Upload
azaidi88
View
254
Download
15
Tags:
Embed Size (px)
DESCRIPTION
Excel-estimate-sample-xls.pdf
Citation preview
Page no 1
1
(CE 5.a )
02.1.1 125 '- 0 " ' -0 " sft
sqm 7.00 / sqm = TK 0.167 lac
2(CE 5 )
CE 5 c
02.1.3 area of excavation = 125 '- 0 " ' 0 " sft
upto 1.5 mm depth 5 ' - 0 " cft
cum 46.00 / cum = TK 1.669 lac
CE 5 f
02.1.61.50 m to 2.0 m depth 1 ' - 8 " cft
cum 53.00 / cum = TK 0.642 lac
1.50 m to 2.0 m depth 1 ' - 6 " cftcum 60.00 / cum = TK 0.653 lac
( Total earth work = cft )
3(A)
(CE 6a )
2.2 hours 178.00 / hour = TK 0.178 lac
3(B)
(CE 6c )
2.4
rm 252.00 / rm = TK 0.509 lac
3(C)
(CE 6d )
2.5
250 '- 0 " ' -2 " sft
410 '- 0 " ' -2 " sft
sft
sqm 390.00 / sqm = TK 1.953 lac
4
CE 11 a3.1
125 '- 0 " ' -0 " sft
deduction : Pile area 850 X 1'- 2" sft
sft
sqm 162.00 / sqm = TK 3.682 lac
25625.00 X
X
=
1211.944
X 8
=X 8
Extra Rate for each additional 0.5 meter depth exceeding 1.5 meter
=
42793.75
= 38437.5
25625.00
@ Tk
X
= Marked A
Earth work in excavation in all kinds of soil for foundation trenches in/c. layout, providing center lines, local bench-
mark pillars, leveling, ramming and preparing the base, fixing bamboo spikes & marking layout with chalk powder,
providing necessary tools and plants, protecting and maintaining the trench dry etc., stacking, cleaning the excavated
earth at a safe distance of out of the area enclosed by the layout etc. all complete and accepted by the Engineer,
subject to submit method statement of carrying out excavation work to the Engineer for approval. However, Engineer's
approval shall not relieve the contractor of his responsibilities and obligations under the contract.
Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead : In medium stiff clayey soil.
X 205 25625.00
Name of work : Construction of IBRAHIM MEDICAL COLLEGE at Darussalam, Mirpur, Dhaka.
Sub Head : Construction of Academic Building with ancillary works.
Part A : Civil construction work of Academic Building.
= 2380.62 @ Tk
Layout and marking for earthwork in excavation in foundation accepted by the Engineer. ( Plinth area of the structure
shall be considered for measurement ).
X 205 = 25625.00
=
@ Tk
= 24467.39
25625.00
One layer of brick flat soling in foundation or in floor with 1st class or picked jhama bricks in/c preparation of bed and
filling the interstices with local sand, leveling in/c the supply of water, electricity and other charges and costs of tools and
plants etc. all complete and accepted by the Engineer.
@ Tk
( Marked B )
205
X
2273.08
@ Tk
= 100
Supplying wooden ballah having an average diameter not less than 150 mm with a minimum end diameter of 100
mm for retaining purpose and driving to a depth as per design and drawing by any method including all arrangements
for staging, hoisting, carrying etc. complete and accepted by the Engineer.
@ Tk
=
=
X
1088.573
Palisding work by supplying bitumen drum sheet walling tied with 20 BWG G.I. Wire fixing the same with already
driven borrak bamboo posts with half split borrak bamboo runners @ 450 c/c horizontally with iron nails, G.I wire etc. All
complete and accepted by the Engineer. ( Rate is excluding the cost of bamboo post )
=
@ Tk
= 202
Bailing out of water caused by inundation or rain, by pump from foundation trenches.
1157.606
3349.70
= 2041.67
500.87
170918.8
= 5391.37
1' - 2"
128125
= 3628.575
@ Tk
=
=25625.00
Page no 2
5
CE 12.a.i
3.4.1
Basement lift side
2X
30 '- 0 " ' -0 " sft
sft
Total sft X 0 ' - "
cft
cum /cum = TK 7.150 lac
6
CE 58
(A)
CE 58a07.21.1
Basement wall 2 X 190 ' - 0 " =2 X 60 ' - 0 " =
2 X 3.1 25 ' =
Ramp wall 1 X 60 ' - 0 " =
=
= X sft
=
Sides of pile cap
PC 12 28 X 45 ' - 0 " =
PC 7 6 X 29 ' - 0 " =
PC 10 12 X 43 ' - 0 " =
PC 14 20 X 42 ' - 2 " =
PC 3 10 X 16 ' - 9 " =
PC 9 2 X 38 ' - 0 " =
PC 6 4 X 31 ' - 0 " =
=
= X 3' - 9"
=
Total =
= /sqm = TK 12.742 lac
(B)
(CE 58b )
07.21.2
sft 43490.52
sqm 648.00 / sqm = TK 14.730 lac 4040.368
7(A)
(CE 8a )
02.10.1
Below basement slab & between pile caps
sft
Deduct, pile cap sftsft X 3 ' - "
cft
quantity same as mark B of Item 4
From Item 10(A) 8424.83=9
=
Mark E
@ Tk
325847.39
6461.85
183.00
1380.00
24467.39
Mass concrete (1:3:6) in foundation with cement, sand (F.M.1.2) and picked jhama chips including breaking chips,
screening, mixing, laying, compacting to levels and curing for at least 7 days in/c the supply of water, electricity and
other charges and costs of tools and plants etc. all complete and accepted by the Engineer.
Water proofing membrane on made up surface below the floor or below the horizontal surfaces below grades with
temporary protective cover using polysterene / 1.5 " thick sand - cement mortar in 4 : 1 / or by equally effective
alternative ( rate is excluding the cost of protective cover which to be paid as per corresponding items)
1767.29 sqm 721.00
717.00
X 23
Mark D
Supplying, best quality pliable, cold applied pre-formed self adhesive rubberized/ bituminous water proofing
membrane of approved brand / origin / manufacturer from an authorized local agent or manufacturer having minimum
thickness 1.5 mm, lined with 2 ply cross laminated high density polyethylene film performances and properties all
conforming to ASTM standards and laying, placing, fixing on made up firm and dry surfaces free from hollows, sharp
protrusions, contaminates etc. laid over-lap by at least 75 mm along the edges and 125 mm at ends ensuring good
initial bond with the surfaces all complete under the strict accordance with the manufacturer recommendations and
instructions providing all safety provisions in all respects and accepted by the Engineer.
=
=
=
Water proofing membrane on external surface of vertical or inclined wall ( excluding cost of back fill / brick wall
on back/ plaster when membrane laid on back wall and concrete cast against membrane which to be paid as per
corresponding items )
7170.00
10
sft
Add , Area same as item 4 Marked "B" =
X 157.00 rft
rft
3907.00
717.00
rft
60.00 rft
380.00 rft120.00
@ Tk
rft
76.00 rft
124.00 rft
19023.13
2273.08
24467.39
=
rft
11853.13 sft
3160.83 rft
3160.83
167.50
1260.00
rft
516.00 rft
rft
rft
174.00
843.33
60159.60
=
Sand filling in foundation trenches and plinth with coarse sand having min. F.M. 0.80 in 150 mm layers including
leveling, watering and compaction to specified percent by ramming each layer up to finished level as per design
supplied by the design office only etc. all complete and accepted by the Engineer.
= 16042.56
=
@ Tk
quantity same as mark B of Item 4 = 24467.39
Page no 3
sides of Basement wall upto 5' depth
2 X 190 ' - 0 " =
2 X 60 ' - 0 " =
2 X 3.14 25 ' =
== X cft
=
Total = cft
= cum 406.00 / cum = TK 7.862 lac
7(B)
(CE 8b )02.10.2
Basement lift side 30 ' - 0 " ' -0 " sftsft X 1 ' - "cft
sides of Basement wall from 5' depth to GL
rft
rft X 4 ' X '
cft
Total cft
cum 652.00 / cum = TK 1.629 lac
8 (A)
CE 9 a
02.13.
quantity same as item 2 cft
cum 55.00 / cum = TK 2.662 lac
8(B)
CE 10 a
02.15.1
1 X 340 ' - 2 " X 176 ' - 0 " = 59869.33 sft
deduct , building area 1 X 190 ' - 0 " X 110 ' - 0 " = 20900.00 sft
= 38969.33 sft X '
= 241220.17 cft
deduct, earth obtained from earth work in excavation = 170918.75 cft
net volume = 70301.42 cft
= 1990.98 cum /cum = TK 6.053 lac
Sub Total 62.281 lac
mark A
X 157.00
657.00
380.00
657.00
4840.52
Earth filling in foundation trenches and plinth in 150 mm layer with earth available within 90 m of the building site,
including carrying, watering, leveling , dressing and compacting to a specified percent each layer up to finished level
etc. all complete and accepted by the Engineer.
