    Structural Design of the Marine Terminal

    Prevention First 2006

    September, 2006

    Long Beach, CA

    POLA / Pacific Energy Berth 408

    Crude Oil Import Terminal Design

    Angel Lim, S.E. & John Posadas, P.E.

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    2/43

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    3/43

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    4/43

    Unique Features

    1st New Oil Terminal Designed to MOTEMS

    Designed to meet new MOTEMS and POLASeismic Code

    81 ft of water depth

    Designed to accommodate VLCCs 3-D analysis between structure and pipes

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    5/43

    Facility Description

    POLA Map Faults

    Structural Components

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    6/43

    POLA Map

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    7/43

    POLA Map

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    8/43

    Faults in Southern California

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    POLA

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    9/43

    Structural Component - Unloading Platform

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    60 ft wide x 100 ft long x 4 ft deep reinforced

    concrete slab

    12-48 steel piles

    Steel piles rigidly connected to underside of slab

    4-16 unloading arms

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    10/43

    Structural Component - Breasting Dolphin

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    4-40 ft sq. x 4 ft deep reinforced concrete slab

    4-48 steel piles

    Piles rigidly connected to underside of slab

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    11/43

    Structural Component - Mooring Dolphin

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    6-25 ft sq. x 5 ft deep reinforced concrete slab

    4-54 battered steel piles

    Piles rigidly connected to underside of slab

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    12/43

    Structural Component - North & South Trestles

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    244 ft long x 22 ft wide South Trestle

    33 deep pre-cast concrete box girders

    Combined cast-in-place and pre-cast

    concrete bent caps at 40 ft o.c.

    2-42 steel piles at each bent

    214 ft long x 37 ft wide North Trestle

    33 deep pre-cast concrete box girders

    Combined cast-in-place and pre-cast

    concrete bent caps at 40 ft o.c.

    2-42

    steel piles at each bent

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    13/43

    Structural Design per MOTEMS

    MOTEMS Risk Classification Seismic Performance Criteria

    Minimum Required Analytical Procedure

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    14/43

    MOT Risk Classification

    Purpose is to establish minimum seismic analysis and structural performance.

    Structural performance is evaluated at a two level criteria:Level 1 and Level 2

    MOTEMS risk classification (Table 31-F-4-1)

    All new MOTS are classified as high risk.

    1. Exposed oil 1200 bbls

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    15/43

    MOTEMS Seismic Performance Criteria

    Design Earthquake Motions:

    Level 1

    Minor or no structural damage

    Temporary or no interruption in operations

    Level 2

    Controlled inelastic structural behavior with repairable damage

    Prevention of structural collapse

    Temporary loss of operations, restorable within months

    Prevention of major spill ( 1200 bbls)

    Seismic Performance Criteria:

    Select: High risk classification:

    Seismic Performance Level: Level 1 Level 2

    Probability of Exceedance: 50% in 50 years 10% in 50 years

    Return Period: 72 years 475 years

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    16/43

    Response Spectra

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    POLA CLE

    MOTEMS

    LEVEL 2

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    17/43

    MOTEMS Minimum Required Analytical Procedures

    Minimum Required Analytical Procedures:

    Select: High / Moderate:

    Configuration: Irregular

    Substructure Material: Concrete/Steel

    Displacement Demand Procedure: Linear Model

    Displacement Capacity Procedure: Non Linear Static

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    18/43

    Minimum Analytical Procedure

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Minimum Analytical Procedure

    Design Approach

    Basic Classif ication

    Seismic Performance

    LevelDisplacement Based

    Design

    Develop

    Computer Model

    Calculate DisplacementDemand

    Calculate DisplacementCapacity

    Check

    Pile Shear

    Design for Shear

    Key Forces

    Check

    P-

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    19/43

    Displacement Capacity Flow Chart

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Develop 2-D

    Models

    Pile P-M Curve

    Non-linear Hinge

    Properties

    Geometry

    Section Properties:

