EAST LINK EXTENSION CENTRAL BELLEVUE CONSTRUCTION OPEN HOUSE The purpose of tonight’s meeting is to provide: • An overview of the construction schedule, sequence and phasing of work on the portion of East Link comprised of the East Main, Bellevue Downtown, Wilburton and Spring District/120th Stations. • A chance to talk with the central Bellevue project team and meet the Contractor that will build the central Bellevue portion of the East Link project. Agenda 5-7 p.m. Open House Meet with project staff and review information about the construction schedule, sequence and phasing. 5:30 p.m. Presentation 7 p.m. Meeting adjourns 5/ 17

EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

CENTRAL BELLEVUE CONSTRUCTION OPEN HOUSE

The purpose of tonight’s meeting is to provide:• An overview of the construction schedule, sequence and

phasing of work on the portion of East Link comprised of the East Main, Bellevue Downtown, Wilburton and Spring District/120th Stations.

• A chance to talk with the central Bellevue project team and meet the Contractor that will build the central Bellevue portion of the East Link project.

Agenda5-7 p.m. Open House

Meet with project staff and review information about the construction schedule, sequence and phasing.

5:30 p.m. Presentation

7 p.m. Meeting adjourns

5/17

Page 2: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

LIGHT RAIL ALIGNMENT

Length: 14 miles

Ride times:

• Mercer Island to University of Washington: 20 minutes

• East Main to Westlake: 21 minutes

• Redmond Technology Center to Bellevue Downtown: 10 minutes

Rider projection: About 50,000 riders will use East Link every day by 2030

Budget: $2.8 billion (2010 $)

Start of service: Targeted 2023

Lake Washington

JudkinsPark

520

23rd

Ave

S

Rainier Ave S

80th

Ave

SE

77th

Ave

SE

152n

d Av

e N

E

NE 6th St

NE 40th

NE 8th St

Main St

P

PP

P

MercerIsland

South Bellevue

East Main

BellevueDowntown

Wilburton

Spring District/120th

Bel-Red/130th

OverlakeVillage

Redmond Technology Center

Intl District/Chinatown

Testing and pre-operations

Targeted 2022

Heavy civil construction

2016-2022

Planning and environmental review

Final design Start of advanced utility relocation

2006-2011 2011-2015 2015 Targeted 2023

East Link in service

5/17

Page 3: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

CENTRAL BELLEVUE OVERVIEW

Travel times• East Main to University of

Washington Station: 28 minutes

• Bellevue Downtown to Westlake Station: 24 minutes

• Wilburton to Redmond Technology Center Station: 9 minutes

• Spring District/120th to Stadium Station: 30 minutes

Highlights:• Four stations including the East Main,

Bellevue Downtown, Wilburton and Spring District/120th stations.

• Nearly two miles of new light rail including at-grade track, track within a tunnel and track on an elevated structure, which includes the segment that will allow light rail to cross over I-405.

5/17

Page 4: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

LIGHT RAIL CONSTRUCTION IN CENTRAL BELLEVUE

Main St

NE 4th St

NE 6th St

Downtown Park

Lake Bellevue

Wilburton Hill Park

NE 8th St NE 8th St

NE Bel-Red RdNE 12th St

NE 12th St108th Ave SE

112th Ave SE

116th Ave SE

124th Ave SE

120th Ave SE

Bellevue Way

56

43

2

1

Spring District/120th

Wilburton

Bellevue Downtown

East Main

The Central Bellevue portion of the project breaks construction into six distinct areas:

• Area 1: East Main Station

• Area 2: South tunnel portal and downtown Bellevue tunnel

• Area 3: North tunnel portal, City Hall parking garage and Bellevue Downtown Station area

• Area 4: Elevated light rail structure and Wilburton Station area

• Area 5: At-grade track area near NE 12th St

• Area 6: Spring District/120th Station area Map keyStationSurface routeTunnel routeElevated routeRetained cut/fill

5/17

Page 5: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

1East Main

AREA 1: EAST MAIN STATION

Approximate construction scheduleSite preparation, clearing and demolition of structures

