Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | i
EXECUTIVE SUMMARY
1. INTRODUCTION
M/s. Ascent Pharma is an existing small scale unit located at Survey No. 163/9 & 11
on S.I.D.C. Road in Shapar-Veraval Industrial Area of Village Veraval (Shapar) in
Kotada Sangani Taluka of Rajkot District in Gujarat state. At present the unit is
manufacturing various Inorganic Chemicals with the total production capacity of 50
TPM. Now, considering the market demand, the unit intends to manufacture various
Bulk Drugs & Drugs Intermediates (Synthetic Organic Chemicals) with total production
capacity of 55 TPM within the existing premises by utilizing existing infrastructure
facilities with the addition of new machineries.
The proposed project is covered under Category ‘5(f)-A’ as per new EIA Notification of
Ministry of Environment & Forest (MoEF), dated 14-Sep-06. Therefore, the unit requires
to obtain Environmental Clearance (EC) from Ministry of Environment & Forest (MoEF),
New Delhi. The EIA report is prepared based on the TOR issued by the MoEF. The EIA
Study has been carried out by M/s. Envisafe Environment Consultants, Ahmedabad,
Gujarat which is based on one season field data collected from the study area during
December 2013 to February 2014 (Winter Season) and the same data has been used
in assessment of impacts due to the proposed project.
2. PROJECT LOCATION & ENVIRONMENTAL SETTINGS
a. Project Proponent : M/s. Ascent Pharma
b. Project Location : Survey No. 163/9 & 11, Shapar-Veraval Industrial Area, S.I.D.C. Road, Village: Veraval (Shapar), Taluka: Kotada Sangani, District: Rajkot, Gujarat.
c. Geographical Details : Altitude - 196 m above MSL
Latitude 22° 8' 54.73" N Longitude 70°47' 54.57" E
d. Land use of Plant site : 100% Industrial Land
e. Minimum Distances From Plant Site
a) City : Rajkot : @ 13.33 km North b) Village : Veraval : @ 2.2 km, North East
Shapar : @ 4.0 km, North West c) Railway Station : Ribda : @ 4.2 km South
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | ii
d) Highway : National Highway No. 8B @ 1.5 km East
e) Sea Coast : Arabian Sea: @ 179 km West f) Domestic Airport : Rajkot : @ 10.83 km NNE
g) International Airport : Ahmedabad : @ 207 km ENE
h) Sea Port : Kandla: @ 190 km NW
f. Distance from severely polluted area
: Aaji Industrial Area: @ 15 km NNE
g. Places of Interest within 10 Km radius from the Plant Site (if, any):
There is no protected area notified under the Wild Life (Protection) Act (1972) & Eco - sensitive area notified under Section 3 of the Environment (Protection) Act – 1986 exists within 10 Km radius areas from the Plant Site.
As per census 2001, Naranka Reserve Forest falls within the study area and unit has obtained No Objection Certificate from the Forest Department, Rajkot for the proposed project.
h. Displacement of population : None
i. Seismic Zone : As per the earthquake sensitivity index, the unit is situated in Zone- III having moderate Damage Risk Zone (MSK- VII).
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | iii
Key Infrastructure Map of the Study Area &
Google Image of Existing Plant
ASCENT PHARMA
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | iv
3. DETAILS OF PROPOSED PROJECT
Status : Small Scale Unit; Proposed Project for manufacturing of various Bulk Drugs & Drugs Intermediates within the existing premises
Product & Capacity :
Sr. No.
Name of Product Capacity TPM
Existing Proposed Total Products 1 Potassium Nitrate 10.0 Nil 10.0 2 Potassium Sulphate 10.0 Nil 10.0 3 Magnesium Hydroxide 10.0 Nil 10.0 4 Potassium Chloride 10.0 Nil 10.0 5 Potassium Iodide 10.0 Nil 10.0 6 Oxyclozanide Nil 25.0 25.0 7 Glibenclamide Nil 20.0 20.0
8 A. 1,2,4 Triazole
Nil 10.0 10.0 B. 4-Amino -1,2,4 Triazole
Total 50.0 55.0 105.0 By-Product 1 Hydrochloric Acid (30%) Nil 15.5 15.5 2 Sodium Bi-Sulphite Nil 26.0 26.0 3 Phosphorous Acid Aq. Nil 3.3 3.3
Use of Products : The products are widely used in pharmaceutical industries for manufacturing of medicines and drugs.
