68

Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO
Page 2: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, operated by the Alliance for Sustainable Energy, LLC.

Do we really need storage to operate the renewable grid of the future?

Paul Denholm

Third Annual TrottierSymposium in Sustainable Engineering, Energy and Design

March 8, 2016

Page 3: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

3

What is the Electric Grid?

• Features –

Supply must always meet demand (sort of)

Large hourly and season variations in electricity demand

Operating reserves to maintain system stability and reliability

A very large rotating machine spinning at 60 Hz

Source: Mullane & O’Malley

Page 4: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

4

Four Independent North America Grids

4

Page 5: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

5

And Many Balancing Areas

5

Page 6: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

6

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

0

10000

20000

30000

40000

50000

60000

0 24 48 72 96 120 144 168

Load

(Fra

ctio

n of

Ann

ual P

eak)

Load

(MW

)

Hour

Summer Maximum Winter Spring Minimum

Hourly electricity demand for three weeks in the ERCOT (Texas) Grid in 2005

Each Balancing Area Must Constantly Balance Variation in Demand

Page 7: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

7

Demand Patterns Similar for Much of the U.S.

NYC (Con Ed) Demand in 2005

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

0 24 48 72 96 120 144 168

Dem

and

(MW

)

Hour

Summer Maximum Spring Minimum Winter

Page 8: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

8

A Few Locations in North America are Winter Peaking

Ontario - 2015

0

5000

10000

15000

20000

25000

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

0 24 48 72 96 120 144 168

Load

(MW

)

Load

(Fra

ctio

n of

Ann

ual P

eak)

Hour & Day

Winter Maximum Fall Minimum

Summer Maximum

Page 9: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

9

Traditional System Operation

9

Variations in demand traditionally met by thermal and hydroelectric plants

GE Energy 2010 (WWSIS)

Page 10: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

10

How Can We Possibly Make the Grid Work with Lots of VG?

1. Claim it isn't possible, or it is possible but lots of storage is needed

2. Just build lots of renewables and see what happens

3. Perform actual science, math, engineering, and analysis

10

Page 11: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

11

Framework – Net Load

Net load- what’s left over when you add wind and solar

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

12 AM 3 AM 6 AM 9 AM 12 PM 3 PM 6 PM 9 PM

Meg

awat

ts

Hour

Load without VG Net Load (Unconstrained)Total Solar Wind

Load, solar, and wind profiles for California on March 29 in a scenario with 11% annual wind and 11% annual solar

assuming no curtailment Denholm et al. 2016

Page 12: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

12

The Most Famous Version

Source: CAISO 2013

Page 13: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

1313

Impacts of Renewables on the Grid

13

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

1-Apr 8-Apr 15-Apr

MW

Load Wind Net Load

Variation in wind output increases net load ramp ate (Increases in this period from 4,052 MW/hour to 4,560 MW/hour)

Uncertainty in wind output increases uncertainty in net load

to be met with conventional generators

Ramp Range (Increases in this two-week period from 19.3 GW/day to 26.2 GW/day)

Four major impacts of variable generation (VG) on the grid:1) Increased need for operating reserves2) Increase in hourly ramp rate3) Increase in uncertainty of net load4) Increase in ramp range

Page 14: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

1414

Quantifying the Impacts of Renewables on the Grid

• How much fuel is actually saved?

• What is the actual economic value?

• Is “backup” needed? Doesn’t this add costs and emissions?

• How much renewables can even be used?

• If the wind blows more at night do you need to store some for use in the day?

• Is storage needed?