Utility work

Construction of infrastructure, East Main Station, track and amenities

Light rail systems installation, testing and certifications

Light rail stations open and service begins

2017 2018 2019 2020 2021 2022 2023

Key construction elements• Structure demolition • East Main Station• New crosswalk on 112th Avenue SE

Map keyStationSurface routeTunnel route

Typical work hours: Monday-Friday, 7 am-6 pm

Main St

SE 2nd St

SE 4th St

112th Ave SE

110th Ave SE

108th Ave SE

5/17

Page 6: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

2Downtown

Bellevue tunnel

(currently under construction)

Bellevue Downtown

AREA 2: SOUTH TUNNEL PORTAL AND DOWNTOWN BELLEVUE TUNNEL

2017 2018 2019 2020 2021 2022 2023

Typical work hours: Monday-Friday, 7 am-6 pm

Approximate construction scheduleDemolition of temporary sound wall

Utility work

Construction of infrastructure and amenities

Light rail systems installation, testing and certifications

Light rail stations open and service begins

Main St

NE 4th St

NE 2nd St

112th Ave SE

Map keyStationSurface routeTunnel routeElevated route

Key construction elements• Tunnel finishes • Traction power substation • New, two-acre Main Street Park

at the south tunnel portal

5/17

Page 7: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

AREA 3: NORTH TUNNEL PORTAL, CITY HALL AND THE BELLEVUE DOWNTOWN STATION

North tunnel portal construction – traffic controlThis summer, Sound Transit will begin a long-term closure of a portion of 110th Avenue NE between NE 4th and NE 6th streets in order to construct the north tunnel portal near Bellevue City Hall.

As early as this August, the closure on 110th Avenue NE will begin and occur in multiple phases:

• Phase 1 (approximately Summer 2017 – Spring 2018): scheduled to last approximately nine months, phase 1 will require the closure of all lanes on 110th Avenue in the work area (illustrated in the graphic) from NE 6th Street to just north of the entrance to the City Center garage.

• Phase 2 (approximately Spring 2018 – Winter 2018): one lane of traffic will be reopened in both the north and southbound direction.

• Phase 3 (approximately Winter 2018 – Spring 2019): phase 3 will require a full closure of all lanes on 110th Avenue in the work area (illustrated in the graphic) as utilities are reinstalled and the roadway is restored.

2017 2018 2019 2020 2021 2022 2023Approximate construction scheduleSite preparation, clearing and demolition of select City Hall infrastructure

Utility work

Construction of infrastructure, Bellevue Downtown Station, reconfigured Bellevue City Hall garage and amenities

Construction of north tunnel portal

Light rail systems installation, testing and certifications

Light rail stations open and service begins

NE 4th St

NE 6th St

NE 8th St

108th Ave SE

3Bellevue Downtown

Typical work hours: Monday-Friday, 7 am-6 pm

110th Ave SE

112th Ave SE

Map keyStationTunnel routeElevated route

Key construction elements• North tunnel portal • Bellevue Downtown Station • Reconfigured Bellevue City Hall

plaza and garage • New crosswalk on 110th Avenue NE

5/17

Page 8: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

4 Wilburton

Bellevue Downtown

AREA 4: ELEVATED LIGHT RAIL STRUCTURE AND WILBURTON STATION

Elevated guideway constructionNearly 40 columns will be constructed to support the elevated guideway that will cross I-405 and transport riders between the Bellevue Downtown and Wilburton stations.

Typical elevated guideway construction consists of:

1. Drilling shafts for column foundations

2. Installing columns

3. Building the guideway, bridge spans and rail

A long-span aerial guideway will be constructed to cross I-405. This work will require nighttime construction to build and remove temporary construction support and is anticipated to commence in mid-2018. After completion of the temporary construction support, work will resume during daytime hours. Additional night work will be necessary to set precast girders for the NE 8th Street crossing.

