32
PSS-Cost Project Researcher: Francisco Romero Rojo Supervisors: Prof Rajkumar Roy SCAF Workshop Dr Essam Shehab 21 st April 2010 Project Manager: Dr Kalyan Cheruvu Estimating the Cost of Obsolescence

Estimating the Cost of Obsolescence - SCAF - Society for Cost … the... · 2018-04-27 · Product-Service Systems (PSS) Obsolescence is Unavoidable Long-term Support Projects

  • Upload
    lyngoc

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

PSS-Cost Project

Researcher: Francisco Romero Rojo

Supervisors: Prof Rajkumar Roy SCAF WorkshopDr Essam Shehab 21st April 2010

Project Manager: Dr Kalyan Cheruvu

Estimating the Cost of Obsolescence

Introduction – PSS-Cost Project

Research Methodology

Framework Description

Concepts

Process

Obsolescence Resolution Profiles

Obsolescence Cost Metrics

Conclusions

Outline

Objectives:• Report on the current practice in WLCC estimation at the bidding stage• Prototype tools for WLCC prediction for In-service Uncertainties,

Obsolescence and Affordability Assessment for availability contracts• Validation of the tools developed using industrial case studies• Development of templates for contract clauses (i.e. terms and

conditions) applicable to availability contracts which protect risks against Uncertainty, Obsolescence and Affordability

• Dissemination of the knowledge through workshops, conferences and journal publications

PSS-Cost Project

Aim: To develop understanding of Whole Life Cycle Cost (WLCC) andaffordability management for Product Service Systems (PSS) in defenceindustry.

PSS-Cost Project

Affordability

Design

Obsolescence

Uncertainty

Introduction

Need to Estimate Obsolescence Cost at Bidding Stage

Availability Contracts / Product-Service Systems

(PSS)

Obsolescence is Unavoidable

Long-term Support Projects • Defence

• Aerospace• Oil and Gas• Nuclear

New ways of Contracting

Research Methodology

Understanding Context

Literature review

COG Meetings

Framework Development Quantitative Validation

Expert opinion Case studies

Conferences and workshops

Industrial Current Practice Capture

Data gathering Data analysis

Develop Research Protocol

Qualitative Validation

Enhancements

Development

EEE-FORCE Framework

Obsolescence Definitions

• Actions performed in order to reduce the risk or potential impact of obsolescence issues

Mitigation Strategies

• Actions carried out once an obsolescence issue arises and needs to be addressed

Resolution Approaches

Obsolescence Resolution Approaches

Existing Stock

Last Time Buy

Cannibalisation (Reclamation)

Authorised Aftermarket

Alternative

Equivalent

Emulation

Redesign

FFF Replacement

Same Component

Minor Redesign

Major Redesign

Obsolescence Resolution Definitions

Resolution Term Definition Existing Stock An item that is owned within the supply chain and that can be allocated to the project.

Last Time Buy As a result of a product discontinuance notice, the procurement of items sufficient to support the life cycle of the project or until the next planned technology upgrade.

Reclamation (Cannibalisation) The use of an item found in surplus equipment or equipment beyond economical repair.

Equivalent An item which is functionally, parametrically and technically interchangeable (form, fit and function).

Alternative An item whose performance may be different from that specified for one or more reasons (e.g., quality or reliability level, tolerance, parametric, temperature range).

Authorised Aftermarket An item is available on the market but not from the original manufacturer or supplier (typically finished goods provided by licensed sources).

Emulation A manufacturing process that produces a substitute form, fit and function, and interface (F3I) item for the unobtainable item. Microcircuit emulation can replicate with state-of-the art devices that emulate the original and can be manufactured and supplied on demand.

Redesign An item is designed out of the system. The cost for redesign can include engineering, programme management, integration, qualification and testing. Redesign can be further broken down into categories, e.g. minor (board re-layout) and major (board replacement).

