Project Indirect Costs are the site-related costs needed for successfully completing a contract that are notdirectly linked to any specific project work package. Project Indirect resources are used to facilitate themanagement and administration of a project and are not linked to specific project works packages.
No Statement
1 Project staff cost are approximately 27% of total Project Indirect Costs
2 Temporary Construction costs are approximately 9% of total Project Indirect Costs
3 Temporary Support Systems & Utilities costs are approximately 9% of total Project Indirect Costs
4 Project Equipment / Total costs are approximately 15% of total Project Indirect Costs
5 Site Office costs are approximately 9% of total Project Indirect Costs
6 Financing & Contractual costs are approximately 9% of total Project Indirect Costs
7 Staff Mobilization & Support costs are approximately 9% of total Project Indirect Costs
8 Material Storage & Handling costs are approximately 9% of total Project Indirect Costs
9 Health, Safety, & Environment Program costs are approximately 3% of total Project Indirect Costs
DISTRIBUTION OF PROJECT INDIRET COSTS AMONG PROJECT SUPPORT ACTIVITES
Project support activities are tasks required for successfully completion a project that are not linked tospecific project work packages.
No Statement
1 Schedule & Coordination of work costs are approximately 5% of total project Indirect Costs
2 Cost Management costs are approximately 5% of total Project Indirect Costs
3 Site Plant & Maintenance costs are approximately 11% of total Project Indirect Costs
4 Contractors Site Supervision costs are approximately 3% of total Project Indirect Costs
5 Shop Drawings costs are approximately 3% of total Project Indirect Costs
6 Quality Assurance costs are approximately 15% of total Project Indirect Costs7 Purchasing & Accounting costs are approximately 11% of total Project Indirect Costs
8 Material Storage & Handling costs are approximately 14% of total Project Indirect Costs
9 Staff Support costs are approximately 14% of total Project Indirect Costs
10 Health, Safety & Environment costs are approximately 6% of total Project Indirect Costs
11 Commissioning costs are approximately 6% of total Project Indirect Costs
DISTRIBUTION OF PROJECT INDIRET COSTS AMONG PROJECT COST OBJECTS
Project cost objects are project elements that include or are part of specific project work packages. Theyare frequently used for monitoring and controlling cost.
No Statement
1 Groundwork consumes approximately 7% of total Project Indirect Costs
2 Concrete Work consumes approximately 13% of total Project Indirect Costs
3 Brickwork & Block work consume approximately 13% of total Project Indirect Costs
4 Structural Metalwork consumes approximately 14% of total Project Indirect Costs
5 Carpentry & Joinery consume approximately 13% of total Project Indirect Costs
6 Finishing consume approximately 15% of total Project Indirect Costs
7 Mechanical & Electrical Services consume approximately 15% f total Project Indirect Costs
8 Building Systems consume approximately 13% of total Project Indirect Costs
7/29/2019 Distribution of Project Indirect Costs Among Project Indirect Resources
2/4
Q1. The current position of most respondents is:
1 General Manager2 Project Manager3 Quantity Surveyor4 Cost Engineer5 Other
Q2 Project indirect Costs (Overhead /Preliminaries/General Requirements) are the site-related
costs needed for successfully completing a contract that are not directly linked to any
specific project work package. Most surveyed companies estimate Project Indirect Costs at
present:
1 Through a detailed analysis of the projectQ3 An allocation basis is used in calculating an Indirect Costs allocation rate to distribute
Indirect Costs among Project items or cost objects. Project cost objects are units that
include or are part of specific project work packages. They are frequently used for
monitoring and controlling cost. The most common allocation basis used to distribute
Project Indirect Costs among project cost object in participating companies is:1 Volume of work2 Project duration3 Material, labor , and equipments cost
Q4 The approximate percentage Project Indirect Costs represent relative to total project cost in
Participating companies over the past five years is:1 11-15%
Q5 Project Indirect resources are used to facilitate the management and administration of a
project And are not linked to specific project work packages. The approximate percentage
each of the following Project Indirect resources represent compared to total Project
Indirect Costs in the participating companies taken over the past five years is:
Project Indirect Resource Percentage
Other
Project Staff-------------------- < 5 6-10 11-15 16-20 21-25 _____ NATemporary Construction----- < 5 6-10 11-15 16-20 21-25 _____ NATemporary Support SystemAnd Utilities-------------------- < 5 6-10 11-15 16-20 21-25 _____ NAProject Equipment/Tools----- < 5 6-10 11-15 16-20 21-25 _____ NA
Site office costs---------------- < 5 6-10 11-15 16-20 21-25 _____ NAFinancing and Contractual
Costs----------------------------- < 5 6-10 11-15 16-20 21-25 _____ NA
Staff Mobilization andSupport costs------------------- < 5 6-10 11-15 16-20 21-25 _____ NAMaterial Storage andHandling costs----------------- < 5 6-10 11-15 16-20 21-25 _____ NA
Health, Safety, andEnvironment Program costs-- < 5 6-10 11-15 16-20 21-25 _____ NA
For questions 6 through 14: Project support activities are tasks required for successfully
completing a project that are not linked to specific project work packages. The approximate
7/29/2019 Distribution of Project Indirect Costs Among Project Indirect Resources
3/4
percentage of the indicated Project Indirect resources cost spent in companies over the past five
years is:
Q6 Financing & Contractual costs (Payable interest, bonds, insurance, etc.)
