EAST LINK EXTENSION
CENTRAL BELLEVUE CONSTRUCTION OPEN HOUSE
The purpose of tonight’s meeting is to provide:• An overview of the construction schedule, sequence and
phasing of work on the portion of East Link comprised of the East Main, Bellevue Downtown, Wilburton and Spring District/120th Stations.
• A chance to talk with the central Bellevue project team and meet the Contractor that will build the central Bellevue portion of the East Link project.
Agenda5-7 p.m. Open House
Meet with project staff and review information about the construction schedule, sequence and phasing.
5:30 p.m. Presentation
7 p.m. Meeting adjourns
5/17
EAST LINK EXTENSION
LIGHT RAIL ALIGNMENT
Length: 14 miles
Ride times:
• Mercer Island to University of Washington: 20 minutes
• East Main to Westlake: 21 minutes
• Redmond Technology Center to Bellevue Downtown: 10 minutes
Rider projection: About 50,000 riders will use East Link every day by 2030
Budget: $2.8 billion (2010 $)
Start of service: Targeted 2023
Lake Washington
JudkinsPark
520
23rd
Ave
S
Rainier Ave S
80th
Ave
SE
77th
Ave
SE
152n
d Av
e N
E
NE 6th St
NE 40th
NE 8th St
Main St
P
PP
P
MercerIsland
South Bellevue
East Main
BellevueDowntown
Wilburton
Spring District/120th
Bel-Red/130th
OverlakeVillage
Redmond Technology Center
Intl District/Chinatown
Testing and pre-operations
Targeted 2022
Heavy civil construction
2016-2022
Planning and environmental review
Final design Start of advanced utility relocation
2006-2011 2011-2015 2015 Targeted 2023
East Link in service
5/17
EAST LINK EXTENSION
CENTRAL BELLEVUE OVERVIEW
Travel times• East Main to University of
Washington Station: 28 minutes
• Bellevue Downtown to Westlake Station: 24 minutes
• Wilburton to Redmond Technology Center Station: 9 minutes
• Spring District/120th to Stadium Station: 30 minutes
Highlights:• Four stations including the East Main,
Bellevue Downtown, Wilburton and Spring District/120th stations.
• Nearly two miles of new light rail including at-grade track, track within a tunnel and track on an elevated structure, which includes the segment that will allow light rail to cross over I-405.
5/17
EAST LINK EXTENSION
LIGHT RAIL CONSTRUCTION IN CENTRAL BELLEVUE
Main St
NE 4th St
NE 6th St
Downtown Park
Lake Bellevue
Wilburton Hill Park
NE 8th St NE 8th St
NE Bel-Red RdNE 12th St
NE 12th St108th Ave SE
112th Ave SE
116th Ave SE
124th Ave SE
120th Ave SE
Bellevue Way
56
43
2
1
Spring District/120th
Wilburton
Bellevue Downtown
East Main
The Central Bellevue portion of the project breaks construction into six distinct areas:
• Area 1: East Main Station
• Area 2: South tunnel portal and downtown Bellevue tunnel
• Area 3: North tunnel portal, City Hall parking garage and Bellevue Downtown Station area
• Area 4: Elevated light rail structure and Wilburton Station area
• Area 5: At-grade track area near NE 12th St
• Area 6: Spring District/120th Station area Map keyStationSurface routeTunnel routeElevated routeRetained cut/fill
5/17
EAST LINK EXTENSION
1East Main
AREA 1: EAST MAIN STATION
Approximate construction scheduleSite preparation, clearing and demolition of structures
Utility work
Construction of infrastructure, East Main Station, track and amenities
Light rail systems installation, testing and certifications
Light rail stations open and service begins
2017 2018 2019 2020 2021 2022 2023
Key construction elements• Structure demolition • East Main Station• New crosswalk on 112th Avenue SE
Map keyStationSurface routeTunnel route
Typical work hours: Monday-Friday, 7 am-6 pm
Main St
SE 2nd St
SE 4th St
112th Ave SE
110th Ave SE
108th Ave SE
5/17
EAST LINK EXTENSION
2Downtown
Bellevue tunnel
(currently under construction)
Bellevue Downtown
AREA 2: SOUTH TUNNEL PORTAL AND DOWNTOWN BELLEVUE TUNNEL
2017 2018 2019 2020 2021 2022 2023
Typical work hours: Monday-Friday, 7 am-6 pm
Approximate construction scheduleDemolition of temporary sound wall
Utility work
Construction of infrastructure and amenities
Light rail systems installation, testing and certifications
Light rail stations open and service begins
Main St
NE 4th St
NE 2nd St
112th Ave SE
Map keyStationSurface routeTunnel routeElevated route
Key construction elements• Tunnel finishes • Traction power substation • New, two-acre Main Street Park
at the south tunnel portal
5/17
EAST LINK EXTENSION
AREA 3: NORTH TUNNEL PORTAL, CITY HALL AND THE BELLEVUE DOWNTOWN STATION
North tunnel portal construction – traffic controlThis summer, Sound Transit will begin a long-term closure of a portion of 110th Avenue NE between NE 4th and NE 6th streets in order to construct the north tunnel portal near Bellevue City Hall.
