58
EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana Environmental Custodial Trust

EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

EAST HELENA SMELTER SITEMINE DESIGN, OPERATIONS & CLOSURE CONFERENCEMAY 4, 2016

Montana Environmental Trust GroupTrustee of the Montana Environmental Custodial Trust

Page 2: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

AGENDA Introductions

• Betsy Burns – EPA Project Manager

• Mark Rhodes – Hydrometrics – Construction Manager for METG

• Joel Gerhart – Pioneer – PPC Design Engineer  

RCRA Corrective Action Corrective Measures Study Overview

Interim Measures Implementation Presentation 

• Evapotranspirative Cover System 

• South Plant Hydraulic Control/Prickly Pear Creek Reconstruction

2

Page 3: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

3

Project Location

PPC Project Area

Plant Site

East Helena

Page 4: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

CORRECTIVE MEASURES STUDY OVERVIEW

CMS Purpose –

Investigate and evaluate potential alternative remedies to protect human health and the environment from the release or potential release of hazardous waste/constituents

4

CMS Goals – Meet requirements of Asarco Consent Decree and applicable regulatory & USEPA 

guidance

Analyze potential actions with consideration of known risks to actual or potential receptors

Include potential actions that will create the greatest net environmental benefit and which are compatible with expected future use.

Page 5: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

CORRECTIVE MEASURES STUDY PROCESS

5

START

Page 6: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

6

Highway 12/East Helena

End of PPC Construction

Plant Site

Lower Lake

Upper Lake

South Plant Area

Tito Park

Smelter Dam

Prickly Pear Creek

Page 7: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

THREE INTERIM MEASURES

7

Reduce infiltration (from precipitation) leaching contaminants from soil to groundwater

Eliminate exposure to contaminated soils Prevent stormwater contact with contaminated 

soil (that then requires treatment)

Reduce infiltration (from precipitation) leaching contaminants from soil to groundwater

Eliminate exposure to contaminated soils Prevent stormwater contact with contaminated 

soil (that then requires treatment)

Evapotranspirative(ET)  Cover System IMEvapotranspirative

(ET)  Cover System IMSource Removal/

Control IMSource Removal/

Control IM

Excavate/consolidate contaminated soils under ET Cover Support wetland habitat and increase flood storage capacity lf feasible, reduce volume of soils that are a source of 

contaminant loading to groundwater 

Excavate/consolidate contaminated soils under ET Cover Support wetland habitat and increase flood storage capacity lf feasible, reduce volume of soils that are a source of 

contaminant loading to groundwater 

South Plant Hydraulic Control  

(SPHC) IM

South Plant Hydraulic Control  

(SPHC) IM Lower elevation of groundwater in south area of 

smelter to reduce the volume of groundwater flowing through heavily contaminated

Provide additional flood storage capacity and establish beneficial wetland habitat

Lower elevation of groundwater in south area of smelter to reduce the volume of groundwater flowing through heavily contaminated

Provide additional flood storage capacity and establish beneficial wetland habitat

Page 8: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

INTERIM MEASURES PURPOSE AND OBJECTIVES

IMs reduce migration of contaminants in groundwater from the former Smelter site to protect public health and the environment via Hydraulic Control – inhibit migration

Source Removal – prevent transport to surface water bodies and mass loading to groundwater

Protective Cover – reduce infiltration, prevent direct contact (human and ecological) with contaminated media, reduce costs, clean and restore surface water runoff 

IM phases implemented in 2015 and 2016 PPC Realignment materials managed within ICS 2 and Central Corridor

Remove existing unused structures (HDS Plant to remain through 2016)

Interim and Final ET Cover construction

Acid Plant removal

IMs incorporated into final remedy (Corrective Measures Study [CMS] Implementation) 8

Page 9: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

IM - WORK COMPLETED TO-DATE

ET Cover System SPHC IM Source Removal/Control

IM 2012 Construction

Air Liquide Demolition

Upper Lake Dewatering

IM 2013 Construction

Demolition Phase 1 East Bench Utility Relocations

Demolition Phase 2 PPC Temporary Bypass

IM 2014 Construction

Interim Cover System 1 Lower Lake Removal TPA Soil Removal

Final Closure of CAMU 2

IM 2015 Construction

ET West Completed PPC Realignment ‐ N & S Reaches Excavated; Channels Partly Completed

