This is a slideshow presentation shown to the Bellevue City Council on Sept. 22, 2014, detailing Sound Transit's tentative traffic maintenance plan when East Link light rail construction begins in the city.

Citation preview

  • East Link Monthly Project Update

    Bellevue City Council

    September 22, 2014

    1

  • Tonights Agenda

    Estimated Project Schedule

    Project Permitting

    Maintenance of Traffic During Construction

    Operation and Maintenance Satellite Facility (OMSF) Update

    2

  • East Link Estimated Schedule

    3

    Early Nov 2014 South Bellevue Final Design Open House

    Dec 2014 East Link Baseline Milestone

    Q2 2015 Downtown Final Design Open House

    Q4 2015 Overlake-Redmond Final Design Open House

    2015 Estimated Construction Early Work - Utility Relocation 136th Pl NE (OPL) - Utility Relocation 112th Ave NE (City)

    Early Q3 2015

    Late Q1 2016

    Estimated Construction - Tunnel (E330)

    Q4 2015 Q4 2016 - South Bellevue (E320)

    Q1 2016 Q1 2017 - Bel Red (E340)

    Q1 2016 Q2 2016 - Redmond-Overlake (E360 Design-Build)

    Q2 2017 - Downtown (E335 GC/CM)

  • Light Rail Permitting

    Submitted Permits

    Shoreline Substantial Development

    Shoreline Variance

    Bel-Red Design and Mitigation

    South Bellevue Design and Mitigation

    4

  • Light Rail Permitting Citizen Advisory Committee (CAC)

    Bi-monthly meetings

    Pre-development review advisory documents All segments

    Final advisory document pending for Bel-Red

    Currently reviewing South Bellevue

    Final advisory document for South Bellevue end of 2014, early 2015

    Downtown/East Main and 120th Station permits submitted later this year

    5

  • Maintenance of Traffic

    Begun meeting with interested community groups and organizations

    Engaging in high level discussion of current construction traffic management concepts

    Understand additional community concerns

    6

  • DRAFT 09/19/2014 7

    SR 520

    I-90

    14

    8th

    Ave

    NE

    112th Ave SE (SE 15th to SE 8th)

    Bellevue Way

    112th Ave SE (SE 8th to Main St)

    I-405

    110th Ave NE

    NE 8th St & 116th Ave NE

    Bel-Red Overlake/Redmond

    NE 8th St

    16

    4th

    Ave

    NE

    Maintenance of Traffic

  • Bellevue Way E320

    Goal: Maintain 2 lanes of traffic in peak direction

    Park & Ride closed during construction (approximately 48 to 60 Months)

    1 Lane each direction with a reversible lane (approximately 36 to 48 Months)

    12 to 15 weekend full closures

    I-90 westbound night closures

    8

    I-90

    DRAFT 09/19/2014

    Maintenance of Traffic

  • 112th Ave SE (SE 15th to Se 8th) E320

    Goal: Minimize traffic diversion to 108th Ave SE and Bellevue Way

    Maintain 1 lane each direction during construction

    Temporary road 1 Lane each direction (18 months)

    112th Ave SE (SE 8th to Main St) E320

    Goal: Minimize construction truck traffic

    Off-peak lane closures

    9

    11

    2th

    Ave

    SE

    Main St.

    Be

    llevu

    e W

    ay

    DRAFT 09/19/2014

    Maintenance of Traffic

  • 110 Ave NE E 330/E335 Goal: Minimize impact to business access Two 1-month full closure of 110th Ave NE

    south of the intersection Two 3-month lane closures (NE 4th to NE

    6th (considering total closure between City Center 2 and NE 6th)

    SB lanes from NE 2nd to NE 3rd closed for duration of construction

    NE 2nd Pl closed for duration of construction

    I-405 E335 Overnight HOV ramp closures Overnight lane closures NE 8th St & 116th Ave NE E335 Goal: Minimize impact to business access Overnight street closures Off-peak lane closures

    10

    I-4

    05

    Main St

    NE 8th St

    11

    6th

    Ave

    NE

    DRAFT 09/19/2014

    Maintenance of Traffic

  • Goal: Minimize impact to businesses Lane closures on NE 20th, 130th, 132nd, 136th, and NE 16th (Spring Blvd.) Intersection closure @ NE 20th/136th PL NE, NE 16th St (Spring Blvd.)/132nd Ave. NE

    and NE 16th St (Spring Blvd.)/136th PL NE Overnight closures at various locations along NE 16th St (Spring Blvd.) Full closure on NE 16th St (Spring Blvd.) from 132nd to 136th PL NE (6 to 9 Months) Full closure on 136th Pl NE from NE 16th St (Spring Blvd.) to NE 20th St (One Month)

    Advanced Utility Relocation (4 to 6 weeks) 11

    NE 20th St

    13

    0th

    Ave

    NE

    13

    2n

    d A

    ve N

    E

    NE Spring Blvd

    Bel-Red E340

    DRAFT 09/19/2014

    Maintenance of Traffic

  • 12

    Overlake/Redmond E360

    Overnight Street/Lane Closures

    NE 24th St

    14

    8th

    Ave

    NE

    14

    0th

    Ave

    NE

    NE 20th St

    DRAFT 09/19/2014

    Maintenance of Traffic

  • OMSF Update

    Sound Transit Board action July 24, 2014

    BNSF site identified as preferred

    Direction to Sound Transit staff

    Design charrette September 5, 2014

    1st Stakeholder workshop September 18, 2014

    2nd Stakeholder workshop October 9, 2014

    13

  • Questions

    14