Components Complexity Levels

OM Levels of Proactiveness

• Same as [3] plus:• Technology Roadmapping• Partnering agreements with suppliers• Consider obsolescence at the design stage

5

• Same as [3] plus:• Technology Roadmapping• Either “Partnering agreements with suppliers” or “Consider obsolescence at the design

stage”4

• Employ obsolescence managers• Use obsolescence monitoring tools • Notify obsolescence issues proactively• Decide the key parts that should be managed proactively

3

• Reactive but making LTB to avoid/solve obsolescence issues2

• Deal with any obsolescence issue reactively• Miss most of the LTB notifications1

•Modularity•Transparency•Use of technology/components/materials less likely to become obsolete•Use multi-sourced components

PR

OA

CT

IVE

RE

AC

TIV

E

Data Input Process

This flowchart represents the five steps followed on this tool and indicates the

data required for each step.

STEP 3A

STEP 3B

Go to STEP 3A if there is information available about the list of components + Obsolescence Monitoring tool + ERP system

OR if there is historical data from a similar product

Go to STEP 3B if there is no information available about the list of components + Monitoring tool + ERP systemNOR there is historical data from a similar product

so the information provided can be based on experience or information from the supplier

STEP4: Obsolescence Resolution Profiles

It represents the probability of using each obsolescence

resolution approach to solve an obsolescence issue

Obsolescence Resolution Profiles

(ORP) Study Methodology

• DELPHI METHOD

• DEFINITIONS REFINEMENT

• TRENDS REFINEMENT

OBSOLESCENCE RESOLUTIONS PROFILE (ORP) STUDY METHODOLOGY

SECO

ND

RO

UN

D

FI

RST

ROU

ND

DEL

PHI

MET

HO

D

First Questionnaire Development

Piloting with obsolescence expert (7 years)

Data Collection at COG Quarterly Meeting (38 experts in obsolescence participated)

Analysis of Responses

Results and Conclusions Second Questionnaire Development

Piloting with obsolescence expert (7 years)

Data Collection at COG Quarterly Meeting (33 experts in obsolescence participated)

Analysis of Responses

Refine Results

Obsolescence Definitions Workshop (38 experts in obsolescence participated) It is identified the need to

breakdown “FFF Replacement” into “Equivalent” and

“Alternative”

Second Questionnaire Development

D

EFIN

ITIO

NS

REFI

NEM

ENT

TREN

DS

REFI

NEM

ENT

(33 e pe ts obso esce ce pa t c pated)

a ys s o espo ses

e e esu ts

Obsolescence Definitions Workshop (38 experts in obsolescence participated) It is identified the need to

breakdown “FFF Replacement” into “Equivalent” and

“Alternative”

Piloting with obsolescence expert (7 years)

Second Questionnaire Development

Data Collection with 6 key experts in obsolescence from COG

Analysis of Responses

Refine Results

ORP Refinement Workshop (6 experts in obsolescence participated) Based on theoretical analysis of

trends with key COG experts

Analysis of Responses

Refine ORP Accordingly

Final ORP Develop alternative ORP

Obs. Mgmt.Level

PartComplexity

1(Reactive) 2 3 4 5

(Proactive)

Low

Medium

High

STEP4: Obsolescence Resolution Profiles

STEP 5: Obsolescence Cost Metrics

•Existing Stock•Last Time Buy •Reclamation (Cannibalisation)•Equivalent•Alternative•Authorised Aftermarket•Emulation•Minor Redesign•Major Redesign

Resolution Approach

•Small•Medium•Large•Very Large

Level of Integration

•Space•Air / Safety Critical•Sea/Submersible•Land-Mobile (military)•Land-Fixed (consumer) Office - Industrial

Type of Platform

•Yes•No

Requalification Required

Obsolescence Cost Metrics

Study Methodology

Conclusions

• A systematic framework has been developed to estimate the cost of materials and EEE components obsolescence for availability contracts in the defence sector.

• Research carried out on software obsolescence has set the basis for further research on the cost estimation for this barely-explored area.

• The EEE-FORCE and M-FORCE tools are currently been validated with the industrial partners and they will be delivered at MACH 2010 in Birmingham on 7th June 2010.

Thank you!

Questions?

For further information please contact:

e-mail: [email protected]

Tel: +44 (0) 1234 750111 Ext:5656

Decision Engineering Centre

Cranfield University, UK