DRAGON STEEL CORPORATION – TaiwanPRIMUS® Plant

Recycling Technologies

Page 2: DRAGON STEEL CORPORATION – Taiwan - Paul Wurth …brochures.paulwurth.com/recycling/...Dragon-Steel-Corporation-en.pdf · DRAGON STEEL CORPORATION – ... The Dragon Steel Taichung

Introduction

In the frame of the expansion of their Taichung (Taiwan) steelmaking facilities, Dragon Steel Corporation (a subsidiary of China Steel Cor-poration) has contracted Paul Wurth for the construction of a new PRIMUS plant.

This plant was to be the first reference for this technology developed by Paul Wurth out-side the group.

The PRIMUS technology is based on a Multiple Hearth Furnace (MHF), used for preheating, calcining and prereducing the residues using economical coal, combined with the i-Meltor®, a specially designed electric arc furnace, for smelting the residues and fuming off the zinc.

The PRIMUS process is an innovative solu-tion for recovering separately iron and zinc as added value materials from iron and steelmak-ing residues: zinc is recovered as zinc oxide, iron as pig iron and gangue materials as inert slag. The PRIMUS process features recovery rates of zinc and iron close to 100 %, while complying with the most stringent environ-mental regulations.

Dragon Steel Taichung site

The Dragon Steel Taichung site (1 300 x 2 100 m) is enclaved between the sea and the city of Taichung, the third largest of Taiwan. This location was the reason for the stringent environmental constraints applicable to the site.

The site was originally equipped with a mini-mill (i.e. Electric Arc Furnace shops) producing approximately 800 000 tonnes per year of carbon-steel long-products.

In the frame of the expansion strategy of the China Steel group to enter into the flat- product steel sector, Dragon Steel started, as a first expansion phase, the construction of a green field integrated iron making plant on its Taichung site, including a sinter plant, a coke oven plant, a blast furnace plant, a converter shop and a hot rolling mill plant.

Project Description

Principle flow sheet of PRIMUS for Dragon Steel

MHF

Project Data

Start of cold commissioning: December 2008

Start of hot commissioning: February 2009

Start-up date: March 2009

Performance test achieved: June 2009

Page 3: DRAGON STEEL CORPORATION – Taiwan - Paul Wurth …brochures.paulwurth.com/recycling/...Dragon-Steel-Corporation-en.pdf · DRAGON STEEL CORPORATION – ... The Dragon Steel Taichung

As a prerequisite for this expansion, local En-vironment Protection Authorities had required Dragon Steel to have beforehand implemented a solution for in-site recycling of residues.

PRIMUS® at DRAGON STEEL

At Dragon Steel, the PRIMUS plant has been designed for recycling stockpiled and future residual material (dust, sludge, etc.) from their existing Electric Arc Furnace shops and from the future plants. It features a nominal recycling capacity of 120 000 tonnes (dry base) of residual material per year and will be operated with different feed mixes, rang-ing from 100 % EAF dust to a high proportion of blast furnace residues, depending on their availability:

` period 1, until stockpiled residues are totally recycled: recycling of stockpiled EAF dust + fresh EAF dust

` period 2, from start-up of first integrated plant: recycling of fresh EAF dust + other residues from the first integrated plant

` period 3, from start-up of second inte-grated plant: recycling of fresh EAF dust + residues from both integrated plants

The whole PRIMUS plant, including surround-ing service ways, is arranged on a 80 x 100 m plot of ground.

PRIMUS® Plant

Principle flow sheet of PRIMUS for Dragon Steel

PRIMUS® Data

Plant capacity:

` 100 % EAF dust = 85 000 tdry / y

` Mix of 20 % EAF dust + 80 % residues BOF / BF = 120 000 tdry / y

MHF : 8 hearths / Ø 8 m

EAF : 21 MW / Ø 6 m Continuous central charge feeding Metal stirring with inert gas

Scope of Works

` Engineering

` Supply of key components

` Project Management

` Technical Direction of site works

i-Meltor®

Page 4: DRAGON STEEL CORPORATION – Taiwan - Paul Wurth …brochures.paulwurth.com/recycling/...Dragon-Steel-Corporation-en.pdf · DRAGON STEEL CORPORATION – ... The Dragon Steel Taichung

International presence:Brazil, Chile, Czech Republic, Germany, India, Italy, Japan, Korea, Mexico, P.R. China, Russia, South Africa, Taiwan, Ukraine, U.S.A., Vietnam

© Copyright 2010-2015 Paul Wurth S.A. – all rights reserved

Non Contractual Data: Paul Wurth believes that the data contained in this folder are correct and accurate, but cannot guarantee same or better performances for any specific site without a detailed quote. Patents and Patents pending. — Paul Wurth equipment and processes are protected in many countries by patents.

Paul Wurth, the Paul Wurth logo, Primus and i-Meltor are trademarks of Paul Wurth S.A. and may be registered in your jurisdiction.

VCA**CER

TIFIED SAFETY SYSTEM

VINCOTTE

ISO 9001ISO 14001

BUREAU VERITASCertification

Paul Wurth S.A.32, rue d’AlsaceL-1122 LuxembourgPhone: (+352) 4970-1Fax: (+352) [email protected]

* TMT – Tapping Measuring Technology, a joint company of Dango & Dienenthal and Paul Wurth.

Off-Gas TreatmentFeed preparation

i-Meltor®

Pig Iron Casting

Technical Highlights