As early as this August, the closure on 110th Avenue NE will begin and occur in multiple phases:
• Phase 1 (approximately Summer 2017 – Spring 2018): scheduled to last approximately nine months, phase 1 will require the closure of all lanes on 110th Avenue in the work area (illustrated in the graphic) from NE 6th Street to just north of the entrance to the City Center garage.
• Phase 2 (approximately Spring 2018 – Winter 2018): one lane of traffic will be reopened in both the north and southbound direction.
• Phase 3 (approximately Winter 2018 – Spring 2019): phase 3 will require a full closure of all lanes on 110th Avenue in the work area (illustrated in the graphic) as utilities are reinstalled and the roadway is restored.
2017 2018 2019 2020 2021 2022 2023Approximate construction scheduleSite preparation, clearing and demolition of select City Hall infrastructure
Utility work
Construction of infrastructure, Bellevue Downtown Station, reconfigured Bellevue City Hall garage and amenities
Construction of north tunnel portal
Light rail systems installation, testing and certifications
Light rail stations open and service begins
NE 4th St
NE 6th St
NE 8th St
108th Ave SE
3Bellevue Downtown
Typical work hours: Monday-Friday, 7 am-6 pm
110th Ave SE
112th Ave SE
Map keyStationTunnel routeElevated route
Key construction elements• North tunnel portal • Bellevue Downtown Station • Reconfigured Bellevue City Hall
plaza and garage • New crosswalk on 110th Avenue NE
5/17
EAST LINK EXTENSION
4 Wilburton
Bellevue Downtown
AREA 4: ELEVATED LIGHT RAIL STRUCTURE AND WILBURTON STATION
Elevated guideway constructionNearly 40 columns will be constructed to support the elevated guideway that will cross I-405 and transport riders between the Bellevue Downtown and Wilburton stations.
Typical elevated guideway construction consists of:
1. Drilling shafts for column foundations
2. Installing columns
3. Building the guideway, bridge spans and rail
A long-span aerial guideway will be constructed to cross I-405. This work will require nighttime construction to build and remove temporary construction support and is anticipated to commence in mid-2018. After completion of the temporary construction support, work will resume during daytime hours. Additional night work will be necessary to set precast girders for the NE 8th Street crossing.
