overall cost • “Too” slow and “too” fast both cost more• Effective Owner management improves all

three

Page 47: Delivering School Construction Successfully

Improving All Three – Q/B/S

“Avoidable failures are common and persistent . . . the volume and complexity of what we know has exceeded our individual ability to deliver its benefits correctly, safely, or reliably.”

“We need a new strategy . . . and there is such a strategy. It is a checklist.”

Page 48: Delivering School Construction Successfully

Getting Things Right

• Ninety-second checklist• Complex world of surgery• Eight hospitals around the

world• All kinds of operations• Reduced deaths and

complications by one-third• No cost

Page 49: Delivering School Construction Successfully

Example Checklists

• Facility appraisals • Facility assessments• Plan/spec reviews• Inter-disciplinary reviews• Scorecards

Page 50: Delivering School Construction Successfully

eTools Examples• Building Information Modeling (BIM)• eProject Management• eDeliverables

Page 51: Delivering School Construction Successfully

Summarizing Success

• Understand the complexity• Identify expertise necessary for the

District’s “Owner” role• Identify/predict the gaps• Bridge the gaps• Use checklists!

Page 52: Delivering School Construction Successfully

Equal Understanding is Key

“Armed with the most the most powerful weapon in anyone’s business arsenal

– understanding – you will have a fighting chance to get the building you want, when you want it, for the price

you originally agreed upon.”

Broken Buildings, Busted Budgets

by Barry LePatner