General Information:
Category As Per EIA Notification 2006
: 5(f)-A
Land Availability : Proposed project will be carried out within the existing premises having an area of 2,292 sqm and no additional land will be required for the proposed project.
Land type & status : Industrial Land
Capital Investment, in Lacs
: Existing: 48.57, Proposed: 36.50 & Total: 85.07
Capital Investment for EMP, in Lacs
: Existing: 0.0, Proposed: 5.5 & Total: 5.5
Recurring Cost for EMP, in Lacs/Annum
: Existing: 2.10, Proposed: 4.65 & Total: 6.75
Resources requirements:
Raw materials : After proposed project, about 18 raw materials will be required including 5 solvents. All the raw
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | v
materials are available in the local market.
Source of water supply : Water supply by Veraval (Shapar) Gram Panchayat through tanker OR private water supply through tanker
Fresh Water Requirement, KLD
: Industrial: Existing: 1.7, Proposed: 6.51, Total: 8.21 Domestic : Existing: 0.5, Proposed: 1.5, Total: 2.0 Gardening : Existing: 0.5, Proposed: 0.8, Total: 1.3
Power Source : Pashchim Gujarat Vij Company Ltd. (PGVCL)
Power Requirement : Existing: 45 KVA, Proposed: 15 KVA, Total: 60 KVA
Fuel Requirement : FO/ LDO (KL/Month): Existing:1.5; Proposed:1.5 ; Total: 3.0
Manpower Requirement, Nos.
: Existing: 11; Proposed: 27 & Total: 38
4. POLLUTION POTENTIAL & CONTROL MEASURES
Water Pollution:
Wastewater Generation, KLD
: Industrial: Existing: Nil, Proposed: 2.10, Total: 2.10 Domestic : Existing: 0.40, Proposed: 1.20, Total: 1.60
Source of Effluent & Management
: Process, Boiler, Cooling, Washing & APCE Out of total industrial effluent generation of 2.10
KLD, 0.40 KLD of condensate water from process will be recovered & reused in cooling make-up and for remaining 1.7 KLD effluent, the unit has proposed to install an effluent treatment plant (ETP) comprising of primary, secondary & tertiary treatment which will be adequate to achieve the discharge norms prescribed by GPCB.
Disposal of Effluent : Treated effluent from ETP only after conforming to the discharge norms will be utilized for greenbelt development.
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | vi
Air Pollution:
Flue Gas Emissions
Sr. No.
Stack Attach to
Ht. & Dia. (m)
Type of Fuel
Concentration of Polluants
Air Pollution Control
Measures
1. Steam Boiler
(0.8 TPH) 12.0 &
0.2 Furnace oil
/ LDO
PM ≤ 150 mg/Nm3 SO2 ≤ 100 ppm NOX ≤ 50 ppm
Adequate stack height is provided
Process Gas Emissions
Product Code
Product Expected Pollutants
Pollution Load
(kg/Batch)
Reaction Time (hr)
Rate of Generation
(kg/hr)
1 (a) Oxyclozanide-stage-I (Using Thionyl Chloride-SOCl2)
HCl 46.50 5 to 6 9.0
SO2 40.75 5 to 6 8.0
1 (b) Oxyclozanide-stage-I (Using Phosphorous tri chloride –PCl3)
HCl 23.25 2 to 3 11.0
Sr. No.
Stack attached
To
Height (m)
Dia. (m)
Temp(°C)
Polluant Concentration
mg/NM3
Control Measures
1. Reactors 15 0.04 40 HCl ≤ 20 mg/Nm3 SO2 ≤ 40 mg/Nm3
Water Scrubber followed by Alkali
Scrubber Hazardous Waste:
Source Type of waste
Cat. Quantity per
Annum Physical- Chemical
Form
Method of Disposal
E P T
Process
Inorganic Salt
28.1 Nil 52.0 MT
52.0 MT
Solid Inorganic
Collection, Storage & disposal by land filling at TSDF site.
