Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Enoch Cree Nation Community Solar FarmThe Journey Thus Far
Presenters: Chase Morin Enoch Cree Nation, and John Kenney Urban Systems
October 23, 2018
Our Story
Enoch Cree Nation (ECN) has engaged Urban Systems to
complete a Solar Farm Technical Feasibility Study to consider
the options of developing, owning, and operating a large scale
solar farm on reserve lands to advance the Nation’s economic,
environmental, and community development interests.
Big Picture:• Global climate change and international commitments to reduce
emissions
• Revolution of energy generation technologies
• Decentralization of energy markets
Closer to home:
• Alberta Climate Leadership Plan / Federal Plan• Expect an investment greater than $10.5 billion and 7,200 new jobs
• Empowerment of Indigenous leadership in the energy sector
• ECN is working to meaningfully participate in this sector
Getting Started – The Big Picture
• Interest from within Enoch Cree Nation to be a leader in Alberta’s renewable energy sector
• In 2017, ECN completed a “Renewable Energy Options Analysis and Pre-Feasibility Study”
• GOAL: understand what opportunities existed and whether or not they made any sense to invest in
Starting from ground zero
Summary of Options Analysis
Technology Resource Scenarios Considered Findings
WindMarginal • 6 m/s at 80 m
• 6 MW• 60 MW
Likely not viable under the REP
SolarStrong • 1200-1300 kWh/kW
• Small to largeLikely to be viable business case (with grant funding) and need to be “creative”
Biomass
Most promising supply is agricultural and community wastes
• Displacement of community energy use
Likely not viable due to low cost of energy (in particular natural gas)
Geo-exchange N/A• Displacement of
community energy use
Likely not viable due to low cost of energy (in particular natural gas)
KEY FINDING: SOLAR PV APPEARS TO BE THE MOST OPTIMAL
Why Solar at ECN?
• Located in an area with a strong solar resource.
• Ample land and roof space on reserve to host large solar PV projects.
• Solar PV projects can be mobilized & developed relatively quickly to leverage available grant funding programs.
• Solar PV projects have a relatively straightforward regulatory approval process.
About Solar Farms
• Key components:
1. Solar panels (fixed)
2. Electrical infrastructure (inverter/transformer)
3. Switch gear
4. Meter
5. Distribution / transmission
• Site access roads
• Scenario 1:• 1 MW Roof Top Mounted Solar on the RCRC
• Scenario 2:• 5 MW RCRC Roof and Parking Lot
• Scenario 3:• 10 MW Solar Farm at a Nation-Owned Site w/ power sold
to an off-taker
• Scenario 4:• 5 MW Solar Farm at a Nation-Owned Site w/ a direct
connection to the RCRC
2018 Pre-Feasibility Study of 4 Project Scenarios
Outcome of the Pre-Feasibility Study
Advance the development of a solar farm project with an Off-Take Agreement in partnership with the River Cree Resort and
Casino
The Proposal/Recommendation
• 10 megawatt solar farm• Approximately 40,000 panels
• Footprint of approximately 90 acres
• Generate 12,500+ MWh per year• Enough power for approximately 1800 homes
• Approximately $1 million of power generated
• Development cost estimated to be $18.5 million
What does a 10 MW Solar Farm Look Like on the Land?
• Visually changes the landscape
• Noise is minimal • Slight hum during the day
• Approximately 30 decibels @ 300 meters (i.e. whisper)
• No night time noise, as solar farm is not operational
• Minimal opportunity for mixed use
• Last a minimum of 25 years
5 Ingredients to Make a Large Scale Solar Farm Work
1. Site control
2. Interconnection to the power grid
3. Contract to sell the power
4. Permits and authorizations
5. Funding
Ingredient #1 – Site Control
• Identified a number of sites of interest at Enoch
• Significant effort allocated to advancing a partnership with a Certificate of Possession holder, but fell through
• Selected a new site with great attributes!
• Actively working to complete site investigations and advance land lease arrangement
Key Learnings:
No site is perfect, and don’t be surprised if the first site you pick isn’t that one that ends up working.
