Internal Office Memorandum II
Engineers Site Visit on 08.07.10
Name of Work: Four Laning & Strengthening of Existing 2 lanes from Km 120.000
to 160.000 of Madurai - Kanyakumari Section of NH-7 in Tamilnadu.
Package: NS-42/TN & NS-43/TN
Subject: Site Inspection of the Engineer of Package: NS-42/TN & NS-43/TN
Reference: Internal Office memorandum I, Dated: 25.06. 2010
The Engineer Mr.Avadesh Sing had visited the site on 08.07.2010 along with the
Contractors representative and SC team. The status of the project and the Engineers
instructions are as follows:-
Package: NS-42/TN
Project Status as on 07.07.10
Physical Progress: 98.41 %
Financial progress: 95.34 % (221.628 Crores; value of work done only)
Compliance of Engineers Instruction
In view of issuing ToC, the Engineer during his previous visit instructed the Contractor to finish
the following works in all aspects. The compliance report of the same as follows:-
Sl.No. Instruction of the Engineer Action Taken Remarks
1
Construction of Median Kerb
and Painting to be completed
(apart from some locations
where there is Public agitation
for median openings)
Completed
2All the Crash Barriers are to be
painted
Completed
3 Reflectors are to be fixed on all Completed
8/9/2019 Engineer's Visit on 08[2].07.10
2/3
the RCC handrail
5
The cut slopes of the hill are to
be trimmed properly by means
of power hammer from top and
bottom of the hill. All loosepockets and hanging cliffs are
to be removed. Thereafter, the
cut slope is to be inspected by
a Geotechnical Expert to be
deputed by the Contractor to
confirm its stability.
Compiled.
Proposal for the slope
protection treatmentshall be submitted by
the Contractor through
the Geotech Expert is
expected by 25th
July,2010.
6 The rehabilitation work of the
existing bridges like hand rail
repairing, removal and relaying
of wearing course and guniting
of the exposed reinforcement
etc., is to be completed.
Removal and relaying
of wearing course and
hand rail fixing has
been completed.
Footpath pavement
concrete and guniting
of the exposed
reinforcement
pending.
7 All the drainage spouts on the
bridges to be completed in view
of pedestrian safety
Drainage spout work
has been completed
except the connecting
pipes at flyoverbeneath the soffit.
8 W-Beam Crash Barrier to be
properly merged with Concrete
Crash Barrier in approaches to
some structures.
Completed
9 All chevron boards are to be
fixed.
Fixed as per the approve list
Package: NS-43/TN :-
The Engineer had inspected package NS-43/TN also. As per Engineers instruction, inspection
of NS-43 project is in progress to assess the work to be carried out by the Contractor before
issuing work completion certificate (after DLP).
8/9/2019 Engineer's Visit on 08[2].07.10
3/3
Date: 13.07.10 Virendra Mittal
Place: Tirunelveli Acting Resident
Engineer
NS-42/TN - Tirunelveli