Distillation Residue
28.1 Nil 14.0 MT
14.0 MT
Semisolid organic
Collection, Storage, Transportation,
Disposal by incineration at
nearby CHWIF OR send for the Co-Processing to the GPCB authorized
agencies
Spent Carbon
28.2 12.4 MT
5.6 MT
18.0 MT
Solid Inorganic
Spent Solvent
28.5 Nil 7400 MT
7400 MT
Liquid & Organic
Collection, Storage & Reuse after
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | vii
Source Type of waste
Cat. Quantity per
Annum Physical- Chemical
Form
Method of Disposal
E P T distillation within
process OR Sell to GPCB
authorized recycler
ETP ETP Sludge
34.3 Nil 2.0 MT
2.0 MT
Solid & Inorganic
Collection, Storage, Transportation,
Disposal by land filling at TSDF site
Raw Material Storage & Handling
Discarded Containers/ Bags
33.3 300 Nos.
700 Nos.
1000 Nos.
Solid-Inorganic
Collection, Storage, Decontamination and Disposal by selling to scrap
vendors / recyclers.
Plant and Machineries
Spent Oil/ Used Oil
5.1 0.05 MT
0.05 MT
0.1 MT
Liquid- Organic
Collection, Storage, Transportation,
Reuse as lubricant within the premises OR sell to registered Reprocessor/ MoEF approved recyclers
Noise & Vibration:
There will be no other source of noise and vibration from the proposed manufacturing
activity except Plant machineries. The adequate precautions are being taken for
abatement of noise pollutions.
5. BASELINE ENVIRONMENT
The baseline environmental quality of air, water, soil, noise, socioeconomic status and
ecology has been assessed in the winter season (December 2013 to February 2014).
For the EIA study, the area falling within 10 km radial distance from project site has
been selected for preparing the site map along with infrastructure setup and
administrative map, land use/land cover map and socio-economic study whereas the
area falling within 5 km was considered to monitor the base line environment quality.
Baseline study was conducted as per the approved TORs issued by MoEF and
guidelines of MoEF/CPCB.
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | viii
5.1 Micro-Meteorology
The site-specific micrometeorological data was collected continuously during the
study period by installing automatic weather station at project site. During the study
period wind was blowing mostly from NNW with average speed of 0.85 m/s and
maximum speed of 7.1 m/s. Average temperature recorded was 20.1°C with
maximum temperature of 34.3°C and minimum of 12.1°C. The average relative
humidity was recorded as 46% and maximum as 83%.
5.2 Ambient Air Quality
The ambient air samples were collected from six locations and analyzed for PM10,
PM2.5, SO2, NOx, HCl, NH3, CO & VOC. All the parameters are well within the NAAQS
except PM10 at three locations including project site. HCl concentration at project site
was also well within the GPCB norms prescribed for industrial area. It was below
detectable limit at other locations. VOC and NH3 concentration (as isobutylene) was
below detectable limit (BDL) at all locations.
5.3 Water Quality
Ground water samples were collected from the five locations and pipe water was
collected from project site once during the study period. TDS was higher than the
permissible limit at Pardi Village. Total Hardness was found higher than the permissible
limit at Pardi, Veraval (Shapar) and Ribda Village. Heavy metals and other parameters
except specified above were well within the permissible limit at all locations and water
collected from all the location is fit for the drinking purposes except the ground water of
Pardi Village.
5.4 Background Noise Level
The monitored noise levels have been compared with the standards prescribed by
MoEF which indicates that Noise levels at project site were found well within the limit for
day & night time. Noise levels at all the residential locations were found higher than the
limit for day time and for night time noise levels were well within the limit. Due to
vehicular movement during day as well as night time, noise levels on Shapar-Veraval
Junction at NH-8A were observed higher than the limit.
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | ix
5.5 Soil Quality
Water Holding Capacity of soil samples were in range of 32% (Veraval (Shapar)
Village) to 40% (Gundasara Village). The texture of soil is observed mainly Sandy Clay
Loam in the study area. The concentration of available Nitrogen, Phosphorous and
Potassium were in the range of 0.3 to 1.2 gm/Kg, 0.04 to 0.1 gm/Kg and 0.5 to 1.0
gm/Kg respectively, which signifies that the soil of the area is fertile. The organic matter
in the soil ranged from 1.2 to 3.9 mg/Kg.
