Engineer's Visit on 08[2].07.10

Embed Size (px)

Citation preview

  • 8/9/2019 Engineer's Visit on 08[2].07.10

    1/3

    Internal Office Memorandum II

    Engineers Site Visit on 08.07.10

    Name of Work: Four Laning & Strengthening of Existing 2 lanes from Km 120.000

    to 160.000 of Madurai - Kanyakumari Section of NH-7 in Tamilnadu.

    Package: NS-42/TN & NS-43/TN

    Subject: Site Inspection of the Engineer of Package: NS-42/TN & NS-43/TN

    Reference: Internal Office memorandum I, Dated: 25.06. 2010

    The Engineer Mr.Avadesh Sing had visited the site on 08.07.2010 along with the

    Contractors representative and SC team. The status of the project and the Engineers

    instructions are as follows:-

    Package: NS-42/TN

    Project Status as on 07.07.10

    Physical Progress: 98.41 %

    Financial progress: 95.34 % (221.628 Crores; value of work done only)

    Compliance of Engineers Instruction

    In view of issuing ToC, the Engineer during his previous visit instructed the Contractor to finish

    the following works in all aspects. The compliance report of the same as follows:-

    Sl.No. Instruction of the Engineer Action Taken Remarks

    1

    Construction of Median Kerb

    and Painting to be completed

    (apart from some locations

    where there is Public agitation

    for median openings)

    Completed

    2All the Crash Barriers are to be

    painted

    Completed

    3 Reflectors are to be fixed on all Completed

  • 8/9/2019 Engineer's Visit on 08[2].07.10

    2/3

    the RCC handrail

    5

    The cut slopes of the hill are to

    be trimmed properly by means

    of power hammer from top and

    bottom of the hill. All loosepockets and hanging cliffs are

    to be removed. Thereafter, the

    cut slope is to be inspected by

    a Geotechnical Expert to be

    deputed by the Contractor to

    confirm its stability.

    Compiled.

    Proposal for the slope

    protection treatmentshall be submitted by

    the Contractor through

    the Geotech Expert is

    expected by 25th

    July,2010.

    6 The rehabilitation work of the

    existing bridges like hand rail

    repairing, removal and relaying

    of wearing course and guniting

    of the exposed reinforcement

    etc., is to be completed.

    Removal and relaying

    of wearing course and

    hand rail fixing has

    been completed.

    Footpath pavement

    concrete and guniting

    of the exposed

    reinforcement

    pending.

    7 All the drainage spouts on the

    bridges to be completed in view

    of pedestrian safety

    Drainage spout work

    has been completed

    except the connecting

    pipes at flyoverbeneath the soffit.

    8 W-Beam Crash Barrier to be

    properly merged with Concrete

    Crash Barrier in approaches to

    some structures.

    Completed

    9 All chevron boards are to be

    fixed.

    Fixed as per the approve list

    Package: NS-43/TN :-

    The Engineer had inspected package NS-43/TN also. As per Engineers instruction, inspection

    of NS-43 project is in progress to assess the work to be carried out by the Contractor before

    issuing work completion certificate (after DLP).

  • 8/9/2019 Engineer's Visit on 08[2].07.10

    3/3

    Date: 13.07.10 Virendra Mittal

    Place: Tirunelveli Acting Resident

    Engineer

    NS-42/TN - Tirunelveli