Interim Cover System 2

Portion of Central Corridor Filled

9

Page 10: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

IM – WORK PLANNED FOR 2016

10

ET Cover System SPHC IM Source Removal/Control

IM 2016 Construction Planned

Continue Demolition Complete N and S Channel Reaches of PPC Realignment

Former Acid Plant Source Removal

Complete ET East (Includes Central Corridor)

Remove Smelter Dam; Complete Middle Reach of PPC Realignment

Additional Speiss MaterialRemoval

Establish PPC Wetlands

Restore flow to PPC

Page 11: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PROPOSED FINAL SITE LAYOUT

ET Cover West  ‐ Completed 2015 ET Cover East in 2016 over:

ICS 2 Central Corridor

PPC Realignment  S and N thirds – Completed 2015 Middle portion ‐ 2016 Wetlands mitigation ‐ 2016

Source Removal IM TPA removal completed 2014 Additional Speiss removal ‐ 2016 Acid Plant Source Removal ‐ 2016

11

Page 12: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

INTERIM MEASURES CONSTRUCTION UPDATE

Page 13: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PHASE I DEMOLITION

AFTER

BEFORE

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 4/15/13COMPLETED: 7/31/13

Page 14: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PHASE I DEMOLITION

SMELTER DAM BRIDGE REPLACEMENT

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 4/15/13COMPLETED: 7/31/13

Page 15: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PHASE II DEMOLITION

DSB DEMOLITION

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 7/15/13COMPLETED: 11/30/13

Page 16: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PHASE II DEMOLITION

COAL MILL AND SODIUM BUILDING DEMOLITION

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 7/15/13COMPLETED: 11/30/13

Page 17: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC BYPASS

CONTRACTOR: CH2MSUBCONTRACTOR: HELENA SAND & GRAVELBEGIN DATE: 7/1/13COMPLETED: 12/20/13

Page 18: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

TPA/ICS 1

CONTRACTOR: CH2MSUBCONTRACTOR: HELENA SAND & GRAVELBEGIN DATE: 5/28/14COMPLETED: 12/14/14

Page 19: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

TPA/ICS 1

CONTRACTOR: CH2MSUBCONTRACTOR: HELENA SAND & GRAVELBEGIN DATE: 5/28/14COMPLETED: 12/14/14

Page 20: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

20

ICS2, ET COVER SYSTEM, PHASE 3 DEMOLITION

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 6/16/15ANTICIPATED COMPLETION: 11/30/16

Page 21: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

21

ICS2, ET COVER SYSTEM, PHASE 3 DEMOLITION

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 6/16/15ANTICIPATED COMPLETION: 11/30/16

Page 22: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

ICS2, ET COVER SYSTEM, PHASE 3 DEMOLITION

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 6/16/15ANTICIPATED COMPLETION: 11/30/16

Page 23: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

23

ICS2, ET COVER SYSTEM, PHASE 3 DEMOLITION

CONTRACTOR: CH2MSUBCONTRACTOR: ENVIROCONBEGIN DATE: 6/16/15ANTICIPATED COMPLETION: 11/30/16

Page 24: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

SPHC PPC REALIGNMENT COMPONENTS

Primary Components

• Construct PPC Temporary Bypass (done)

• Remove Smelter Dam (done)

• Remove Upper Lake Diversion and Breach Dike (done)

• Reconstruct Tito Park/Lower Lake Areas (in progress)

• Construct PPC Realignment (in progress)

24

Page 25: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

KEY DESIGN OBJECTIVES Groundwater elevations as low as possible to meet gradients and 

water interface with wetland areas. Create a sustainable creek

• Develop stable flow conditions and gradients; • Designing for low and high flows, • Adequate storage capacity and • Natural processes

Design a stable stream channel and floodplain that meets all applicable permitting requirements