5.6 Land Use Pattern
Classification of land use/land cover was derived using GIS software from satellite
image. About 68.96% of the study area is covered under agricultural land. There is
3.55% land acquired for the industrial purposes in the study area. 0.96 % area is water
body consists of lake/pond and river. Also, there is no protected area notified under the
Wild Life (Protection) Act (1972) & Eco - sensitive area notified under Section 3 of the
Environment (Protection) Act-1986 exists within 10 Km radius areas from the Plant Site.
As per census 2001, Naranka Reserve Forest falls within the study area and unit has
obtained No Objection Certificate from the Forest Department, Rajkot for the proposed
project.
5.7 Socio-Economic Study
As per the 2011 census, the study area of 10 km from the project site comprises of total
four Talukas of Rajkot District namely Rajkot, Kotada Sangani, Gondal and Lodhika.
There are 41 villages falling within the study area having total population of around
1,06,313 indicating that the area is sparsely populated with scattered settlements.
Overall literacy rate in the study area is 68.6%, which show that literacy rate in the
study area is comparatively high. The overall employment ratio for the 41 villages in the
study area is 44.0%, which shows that employment ratio is low. Thus, the proposed
project will help to improve the economical status in the study area by providing more
employment opportunities. The area is well developed in terms of education,
communication, health services and banking facilities.
5.8 Biological Environment
More than 60% of land in the study area is agricultural land utilizing for general crops
like Groundnut, Jeeru, Kapaas, Dangar, Jowar, Ghanv, Makai etc. It is observed during
site visit that all species encountered are quite common and found everywhere. No
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | x
endangered and rare species were observed. Also, there are no zoological parks or
sanctuaries in the study area.
6. ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
6.1 Impacts During Construction Phase & Its Mitigation Measures
During Construction Phase of proposed project, the fugitive dust emission due to civil
work and vehicular movement is not expected to spread too far as water spraying will
be carried out to suppress the dust emission at the site and as well as on road. The
increase in noise levels due to the movement of vehicles will be taken care of by
regulating the movement of vehicles and the impact on the human beings will be taken
care of by providing the working people with ear plugs / ear muffs. As the proposed
project will be carried out within existing premises, there will not be any significant
impact on the ecology of the study area.
6.2 Impact During Operation Phase & Mitigation Measures
a) Air Environment
After the proposed project, the major sources of air pollution will be flue gas emissions
and process gas emissions. Flue gas emissions will be from stack attached to existing
steam boiler which will be utilized for proposed project also. In existing unit, there is no
emission from the process. For the proposed process gas emission, adequate
scrubbing system will be provided.
The maximum 24-hourly average ground level concentration for pollutants due to
proposed project calculated using mathematical model (ISCST3) for PM10, SO2, NOx
and HCl is very negligible even for the worst case scenario.
There will be the fugitive dust emissions due to the manufacturing activities, raw
materials handling, loading and unloading of raw materials and finished goods,
conveying and feeding point, vehicular movements, etc. Adequate measures will be
taken to control the fugitive emissions. Hence, there will not be any significant impact
on air environment due to proposed project.
b) Water Environment
Additional water requirement of 8.81 KLD will be met through water supply by Veraval
(Shapar) Gram Panchayat through tanker same as existing practice. Unit is also bought
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | xi
water from Private water supplier through tankers in case of non-availability of main
source. After proposed project also, this will be kept as stand by source.
As per Guidelines issued by Central Ground Water Authority, Ministry of Water
Resources, New Delhi, dated 15/11/2012, the unit falls under White Zone (Safe) and do
not covered under the list of critical areas published by CGWA. Also the water
requirement of the plant is 11.51 KL/Day which falls within the limit of 100 KLD as per
CGWA; therefore the unit does not require obtaining permission from CGWA for the
use/abstraction of ground water.
After the proposed project, 1.6 KLD domestic wastewater will be discharged to soak pit
through septic tank same as current practice. Presently there is no effluent generation
from industrial activities and unit maintains the zero effluent discharge. The total
industrial wastewater generation after proposed project will be 2.10 KLD which includes
wastewater generation from process, APCM, boiler, cooling and washing activities. 0.40
KLD of condensate water from process will be recovered & reused in cooling make-up.