14

Page 15: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

15

How We Do Grid Integration Science

o Software that simulates a large interconnected grid considering thousands of generators, and transmission

15

PV science machine

Grid integrationscience machine

Page 16: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

16

Grid Simulation Requirements

• Very expensive commercial software package that includes existing generation mix, transmission systemo ~10 Vendors/Software packageso Annual licenses routinely exceed $100ko Massive databaseo ~5 hours to >400 days per simulation

• Names includeo “security constrained unit commitment and economic dispatch”o “production cost model”o “chronological dispatch model”

Page 17: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

17

Steps to Performing a Realistic Analysis of Renewables on the Grid

1. Acquire detailed solar and wind datao Use lots of wind and solar simulations to consider spatial diversity

o Sub-hourly wind and solar data across large amounts of the U.S. didn’t exist before a few years ago

2. Calculate change in reserve requirementso Use standard industry methods for calculating changes in

regulation reserve requirements based on variability o Consider new methods of addressing

longer term variability and uncertainty

3. Modify data sets to incorporate morerealistic generator performance

0 50 100 150 200 2506

7

8

9

10

11

12

13

14

Generation (MW)

Hea

t Rat

e (m

mbt

u/M

Wh)

Front Range CC Unit 2

Lew et al. 2013

Page 18: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

18

Steps to Performing a Realistic Analysis of Renewables on the Grid

4. Hit go and wait…•

18

Page 19: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

19

Simulation Outputs

• Did the grid work?• Did you drop load or violate reserve

requirements?

• What was the impact of forecast error or variability on cycling costs and emissions?

• Did you actually use all the renewable generation?o How much curtailment?

• Did a bunch of bad things happen to indicate storage is needed?

19

Page 20: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

20

Example Dispatch in Colorado

Denholm et al. 2014

Page 21: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

21

Power Flow and Transmission

NELWAY

BRIDGER

COLSTRIP

GOSHEN

BORAH

KINPORT

MIDPOINT

SUMMERLAKE

MALIN

CAPTJACK

MERIDIAN

ALVEY

ALLSTON

KEELER

PEARL

ROUNDMT

OLINDA

JOHN DAY

MARION

LANE

GRIZZLY

BUCKLEY

THEDALLES

OSTRANDER SLATT

McNARY(1169 MW)

BOARDMAN

PAUL /CENTRALIA

RAVER

MONROE

CUSTER

ECHOLAKE

CHIEFJOE GRAND COULEE

SCHULTZ

HANFORD

ASHE

VANTAGE

LOWMON

LITGOOSE

LOWGRANITE

TAFT

GARRISON

DWORSHAK

TOWNSENDBROADVIEW

BELL

DIXONVILLE

BENLOMOND

NAUGHTON

ANACONDA

ATLANTICCITY

ROCKSPRINGS

MONUMENT

MUSTANG

SPENCE

BILLINGS

YELLOWTAIL

CUSTER

GREATFALLS

OVANDO

HOTSPRINGS

CABGORGE

NOXON

LOLO

HELLSCANYON

ROUNDUP

OXBOW

BROWNLEE

BOISE

ENTERPRISE

WALLAWALLA

LAGRANDE

HATWAI

MOSCOW

BENEWAH

RIVERTON

BUFFALO

OREGONBASIN

THERMOPOLIS

WYODAK

CASPER

SHERIDAN

PLATTE

DAVE JOHNSTON

MILES CITYDC TIE

GRANTSPASS

COPCO

LONEPINE

ROSS

ONTARIO

CALDWELLBURNS

WANETA

BOUNDARY

VACA-DIXON

TRACY

TESLA

TABLEMT

LOSBANOS

MOSSLANDING

TERMINAL

MONA

FOUR CORNERS

90SOUTH

CAMPWILLIAMS

BONANZA

HUNTINGTON

SIGURD

IPPGONDER

HARRYALLEN

MACHACEKFTCHURCHILL

AUSTIN

PAVANT

HUNTER

SYLMAR

ADELANTO

GLENCANYON

VALMY(562 MW)

HUMBOLDT

TRACY

VALLEYROAD

CROSS-OVER

AMPS

JEFFERSON

DILLONPETERSONFLATS

DRUM

WEEDJCT

CASCADE

RESTON

OLYMPIA

INGLEDOW

ROCKYREACH

MIDWAY

LIBBY

HUNGRY HORSE

CRAIG

SAN JUAN

HAYDEN

LARAMIERIVER

ARCHER

AULT

RIFLE

MONTROSE

PINTO

CURECANTI PONCHA

SIDNEY

STORY

L E G E N D:

500KV

+-500KVDC

345KV230KV115-161KV

LANGE

WESTHILL

STEGAL

COMANCHEMIDWAY

DANIELS PARKMALTA

SMOKY HILL

PAWNEE(530 MW)

VALMONT

DILLON

BEAVER

WARNERHILL TOP

BORDERTOWN

REDBUTTE

FLAMINGGORGE

TREASURETON

K-FALLSCO GEN

BOYLE

NLEWISTON

DIABLO

GATES

MIDWAY

RINALDI

VINCENT

VICTORVILLE

LUGO

MIRALOMASERRANO

VALLEY

DEVERS

MIGUEL IMPERIALVALLEY

MOJAVE

EL DORADO

MCCULLOUGHMEAD

MARKETPLACE

NAVAJO

MOENKOPI

YAVAPAI

TABLE MESA

PALO VERDE

WESTWING

FLAGSTAFF

PINNACLE PEAK

CHOLLA

NORTH GILA LIBERTY

KYRENE SILVERKING

CORONADO

SOUTH

BICKNELL VAIL

GREENLEE

SPRINGERVILLE

SAGUARO

TORTOLITA

PARKER

PRESCOTT

ROUNDVALLEY

SELIGMANDAVIS

CAMINO

EAGLEMT.

BLYTHE

KNOB

GILATIJUANA

METROPOLIJUAREZ

LOMAS

CIPRES

LAROSITA

SAN LUIS

MEXICALI

INTERGENSEMPRA

MERIDIAN

CHEEKYE

MALASPINA

DUNSMUIR

SAHTLAM

GOLD RIVER

ARNOTT

CLAYBURNROSEDALE

WHALEACH

BRIDGERIVER

NICOLA

KELLYLAKE

100 MILEHOUSE

SODACREEK

BARLOW

WILLISTON

GLENANNAN

TELKWA

SKEENA

PRINCE RUPERT

KITMAT

KEMANO

SAVONA

MICA

REVELSTOKE

ASHTONCREEK

SELKIRK CRANBROOK

INVERMERE

NATAL

PEIGAN N. LETHBRIDGE

LANGDON

JANETSARCEE

REDDEER

BENALTO

BRAZEAU

BICKERDIKE KEEPHILLSELLERSLIE

W. BROOKS

WAREJTN. JENNER

EMPRESS

SHEERNESS

EAST EDMONTONCLOVERBAR

LAMOUREUX

DEERLAND

WHITEFISHLAKE

MARGUERITELAKE

RUTH LAKE

MITSUE

N. CALDER

N. BARRHEAD

LITTLESMOKY

LOUISECREEK

SAGITAWAH

WABAMUNSUNDANCE

MCKINLEY

P.E.G.S.AMBROSIA WEST

MESA

B-A

NORTON

OJO

TAOS

BLACKWATER

ARTESIAAMRAD

CALIENTENEWMAN

ARROYO

DIABLO

LUNA

HIDALGO

LEUPP

EL CENTRO

KENNEDY

PEACE CANYON

PEACE RIVER

BATTLE RIVER

METISKOW

LEUPP

ELCENTRO

KDY 5CX3

PCN500

GMS500

BAT RV79

METIS644

LEUPP

ELCENTRO

KDY 5CX3

PCN500

GMS500

BAT RV79

METIS644

Red indicates high costs and transmission constraints

Source: RMATS Study

Page 22: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

22

Example Simulation - Solar PV in the Summer

22

0

10,000

20,000

30,000

40,000

50,000

60,000

Bas 2% 6% 10%PV Penetration and Hour

Gen

erat

ion

(MW

)

PV

GasTurbinePumpedStorageHydro

CombinedCycleImports

Coal

Nuclear

Wind

Geo

Base (no PV) 2% 6% 10%

Simulated Dispatch in California for a Summer Day with PV Penetration from 0-10%

Denholm et al. 2008

Page 23: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

23

Reserve Violations can Indicate Loss of Reliability

Page 24: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

2424

First Generation of Wind Integration Studies (<2010, up to about - 20% Penetration)

• Focused on basic operability and “integration costs”.

• Integration costs are modest (typically less than $5/MWh). Ongoing questions as to what this even means….

