Design and Construction of the SH58 Flyover Bridge Over IH70

Embed Size (px)

Citation preview

  • Design and Construction of theSH58 Ramp A Flyover Bridge over IH70

  • SH58 Ramp A 1 traffic lane with two full shoulders

    Provides access to East side of Golden, CO from IH70 Spans over Clear Creek, Bike Path, IH70 and Eastbound SH58

    Connects eastbound IH70 to westbound SH58

  • Golden, Colorado

    IH70

    SH58

    DowntownGolden

    Coors Brewery

    Location ofRamp A

  • Whats so special about this Bridge?

    n Contractor Initiated VE Redesignn Built over complex site with numerous traffic crossingsn Varying Curvature along lengthn Refined details from previous projectsn Innovative substructure designn Slender Cross Section relative to spansn Aesthetically pleasing structure in high profile area

  • Ramp A Bridge Information

    19.50Girder Spacing

    38.00Deck Width

    4230 l.f.2Number of Girder Lines

    147.50 to 235.0010Number of Spans

    7 WebsU86 CDOT Girders

  • Unit 1 at West End Bridge4 Span Unit, 154, 205, 235, & 186

    Eastbound IH70 exits to Ramp ARoadway in spiral curve at Abutment 1 transitions to 809 radius curve

    +5.00% cross fall and 6.00% cross fallSpan 2 crosses bike path and Clear Creek

    Span 3 crosses Eastbound IH70Span 4 crosses Westbound IH70

  • Ramp A, Unit 23 Span Unit, 147.5, 205 & 186

    Span 6 crosses Eastbound SH58

  • Ramp A Unit 3 at East End Bridge4 Span Unit, 187, 200, 200 & 188.5

    Roadway transitions from 809 radius curve to straight bearing-5.00% cross fall and 6.00% to -2.00% cross fall transition

    Returns to grade at Abutment 11

  • Abutments at each end of bridge with expansion bearings7 Integral Fixed Piers No Bearings

    2 Interior Expansion Piers with expansion bearingsDrilled shaft foundations

    Substructure Design

  • Conventional Abutments supporting thesuperstructure on expansion bearings

  • Abutment Diaphragm Formwork

  • Abutment Diaphragm ready for post tensioningBack wall and wing walls are cast after PT is

    stressed and grouted

  • Completed Abutment 1MSE wall at approach slab

    Expansion joint built into back wall

  • 13 x 4 Column on side by side 48 CaissonsIntegral with Superstructure

    Flexible piers and foundations accommodatelongitudinal movements without bearings

    Fixed Interior Piers

  • Girders supported on falsework on either side of pierBottom section of pier cap supports concrete of upper cap

    Erection at Fixed Piers

  • 5-0 x 12-6 composite cap w/ 2 rows of 4 1 3/8 PT bars3-4 lower section of cap supports 8-9 upper section during casting

    Composite cap shown supports Dead Load of BridgeFull Section w/ top mat of deck reinforcing supports SDL & traffic loads

    Interior Pier Cap Reinforcing

  • Integral Cap after post tensioningSection shown supports bridge dead load

    including deck

  • Interior Expansion Pier13 x 6 Column on footing and 4 - 36 Caissons

    8 wide cap to accommodate two rows of bearingsShallow cap post tensioned to match fixed pier aesthetics

  • 8-0 wide cap, 7-0 Deep, Post Tensioned w/ 7 1 3/8 PT bars

    Expansion Pier Cap Reinforcing

  • Completed Fixed and Expansion Piers

  • Precasting of U GirdersCurved casting bed, Single girder casting

  • Typical Girder Cross Section

  • Typical Girder Reinforcing

  • Post Tensioning Details at Girder Splices

  • Reinforcing and PT ducts in placein curved girder casting bed

  • End Diaphragm of typical GirderGrouted Post Tensioning in bottom slabShear keys in face of diaphragm / splice

    Mono strand temp PT for handling and crack control

  • Superstructure Erection

    n Maximum Girder Weight = 265 kipsn Trucked from casting yard on high load, steerable trailersn Girders erected with 240 ton to 300 ton hydraulic and crawler cranesn Night erection at road crossings, Day erection on Units 2 & 3n Supported on falsework, curved girder braces for stability

  • Precast Girder Erection and PT Layout Unit 1

  • Primary support provided by vertical shoringStraddle bents used at IH70 and SH58 traffic crossings

    Precast Girders supported on falsework during erection

  • Typical shoring tower at girder splice

  • Precast Girders lifted with cranes and set on Falsework

  • Curved girders on Falseworkn Girders are braced against shoring prior to being released from cranesn Set on Leveling Pads at all shoring towersn Girders set on permanent bearings at Abutments and Expansion Piers

  • Unit 1 Erection, Looking west

    n Straddle Bents support girders over IH70n Girder Erection - December 2007n PT stressed and falsework removed March 2008

  • Unit 1 Erectionn Looking west at Spans 1 & 2n Span 2 crosses bike path and Clear Creekn Span 2 Girders set with 400 ton crane on existing bridgesn Longitudinal PT is stressed and falsework removed

  • Unit 1 Erectionn Looking east at Spans 3 & 4n Span 3, 235 span over eastbound IH70 on 809 curven Span 4, 186 end span cross westbound IH70

  • Unit 3 Erection, Began May 5, 2008

    n Girders erected from Abutment 11 in down station directionn Majority of Girders erected during the day.

  • Unit 3 Erection, Completed May 7, 2008

    n 4 spans, 14 girders, set in 2 shifts

  • Unit 2 Erection, Began May 8, 2008

    n Span 6, 205 long, crosses SH58.n Girders supported on straddle bent at SH58 crossing.n Girders erected at night in down station direction toward Unit 1

  • Unit 2 Erection Completed, May 9, 2008Combined Units 2 & 3, 24 Girders set in 5 days

  • n Curved Girders braced against to bracket attached to pier capsn Girders supported on tongue section in notch on permanent bearingsn CIP Diaphragms cast at end of each girder.

    Expansion Pier 8 US end of Unit 2, DS end of Unit 3

  • n Girders set on precast tongue sectionn CIP Diaphragm cast against end of girder doubles at PT anchorage blockn Diaphragms designed to allow double end stressing with short stroke ram

    Post Tensioning Details at Expansion Piers

  • Expansion Pier Diaphragm cast on one side

  • Units 2 & 3 Prepared for Post Tensioningn Closures Cast at each Splicen Fixed Pier Diaphragms Cast and Pier Caps stressedn Precast Lid Slabs placed between webs

  • Precast Girder Lid Slab Details

    Precast Panel set between webs and closure cast and cured prior to post tensioning.Lid Slab closes the cross section and greatly increases the torsional strength and

  • Girders ready for longitudinal post tensioningn Lid Slabs set between websn Girder splices castn End Diaphragms castn Fixed Pier Caps cast and post tensioned.

  • Post Tensioning Stressed, Girders are self supporting

    n Deck Panels between girders setn Overhang forms placedn Deck reinforcing placedn Deck grades set and concrete placed.

  • Bridge Construction completed and opened to traffic inNovember 2008

    Officially dedicated on December 12, 2008

  • SH58 Ramp A Flyover Bridgen Advances CDOTs vision of establishing precast concrete as a viable

    design option for complex, long span interchange projects.n Establishes a sustainable technology that utilizes standard, commercially

    available precast concrete products and construction methods.n Creates an aesthetically pleasing, durable, cost effective structures.