    The purpose of this procedure is to standardize request for

    Customer approval for any items initiated by FieldEngineering or any project department.

    The scope of this procedure covers request for approval of

    MMG supplied permanent materials, consumables which

    form part of the plant components, e.g. welding rods, sand,

    aggregates, backfills, grouting materials, etc.. This may

    include product data, technical literatures, brochures,

    specification and /or samples product.

    The scope also covers request for approval of field

    generated construction procedures, detail drawings, as built

    drawings, and other items which requires the approval of the

    Customer before it is purchased or implemented.

  • 7/30/2019 END-3-014 Request for Approval

    3/10

    CUSTOMER

    Any person authorized by the Customer, quoted in the Contract

    Document.

    REFERENCES :

    Document Control Procedure No. END-3-010

    PROJECT MANAGER

    Review and approved all outgoing Request for Approval Form No.

    END-4-014B

    FIELD ENGINEERING MANAGER

    SUPERINTENDENT / SUPERVISOR OR HEADCheck all Request for Approval initiated by Engineering and those

    request for approval initiated by other project department before it

    is forwarded to the Project Manager for approval.

  • 7/30/2019 END-3-014 Request for Approval

    4/10

    (continuation)

    OTHER PROJECT DEPARTMENT HEADS

    Check and review all Request for Approval (initiated by

    each concerned discipline department) and forward to the

    Field Engineering Manager/Superintendent/Supervisor or

    Head before it is forwarded to the Project Manager for

    approval.

    FIELD ENGINEER

    Initiates and prepares Request for Approval originated by

    Field Engineering Support Group.

    DOCUMENT CONTROLLER

    Record and control all outgoing and incoming Request for

    Approval and facilitate distribution.

  • 7/30/2019 END-3-014 Request for Approval

    5/10

    Requesting Department shall prepare the Request for Approval

    Form No. END-4-014B for proposed construction procedures;

    product data, technical literature, specifications, brochures; detaildrawings, as-built drawings, product samples and the like.

    Request for Approval is then forwarded to the appropriate

    Manager / Superintendent / Supervisor or Head for review.

    The Manager/Superintendent/Supervisor or Head shall sign the

    space provided for Department Head and indicate the date whensigned to confirmed completion of his review.

    The Request for Approval is then forwarded to the Project

    Manager for final review and approval signature.

    The Document Controller prepares Transmittal Form No. QAD-4-

    202 assigns a control number which is recorded in the Request forApproval Control Log Form No. END-4-014C. The approved Request

    for Approval is then forwarded to the Customer.

  • 7/30/2019 END-3-014 Request for Approval

    6/10

    (continuation)

    The Customer will make a review of the request and

    transmit back their approval / disapproval and / orcomments.

    Any comments on the Request for Approval form made

    by the Customer will be considered by MMG for revision,

    action and re-submission to the Customer for further

    review.

    Received approved / disapproved Request for Approval

    from the Customer will be distributed for implementation to

    the concerned originator of the Request for Approval. The

    Document Controller will reproduce a copy or copies for

    distribution and keep the original copy of Form No. END-4-

    014B for file record. The Document Controller shall update

    his record for this particular Request for Approval number

    on Form No. END-4-014C.

  • 7/30/2019 END-3-014 Request for Approval

    7/10

    PROJECT FIELD ENGINEERING

    TASK TITLE

    REQUEST FOR APPROVAL

    (END-3-014)

    SUPERVISING / FIELD ENGINEER

    Prepare request for Approval

    (END-4-014B)

    Endorse to Project Managers forhis signature

    Approved / Disapproved RFAdistributed for implementation /

    information to the originator

    (END-4-014)

    Make revision, action, re-submission to Customer for further

    review / approval

    Assign Control Number andtransmit RFA to Customer

    (QAD-4-202 / END-4-014C)

    START

    SUPERVISING / FIELD ENGINEERS

    SUPERVISING / FIELD ENGINEER

    PROJECT DOCUMENT CONTROLLER

    A1

    End

    CUSTOMERREVIEWS

    RFA

    SUPERVISING / FIELD ENGINEER

  • 7/30/2019 END-3-014 Request for Approval

    8/10

    PROCEDURE FOR REQUEST FOR APPROVAL

    Procedure covers Request for Approval (RFA) of MMG supplied

    materials (product data, technical literature, specifications,

    brochures, product samples), consumables which form part of the

    plant components, e.g., sand, aggregates, backfills, grouting

    materials, construction, procedures, detail drawing generated at

    site, as-built drawings and etc

    REQUEST FOR APPROVAL RAISED BY FIELD ENGINEERING

    Prepare Request for Approval (RFA) Form No. END-4-014B for

    material product data, specifications, brochures, technical

    literature, product samples, product sample for MMG supplied

    materials, which needs prior approval by Customer or Customer

    Representative before it is purchased.

    RFA is then forwarded to the appropriate Manager / Superintendent /

    Field Supervisor for review. Then it is endorsed by the ProjectManager.

  • 7/30/2019 END-3-014 Request for Approval

    9/10

    REQUEST FOR APPROVAL RAISED BY FIELD ENGINEERING

    (continuation)

    Transmit the RFA to the Customer or Customer

    Representative using the transmittal Form QAD-4-202 and

    assign a control number which is recorded in Form END-4-

    014C Request for Approval Control Log

    Customer will review the RFA and transmit back their

    approval / disapproval and / or comments.Any comments on the RFA made by the Customer will be

    considered by MMG for revision, action and re-submission to

    the Customer for further review / approval.

    Request for Approval from the Customer will be

    reproduced and distributed for implementation or informationto the concerned originator of the Request for Approval.

    Update END-4-014C.