• Spatial diversity smooths aggregated wind output reducing short-term fluctuations to hour time scales

• Almost all the wind can be used (very little curtailment)

• Additional reserves have a modest impact on operational costs

Page 25: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

2525

Second Generation• Higher penetration (up to 35% penetration of wind and solar)

• Examines impact of increased system flexibility

• General Conclusions

• Extensive co-operation will be needed

• We may be nearing the flexibility limits of the grid as it exist today

• High solar penetrations are more difficult than high wind

• Curtailment may be the primary limitation for economic deployment of wind and solar

Page 26: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

26

Limits to VG Penetration - Curtailment

• There are no technical limits to how much VG can be put on the grid – only economic limits

• You can always find a piece of hardware to solve the problem (including storage….)

• At high penetration, economic limits will likely be due to curtailment

Page 27: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

27

WWSIS II High Wind Case (8% solar, 25% wind)

http://www.nrel.gov/electricity/transmission/western_wind.html

Curtailment

Lew et al. 2013

Page 28: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

2828

WWSIS II High Wind Solar (25% solar, 8% wind)

Solar is 60% PV and 40% Concentrating Solar Power with 6 hours thermal storage

Curtailment

Lew et al. 2013

Page 29: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

29

Sources of Curtailment

Too much supply, not enough demand, when considering:• Ramp constraints• Transmission constraints• Minimum output levels from hydro and thermal

generatorso This also includes the need to operate partially loaded

capacity to maintain system reliability

• Many of these challenges are institutional in addition to technical

Page 30: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

3030

Current System FlexibilityLimited by Baseload Capacity

Price/Load Relationship in PJM

Below Cost Bids

0

50

100

150

200

250

0 10000 20000 30000 40000 50000 60000

Load (MW)

Who

lesa

le P

rice

($/M

Wh)

0

5

10

15

20

25

30

35

18000 20000 22000 24000 26000Load (MW)

Who

lesa

le P

rice

($/M

Wh)

Plant operators would rather sell energy at a loss than incur a costly shutdown. Wind and solar may be curtailed under these conditions.

30

Page 31: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

31

Impacts of “Must-Run” Generation

0

10000

20000

30000

40000

50000

60000

70000

143

987

713

1517

5321

9126

2930

6735

0539

4343

8148

1952

5756

9561

3365

7170

0974

4778

8583

23Potentially met by solar

Off limits to solar

CAISO estimate of must run generation in current system

This translates into 41% of CAISO load “off limits” to wind and solar

Page 32: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

32

Curtailment with Limited Flexibility

Used and curtailed VG in California on March 29 in a scenario with 11% annual wind and 11% annual solar

0%

5%

10%

15%

20%

25%

1-Jan 1-Feb 1-Mar 1-Apr 1-May 1-Jun 1-Jul 1-Aug 1-Sep 1-Oct 1-Nov 1-Dec

Frac

tion

of D

aily

Sol

ar E

nerg

y Cu

rtai

led 11% Annual Solar

15% Annual Solar

Denholm et al. 2016

Page 33: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

33

Curtailment Increases RapidlyMarginal curtailment = curtailment of all incremental VG moving from one penetration level to the next Total curtailment = curtailment rate of all PV installed on the system at a certain penetration level

Marginal and average curtailment due to overgeneration under increasing penetration of PV in California with limited grid flexibility

0%

10%

20%

30%

40%

50%

60%

70%

6% 8% 10% 12% 14% 16% 18% 20% 22% 24%

Annu

al S

olar

Cur

tailm

ent

Annual Solar Energy Penetration

Marginal Curtailment

Total Curtailment

Denholm et al. 2016

Page 34: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

34

Consequences of RE curtailment

• Technically easy to do (at least on utility-scale renewable energy generation)

• But reduces economic benefits measured by either increased cost of decreased benefit

Page 35: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

35

Impact of VG curtailment on LCOECurtailed energy means less can be sold and incremental costs of additional PV rise dramatically