Afford materials for use in other construction actions (such as ET Cover)

25

Page 26: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

DiversionDiversion

Upper Lake ComplexUpper Lake Complex

Flat Depositional ReachFlat Depositional Reach

Steep, Narrow, Slag and Bench ErosionSteep, Narrow, Slag and Bench Erosion

Smelter DamSmelter Dam

Page 27: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

CHANNEL SLOPE

3840

3860

3880

3900

3920

3940

3960

3980

‐7000 ‐6000 ‐5000 ‐4000 ‐3000 ‐2000 ‐1000 0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000 11000 12000

Elevation (ft)

Station (ft)

Prickly Pear Creek2011 Profile

Reach 1

Reach 2

Reach 3

Reach 4

Reach 5

Reach 6

East Helena

0.87%

0.29% 0.28%0.51%

0.55%0.46%

0.61%

‐‐‐W

ylieDrive ‐‐‐SmelterD

am

‐‐‐Highw

ay 12 ‐‐‐Upp

er La

ke Diversion

EAST HELENA

0.5%

Page 28: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

East Bench/Repository

Fine Subgrade

Smelter Dam

BN ROW

Pipeline

Slag Pile

TBC

Page 29: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

29

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 30: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 31: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 32: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 33: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

33

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 34: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 35: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 36: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

36

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 37: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 38: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

38

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 39: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 40: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 41: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

41

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 42: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 43: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

43

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 44: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 45: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 46: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 47: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

47

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 48: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 49: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 50: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

PPC REALIGNMENT

CONTRACTOR: PIONEER TECHNICAL SERVICESSUBCONTRACTOR: HELENA SAND AND GRAVELBEGIN DATE: 6/10/15ANTICIPATED COMPLETION: 11/30/16

Page 51: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

GROUNDWATER UPDATE

CURRENT GROUNDWATER CONDITIONS/TRENDS

2014/2015 SOURCE AREA INVESTIGATIONS

GROUNDWATER MODELING UPDATE

Page 52: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

RECENT ACTIVITIES AFFECTING GROUNDWATER CONDITIONS

ICS-1 Construction (2014)ET Cap (2015)

Plant Site Demolition(2012-2015)

Upper Lake Dewatering(November 2011)

PPC Bypass(October 2013)

Tito Park Area Removal(2014)

Wilson Ditch Abandoned (Fall 2011)

ICS-2 Construction (2015)

Upper Lake Marsh Dewatering/PPC Realignment

(2015-2016)

Prickly Pear Creek Channel Construction

(2015)

Page 53: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

ACID PLANT AREA GROUNDWATER LEVELS RELATIVE TO SOIL CONTAMINATION

Page 54: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

SELENIUM CONCENTRATION PLUMES

PS35

Page 55: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

Slide 54

PS35 is there an update to this?Park, Stephanie/MGM, 1/25/2016

Page 56: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

ARSENIC CONCENTRATION PLUMES

PS34

Page 57: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

Slide 55

PS34 Is there an update to this?Park, Stephanie/MGM, 1/25/2016

Page 58: EAST HELENA SMELTER SITE MINE DESIGN ......EAST HELENA SMELTER SITE MINE DESIGN, OPERATIONS & CLOSURE CONFERENCE MAY 4, 2016 Montana Environmental Trust Group Trustee of the Montana

SUMMARY OF GROUNDWATER CONDITIONS

Groundwater and surface water monitoring conducted seasonally to document current hydrologic conditions and trends, monitor residential well water quality, and support project planning and remedial design.

Groundwater levels on site have declined from 1 to 2 feet in east (beneath slag pile), to up to 10 feet on west Plant Site.

Contaminant concentrations in primary sources areas, West Se Source Area and North Plant Arsenic Source Area, have decreased by more than 75% in some areas. Close correlation with GW levels indicates reductions due at least in part to SPHC IM.

Some decreases in contaminant concentrations evident immediately downgradient of site, but more time required before significant downgradient reductions realized.

Future monitoring to focus on GW remedy effectiveness to determine what additional actions may be necessary.