The unit has proposed to install their own effluent treatment plant (ETP) comprising of
primary, secondary & tertiary treatment for remaining 1.7 KLD effluent which will be
adequate to achieve the discharge norms prescribed by GPCB. Treated effluent will be
used for gardening and plantation within the premises. Thus, there will not be any
impact on water environment.
c) Land Environment
As the proposed project will be carried out within the existing premises, there will not be
any change in land use pattern, forest cover or vegetation in surrounding area. As far
as effluent disposal is concerned, treated effluent from ETP only after conforming to the
discharge norms will be utilized for greenbelt development. Regular maintenance of
pumps and flange connections in the pipelines will be carried out and proper care will
be taken while loading, unloading and transfer of materials to avoid any soil/land
contamination. The hazardous waste generated will be stored and handle as per the
Hazardous Wastes (Management, Handling and Transboundary Movement) Rules,
2008. Hence, there will not be any impact on land /soil environment.
d) Noise
During operational phase the impact on noise environment will be due to manufacturing
activities, utilities and transportation activities (transportation of raw materials and
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | xii
finished products). The noise pollution management will be taken up by selecting low
noise generating equipment, Isolating the noise generating equipments and working
area and by administrative & safety measures, providing noise level monitoring,
remedial measures, providing noise safety appliances to the working personnel.
e) Green belt development
Unit has already developed green belt in 340 m2 within the premises and this will be
increased up to 760 m2 (33.16% of total area) after the proposed project which will not
only improve the soil conditioning but will also prevent soil erosion and the landscape &
give slight beneficial impact on the land usage. Greenbelt will minimize the level of
possible air pollutants and will also minimize noise pollution.
7. ENVIRONMENTAL MANAGEMENT PLAN
The environmental management plan is proposed with respect to the all proposed
activities considering affected environmental attributes and impact zone which is
summarized here under:
Sr. No.
Activity Management Plan
1. Manufacturing activities and operations of utilities
Ensure provision of Environmental Management system (EMS) as proposed / committed for environmental pollution control. Ensure the efficient operations of provided EMS. Ensure proper treatment and reuse of treated effluent for
greenbelt development. Regular monitoring w.r.t EMS, ambient air quality, work area,
noise, water quality as per the monitoring program. Review the monitoring reports and take corrective measures
as required. Ensure the submission of monitoring reports to the concerned
authority as per the norms. Ensure compliance of stipulated conditions by concerned
authorities. Ensure optimum use of resources. Regular monitoring of water consumption. Maintain proper record of resources utilization. Ensure the close manufacturing systems in order to minimize
fugitive emissions. Ensure the regular maintenance of reactors and other process
equipments. Ensure regular usage of proper PPE's by workers in the plant. Ensure the collection, storage, handling, transportation &
disposal of all the hazardous wastes as per the Hazardous
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | xiii
Sr. No.
Activity Management Plan
Waste (Management, Handling & Transboundary Movement) Rules, 1989 as Amended in 2008. Proper and timely oiling, lubrication, preventive maintenance of
all plant machinery & equipments. Explore the technology for cleaner production, waste
minimization, treatment/ reuse / recycle / co-incineration of wastes.
2. Storage & handling of hazardous chemicals and hazardous waste
Ensure the storage and handling of all the chemicals in a proper manner to avoid any spillages and also to prevent runoff contamination in monsoon. Ensure collection & treatment of spillages, if any ensure good
housekeeping to maintain clean and orderly working environment. Provide training to the persons handling chemicals &
hazardous wastes. Ensure the provision of designated hazardous waste storage
area with proper roofing and leachate collection. Ensure the disposal of hazardous wastes at approved TSDF
with manifest only. Ensure availability of MSDS of all the Hazardous materials to
the on-site emergency team. 3. Domestic
activities Regular monitoring of water consumption and ensure optimum
use of water. Ensure proper discharge of sewage to soak pit through septic
tank. 4. Green belt
development Maintain existing green belt by regular watering, soil
enrichment work (applying manure) weeding and provide proper protection. Ensure the further development of greenbelt as proposed.