6570.00=
@ Tk
=
=
= 8820.00
Sand filling in foundation trenches and plinth with coarse sand having min. F.M. 1.20 in 150 mm layers including
leveling, watering and compaction to specified percent by ramming each layer up to finished level as per design
supplied by the design office only etc. all complete and accepted by the Engineer.
Earth filling in foundation trenches and plinth in 150 mm layers with carted earth carried by truck or any other means
loading & unloading at both ends in/c. leveling, watering and consolidating including local carriage each layer up to
finished level. in/c cost of water & test (carried from beyond 300 m) etc. all complete and accepted by the Engineer.
########
249.79 @ Tk
quantity same as mark A of Item 5 =
=
cft
rft
120.00
5 ' X 2' - 6"
1500.00
6.19
= 657.00 2.5
6= 2250.00
@ Tk
=1500.00
rft
@ Tk 304.00
=
1936.34
X 25
68372.10
8212.5
rft
rft
657.00
Page no 4
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
7.00 9.00 0.167 0.214 0.0% 28.6%
59.00 79.00 2.141 2.867 28.3% 33.9%
69.00 92.00 0.836 1.115 30.2% 33.3%
69.00 92.00 0.751 1.001 15.0% 33.3%
237.00 271.00 0.237 0.271 33.1% 14.3%
344.00 430.00 0.695 0.869 36.5% 25.0%
417.00 475.00 2.089 2.379 6.9% 13.9%
234.00 317.00 5.319 7.206 44.4% 35.5%
TotalRate
Page no 5
4,749.00 5641.00 8.691 10.323 21.6% 18.8%
734.00 798.00 12.972 14.103 1.8% 8.7%
655.00 712.00 14.889 16.184 1.1% 8.7%
Page no 6
476.00 549.00 9.217 10.630 17.2% 15.3%
776.00 857.00 1.938 2.141 19.0% 10.4%
70.00 93.00 3.388 4.502 27.3% 32.9%
264.00 393.00 5.256 7.825 -13.2% 48.9%
68.586 81.6296045 10.1% 19.0%
Page No 4B.F Tk 62.281 lac
9. (A)(CE 70 c )
09.09.3
14" X 14" size pre cast pile ( 1:1.5:3 ) with stone chips
850 X 45 ' - 0 " = 38250.00 rft
= 11661.59 rm @ TK 885.00 / r m = TK 103.205 lac
cft )
9. (B)
CE 70 d
09.09.4 = 850.00 no @ TK 1444.00 each 12.274 lac
9. (C)
(CE 72a )
09.14. = 2 set @ TK 161634.00 / set = TK 3.233 lac
9. (D)
(CE 72d )
09.17.
= 11661.59 rm @ TK 458.00 / rm 53.410 lac
9. (E)
(CE 68 )
09.6.
850 X 3 ' X 14 " X 14 " = 3470.83 cft
= 98.30 cum @ TK 1688.00 / cum = TK 1.659 lac
9 (F)(CE 69 )09.7.
09.7.2 For 75 tonne load = 2 test @ TK 52397.00 / test = TK 1.048 lac
09.7.3 For 125 tonne load = 2 test @ TK 78740.00 / test = TK 1.575 lac
09.8.2 For intermediate loading from 75 tonne to 125 tonne for each additiional tonne
= 30.00 tonne @ TK 500.00/ tonne = TK 0.150 lac
238.684 lac
14 X 14 X 45 X 850 / 144 cft = 52062.50
Pre-cast driven pile with reinforced cement concrete works with minimum cement content relates to mix ratio (1.1.5:3) having
minimum fcr = 30 Mpa, and satisfying a specified compressive strength f'c = 25 Mpa at 28 days on standard cylinders as per
standard practice of Code ACI / BNBC / ASTM & cement conforming to BDS EN - 197 - 1 - CEM 1 ( 32.5 to 52.5 N ) ASTM -C 150
Type - I, best quality coarse sand (F.M.2.2), 20 mm down well graded stone chips conforming to ASTM C - 33 , mixing in standard
mixture machine and fed by standard measuring boxes, in/c cost of breaking chips, screening through proper sieves, cleaning and
washing, centering and shuttering with M.S sheet, M.S angle, F.I bar, nuts & bolts, preparation of bed, laying polythene, placing of
reinforcement cage in position, casting, compacting by vibrators and tapered rods, curing for 28 days etc. in/c cost of water,
electricity & other charges, providing pile shoe as per design & drawing, driving the pile up to the design depth as per standard
practice or specified method providing head cushion, all equipments including mobilization, demobilization & hire charge of driving
set, labour,
shampering, test of materials & concrete etc. all complete as per design, drawing and accepted by the Engineer.
(rate is excluding the cost of reinforcement and its fabrication , binding, welding and placing and driving pile).
Driving 14" X 14" size pre-cast pile with automatic rig fitted with automatic diesel hammer . Before commencing driving
operation by rig fitted with automatic diesel operated hammer, contractor shall submit method statement for carrying the operation
including sequence of driving to the Engineer for approval. However, Engineer's approval shall not relieve the contractor of his
responsibilities and obligations under contract.
Labour for breaking head of hardened cast in situ bored pile/pre-cast pile up to a required length by any means but without
damaging the rest and removing the dismantled materials such as concrete to a safe distance including scraps and cleaning
concrete from steel/M.S. rods, straightening & bending of pile bars, preparation and making platform where necessary, carrying, all
sorts of handling, stacking the same properly after clearing, leveling and dressing the situ and clearing the bed etc. complete in all
respect and accepted by the Engineer.
(Measurement will be given for the actual pile head volume to be broken).
Conducting static load test for the cast in situ/pre-cast pile providing required scaffolding, bracing, jacks, pressure test gauge,
loading unloading loads, Kent ledge and other plants and equipment including staging, mobilization, demobilization, hire charge,
gunny bags & sand and filling sacs/gunny bags for loading, recording readings & preparation of results in standard forms & other
incidental charges as per standard practice and procedures in/c submission of load test report, furnishing all graph and chart etc.
complete in all respects approved and accepted by the Engineer.
Before commencing load test, contractor shall submit method statement for conducting load test to the Engineer for approval.
However, Engineer's approval shall not relieve the contractor of his responsibilities and obligations under contract
Sub Total
Pile shoe as per design and drawing
Mobilization and demobilization of automatic diesel hammer mounted pre-cast pile driving complete rig set
( Total volume of RCC in pile =
Page No 5
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 68.586 81.629605
1,032.00 1277.00 120.348 148.918 16.61% 23.74%
1,924.00 2191.00 16.354 18.624 33.24% 13.88%
106,963.00 117704.00 2.139 2.354 -33.82% 10.04%
571.00 633.00 66.588 73.818 24.67% 10.86%
2,318.00 2950.00 2.279 2.900 37.32% 27.26%
63,628.00 84508.00 1.273 1.690 21.43% 32.82%
96,222.00 117936.00 1.924 2.359 22.20% 22.57%
650.00 881.93 0.195 0.265 30.00% 35.68%
279.685 332.55666 17.18 18.90%
Rate Total
Sub Total
Page No 5
238.684 lac
10
CE 53
07.6.