Marginal and average PV LCOE (based on SunShot goals) due to overgeneration under increasing penetration of PV in California with

limited grid flexibility

6

7

8

9

10

11

12

13

14

15

6% 8% 10% 12% 14% 16% 18% 20% 22% 24%

PV C

ost D

ue to

Cur

tailm

ent

(Cen

ts/k

Wh)

Annual Solar Energy Penetration

Marginal Cost

Total Cost

Denholm et al. 2016

Page 36: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

36

Avoided Generation and Fuel

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

10% 15% 20%

Avoi

ded

Gen

erat

ion

(MW

h pe

r MW

h of

Po

tent

ial P

V G

ener

atio

n)

Annual PV Penetration

total gas

total coal

total other

total gen

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

10% 12% 14% 16% 18% 20% 22%

Avoi

ded

Fuel

(BTU

per

kW

h of

Pot

entia

l PV

Gen

erat

ion)

Annual PV Penetration

Gas

Coal

Other

total fuel

Page 37: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

37

Avoided Generation Costs

-10

0

10

20

30

40

50

60

70

10% 12% 14% 16% 18% 20% 22% 24%Avoi

ded

Prod

uctio

n Co

st o

f PV

per u

nit

of P

oten

tial G

ener

atio

n ($

/MW

h)

Annual PV Penetration

vom

start

fuel

emissions

total

This is the avoided production (variable) costs of PV

Page 38: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

3838

Increasing PV Value and Avoiding Curtailment

• While storage provides an “obvious” answer to the problem of supply-demand coincidence, there are a number of options

Denholm et al. 2010

Page 39: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

39

Flexibility Supply Curve Concept

39

Denholm et al. 2010

Page 40: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

40

Flexibility Supply Curve Concept

40

You probably do this firstCochran et al. 2015

Page 41: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

41

Mitigation Options

Type Description

Generator flexibility Ability of conventional generation to vary output over various time scales

Storage flexibility Ability to store energy during periods of low demand and release that energy during periods of high demand

Geographic flexibility Ability to use transmission to share energy and capacity across multiple regions

Load flexibility Ability to vary electricity demand in response to grid conditions

Page 42: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

42

Impact of Increased Flexibility Dropping the minimum generation level increases the amount of load served by PV

Net load on March 29 in a scenario with 15% annual solar increasing the grid flexibility

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

12 AM 3 AM 6 AM 9 AM 12 PM 3 PM 6 PM 9 PM

Net

Loa

d (M

W)

Hour

Limited Flexiblity

Enhanced Flexibility

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

12 AM 3 AM 6 AM 9 AM 12 PM 3 PM 6 PM 9 PM

Sola

r Cur

tailm

ent (

MW

)

Hour

Limited Flexiblity

Enhanced Flexibility

Denholm et al. 2016

Page 43: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

43

Increased Flexibility = Increased PenetrationPV penetration of 25% with less than 20% marginal and 5% total curtailment

Marginal and average curtailment due to overgeneration under increasing penetration of PV in California with enhanced grid flexibility

0%

10%

20%

30%

40%

50%

60%

70%

6% 8% 10% 12% 14% 16% 18% 20% 22% 24% 26% 28% 30% 32%

Annu

al S

olar

Cur

tailm

ent

Annual Solar Energy Penetration

Limited Flexibility(Marg.)Limited Flexibility(Total)Enhanced Flexibility(Marg.)Enhanced Flexibility(Total)

Denholm et al. 2016

Page 44: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

44

And More Competitive Costs

Marginal and average LCOE due to overgeneration under increasing penetration of PV in California with enhanced grid flexibility

6

7

8

9

10

11

12

13

14

15

6% 8% 10% 12% 14% 16% 18% 20% 22% 24% 26% 28% 30% 32%

PV C

ost D

ue to

Cur

tailm

ent

(Cen

ts/k

Wh)

Annual Solar Energy Penetration

Limited Flexibility(Marg.)Limited Flexibility(Total)Enhanced Flexibility(Marg.)Enhanced Flexibility(Total)

Denholm et al. 2016

Page 45: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

45

Increased Flexibility Increases VG Value

0

10

20

30

40

50

60

70

10% 12% 14% 16% 18% 20% 22% 24% 26% 28% 30%

Avoi

ded

Prod

uctio

n Co

st o

f PV

per u

nit

of P

oten

tial G

ener

atio

n ($

/MW

h)