Ingredient #2 – Interconnection
• Renewable energy projects require interconnection with existing power system infrastructure
• Electrical engineering is complicated and existing utility have rigorous standards
• Preliminary assessments have proven to be positive for the Enoch solar farm
• Enoch is completing a detailed interconnection study to define interconnection requirements and costs
Key learnings:
Interconnection is $$$, the studies take a long time, but critical to a project’s viability
Ingredient #3 – Contract to Sell the Power
Three key options:
• Option 1: Follow the heard and compete in the Renewable Energy Program (REP)• Basic renewable energy economics not favourable to solar
• LCOE - Solar: $110 -150 / MWh vs Wind: $30 - $35 / MWh
• Option 2: “Behind the Fence”• The Alberta Micro-Generation Regulation is great framework but need to have direct
connection• Land constraints
• Option 3: Leverage Alberta’s unique and competitive power market• Sell the energy to ourselves!
Summary of the Alberta Wholesale Power Market
• The market price for electricity is constantly changing, moving up and down
throughout the year, month, week, day and even hourly
• How is the price set?
• The power pool represents the wholesale power market in AB
• Bid process where generators bid to sell power to the market
• This is overseen by the Alberta Electricity System Operator (AESO)
What is an Off-Take Agreement?
• An Off-Take Agreement can stabilize the power price for:
• The generator (i.e. solar farm)
• The customer (i.e. the Casino)
• But how?
• Negotiate a strike price that reflects interests of the generator and customer
• Enter a long-term contract (i.e. 25 year Off-Take Agreement)
Why an Off-Take For Enoch
Overall benefit to Enoch:
• Casino has a large power load
• Hedge both the solar farm and casino from external market conditions
• Support viability of solar farm and fix a major operational cost of the
casino
• Aim to achieve profitability from RECs sold (e.g. Edmonton)
Ingredient #4 – Permits and Authorizations
• The project we are looking to advance can be considered “straight forward” from a regulatory approval perspective
• Actively working to secure approvals from:• Enoch Land Management Bylaws, Policies and Protocols
• Alberta Utilities Commission
• Environmental regulations (federal and provincial)
Key Learnings
Balancing aggressive project timelines, overall project definition and lead time for regulatory processes is challenging!
Ingredient #5 – Funding
• The good news is, once we’ve got the other ingredients together, Enoch will be well positioned to:
• Raise debt financing from lending institutions both traditional & non-traditional
• Leverage existing federal and provincial programs/grants
Key learnings:
Be proactive and strategically share your story. The money will come.
Identification
Project Definition
Pre-feasibility
Detailed Feasibility/Pre-Design
Approvals
Design/Build
Construction
The Lifecycle of Most Renewable Energy Projects
COD
The Plan for Getting it Built
• Finalize key site investigations
• Interconnection, environmental, noise, geotech, survey, etc.
• Detailed project costing and update business case
• Strike lease agreement and finalize off-take agreement
• Advance project funding/financing
• Submit regulatory applications
• Site plan / design
• Final investment decision
Summary of the Story So Far…
• Understand your options and resources
• Be open to innovative and unique ways to advance projects
• Come up with a clear plan to:
• Secure land
• Proactively advance interconnection work
• Sell the power
• Advance permitting asap
• Attract funding
Summary of the Alberta Power Pool -Simplified Scenario
• Assume a demand for 350 MWh of power at 7 pm tonight
• 3 companies (A,B, and C) are each able to supply 100 MWh of this demand (baseload), and two (D and E) that can provide 50 MWh of peaking power
• Companies A, B, and C submit their bid price for the first 300 MWh• Company A - $40/MWh • Company B - $50/MWh • Company C - $60/MWh
• Companies D and E submit their bid prices for the peak 50 MWh• Company D - $70/MWh • Company E - $100/MWh
• AESO first selects Companies A, B and C (baseload) then selects Company D (the lowest bid) for the peaking demand
• Company D sets the power price for the entire pool