CE 53 a ( A ) In Individual and combined footing of column
07.6.1.1
(I) concrete
PC 7 6 X 8 ' - 4 " X 9 ' - 6 " = 475.00 sft
deduct -12 X 2 ' - 8 " X 3 ' - 0 " = -96.00 sft
PC 12 28 X 13 ' - 0 " X 9 ' - 6 " = 3458.00 sft
PC 6 4 X 9 ' - 6 " X 6 ' - 0 " = 228.00 sft
PC 9 2 X 9 ' - 6 " X 9 ' - 6 " = 180.50 sft
PC 14 20 X 14 ' - 6 " X 11 ' - 6 " = 3335.00 sft
deduct -40 X 3 ' - 4 " X 5 ' - 9 " = -766.67 sft
PC 3 10 X 6 ' - 0 " X 5 ' - 6 " = 330.00 sft
deduct -10 X 3 ' - 0 " X 1 ' - 6 " = -45.00 sft
PC 10 12 X 13 ' - 0 " X 8 ' - 6 " = 1326.00 sft
= 8424.83 sft X 3 ' 9 "
= 31593.13 cft
= 894.74 cum @ TK 6126.00 / cum = TK 54.812 lac
07.6.1.2 (ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Perimeter of PC 7 = 29.00 rft
Perimeter of PC 12 = 45.00 rft
Perimeter of PC 6 = 31.00 rft
Perimeter of PC 9 = 38.00 rft
Perimeter of PC 14 = 42.17 rft
Perimeter of PC 3 = 20.68 rft
Perimeter of PC 10 = 43.00 rft
PC 7 6 X 29 ' - 0 " X 3 ' - 9 " = 652.50 sft
PC 12 28 X 45 ' - 0 " X 3 ' - 9 " = 4725.00 sft
PC 6 4 X 31 ' - 0 " X 3 ' - 9 " = 465.00 sft
PC 9 2 X 38 ' - 0 " X 3 ' - 9 " = 285.00 sft
PC 14 20 X 42 ' - 2 " X 3 ' - 9 " = 3162.50 sft
PC 3 10 X 20 ' - 8 " X 3 ' - 9 " = 775.00 sft
PC 10 12 X 43 ' - 0 " X 3 ' - 9 " = 1935.00 sft
= 12000.00 sft
= 1114.83 sqm @ TK 289.00 / sqm = TK 3.222 lac
BF
Pile cap
Reinforced cement concrete works using steel shutter with minimum cement content relates to mix ratio (1.1.5:3) having
minimum fcr = 30 Mpa, and satisfying a specified compressive strength f'c = 25 Mpa at 28 days on standard cylinders as
per standard practice of Code ACI / BNBC / ASTM & cement conforming to BDS EN - 197 - 1 - CEM 1 ( 32.5 to 52.5 N )
ASTM -C 150 Type - I, best quality coarse sand (F.M.2.2), 20 mm down well graded stone chips conforming to ASTM C -
33 , making, placing shutter in position and maintaining true to plumb, making shutter water tight properly, placing
reinforcement in position , mixing in standard mixture machine with hopper fed by standard measuring boxes,casting in
forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering including cost of
water, electricity, testing and other charges etc. all complete approved and accepted by the Engineer.
(rate is excluding the cost of reinforcement and its fabrication , binding, welding and placing )
Page No 6
CE 53b ( B ) In raft / mat / floor slab at plinth level
07.6.2
07.6.2.1 (I) concrete
1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft
2 X 0.5 X 3.1 X 25 ' - 0 " X 25 ' - 0 " = 1962.50 sft
= 24698.50 sft X 1 ' 0 "
= 24698.50 cft
= 699.48 cum @ TK 6126.00 / cum = TK 42.850 lac
07.6.2.2 (ii) Formwork / shuttering, prop and necessary supports etc ( steel )
2 X 116 ' - 0 " X 1 ' - 0 " = 232.00 sft
2 X 196 ' - 0 " X 1 ' - 0 " = 392.00 sft
2 X 3.1 X 25 ' - 0 " X 1 ' - 0 " = 78.50 sft
= 702.50 sft
= 65.26 sqm @ TK 306.00 / sqm = TK 0.200 lac
(I) Concrete
1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft
0.5 X 3.14 25 ' X 25 ' X 2 = 1962.5 sft
= 24698.50 sft
Deduction
( lift wall) 4 X 10 ' - 10 " X 7 ' - 6 " = 325.00 sft
( Ramp ) 1 X 18 ' - 4 " X 50 ' - 0 " = 916.67 sft
( stair) 1 X 8 ' - 0 " X 12 ' - 0 " = 96.00 sft
= 1337.67 sft
Net Area = 24698.50 - sft
(mark A) = 23360.83 sft
Net volume = 23360.83 sft X 0 ' 6 "
= 11680.42 cft
= 330.80 cum @ TK 6126.00 / cum = TK 20.265 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Bottom area same as mark A of above = 23360.83 sft
sides 2 X 116 ' - 0 " X 0 ' - 6 " = 116.00 sft
2 X 196 ' - 0 " X 0 ' - 6 " = 196.00 sft
2 X 3.1 X 25 ' - 0 " X 0 ' - 6 " = 78.50 sft
= 23751.33 sft
= 2206.55 sqm @ TK 306.00 / sqm = TK 6.752 lac
X
( - )
1337.67
Basement floor
Floor slab of Ground Floor
(semi circular portion )
Page No 7
CE 53f ( C ) In Roof slab of all types, cantilever slab and drop panel
07.6.7.1
(I) Concrete
1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft
0.5 X 3.14 25 ' X 25 ' = 981.25 sft
= 23717.25 sft
Deduction :
0.5 X 11 ' - 4 " X 10 ' - 0 " = 56.67 sft
0.5 X 11 ' - 4 " X 10 ' - 0 " = 56.67 sft
0.5 X 28 ' - 4 " X 5 ' - 10 " = 82.64 sft
(void at middle) 2 X 38 ' - 0 " X 28 ' - 0 " = 2128.00 sft
( Lobby area ) 1 X 30 ' - 0 " X 20 ' - 6 " = 615.00 sft
( middle stair) 1 X 23 ' - 2 " X 11 ' - 10 " = 274.14 sft
( side stairs void) 1 X 15 ' - 3 " X 18 ' - 4 " = 279.58 sft
1 X 15 ' - 0 " X 18 ' - 4 " = 275.00 sft
(side stair area) 2 X 10 ' - 1 " X 6 ' - 0 " = 121.00 sft
(corner stair area) 1 X 7 ' - 4 " X 14 ' - 9 " = 108.17 sft
= 3996.86 sft
Net Area = 23717.25 - sft
(mark A ) = 19720.39 sft X 0 ' 6 "
= 9860.19 cft
= 279.25 cum @ TK 6126.00 / cum = TK 17.107 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Bottom area same as above = 19720.39 sft
sides 2 X 116 ' - 0 " X 0 ' - 6 " = 116.00 sft
2 X 196 ' - 0 " X 0 ' - 6 " = 196.00 sft
2 X 3.1 X 25 ' - 0 " X 0 ' - 6 " = 78.50 sft
= 20110.89 sft
= 1868.35 sqm @ TK 488.00 / sqm = TK 9.118 lac
(I) Concrete
1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft
2 X 30 ' - 0 " X 15 ' - 0 " = 900.00 sft
= 23636.00 sft
Deduction :
(void at middle) 2 X 38 ' - 0 " X 28 ' - 0 " = 2128.00 sft
( middle stair) 1 X 23 ' - 2 " X 11 ' - 10 " = 274.14 sft
( side stairs void) 1 X 15 ' - 3 " X 18 ' - 4 " = 279.58 sft
1 X 15 ' - 0 " X 18 ' - 4 " = 275.00 sft
( side stair area) 2 X 10 ' - 1 " X 6 ' - 0 " = 121.00 sft
= 3077.72 sft
3996.86
( i ) Ground Floor Roof slab
(semi circular portion )
( - )
add projected area
(ii) 1st Floor roof slab
( - )
X
(void at Dept of
Forensic
medicine )
Page No 8
Net Area = 23636.00 - sft
( mark B ) = 20558.28 sft X 0 ' 6 "
= 10279.14 cft
= 291.11 cum @ TK 6166.38 / cum = TK 17.951 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Bottom area same as mark B of above = 20558.28 sft
sides 2 X 116 ' - 0 " X 0 ' - 6 " = 116.00 sft
2 X 196 ' - 0 " X 0 ' - 6 " = 196.00 sft
2 X 3.1 X 25 ' - 0 " X 0 ' - 6 " = 78.50 sft
= 20948.78 sft
= 1946.19 sqm @ TK 502.90 / sqm = TK 9.787 lac
(I) Concrete
area same as 1st floor roof slab= 20558.28 sft X 0 ' 6 " (mark C)
= 10279.14 cft
= 291.11 cum @ TK 6206.76 / cum = TK 18.069 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
area same as 1st floor = 20948.78 sft
= 1946.19 sqm @ TK 517.80 / sqm = TK 10.077 lac
(I) Concrete
area same as 2nd floor = 20558.28 sft X 0 ' 6 "
= 10279.14 cft
= 291.11 cum @ TK 6247.14 / cum = TK 18.186 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
area same as 2nd floor = 20948.78 sft
= 1946.19 sqm @ TK 532.70 / sqm = TK 10.367 lac
(I) Concrete
area same as 3rd floor = 20558.28 sft X 0 ' 6 "
= 10279.14 cft
= 291.11 cum @ TK 6287.52 / cum = TK 18.304 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
area same as 3rd floor = 20948.78 sft
= 1946.19 sqm @ TK 547.60 / sqm = TK 10.657 lac
3077.72
(iii) 2nd Floor roof slab
(v) 4th Floor roof slab
(iv ) 3rd Floor roof slab
Page No 9
(I) Concrete