2017 2018 2019 2020 2021 2022 2023Approximate construction scheduleSite preparation, clearing and demolition of structures
Utility work
Construction of infrastructure, Wilburton Station, elevated track and amenities
Light rail systems installation, testing and certifications
Light rail stations open and service begins
Typical work hours: Monday-Friday, 7 am-6 pm
Work in area 4 will require night and weekend construction during select time periods
Lake Bellevue
NE 8th St
NE 10th St
NE 6th St
NE 12th St
116th Ave SE
120th Ave SE
112th Ave SE
110th Ave SE
Map keyStationSurface routeTunnel routeElevated routeRetained cut/fill
Key construction elements• Structure demolition • Elevated light rail construction
including a long-span over I-405 • Sturtevant Creek pedestrian bridge • Wilburton Station
5/17
EAST LINK EXTENSION
AREA 5: AT-GRADE TRACK NEAR NE 12TH ST
2017 2018 2019 2020 2021 2022 2023
Typical work hours: Monday-Friday, 7 am-6 pm
Approximate construction scheduleSite preparation, clearing and demolition of existing BNSF track
Utility work
Construction of infrastructure, track and amenities
Light rail systems installation, testing and certifications
Light rail stations open and service begins
NE 12th St
120th Ave SE
116th Ave SE
5Spring District/120th
Key construction elements• Traction power substation• Coordination with City of Bellevue’s
Spring Boulevard project• Interface with Sound Transit’s
Operations and Maintenance Facility: East projectMap key
StationSurface routeTunnel routeElevated routeRetained cut/fill
5/17
EAST LINK EXTENSION
AREA 6: SPRING DISTRICT/120TH STATION
Typical work hours: Monday-Friday, 7 am-6 pm
2017 2018 2019 2020 2021 2022 2023Approximate construction schedule120th Avenue overpass (City of Bellevue project)
124th Avenue overpass (City of Bellevue project)
Site preparation, clearing and hardscape demolition
Utility work
Construction of infrastructure, Spring District/120th Station, track and amenities
Light rail systems installation, testing and certifications
Light rail stations open and service begins
6
Spring District/120th
Lake Bellevue
NE Bel-Red RdNE 12th St
124th Ave SE
120th Ave SE
Key construction elements• Spring District/120th Station • Coordination with City of Bellevue’s
120th and 124th Avenue overpass projectsMap key
StationSurface routeTunnel routeElevated routeRetained cut/fill
5/17
EAST LINK EXTENSION
EAST MAIN STATION
SOUTH PLAZA VIEW
LANDSCAPE PLAN
EAST MAIN STATION AREA
5/17
EAST LINK EXTENSION
BELLEVUE DOWNTOWN STATION
AERIAL VIEW
EAST ENTRANCE VIEW 5/17
EAST LINK EXTENSION
WILBURTON STATION
STATION VIEW LOOKING NORTHWEST
WILBURTON STATION AREA PLATFORM VIEW LOOKING SOUTH
5/17
EAST LINK EXTENSION
SPRING DISTRICT/120TH STATION
PLATFORM VIEW LOOKING WEST
SITE PLANCITY OF BELLEVUE - 2009 PEDESTRIAN & BICYCLETRANSPORTATION PLAN
LEGEND
BUS ROUTE
BICYCLE LANE
PROPOSED NEW SIDEWALKS
OFF STREET PATH
BICYCLE ROUTE
LIGHT RAIL TRACKS
STATION
PATRON CATCHMENTAREA
FUTURE DEVELOPMENT
120T
H A
VE N
E
124T
H A
VE N
E
NE 15TH ST (FUTURE)
NE 16TH ST (FUTURE)
1/4 MILE RADIUS
120TH AVE NE STATION
EAST LINKNEIGHBORHOOD CONTEXT PLAN
SPRING DISTRICT/120TH STATION STATION AREA
5/17
EAST LINK EXTENSION
SOUND TRANSIT COMMUNITY OUTREACH
Contact us
tel: 206-398-5465
email: [email protected]
web: soundtransit.org/eastlink
24-hour Construction Hotline: 1-888-298-2395For issues that need immediate attention after normal business hours
Community Outreach’s mission is to represent Sound Transit’s interests in the community, and the community’s interest in Sound Transit. During construction, it is our job to keep community members informed of major construction activities and project progress. We are your point of contact for Sound Transit’s projects.
Good Neighbor Commitments:• Provide advanced notification of work activities.• Maintain business and residential access.• Maintain a clean work site.• Minimize noise, dust and debris.• Provide wayfinding and signage.• 24-hour construction hotline.