10
Detector Control System at the GIF++ A. Polini (INFN Bologna) on behalf of WP 8.5.3 group 12/02/2014 Outline Quick reminder on the GIF++ DCS Status and latest developments Next Steps

Detector Control System at the GIF++

Embed Size (px)

DESCRIPTION

Detector Control System at the GIF++. A. Polini (INFN Bologna) on behalf of WP 8.5.3 group 12/02/2014. Outline Quick reminder on the GIF++ DCS Status and latest developments Next Steps. DCS Reminder. Counting Room. AC/DC converter. 48V. 48V. …. OPC. …. Crate1. Crate2. Branch - PowerPoint PPT Presentation

Citation preview

Page 1: Detector Control System at the GIF++

Detector Control System at the GIF++A. Polini (INFN Bologna)

on behalf of WP 8.5.3 group12/02/2014

Outline• Quick reminder on the GIF++ DCS• Status and latest developments• Next Steps

Page 2: Detector Control System at the GIF++

A. Polini

DCS Reminder• Use PVSS/WinCC OA (as in LHC experiments)

– Many components, devices, HW and SW already available (CAEN System, CAN PSU, ELMB, ENV Sensors, VME crates etc.)

• CAEN Easy Power System– 1 mainframe, 1 Power Generator, 1-2 crates + with HV and LV

boards(*) and 1 ADC A-3801 board for monitoring (128 channels), this includes also ENV and gas monitoring

(*) Some Low Voltage possibly external (non CAEN) with remote control via PVSS• Mainframe and PCs possibly

placed proximity of the control room (non radiation area) along with DAQ PCs and equipment.

• EASY crates and other equipment, more close to detector area.

2A. Polini

2

Mainframe

OPC

BranchControllers HV/LV Boards

Crate1 Crate2

AC/DC converter

48V 48V

Hostile Area

Counting Room

A. Polini

Gif++ CERN February 12th 2014

Page 3: Detector Control System at the GIF++

A. Polini

Hardware Status (Dec 2013)• Material already available

– 1 CAEN mainframe (SY-1527 + PS A-1531 A-1532)– 1 (non EASY) HV board A-1526P (6ch 15 kV+)– 1 Branch Controller A-1676– 1 PC (courtesy of ATLAS DCS, spare of past generation)

DELL PowerEdge 1950

• Items to buy or rent at E-pool– EASY 3000 Crate on loan from ATLAS Muons– 1 ADC A-3801 on loan from ATLAS Muons– HV/LV/PS

Gif++ CERN February 12th 2014

Page 4: Detector Control System at the GIF++

A. Polini

Hardware Status (Feb 2014)• Material installed

– 1 CAEN mainframe (SY-1527 + PS A-1531 A-1532)– 1 (non EASY) HV board A-1526P (6ch 15 kV+) (repaired ok)– 1 Branch Controller A-1676– 2 PC (courtesy of ATLAS DCS, spare of past generation)

DELL PowerEdge 1950

• Also installed (on loan from ATLAS Muons)– EASY 3000 Crate– 1 ADC A-3801

B. 190

GIF

Gif++ CERN February 12th 2014

Page 5: Detector Control System at the GIF++

A. Polini

Test Location in B190 (old GIF) (i)

• 2 computers (Dell 1950) installed in CMF (NSC ATLAS_GIF_DCS)• hostnames: pcgifdcs01, pcgifdcs02• Windows 2008 Server R.2• PVSS 3.8 and WinCCOA 3.11

Gif++ CERN February 12th 2014

Page 6: Detector Control System at the GIF++

A. Polini

Test Location in B190 (old GIF) (ii)

• 1 CAEN Mainframe + 1 HV 3516P board, 6ch, 12 KV• 1 EASY crate + 1 ADC A3801 (128 ch) + 2

patchpanels (4x32 pair connectors 16x8 pairs)• Mainframe hostname: pscaengif01

System could be developed/used in conjunction with existing GIF

CMS GIF Setup

Gif++ CERN February 12th 2014

Page 7: Detector Control System at the GIF++

A. Polini

Plans and OutlookStatus:• A neat temporary location for GIF++ setup has been established• Some HW for setting up a template DCS is available and ready for

installation• This system will be used for test, developments within the DCS itself

and will help in defining and develop the interfaces with the other subsystems (detectors, DAQ RadMon and GCS).

Next Steps:• Create a baseline DCS (WinCC-OA, simple control and monitoring, data

archiving) to control the HW already available– Exercise useful to build up young expertise following next developments– System can be used to test parts of the final system (ENV sensors etc).– Options for synergies (existing GIF tests)

Reminder:• To further adapt to final needs • need precise specifications from Users/Detectors• HW procurement

Gif++ CERN February 12th 2014

Page 8: Detector Control System at the GIF++

A. Polini

backup

Gif++ CERN February 12th 2014

Page 9: Detector Control System at the GIF++

A. Polini

Cost Estimate (i)• DCS Caen Equipment ~ 15k€ (a bit less w/o EASY)

• RPC HV (12 KV min 6 ch): 5k€ - 8k€

• TGCs: (3 KV, min 8 channels) 3.2k€ - 7.4k€

• Extended Monitoring (ADC) and DAC (only w/ EASY)

WA3485XAAAAA A3485 A3485 - AC/DC Converter for EASY3000 and EASY4000 400 V 3-phase 48 V 5000 W € 5,873

WA1676AXAAAA A1676A A1676A - EASY Branch Controller (up to 6 EASY crates controlled) € 1,350

WEASY3000MB0 EASY3000 EASY3000 - Crate for EASY3000 Power Supply System for Hostile Area - APP Conn. € 2,575

WE3512XPAAAA A3512P A3512P - EASY3000 H.V. channels +12 KV 1 mA (6 ch) € 7,758

WSY1527L1529 SY1527LC SY1527LC Universal Multichannel Power Supply System - Low Cost - 750 W € 5,720

WSY1527A1531 A1531 SY1527 Primary Power Supply € 877

WE3801XAAAAA A3801 A3801 - EASY3000 128 Channel ADC Board € 3,008

WE3802XAAAAA A3802 A3802 - EASY3000 128 Channels DAC 0-4 V 4 mA € 3,008

WA1526XAAAAA A1526P SY1527 H.V. channels +15 KV 1/0.1 mA - CPE Conn. common floating (6 ch) € 4,918

WE3540XPAAAA A3540P A3540P - EASY3000 H.V. channels +4 KV 1 mA (12 ch) € 7,323

WA1733NAAAAA A1733N SY1527 H.V. channels -3/4 KV 3/2 mA - SHV Conn. (12 ch) € 3,181

Gif++ CERN February 12th 2014

Page 10: Detector Control System at the GIF++

A. Polini

Cost Estimate (ii)Low Voltage:• RPC: (~45 W)

• TGC: LV requirements for TGC not yet available (as being heavily dependent on Front End electronics and detector design

Option of using external (remotely controlled) Low Voltage systems possibly connected to DCS (CAN etc.)• Cheaper• Still controllable within DCS system

PC and infrastructure:• 2500 CHF

WE3009XAAAAA A3009 A3009 - EASY3000 L.V. channels 8 V/9 A/45 W float ing - APP Conn. (12 ch) € 7,105

Gif++ CERN February 12th 2014