Annual PV Penetration

Base

Increased OperationalFlexibility

0

10

20

30

40

50

60

70

80

90

10% 15% 20% 25% 30% 35%

Tota

l Val

e P

V pe

r uni

t of P

oten

tial

Gen

erat

ion

($/M

Wh)

Annual PV Penetration

Increased OperationalFlexibility

Base

Operational value

Total value

Page 46: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

4646

Curtailment as a Function of Flexibility

Average curtailment rate as a function of VG penetration for different flexibilities in ERCOT

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

50%

0% 10% 20% 30% 40% 50% 60% 70% 80%

Fraction of System Electricity from Wind

Frac

tion

of W

ind

Gen

erat

ion

Curta

iled

80% flexiblity (12 GW min load)

90% flexibility (6 GW min load)

100% flexibility (0 min load)

Denholm and Hand 2011

Page 47: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

4747

Different RE Mixes Improves Supply/Demand Coincidence

47

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

50%

20% 30% 40% 50% 60% 70% 80%Fraction of System Electricity from Solar and Wind

Frac

tion

of V

G C

urta

iled

0/10020/8030/7040/6060/4080/20

Solar / Wind Mix

Denholm and Hand 2011

Page 48: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

4848

How High Can We Go?

• Can renewables themselves largely de-carbonize the electric sector?

• Results from various studies indicate that beyond 35% VG, new sources of flexibility will be needed for economic deployment of renewables

• Need to perform scenario analysis to consider all options and mixes of renewable resources

Page 49: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

49

Renewable Electricity Futures

Technology cost & performanceResource availabilityDemand projectionDemand-side technologiesGrid operationsTransmission costs

Black & Veatch

Technology Teams

Flexible Resources

End-Use Electricity

System Operations

Transmission

ABB inc.GridView

(hourly production cost)

rooftop PVpenetration

2050 mixof generators

does it balancehourly?

ImplicationsGHG Emissions

Water UseLand Use

Direct Costs

Capacity & Generation 2010-2050

Mai et al. 2012

Page 50: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

50

RE Resource Supply from 30% - 90% Electricity

Additional variability challenges system operations, but can be addressed through increased use of supply- and demand-side flexibility options and new transmission.

Mai et al. 2012

Page 51: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

51

A Transformation of the U.S. Electricity System

RE generation from technologies that are commercially available today, in combination with a more flexible electric system, is more than adequate to supply 80% of total U.S. electricity generation in 2050—while meeting electricity demand on an hourly basis in every region of the country.

Mai et al. 2012

Page 52: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

52

How? Build New Transmission…

52

-1

-0.5

0

0.5

1

0 2190 4380 6570 8760Tr

ansm

issi

on u

sage

/ ca

paci

ty

Hours

CO to KS MT to ND

Mai et al. 2012

Page 53: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

53

Deploy Dispatchable Renewables

Source: Denholm et al (2012)

Page 54: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

54

0

50

100

150

200

250

Apr-27 00:00

Apr-27 12:00

Apr-28 00:00

Apr-28 12:00

Apr-29 00:00

Apr-29 12:00

Apr-30 00:00

Apr-30 12:00

Pow

er (G

W)

Coal

0102030405060708090

Apr-27 00:00

Apr-27 12:00

Apr-28 00:00

Apr-28 12:00

Apr-29 00:00

Apr-29 12:00

Apr-30 00:00

Apr-30 12:00

Pow

er (G

W)

Gas CC

0

1

2

3

4

5

6

Apr-27 00:00

Apr-27 12:00

Apr-28 00:00

Apr-28 12:00

Apr-29 00:00

Apr-29 12:00

Apr-30 00:00

Apr-30 12:00

Pow

er (G

W)

Gas CT

05

1015202530354045

Apr-27 00:00

Apr-27 12:00

Apr-28 00:00

Apr-28 12:00

Apr-29 00:00

Apr-29 12:00

Apr-30 00:00

Apr-30 12:00

Pow

er (G

W)