1 X 196 ' - 0 " X 116 ' - 0 " = 22736.00 sft
Deduction :
Open front & back 2 X 28 ' - 4 " X 80 ' - 0 " = 4533.33 sft
( middle stair) 1 X 23 ' - 2 " X 11 ' - 10 " = 274.14 sft
( side stairs void) 1 X 15 ' - 3 " X 18 ' - 4 " = 279.58 sft
1 X 15 ' - 0 " X 18 ' - 4 " = 275.00 sft
( side stair area) 2 X 10 ' - 1 " X 6 ' - 0 " = 121.00 sft
= 5483.06 sft
Net Area = 22736.00 - sft
(mark D) = 17252.94 sft X 0 ' 6 "
= 8626.47 cft
= 244.31 cum @ TK 6327.90 / cum = TK 15.459 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Bottom area same as above = 17252.94 sft
sides 2 X 116 ' - 0 " X 0 ' - 6 " = 116.00 sft
2 X 196 ' - 0 " X 0 ' - 6 " = 196.00 sft
= 17564.94 sft
= 1631.82 sqm @ TK 562.50 / sqm = TK 9.179 lac
(I) Concrete
1 X 116 ' - 0 " X 30 ' - 0 " = 3480.00 sft
= 3480.00 sft X 0 ' 6 "
= 1740.00 cft
= 49.28 cum @ TK 6380.53 / cum = TK 3.144 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Bottom area same as above = 3480.00 sft
sides 2 X 116 ' - 0 " X 0 ' - 6 " = 116.00 sft
2 X 30 ' - 0 " X 0 ' - 6 " = 30.00 sft
= 3626.00 sft
= 336.86 sqm @ TK 584.86 / sqm = TK 1.970 lac
CE 53h ( D ) In Waffle or ribbed floor / roof slab
waffle roof slab of 1st floor
07.6.11(I) Concrete
0.5 X 3.14 25 ' X 25 ' = 981.25 sft
1 30 ' X 10 ' = 300 sft
= 1281.25 sft X 0 ' 6 "
= 640.63 cft
5483.06
( - )
(vi) 5th Floor roof slab
X
X
( vii ) 6th Floor roof slab ( chillakota )
Page No 10
Ribbed beam
20 X 12 ' - 6 " X 2 ' - 0 " = 500.00 sft
10 X 25 ' - 0 " X 2 ' - 0 " = 500.00 sft
4 X 30 ' - 0 " X 2 ' - 0 " = 240.00 sft
12 X 10 ' - 0 " X 2 ' - 0 " = 240.00 sft
= 1480.00 sft X 0 ' 6 "
= 740.00 cft
Total = 1380.63 cft
( mark A ) = 39.10 cum @ TK 6349.38 / cum = TK 2.483 lac
(ii) Formwork / shuttering, prop and necessary supports etc ( steel )
Bottom area same as above = 1281.25 sft
sides 1 X 78 ' - 6 " X 0 ' - 6 " = 39.25 sft
2 X 30 ' - 0 " X 0 ' - 6 " = 30.00 sft
= 1350.50 sft
add, Ribbed beam
1 X 740 ' - 0 " X 4 ' - 6 " = 3330.00 sft
Total = 4680.50 sft
( mark B ) = 434.83 sqm @ TK 466.90 / sqm = TK 2.030 lac
GF Floor Slab = 9860.19 cft
GF Roof slab = 9860.19 cft
1st Floor Roof Slab = 10279.14 cft
1st Floor waffle roof = 640.63 cft
2nd Floor Roof slab = 10279.14 cft
3rd Floor roof Slab = 10279.14 cft
4th Floor Roof Slab = 10279.14 cft
5th Floor Roof Slab = 8626.47 cft
6th Floor roof Slab = 1740.00 cft
= 71844.04 cft
sub total = TK 540.673 lac
(Total Slab volume )
Page No 11
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 279.6846 332.5567
7,099.00 8,858.00 63.517 79.25571 15.9% 24.8%
255.00 326.00 2.843 3.634337 -11.8% 27.8%
Rate Total
Page No 12
7,099.00 8,858.00 49.656 61.95959 15.9% 24.8%
260.00 328.00 0.170 0.214065 -15.0% 26.2%
7,099.00 8,858.00 23.483 29.30193 15.9% 24.8%
260.00 328.00 5.737 7.237493 -15.0% 26.2%
Page No 13
21540.61
7,099.00 8,858.00 19.824 24.73566 15.9% 24.8%
387.00 437.00 7.231 8.164677 -20.7% 12.9%
Page No 14
7,149.00 8,925.00 20.812 25.98168 15.9% 24.8%
406.00 462.00 7.902 8.991393 -19.3% 13.8%
7,199.00 8,992.00 20.957 26.17673 16.0% 24.9%
425.00 487.00 8.271 9.47794 -17.9% 14.6%
7,249.00 9,059.00 21.103 26.37177 16.0% 25.0%
444.00 512.00 8.641 9.964487 -16.7% 15.3%
7,299.00 9,126.00 21.248 26.56681 16.1% 25.0%
463.00 537.00 9.011 10.45103 -15.4% 16.0%
Page No 15
2112.226
509.3883
1602.838
7,349.00 9,193.00 17.954 22.45912 16.1% 25.1%
482.00 562.00 7.865 9.170846 -14.3% 16.6%
7,415.00 9,282.00 3.654 4.573968 16.2% 25.2%
510.00 600.00 1.718 2.021182 -12.8% 17.6%
Page No 16
7,435.00 9,295.00 2.907 3.634356 17.1% 25.0%
458.00 568.00 1.992 2.469829 -1.9% 24.0%
sub total 606.179 735.3713 12.1% 21.3%
Page No 11
BF 540.673 lac
CE 53 g ( E ) In Stair case slabs and steps.
7.6.10 (i) Ground Floor
(I) Concrete
Basement to GF Ramp 1 X 61 ' - 0 " X 18 ' - 4 " X 0 ' - 10 " = 931.94 cft
GF entrance ramp 2 X 8 ' - 0 " X 6 ' - 0 " X 0 ' - 8 " = 64.00 cft
Basement stair : slab 2 X 9 ' - 9 " X 3 ' - 0 " X 0 ' - 8 " = 39.00 cft
landing 0.5 X 3.14 3 ' X 3 ' X 0 ' - 8 " = 9.42 cft
steps 22 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 0 " = 13.75 cft
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " X 0 ' - 8 " = 326.67 cft
landing 3.1 X 3 ' - 0 " X 3 ' - 0 " X 0 ' - 8 " = 84.00 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 0 " = 27.50 cft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " X 0 ' - 8 " = 544.44 cft
landing 1 X 11 ' - 10 " X 4 ' - 10 " X 0 ' - 8 " = 533.81 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 5 ' - 0 " = 45.83 cft
long side stair : slab 4 X 11 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 508.15 cft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 203.26 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 4 ' - 8 " = 42.78 cft
corner stair : slab 2 X 11 ' - 8 " X 3 ' - 6 " X 0 ' - 8 " = 381.11 cft
landing 0.5 X 3.14 4 ' X 4 ' X 0 ' - 8 " = 16.75 cft
steps 22 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 6 " = 16.04 cft
Entrance stair : slab 1 X 28 ' - 4 " X 4 ' - 2 " X 0 ' - 8 " = 78.70 cft
steps 5 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 28 ' - 4 " = 29.51 cft
Back Entrance : slab 1 X 5 ' - 10 " X 4 ' - 2 " X 0 ' - 8 " = 16.20 cft
steps 5 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 5 ' - 10 " = 6.08 cft
Side Entrance : slab 4 X 8 ' - 6 " X 4 ' - 2 " X 0 ' - 8 " = 94.44 cft
steps 20 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 8 ' - 6 " = 35.42 cft
= 4048.82 cft
= 114.6649 cum @ TK 6309.00 / cum = TK 7.234 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Basement to GF Ramp 1 X 61 ' - 0 " X 18 ' - 0 " = 1098.00 sft
GF entrance ramp 2 X 8 ' - 0 " X 6 ' - 0 " = 96.00 sft
Basement stair : slab 2 X 9 ' - 9 " X 3 ' - 0 " = 58.50 sft
landing 0.5 X 3.14 3 ' X 3 ' = 5.09 sft
steps 22 X 3 ' - 0 " X 0 ' - 6 " = 33.00 sft
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 3 ' - 0 " = 28.26 sft
steps 44 X 3 ' - 0 " X 0 ' - 6 " = 66.00 sft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
steps 44 X 4 ' - 10 " X 0 ' - 6 " = 106.33 sft
long side stair : slab 4 X 11 ' - 8 " X 4 ' - 8 " = 217.78 sft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " = 68.38 sft
steps 44 X 4 ' - 8 " X 0 ' - 6 " = 102.67 sft
corner stair : slab 2 X 11 ' - 8 " X 3 ' - 6 " = 81.67 sft
landing 0.5 X 3.14 4 ' X 4 ' = 6.95 sft
steps 22 X 4 ' - 0 " X 0 ' - 6 " = 44.00 sft
Entrance stair : slab 1 X 28 ' - 4 " X 4 ' - 2 " = 118.06 sft
steps 5 X 28 ' - 4 " X 0 ' - 6 " = 70.83 sft
Back Entrance : slab 1 X 5 ' - 10 " X 4 ' - 2 " = 24.31 sft
steps 5 X 5 ' - 10 " X 0 ' - 6 " = 14.58 sft
Side Entrance : slab 4 X 8 ' - 6 " X 4 ' - 2 " = 141.67 sft
steps 20 X 8 ' - 6 " X 0 ' - 6 " = 85.00 sft
X
X
X
X
Page No 12
Ramp side 2 X 61 ' - 0 " X 0 ' - 10 " = 101.67 sft
Basement stair side 1 X 2 X = 44.40 sft
steps side 7 X 2 X = 310.80 sft
Entrance stair side 2 X 5 ' - 0 " X 1 ' - 0 " = 10.00 sft
Back stair side 2 X 5 ' - 0 " X 1 ' - 0 " = 10.00 sft