5. CSR activities Give preference to local people for the recruitment. Ensure to carry out CSR activities as proposed.
6. Transportation of hazardous chemicals and hazardous waste
Vehicles must be PUC certified. Ensure vehicular movement only during day time. Ensure the transportation only by covered vehicles. Ensure availability of manifest/TREM card with driver during
the transportation of Hazardous Waste / hazardous chemicals. Ensure regular maintenance and optimum use of the vehicles. Educate driver about the characteristics of wastes/ chemicals
and immediate actions in case of any spillage or accident. Ensure availability of MSDS of all the Hazardous materials to
the Off-site Emergency team.
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | xiv
8. ENVIRONMENTAL MONITORING PROGRAMME
From the monitoring point of view, the important components are air, water, soil, noise
and occupational health & safety. Regular monitoring will be carried out after the
proposed project as per the monitoring program. Unit will establish a small scale
laboratory at ETP area for regular wastewater monitoring. Untreated and treated
wastewater of ETP will be daily analysed with respect to pH, TDS and COD. Flow
meters will be provided at the outlet of ETP for regular monitoring of wastewater
quantity. Unit has already made necessary tie-up with nearby hospitals for the medical
assistance in case of any emergency. Unit will establish a well organized Environmental
Management Cell (EMC) which will perform all the environmental management
activities.
Unit will also prepare EHS policy to adhere with standard operating process in order to
comply with the statue and bring into focus any infringement of any norms and
directives with regards to the Environment, Health & Safety and to take further
corrective actions. Voluntary reporting of environmental performance with reference to
EMP will be undertaken. Plant In-charge will co-ordinate all monitoring programs at site
and data generated will be submitted regularly to the statutory agencies. Frequency of
reporting shall be as per the requirement of GPCB and MoEF.
9. ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
The proposed project will be carried out within the existing premises and existing
infrastructure facilities will also be utilized with the addition of new machinery for the
proposed project. Thus, no alternative for the site was considered due to the availability
of infrastructure, land, water sources, fuel transportation, power etc.
For the proposed products i.e. various Bulk Drugs & Drugs Intermediates (Synthetic
Organic Chemical), unit will adopt latest and best technology available so far in the
market. Moreover, the unit is very concerns and conscious about the product quality
and equally about the environmental protection and resource conservation; and hence
they put their efforts for replacing/upgrading their existing plant and machineries from
time to time with the best available technology.
Environmental Impact Assessment (EIA) Report
Proposed Project for Manufacturing of Synthetic Organic Chemicals
Executive Summary
Page | xv
10. RISK AND SAFETY MANAGEMENT
The unit is very much aware of their obligation to protect all persons at work and others
in the neighborhood that may be affected by an unfortunate and unforeseen incidence
occurring at the works. Unit has provided all the adequate safety measures in the
existing plant. After proposed project also, any hazard either to employees or others
arising from activities at the plant site shall as far as possible, be handled by the
personnel of the company and prevented from spreading any further. In the case of
eventuality the on-site and off-site emergency plan proposed by the unit will be
adequate and may be able to control the situation. After the proposed project all the
required safety measures will be taken and unit will also carry out safety audit through
authorized agency/organization.
11. PROJECT BENEFITS
Unit has contributed reasonably as part of their CSR and carried out various activities in
nearby villages. Unit is spending annually about Rs. 25,000 for such activities. In
addition to this employment opportunity for 27 persons and for many other skilled-
unskilled labors during construction and other ancillary activities during operation will be
generated after the proposed project. Unit has planned to carry out various activities for
the upliftment of poor people, welfare of women & labors, education of poor students as
part of Corporate Social Responsibility (CSR) in the nearby villages and therefore unit
will make additional provision of Rs. 25,000. Therefore, after proposed project, unit will
spent at least Rs. 50,000 every year towards CSR activities.
12. CONCLUSION
It can be concluded on a positive note that after the implementation of the mitigation
measures and environmental management plans, the proposed project activities during
the construction and operation phase would have manageable & largely have reversible
impacts on the environment and on balance the project would be beneficial to
surrounding communities and the region.