Coal

02468

1012141618

Apr-27 00:00

Apr-27 12:00

Apr-28 00:00

Apr-28 12:00

Apr-29 00:00

Apr-29 12:00

Apr-30 00:00

Apr-30 12:00

Pow

er (G

W)

Gas CC

0

1

2

3

4

5

6

Apr-27 00:00

Apr-27 12:00

Apr-28 00:00

Apr-28 12:00

Apr-29 00:00

Apr-29 12:00

Apr-30 00:00

Apr-30 12:00

Pow

er (G

W)

Gas CTBa

selin

e sc

enar

io

80%

RE-

ITI s

cena

rio

Design for cycling

Mai et al. 2012

Page 55: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

55

Harness Responsive Demand (smart grid?)

55

0

20

40

60

80

100

120

Baseline

30% R

E

40% R

E

50% R

E

60% R

E

70% R

E

80% R

E

90% R

E

Con

tribu

tion

to O

pera

ting

Res

erve

requ

irem

ent (

GW

)

Generators Storage Interruptible Load

Mai et al. 2012

Page 56: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

56

0

2

4

6

8

10

12

14

16

18

Curt

ailm

ent (

TWh)

EastWECCERCOT

Accept inevitable curtailment in the spring.

• 8-10% of wind, solar, hydropower curtailed in 2050 under 80% RE scenarios

Mai et al. 2012

Page 57: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

57

• RE Futures develops about 80 GW of new storage, in addition to the 20 GW of pumped storage existing in the U.S.

• Lower cost storage would be more competitive

• We don’t understand the opportunities of a world with low cost energy storage

..And yes, develop new storage

Mai et al. 2012

Page 58: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

5858

Energy Storage Can Reduce VG Curtailment

580%

5%

10%

15%

20%

25%

30%

35%

40%

20% 30% 40% 50% 60% 70% 80%Fraction of System Electricity from Wind&Solar

Frac

tion

of V

G C

urta

iled

No Storage4 hours8 hours12 hours24 hours

Denholm and Hand 2011

Page 59: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

59

Cost Optimal Storage Deployment?

Now - Conventional Pumped Hydro: ~ 20 GW

Future 80-140 GW depending on REF scenario

Mai et al. 2012

Page 60: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

60

But we are just not there yet….

Value of bulk storage (sited on the transmission network) in today’s system

800

1000

1200

1400

1600

1800

2000

2200

2400

Base Device

(300 MW)

Increased Efficiency

No PHS Double Natural

Gas Price

2X NG and No PHS

Brea

keve

n ca

pita

l cos

t fo

r an

8-ho

ur

stor

age

devi

ce ($

/kW

)

High

Mid

Low

Divide by 8 to get $/kWh installed cost

$200/kWh installed cost

Denholm et al. 2013

Page 61: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

61

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

12 AM 4 AM 8 AM 12 PM 4 PM 8 PM 12 AM 4 AM 8 AM 12 PM 4 PM 8 PM

Meg

awat

ts

Hour

Load without PV

14% PV

Storage/PV Synergy

Less time between peak and off-peak period

0

1

2

3

4

5

6

0% 5% 10% 15% 20% 25% 30%

Hour

s of S

tora

ge N

eede

d to

Rel

iabl

y Re

duce

Net

Dem

and

Annual PV Penetration (Potential)

2650 MW

1325 MWNarrower peak means less storage needed

Denholm et al. 2016

Page 62: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

62

A Tipping Point for Storage?

The adoption of storage may be primarily driven by its ability to offset conventional capacity aided by the increase in value associated with VG deployment

9001,0001,1001,2001,3001,4001,5001,6001,7001,8001,9002,0002,1002,2002,3002,400

225250275300325350375400425450475500525550575600

8 10 12 14 16 18 20

4-Ho

ur B

atte

ry C

ost (

$/kW

)

4-Ho

ur B

atte

ry C

ost (

$/kW

h)

Battery Lifetime (Years)

20% PV $1500/kW CT

15% PV $1500/kW CT

20% PV $900/kW CT

15% PV $900/kW CT

Denholm et al. 2015

Page 63: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

63

Conclusions: What I Think I Know About the Grid and Storage (<35%)

• Numerous studies have demonstrated the feasibility of 35% RE

• New methods of grid operation are required• Significantly increased cooperation across large

areas• More ramping of thermal units• Storage is probably not the least-cost option

for increased integration

Page 64: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

64

What I Think I Know About the Grid and Storage (>35%)

• Less explored territory• Curtailment rates increase• Any and all sources of grid flexibility will be needed

• Demand Response• Long distance transmission?