Side stair side 2 X 5 ' - 0 " X 1 ' - 0 " = 10.00 sft
= 3384.46 sft
= 314.42 sqm
@ TK 390.00 / sqm = TK 1.226 lac
(ii) 1st Floor
(I) Concrete
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " X 0 ' - 8 " = 326.67 cft
landing 3.1 X 3 ' - 0 " X 4 ' - 8 " X 0 ' - 8 " = 130.67 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 0 " = 27.50 cft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " X 0 ' - 8 " = 544.44 cft
landing 1 X 11 ' - 10 " X 4 ' - 10 " X 0 ' - 8 " = 533.81 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 5 ' - 0 " = 45.83 cft
long side stair : slab 4 X 11 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 508.15 cft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 203.26 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 4 ' - 8 " = 42.78 cft
= 2363.11 cft
= 66.9247 cum @ TK 6349.38 / cum = TK 4.249 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 4 ' - 8 " = 43.96 sft
steps 44 X 3 ' - 0 " X 0 ' - 6 " = 66.00 sft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
steps 44 X 5 ' - 0 " X 0 ' - 6 " = 110.00 sft
long side stair : slab 4 X 11 ' - 8 " X 4 ' - 8 " = 217.78 sft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " = 68.38 sft
steps 44 X 4 ' - 8 " X 0 ' - 6 " = 102.67 sft
Stair slab side 6 X 2 X = 266.40 sft
= 1305.71 sft
= 121.3038 sqm @ TK 404.90 / sqm = TK 0.491 lac
(iii) 2nd Floor
(I) Concrete
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " X 0 ' - 8 " = 326.67 cft
landing 3.1 X 3 ' - 0 " X 4 ' - 8 " X 0 ' - 8 " = 130.67 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 0 " = 27.50 cft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " X 0 ' - 8 " = 544.44 cft
landing 1 X 11 ' - 10 " X 4 ' - 10 " X 0 ' - 8 " = 533.81 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 5 ' - 0 " = 45.83 cft
long side stair : slab 4 X 11 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 508.15 cft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " X 0 ' - 8 " = 203.26 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 4 ' - 8 " = 42.78 cft
= 2363.11 cft
= 66.9247 cum @ TK 6389.76 / cum = TK 4.276 lac
22.20 sft
22.20 sft
22.20 sft
Page No 13
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 4 ' - 8 " = 43.96 sft
steps 44 X 3 ' - 0 " X 0 ' - 6 " = 66.00 sft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
steps 44 X 5 ' - 0 " X 0 ' - 6 " = 110.00 sft
long side stair : slab 4 X 11 ' - 8 " X 4 ' - 8 " = 217.78 sft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " = 68.38 sft
steps 44 X 4 ' - 8 " X 0 ' - 6 " = 102.67 sft
Stair slab side 6 X 2 X = 266.40 sft
= 1305.71 sft
= 121.3038 sqm @ TK 419.80 / sqm = TK 0.509 lac
(iv) 3rd Floor
(I) Concrete
area same as 2nd Floor = 2363.11 cft
= 66.9247 cum @ TK 6430.14 / cum = TK 4.303 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
area same as 2nd Floor = 1305.71 sft
= 121.3038 sqm @ TK 434.70 / sqm = TK 0.527 lac
(v) 4th Floor
(I) Concrete
area same as 3rd Floor = 2363.11 cft
= 66.9247 cum @ TK 6470.52 / cum = TK 4.330 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
area same as 3rd Floor = 1305.71 sft
= 121.3038 sqm @ TK 449.60 / sqm = TK 0.545 lac
(vi) 5th Floor
(I) Concrete
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " X 0 ' - 8 " = 326.67 cft
landing 3.1 X 3 ' - 0 " X 4 ' - 8 " X 0 ' - 8 " = 130.67 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 3 ' - 0 " = 27.50 cft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " X 0 ' - 8 " = 544.44 cft
landing 1 X 11 ' - 10 " X 4 ' - 10 " X 0 ' - 8 " = 533.81 cft
steps 44 X 0.5 X 0 ' - 10 " X 0 ' - 6 " X 5 ' - 0 " = 45.83 cft
= 1608.93 cft
= 45.56573 cum @ TK 6510.90 / cum = TK 2.967 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Side stair : slab 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 4 ' - 8 " = 43.96 sft
steps 44 X 3 ' - 0 " X 0 ' - 6 " = 66.00 sft
middle stair : slab 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
steps 44 X 5 ' - 0 " X 0 ' - 6 " = 110.00 sft
Stair slab side 4 X 2 X = 177.60 sft
= 828.09 sft
= 76.93123 sqm @ TK 464.50 / sqm = TK 0.357 lac
(Total RCC volume in stair from Basement to 5th floor = cft )
22.20 sft
22.20 sft
15110.19
Page No 14
CE 53 e ( F ) In Tee beam, Ell beam , Rectangular beam
7.6.6 (i) Ground Floor
(I) Concrete
GF Floor beams
Long direction 4 X 190 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 1520.00 cft
2 X 219 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 1095.00 cft
Short direction 10 X 80 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 1600.00 cft
21 X 30 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 1575.00 cft
semi circular , 2 X 3.1 X 25 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 314.00 cft
GF Roof beams
Long direction 4 X 190 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 1520.00 cft
2 X 219 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 1095.00 cft
Short direction 10 X 84 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 1680.00 cft
14 X 30 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 1050.00 cft
Stair beam 2 X 11 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 44.00 cft
semi circular , 2 X 3.1 X 25 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 314.00 cft
= 11807.00 cft
= 334.38 cum @ TK 6126.00 / cum = TK 20.484 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
GF Floor beams
Long direction 4 X 190 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3040.00 sft
2 X 219 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 2190.00 sft
Short direction 10 X 80 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3200.00 sft
21 X 30 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 3150.00 sft
semi circular , 2 X 3.1 X 25 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 628.00 sft
GF Roof beams
Long direction 4 X 190 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3040.00 sft
2 X 219 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 2190.00 sft
Short direction 10 X 84 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3360.00 sft
14 X 30 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 2100.00 sft
Stair beam 2 X 11 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 88.00 sft
semi circular , 2 X 3.1 X 25 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 628.00 sft
= 23614.00 sft
= 2193.794 sqm @ TK 386.00 / sqm = TK 8.468 lac
(ii) 1st Floor
(I) Concrete
Long direction 4 X 190 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 1520.00 cft
2 X 219 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 1095.00 cft
Short direction 10 X 80 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 1600.00 cft
15 X 30 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 1125.00 cft
semi circular , 2X 3.1 X 25 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 314.00 cft