Project support activity Percentage
Other1 Purchasing and Accounting- < 5 6-10 11-15 16-20 21-25 __60__ NA2 Material Storage and
Handling----------------------- < 5 6-10 11-15 16-20 21-25 _____ NA3 Health, Safety, and
Environment------------------ < 5 6-10 11-15 16-20 21-25 _____ NA
Q7 Staff Mobilization and Support costs
Project support activity PercentageOther
1 Staff Support (Travel,Housing, living) ------------- < 5 6-10 11-15 16-20 21-25 __100_ NA
Q8 Project Staff (Project/site management and administration staff)
Project support activity PercentageOther
1 Scheduling andCoordinating of work ------ < 5 6-10 11-15 16-20 21-25 _____ NA
2 Cost Management ----------- < 5 6-10 11-15 16-20 21-25 _____ NA3 Site Plant and Maintains---- < 5 6-10 11-15 16-20 21-25 _____ NA
4 Contactors SiteSupervision------------------- < 5 6-10 11-15 16-20 21-25 _____ NA
5 Shop Drawings--------------- < 5 6-10 11-15 16-20 21-25 _____ NA
6 Quality Assurance----------- < 5 6-10 11-15 16-20 21-25 _____ NA
7 Purchasing andAccounting-------------------- < 5 6-10 11-15 16-20 21-25 _____ NA
8 Material Storage andHandling----------------------- < 5 6-10 11-15 16-20 21-25 _____ NA
9 Health, Safety, andEnvironment------------------ < 5 6-10 11-15 16-20 21-25 _____ NA
10 Communication-------------- < 5 6-10 11-15 16-20 21-25 _____ NA
Q9 Material Storage and Handling costs
Project support activity PercentageOther
1 Material Storage and
Handling ---------------------- < 5 6-10 11-15 16-20 21-25 _77.5_ NA2 Quality Assurance----------- < 5 6-10 11-15 16-20 21-25 _____ NA
Q10 Health, Safety, and Environment Program costs
Project support activity PercentageOther
1 Health, Safety, andEnvironment ------------------ < 5 6-10 11-15 16-20 21-25 __100_ NA
7/29/2019 Distribution of Project Indirect Costs Among Project Indirect Resources
4/4
Q11 Temporary Support Systems and Utilities
Project support activity PercentageOther
1 Site plant andMaintenance ------------------ < 5 6-10 11-15 16-20 21-25 _____ NA
2 Material Storage and
Handling------------------------ < 5 6-10 11-15 16-20 21-25 _____ NA3 Staff Support (Travel,
Housing, living) --------------- < 5 6-10 11-15 16-20 21-25 _____ NA4 Health, Safety, and
Environment------------------- < 5 6-10 11-15 16-20 21-25 _____ NA
Q12 Project Equipment/Tools
Project support activity PercentageOther
1 Site plant and
Maintenance ------------------ < 5 6-10 11-15 16-20 21-25 _____ NA2 Quality Assurance------------ < 5 6-10 11-15 16-20 21-25 _____ NA
3 Material Storage andHandling------------------------ < 5 6-10 11-15 16-20 21-25 _____ NA
4 Health, Safety, and
Environment------------------- < 5 6-10 11-15 16-20 21-25 _____ NA5 Commissioning---------------- < 5 6-10 11-15 16-20 21-25 _____ NA
Q13 Site Office costs
Project support activity PercentageOther
1 Scheduling andCoordination of Work-------- < 5 6-10 11-15 16-20 21-25 _____ NA
2 Cost Management-------------- < 5 6-10 11-15 16-20 21-25 _____ NA
3 Shop Drawings ----------------- < 5 6-10 11-15 16-20 21-25 _____ NA4 Quality Assurance------------- < 5 6-10 11-15 16-20 21-25 _____ NA5 Purchasing and
Accounting--------------------- < 5 6-10 11-15 16-20 21-25 _____ NA
Q14 Temporary Construction (Temporary roads, scaffolding, etc.)
Project support activity PercentageOther
1 Scheduling and
Coordination of Work-------- < 5 6-10 11-15 16-20 21-25 _____ NA