• Value of storage increases• At some point low cost sources of flexibility will be

exhausted and storage will be an increasingly attractive means of utilizing wind and solar • Non obvious sources of storage may be cost-competitive

(Thermal storage in buildings, CSP with TES)• Storage adoption may be driven by its ability to

replace conventional capacity

Page 65: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

65

Questions?

Paul [email protected]

Page 66: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

66

Selected References• Brinkman, G., J. Jorgenson, A. Ehlen, J. Caldwell (2015). “The California 2030 Low Carbon Grid Study,” NREL TP-

6A20-64884• CASIO (2013). What the Duck Curve Tells us about Managing a Green Grid. • Denholm, P., K. Clark, and M. O’Connell. (2016). On the Path to SunShot: Emerging Issues and Challenges in

Integrating High Levels of Solar into the Electrical Generation and Transmission System. Golden, CO: National Renewable Energy Laboratory. NREL/TP-6A20-65800.

• Denholm, P., M. O'Connell, G. Brinkman, J. Jorgenson (2015). Overgeneration from Solar Energy in California: A Field Guide to the Duck Chart. NREL/TP-6A20-65023

• Denholm, P., V. Diakov, R. Margolis (2015) The Relative Economic Merits of Storage and Combustion Turbines for Meeting Peak Capacity Requirements under Increased Penetration of Solar Photovoltaics. NREL/TP-6A20-64841

• Denholm, P., J. Jorgenson, M. Hummon, T. Jenkin, B. Kirby, O. Ma, M. O'Malley, and D. Palchak. (2013) Value of Energy Storage for Grid Applications. NREL Report No. TP-6A20-58465.

• Denholm, P., and M. Hand. (2011) “Grid Flexibility and Storage Required to Achieve Very High Penetration of Variable Renewable Electricity” Energy Policy 39, 1817-1830.

• Denholm, P. and M. Mehos. (2011) “Enabling Greater Penetration of Solar Power via the Use of Thermal Energy Storage” NREL Report No. TP-6A20-52978.

• Denholm, P., E. Ela, B. Kirby, and M. Milligan. (2010) “The Role of Energy Storage with Renewable Electricity Generation” NREL/TP-6A2-47187.

• Denholm, P., R. M. Margolis and J. Milford. (2008) “Production Cost Modeling for High Levels of PhotovoltaicsPenetration” NREL/TP-581-42305.

• Denholm, P., and R. M. Margolis. (2007) “Evaluating the Limits of Solar Photovoltaics (PV) in Electric Power Systems Utilizing Energy Storage and Other Enabling Technologies”. Energy Policy. 35, 4424-4433.

• Mai; R. Wiser; D. Sandor; G. Brinkman; G. Heath; P. Denholm; D.J. Hostick; N. Darghouth; A. Schlosser; K. Strzepek 2012 Renewable Electricity Futures Study. NREL/TP-6A20-52409

• Lew, D.; Brinkman, G.; Ibanez, E.; Florita, A.; Heaney, M.; Hodge, B. M.; Hummon, M.; Stark, G.; King, J.; Lefton, S. A.; Kumar, N.; Agan, D.; Jordan, G.; Venkataraman, S. (2013). “Western Wind and Solar Integration Study Phase 2.” NREL Report No. TP-5500-55588.

Page 67: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO

Contact:Paul [email protected]

Page 68: Do we really need storage to - Trottier Symposium · 2016. 3. 8. · Third Annual Trottier Symposium in Sustainable Engineering, Energy and Design. March 8, 2016. 3. ... ROSS ONTARIO