stair landing beam 2 X 11 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 44.00 cft
= 5698.00 cft
= 161.37 cum @ TK 6166.38 / cum = TK 9.951 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Long direction 4 X 190 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3040.00 sft
2 X 219 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 2190.00 sft
Short direction 10 X 80 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3200.00 sft
15 X 30 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 2250.00 sft
semi circular , 2X 3.1 X 25 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 628.00 sft
stair landing beam 2 X 11 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 88.00 sft
= 11396.00 sft
= 1058.714 sqm @ TK 400.90 / sqm = TK 4.244 lac
Page No 15
(iii) 2nd Floor
(I) Concrete
Quantity same as 1st floor = 5698.00 cft
= 161.37 cum @ TK 6206.76 / cum = TK 10.016 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Quantity same as 1st floor = 11396.00 sft
= 1058.714 sqm @ TK 415.80 / sqm = TK 4.402 lac
(iv) 3rd Floor
(I) Concrete
Quantity same as 2nd floor = 5698.00 cft
= 161.37 cum @ TK 6247.14 / cum = TK 10.081 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Quantity same as 2nd floor = 11396.00 sft
= 1058.714 sqm @ TK 430.70 / sqm = TK 4.560 lac
(v) 4th Floor
(I) Concrete
Quantity same as 3rd floor = 5698.00 cft
= 161.37 cum @ TK 6287.52 / cum = TK 10.146 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Quantity same as 3rd floor = 11396.00 sft
= 1058.714 sqm @ TK 445.60 / sqm = TK 4.718 lac
(vi) 5th Floor
(I) Concrete
Long direction 4 X 190 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 1520.00 cft
2 X 190 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 950.00 cft
Short direction 20 X 20 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 800.00 cft
20 X 20 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 1000.00 cft
4 X 30 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 300.00 cft
= 4570.00 cft
= 129.43 cum @ TK 6327.90 / cum = TK 8.190 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Long direction 4 X 190 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 3040.00 sft
2 X 190 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 1900.00 sft
Short direction 20 X 20 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 1600.00 sft
20 X 20 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 2000.00 sft
4 X 30 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 600.00 sft
= 9140.00 sft
= 849.1267 sqm @ TK 460.50 / sqm = TK 3.910 lac
(vii) 6th Floor
(I) Concrete
Long direction 3 X 110 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " = 660.00 cft
Short direction 4 X 30 ' - 0 " X 1 ' - 0 " X 2 ' - 0 " 240.00
3 X 30 ' - 0 " X 1 ' - 0 " X 2 ' - 6 " = 225.00 cft
= 1125.00 cft
= 31.86 cum @ TK 6380.53 / cum = TK 2.033 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Long direction 3 X 110 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 1320.00 sft
Short direction 4 X 30 ' - 0 " X( 1 ' - 0 " + 3 ' - 0 ")= 480.00 sft
3 X 30 ' - 0 " X( 1 ' - 0 " + 4 ' - 0 ")= 450.00 sft
= 2250.00 sft
= 209.0301 sqm @ TK 482.86 / sqm = TK 1.009 lac
( Total RCC in Beam From GF to 6th Floor = 45992.00 cft )
Page No 16
CE 53d ( G ) In Pedestal, Column, Capital, Lift wall and wall
7.6.4 (i) Below PL & in GF
(I) Concrete
Below PL
Column C1 32 X 3 ' - 0 " X 3 ' - 0 " X 10 ' - 0 " = 2880.00 cft
column C2 28 X 3 ' - 0 " X 2 ' - 3 " X 10 ' - 0 " = 1890.00 cft
Column C3 4 X 1 ' - 3 " X 2 ' - 6 " X 10 ' - 0 " = 125.00 cft
Column C4 18 X 1 ' - 0 " X 2 ' - 1 " X 10 ' - 0 " = 375.00 cft
= 5270.00 cft
GF column
Column C1 32 X 2 ' - 9 " X 2 ' - 9 " X 12 ' - 0 " = 2904.00 cft
column C2 28 X 2 ' - 9 " X 2 ' - 0 " X 12 ' - 0 " = 1848.00 cft
Column C3 4 X 1 ' - 3 " X 2 ' - 6 " X 12 ' - 0 " = 150.00 cft
Column C4 18 X 1 ' - 0 " X 2 ' - 1 " X 12 ' - 0 " = 450.00 cft
= 5352.00 cft
Basement wall
Short direction 2 X 60 ' - 0 " X 1 ' - 0 " X 10 ' - 0 " = 1200.00 cft
Semi circular 2 X 3.14 25 ' X 1 ' - 0 " X 10 ' - 0 " = 1570.00 cft
Long direction 2 X 192 ' - 0 " X 1 ' - 0 " X 10 ' - 0 " = 3840.00 cft
= 6610.00 cft 614.084
Shear wall around side stair4 X 3.14 4 ' X 1 ' - 0 " X 10 ' - 0 " = 502.40 cft
Lift wall in basement floor 4 X 36 ' - 8 " X 0 ' - 10 " X 10 ' - 6 " = 1283.33 cft
Lift wall in GF 4 X 36 ' - 8 " X 0 ' - 10 " X 12 ' - 6 " = 1527.78 cft
= 3313.51 cft
Total (col+ lift wall+basement wall) = 20545.51 cft
= 581.86 cum @ TK 6195.00 / cum = TK 36.046 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
basement floor column
Column C1 32 X 2 X( 3 ' - 0 " + 3 ' - 0 ") = rft
Column C2 28 X 2 X( 3 ' - 0 " + 2 ' - 3 ") = rft
Column C3 4 X 2 X( 1 ' - 3 " + 2 ' - 6 ") = rft
Column C4 14 X 2 X( 1 ' - 0 " + 2 ' - 1 ") = rft
= ' X 10 '
= sft
Basement floor lift wall 4 X 75 ' - 0 " X 10 ' - 6 " = sft
Shear wall 2 X 26 ' - 2 " X 10 ' - 6 " = sft
Basement floor RCC wall 2 X( 190 ' - 0 " + 60 ' - 0 ") = rft
2 X 3.1 X 25 ' - 0 " = rft
= X 10 ' X 2 ( for both sides )
= sft
GF column face
Column C1 32 X 2 X( 2 ' - 9 " + 2 ' - 9 ") = rft
Column C2 28 X 2 X( 2 ' - 9 " + 2 ' - 0 ") = rft
Column C3 4 X 2 X( 1 ' - 3 " + 2 ' - 6 ") = rft
Column C4 18 X 2 X( 1 ' - 0 " + 2 ' - 1 ") = rft
= ' X12 '
= sft
GF lift wall 4 X 75 ' - 0 " X 12 ' - 6 " = sft
Shear wall 2 X 26 ' - 2 " X 12 ' - 6 " = sft
Total = sft
= sqm @ TK 319.00 / sqm = TK 11.349 lac3557.69
38295.00
rft
30.00
13140.00
111.00
266.00
3750.00
759.00
9108.00
86.33
794.33
7943.33
X
X
294.00
3150.00
500.00
157.00
657.00
30.00
549.50
654.17
352.00
384.00
Page No 17
(ii) 1st Floor
(I) Concrete
Column C1 32 X 2 ' - 9 " X 2 ' - 9 " X 12 ' - 0 " = 2904.00 cft
column C2 28 X 2 ' - 9 " X 2 ' - 0 " X 12 ' - 0 " = 1848.00 cft
Column C3 4 X 1 ' - 3 " X 2 ' - 6 " X 12 ' - 0 " = 150.00 cft
Column C4 18 X 1 ' - 0 " X 2 ' - 1 " X 12 ' - 0 " = 450.00 cft
= 5352.00 cft
Lift wall 4 X 36 ' - 8 " X 0 ' - 10 " X 12 ' - 6 " = 1527.78 cft
Shear wall 2 X 3.14 4 ' X 1 ' - 0 " X 12 ' - 0 " = 301.44 cft
total lift & shear wall = 1829.22 cft
total ( column + lift wall ) = 7181.22 cft
= 203.38 cum @ TK 6235.38 / cum = TK 12.681 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
column face
Column C1 32 X 2 X( 2 ' - 9 " + 2 ' - 9 ") = rft
Column C2 28 X 2 X( 2 ' - 9 " + 2 ' - 0 ") = rft
Column C3 4 X 2 X( 1 ' - 3 " + 2 ' - 6 ") = rft
Column C4 18 X 2 X( 1 ' - 0 " + 2 ' - 1 ") = rft
= rft X 12'
= sft
lift wall 4 X 75 ' - 0 " X 12 ' - 6 " = sft
Shear wall 2 X 26 ' - 2 " X 12 ' - 6 " = sft
Total = sft
= sqm @ TK 333.90 / sqm = TK 4.191 lac
(iii) 2nd Floor
(I) Concrete Quantity same as 1st floor = 7181.22 cft
= 203.38 cum @ TK 6275.76 / cum = TK 12.763 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Quantity same as 1st floor = 13512.17 sft
= 1255.31 sqm @ TK 348.80 / sqm = TK 4.379 lac
(iv) 3rd Floor