    E, A and Ieff

    Soil Springs Seismic Mass

    Lower Bound Upper Bound

    Pile Moment-

    Curvature Curves

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    20/43

    Seismic Mass

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    10% Live Load Added Dead Load

    Dead Load

    Pile Mass

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    21/43

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    22/43

    SAP2000 2-D Model Layout

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Typical top

    hinge

    Pile

    p-y soilsprings

    Deck

    Typical in-

    ground hinge

    1 2 3

    45

    6

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    23/43

    Pushover Curves

    Total

    0

    50

    100

    150

    200

    250

    300

    0.0 4.0 8.0 12.0 16.0 20.0 24.0 28.0

    Displacement, inches

    Base

    Shear,

    kips

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Level 1

    Level 2

    Base

    Shear,

    kips

    Displacement, inches

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    24/43

    Displacement Demand Flow Chart

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Displacement Demand =

    Transverse Displacement

    Demand x DMF

    Calculate

    Displacement Demand

    Initial Stiffness Method

    For Initial Check

    Substitute Structure

    Method (Iterative)

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    25/43

    Displacement Demand Flow Chart

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Initial Stiffness Methodfor in itial check

    Calculate

    Displacement Demand

    Initial stiffness

    from pushover curve

    Damping = 5%

    gK

    WT 2=

    Read displacement demand

    form displacement

    spectra for 5% damping

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    26/43

    Demand-to-Capacity Ratio (DCR)

    Demand x DMF / Capacity < 1.0

    DCR < 1.0

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    27/43

    Mooring & Berthing per MOTEMS

    Mooring/Berthing Risk Classification Mooring Analysis

    Berthing Analysis

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    28/43

    MOTEMS Mooring/Berthing Risk Classification

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Based on site specific parameters:

    1. Wind

    2. Current

    3. Hydrodynamic effects of passing vessels

    4. Change in vessel draft

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    29/43

    Mooring Analysis

    Load Generated By Wind

    Wave

    Passing Vessel Seiche

    Tsunami

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    MOTEMS Ref. 3105F.3.1

    3105F.3.1

    3105F.3.2 3105F.3.3

    3105F.3.4

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    30/43

    MOTEMS Windspeed Conversion Factor

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    31/43

    MOTEMS Current Velocity Correction Factor

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    32/43

    Berthing Analysis

    Fender Design

    Berthing Energy Demand

    Evessel = (W*Vn2/g)

    Berthing Energy Capacity

    Efender = Cb*Cm*Evessel

    Tanker Contact LengthLc = 2r Sin

    Longitudinal or Vertical Berthing ForcesF = N

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    MOTEMS B thi V l it Sit C diti

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    33/43

    MOTEMS Berthing Velocity, Site Conditions

    & Max. Berthing Angle Tables

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    St t l D t il

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    34/43

    Structural Details

    Ship Design Parameters

    General Layout & Elevation

    Mooring Layout for VLCC Section at Unloading Platform

    ULP Rigid Frame Joint Detail

    ULP Reinforcing MD Deck & Pile Reinforcing

    MD Deck Reinforcing Plans

    N & S Trestle Box Girder Layout N & S Pier Layout & Cap Bm Details

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    35/43

    G l L t Pl & W t id El ti

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    36/43

    General Layout Plan & Waterside Elevation

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Mooring Layout for VLCC

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    37/43

    Mooring Layout for VLCC

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Section at Unloading Platform

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    38/43

    Section at Unloading Platform

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    North & South Trestle Box Girder Layout

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    39/43

    North & South Trestle Box Girder Layout

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    40/43

    Project Photos

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    41/43

    Project Photos

    STRUCTURAL DESIGN OF THE MARINE TERMINAL

    Project Photos

  • 8/14/2019 DESIGN OF THE PORT OF LOS ANGELES PIER 400 CRUDE OIL TERMINAL.pdf

    42/43

    Project Photos

    STRUCTURAL DESIGN OF THE MARINE TERMINAL