2017 2018 2019 2020 2021 2022 2023Approximate construction scheduleSite preparation, clearing and demolition of structures

Utility work

Construction of infrastructure, Wilburton Station, elevated track and amenities

Light rail systems installation, testing and certifications

Light rail stations open and service begins

Typical work hours: Monday-Friday, 7 am-6 pm

Work in area 4 will require night and weekend construction during select time periods

Lake Bellevue

NE 8th St

NE 10th St

NE 6th St

NE 12th St

116th Ave SE

120th Ave SE

112th Ave SE

110th Ave SE

Map keyStationSurface routeTunnel routeElevated routeRetained cut/fill

Key construction elements• Structure demolition • Elevated light rail construction

including a long-span over I-405 • Sturtevant Creek pedestrian bridge • Wilburton Station

5/17

Page 9: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

AREA 5: AT-GRADE TRACK NEAR NE 12TH ST

2017 2018 2019 2020 2021 2022 2023

Typical work hours: Monday-Friday, 7 am-6 pm

Approximate construction scheduleSite preparation, clearing and demolition of existing BNSF track

Utility work

Construction of infrastructure, track and amenities

Light rail systems installation, testing and certifications

Light rail stations open and service begins

NE 12th St

120th Ave SE

116th Ave SE

5Spring District/120th

Key construction elements• Traction power substation• Coordination with City of Bellevue’s

Spring Boulevard project• Interface with Sound Transit’s

Operations and Maintenance Facility: East projectMap key

StationSurface routeTunnel routeElevated routeRetained cut/fill

5/17

Page 10: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

AREA 6: SPRING DISTRICT/120TH STATION

Typical work hours: Monday-Friday, 7 am-6 pm

2017 2018 2019 2020 2021 2022 2023Approximate construction schedule120th Avenue overpass (City of Bellevue project)

124th Avenue overpass (City of Bellevue project)

Site preparation, clearing and hardscape demolition

Utility work

Construction of infrastructure, Spring District/120th Station, track and amenities

Light rail systems installation, testing and certifications

Light rail stations open and service begins

6

Spring District/120th

Lake Bellevue

NE Bel-Red RdNE 12th St

124th Ave SE

120th Ave SE

Key construction elements• Spring District/120th Station • Coordination with City of Bellevue’s

120th and 124th Avenue overpass projectsMap key

StationSurface routeTunnel routeElevated routeRetained cut/fill

5/17

Page 11: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

EAST MAIN STATION

SOUTH PLAZA VIEW

LANDSCAPE PLAN

EAST MAIN STATION AREA

5/17

Page 12: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

BELLEVUE DOWNTOWN STATION

AERIAL VIEW

EAST ENTRANCE VIEW 5/17

Page 13: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

WILBURTON STATION

STATION VIEW LOOKING NORTHWEST

WILBURTON STATION AREA PLATFORM VIEW LOOKING SOUTH

5/17

Page 14: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

SPRING DISTRICT/120TH STATION

PLATFORM VIEW LOOKING WEST

SITE PLANCITY OF BELLEVUE - 2009 PEDESTRIAN & BICYCLETRANSPORTATION PLAN

LEGEND

BUS ROUTE

BICYCLE LANE

PROPOSED NEW SIDEWALKS

OFF STREET PATH

BICYCLE ROUTE

LIGHT RAIL TRACKS

STATION

PATRON CATCHMENTAREA

FUTURE DEVELOPMENT

120T

H A

VE N

E

124T

H A

VE N

E

NE 15TH ST (FUTURE)

NE 16TH ST (FUTURE)

1/4 MILE RADIUS

120TH AVE NE STATION

EAST LINKNEIGHBORHOOD CONTEXT PLAN

SPRING DISTRICT/120TH STATION STATION AREA

5/17

Page 15: EAST LINK ETENSION · Highlights: • Four stations including the East Main, Bellevue Downtown, Wilburton and Spring District/120th stations. • Nearly two miles of new light rail

EAST LINK EXTENSION

SOUND TRANSIT COMMUNITY OUTREACH

Contact us

tel: 206-398-5465

email: [email protected]

web: soundtransit.org/eastlink

24-hour Construction Hotline: 1-888-298-2395For issues that need immediate attention after normal business hours

Community Outreach’s mission is to represent Sound Transit’s interests in the community, and the community’s interest in Sound Transit. During construction, it is our job to keep community members informed of major construction activities and project progress. We are your point of contact for Sound Transit’s projects.

Good Neighbor Commitments:• Provide advanced notification of work activities.• Maintain business and residential access.• Maintain a clean work site.• Minimize noise, dust and debris.• Provide wayfinding and signage.• 24-hour construction hotline.