(I) Concrete Quantity same as 2nd floor = 7181.22 cft
= 203.38 cum @ TK 6316.14 / cum = TK 12.846 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Quantity same as 2nd floor = 13512.17 sft
= 1255.31 sqm @ TK 363.70 / sqm = TK 4.566 lac
(v) 4th Floor
(I) Concrete Quantity same as 3rd floor = 7181.22 cft
= 203.38 cum @ TK 6356.52 / cum = TK 12.928 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Quantity same as 3rd floor = 13512.17 sft
= 1255.31 sqm @ TK 378.60 / sqm = TK 4.753 lac
(vi) 5th Floor
(I) Concrete
Column C1 32 X 2 ' - 9 " X 2 ' - 9 " X 11 ' - 6 " = 2783.00 cft
column C2 28 X 2 ' - 9 " X 2 ' - 0 " X 11 ' - 6 " = 1771.00 cft
Column C3 4 X 1 ' - 3 " X 2 ' - 6 " X 11 ' - 6 " = 143.75 cft
Column C4 16 X 1 ' - 0 " X 2 ' - 1 " X 11 ' - 6 " = 383.33 cft
= 5081.08 cft
Lift wall 4 X 36 ' - 8 " X 0 ' - 10 " X 12 ' - 0 " = 1466.67 cft
Shear wall 2 X 3.14 4 ' X 1 ' - 0 " X 12 ' - 0 " = 301.44 cft
lift & shear wall = 1768.11 cft
total ( column + lift wall + shear wall) = 6849.19 cft
= 193.97 cum @ TK 6396.90 / cum = TK 12.408 lac
30.00
13512.17
1255.31
111.00
759.00
9108.00
3750.00
266.00
654.17
X
X
352.00
Page No 18
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Column C1 : 2X 32 X( 2 ' - 9 " + 2 ' - 9 ") X 11 ' - 6 " = 4048.00 sft
Column C2 : 2X 28 X( 2 ' - 9 " + 2 ' - 0 ") X 11 ' - 6 " = 3059.00 sft
Column C3 : 2X 4 X( 1 ' - 3 " + 2 ' - 6 ") X 11 ' - 6 " = 345.00 sft
Column C4 : 2X 16 X( 1 ' - 0 " + 2 ' - 1 ") X 11 ' - 6 " = 1134.67 sft
= 8586.67 sft
lift wall 4 X 75 ' - 0 " X 12 ' - 0 " = sft
Shear wall 2 X 26 ' - 2 " X 12 ' - 0 " = sft
Total = 12814.67 sft
= 1190.51 sqm @ TK 393.50 / sqm = TK 4.685 lac
(vii) 6th Floor
(I) Concrete
Column C1 8 X 2 ' - 9 " X 2 ' - 9 " X 11 ' - 6 " = 695.75 cft
column C2 4 X 2 ' - 9 " X 2 ' - 0 " X 11 ' - 6 " = 253.00 cft
Column C4 6 X 1 ' - 0 " X 2 ' - 1 " X 11 ' - 6 " = 143.75 cft
= 1092.50 cft
Lift wall 4 X 36 ' - 8 " X 0 ' - 10 " X 12 ' - 0 " = 1466.67 cft
Shear wall 2 X 3.14 4 ' X 1 ' - 0 " X 12 ' - 0 " = 301.44 cft
lift & shear wall = 1768.11 cft
total ( column + lift wall + shear wall) = 2860.61 cft
= 81.01 cum @ TK 6449.53 / cum= TK 5.225 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
Column C1 : 2X 8 X( 2 ' - 9 " + 2 ' - 9 ") X 11 ' - 6 " = 1012.00 sft
Column C2 : 2X 4 X( 2 ' - 9 " + 2 ' - 0 ") X 11 ' - 6 " = 437.00 sft
Column C3 : 2X 6 X( 1 ' - 0 " + 2 ' - 1 ") X 11 ' - 6 " = 425.50 sft
= 1874.50 sft
lift wall 4 X 75 ' - 0 " X 12 ' - 0 " = sft
Shear wall 2 X 26 ' - 2 " X 12 ' - 0 " = sft
Total = 6102.50 sft
= 565.36 sqm @ TK 415.86 / sqm = TK 2.351 lac
( Total RCC in Column below GF =
( Total RCC in Column above GF =
( Total RCC in lift wall + shear wall =
sub Total = TK 815.073 lac
3600.00
3600.00
628.00
628.00
5270.00
cft )
32933.58
cft )
cft )
12900.89
X
Page No 19
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 606.17903 735.3713
7,335.00 9161.00 8.411 10.50445 16.3% 24.9%
Rate Total
Page No 20
301.00 362.00 0.946 1.138214 -22.82 20.3%
7,385.00 9228.00 4.942 6.175811 16.31 25.0%
320.00 387.00 0.388 0.469446 -20.97 20.9%
7,435.00 9295.00 4.976 6.220651 16.36 25.0%
Page No 21
339.00 412.00 0.411 0.499772 -19.25 21.5%
7,485.00 9362.00 5.009 6.26549 16.40 25.1%
358.00 437.00 0.434 0.530098 -17.64 22.1%
7,535.00 9429.00 5.043 6.31033 16.45 25.1%
377.00 462.00 0.457 0.560424 -16.15 22.5%
7,585.00 9496.00 3.456 4.326922 16.50 25.2%
396.00 487.00 0.305 0.374655 -14.75 23.0%
Page No 22
7,099.00 8858.00 23.738 29.61949 15.88 24.8%
298.00 361.00 6.538 7.919597 -22.80 21.1%
7,149.00 8925.00 11.536 14.40234 15.94 24.8%
317.00 386.00 3.356 4.086637 -20.93 21.8%
Page No 23
7,199.00 8992.00 11.617 14.51045 15.99 24.9%
336.00 411.00 3.557 4.351315 -19.19 22.3%
7,249.00 9059.00 11.698 14.61857 16.04 25.0%
355.00 436.00 3.758 4.615994 -17.58 22.8%
7,299.00 9126.00 11.778 14.72669 16.09 25.0%
374.00 461.00 3.960 4.880673 -16.07 23.3%
7,349.00 9193.00 9.511 11.89805 16.14 25.1%
393.00 486.00 3.337 4.126756 -14.66 23.7%
7,415.00 9282.00 2.362 2.957307 16.21 25.2%
421.00 524.00 0.880 1.095318 -12.81 24.5%
Page No 24
7,188.00 8971.00 41.824 52.19875 16.03 24.8%
254.00 314.00 9.037 11.17115 -20.38 23.6%
Page No 25
7,238.00 9038.00 14.720 18.38115 16.08 24.9%
273.00 339.00 3.427 4.255504 -18.24 24.2%
7,288.00 9105.00 14.822 18.51741 16.13 24.9%
292.00 364.00 3.666 4.569332 -16.28 24.7%
7,338.00 9172.00 14.924 18.65368 16.18 25.0%
311.00 389.00 3.904 4.883159 -14.49 25.1%
7,388.00 9239.00 15.025 18.78994 16.23 25.1%
330.00 414.00 4.143 5.196987 -12.84 25.5%
7,438.00 9306.00 14.428 18.05114 16.28 25.1%
Page No 26
349.00 439.00 4.155 5.226346 -11.31 25.8%
7,504.00 9395.00 6.079 7.611271 16.35 25.2%
377.00 477.00 2.131 2.696769 -9.34 26.5%
900.87027 1102.76 10.53 22.4%
Page No 19
BF 815.07273 lac
11
CE 51
7.4
CE 51 e ( H ) In Tie Beams and Lintels.
7.4.5
(I) GF
(I) Concrete
Lintel for 10" wall
Basement ramp side wall 1 X 60 ' - 0 " = 60.00 rft
GF walls
semi circular part 3.1 X 25 ' - 0 " = 78.50 rft
2 X 11 ' - 3 " = 22.50 rft
Dept of Forensic medicine side14 X 20 ' - 0 " = 280.00 rft
General office side 8 X 20 ' - 0 " = 160.00 rft
1 X 18 ' - 4 " = 18.33 rft
1 X 10 ' - 0 " = 10.00 rft
1 X 10 ' - 6 " = 10.50 rft
2 X 7 ' - 1 " = 14.17 rft
2 X 5 ' - 5 " = 10.83 rft
1 X 17 ' - 4 " = 17.33 rft
1 X 7 ' - 10 " = 7.83 rft
1 X 2 ' - 5 " = 2.42 rft
between lift 4 X 2 ' - 11 " = 11.67 rft
side stair c .g 1 X 7 ' - 6 " = 7.50 rft
2 X 7 ' - 9 " = 15.50 rft
1 X 7 ' - 3 " = 7.25 rft
( mark A ) = 734.33 rft
= 734.33 rft X 0 ' - 10 " X 0 ' - 6 "
= 305.97 cft
Lintel for 5" wall
Basement 4 X 28 ' - 4 " = 113.33 rft
4 X 14 ' - 7 " = 58.33 rft
back entry 2 X 5 ' - 0 " = 10.00 rft
1 X 9 ' - 7 " = 9.58 rft
lift side inspection room 4 X 11 ' - 9 " = 47.00 rft
4 X 4 ' - 3 " = 17.00 rft
Male toilet 1 X 11 ' - 2 " = 11.17 rft
1 X 19 ' - 7 " = 19.58 rft
1 X 11 ' - 3 " = 11.25 rft
4 X 4 ' - 9 " = 19.00 rft
1 X 8 ' - 6 " = 8.50 rft
2 X 4 ' - 2 " = 8.33 rft
Reinforced cement concrete works using steel shutter with minimum cement content relates to mix ratio
(1:2:4) having minimum fcr = 27 Mpa, and satisfying a specified compressive strength f'c = 22 Mpa at 28
days on standard cylinders as per standard practice of Code ACI / BNBC / ASTM & cement conforming to
BDS EN - 197 - 1 - CEM 1 ( 32.5 to 52.5 N ) ASTM -C 150 Type - I, best quality coarse sand (F.M.2.2), 20
mm down well graded stone chips conforming to ASTM C - 33 , making, placing shutter in position and
maintaining true to plumb, making shutter water tight properly, placing reinforcement in position , mixing in
standard mixture machine with hopper fed by standard measuring boxes,casting in forms, compacting by
vibrator machine and curing at least for 28 days, removing centering - shuttering including cost of water,
electricity, testing and other charges etc. all complete approved and accepted by the Engineer.
(rate is excluding the cost of reinforcement and its fabrication , binding, welding and placing )
Page No 20
Female toilet 1 X 11 ' - 2 " = 11.17 rft
2 X 19 ' - 7 " = 39.17 rft
1 X 8 ' - 6 " = 8.50 rft
4 X 4 ' - 9 " = 19.00 rft
void box 12 X 7 ' - 6 " = 90.00 rft
4 X 8 ' - 4 " = 33.33 rft
2 X 8 ' - 0 " = 16.00 rft
( mark B ) = 550.25 rft X 0 ' - 5 " X 0 ' - 6 "
= 114.64 cft
= 420.61 cft
= 11.91 cum = TK 0.762 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
10 " lintel = 734.33 rft X1.83 rft = sft
5 " lintel = 550.25 rft X1.43 rft = sft
Total = 2130.69 sft
= 197.95 sqm = TK 0.631 lac
(ii) 1st Floor
(I) Concrete
Lintel for 10" wall
Dept of anatomy 3.1 X 25 ' - 0 " = 78.50 rft
2 X 13 ' - 0 " = 26.00 rft
14 X 20 ' - 0 " = 280.00 rft
between lift 4 X 2 ' - 11 " = 11.67 rft
office block side 12 X 20 ' - 0 " = 240.00 rft
(mark C) = 636.17 rft X 0 ' - 10 " X 0 ' - 6 "
= 265.07 cftLintel for 5" wall
lobby side 2 X 20 ' - 11 " = 41.83 rft
semicircular side wall 1 X 28 ' - 4 " = 28.33 rft
lift side inspection room 4 X 16 ' - 0 " = 64.00 rft
corner stair side 1 X 10 ' - 3 " = 10.25 rft
1 X 21 ' - 3 " = 21.25 rft
Male toilet 1 X 11 ' - 2 " = 11.17 rft
1 X 19 ' - 7 " = 19.58 rft
1 X 11 ' - 3 " = 11.25 rft
4 X 4 ' - 9 " = 19.00 rft
1 X 8 ' - 6 " = 8.50 rft
2 X 4 ' - 2 " = 8.33 rft
Female toilet 1 X 11 ' - 2 " = 11.17 rft
2 X 19 ' - 7 " = 39.17 rft
1 X 8 ' - 6 " = 8.50 rft
4 X 4 ' - 9 " = 19.00 rft
void box 15 X 7 ' - 6 " = 112.50 rft
5 X 8 ' - 4 " = 41.67 rft
2 X 8 ' - 0 " = 16.00 rft
(mark D) = 491.50 rft X 0 ' - 5 " X 0 ' - 6 "
= 102.40 cft
= 367.47 cft
= 10.41 cum = TK 0.670 lac
@ TK 319 / sqm
1343.83
Total in GF
/ cum@ TK 6400
786.86
Total in 1st Floor
/ cum@ TK 6440.38
Page No 21
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
10 " lintel = 636.17 rft X1.83 rft = sft
5 " lintel = 491.50 rft X1.43 rft = sft
Total = 1867.03 sft
= 173.45 sqm = TK 0.579 lac
(iii) 2nd Floor
(I) Concrete
Lintel for 10" wall
2 X 2 X 2 ' - 11 " = 11.67 rft
2 X 3.1 X 25 ' - 0 " = 157.00 rft
2 X 2 X 13 ' - 0 " = 52.00 rft
2 X 1 X 28 ' - 4 " = 56.67 rft
2 X 14 X 20 ' - 0 " = 560.00 rft
2 X 2 X 10 ' - 1 " = 40.33 rft
(mark E) = 877.67 rft X 0 ' - 10 " X 0 ' - 6 "
= 365.69 cft
Lintel for 5" wall
Male toilet 1 X 11 ' - 2 " = 11.17 rft
1 X 19 ' - 7 " = 19.58 rft
1 X 11 ' - 3 " = 11.25 rft
4 X 4 ' - 9 " = 19.00 rft
1 X 8 ' - 6 " = 8.50 rft
2 X 4 ' - 2 " = 8.33 rft
lift side inspection 4 X 16 ' - 0 " = 64.00 rft
Female toilet 1 X 11 ' - 2 " = 11.17 rft
2 X 19 ' - 7 " = 39.17 rft
1 X 8 ' - 6 " = 8.50 rft
4 X 4 ' - 9 " = 19.00 rft
void box 17 X 7 ' - 6 " = 127.50 rft
4 X 8 ' - 4 " = 33.33 rft
3 X 8 ' - 0 " = 24.00 rft
(mark F) = 404.50 rft X 0 ' - 5 " X 0 ' - 6 "
= 84.27 cft
= 449.97 cft
= 12.74 cum = TK 0.826 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
10 " lintel = 877.67 rft X1.83 rft = sft
5 " lintel = 404.50 rft X1.43 rft = sft
Total = 2184.57 sft
= 202.95 sqm = TK 0.708 lac
1164.19
702.85
@ TK
578.44
/ sqm
333.9 / sqm
Total in 2nd Floor
6480.76 / cum@ TK
1606.13
348.8@ TK
Total lintel for 10" wall =
Page No 22
(iv) 3rd Floor
(I) Concrete
Lintel for 10" wall ( same as 2nd floor ) = 877.67 rft X 0 ' - 10 " X 0 ' - 6 "
= 365.69 cft
Lintel for 5" wall ( same as 2nd floor ) = 404.50 rft X 0 ' - 5 " X 0 ' - 6 "
= 84.27 cft
= 449.97 cft
= 12.74 cum = TK 0.831 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
( same as 2nd floor ) = 2184.57 sft
= 202.95 sqm = TK 0.738 lac
(v) 4th Floor
(I) Concrete
Lintel for 10" wall ( same as 3rd floor ) = 877.67 rft X 0 ' - 10 " X 0 ' - 6 "
= 365.69 cft
Lintel for 5" wall ( same as 3rd floor ) = 404.50 rft X 0 ' - 5 " X 0 ' - 6 "
= 84.27 cft
= 449.97 cft
= 12.74 cum = TK 0.836 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
( same as 3rd floor ) = 2184.57 sft
= 202.95 sqm = TK 0.768 lac
(vi) 5th Floor
(I) Concrete
Lintel for 10" wall
outer wall 2 X 20 X 20 ' - 0 " = 800.00 rft
2 X 2 X 2 ' - 11 " = 11.67 rft
(mark G) = 811.67 rft X 0 ' - 10 " X 0 ' - 6 "
Total lintel for 10" wall = = 338.19 cft
Lintel for 5" wall
lift side inspection 4 X 16 ' - 0 " = 64.00 rft
Male toilet 1 X 11 ' - 2 " = 11.17 rft
1 X 20 ' - 0 " = 20.00 rft
1 X 19 ' - 7 " = 19.58 rft
1 X 11 ' - 3 " = 11.25 rft
4 X 4 ' - 9 " = 19.00 rft
1 X 8 ' - 6 " = 8.50 rft
2 X 4 ' - 2 " = 8.33 rft
Female toilet 1 X 11 ' - 2 " = 11.17 rft
2 X 19 ' - 7 " = 39.17 rft
1 X 8 ' - 6 " = 8.50 rft
4 X 4 ' - 9 " = 19.00 rft
2 X 20 ' - 0 " = 40.00 rft
void box 17 X 7 ' - 6 " = 127.50 rft
4 X 8 ' - 4 " = 33.33 rft
3 X 8 ' - 0 " = 24.00 rft
= 464.50 rft X 0 ' - 5 " X 0 ' - 6 "
= 96.77 cft
Total = 434.97 cft
= 12.32 cum = TK 0.813 lac/ cum@ TK 6601.9
378.6 / sqm
/ cum
@ TK
/ cum
Total in 3rd Floor
@ TK 6521.14
363.7 / sqm
Total in 4th Floor
@ TK 6561.52
@ TK
Page No 23
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
10 " lintel = 811.67 rft X1.83 rft = sft
5 " lintel = 464.50 rft X1.43 rft = sft
Total = 2149.59 sft
= 199.70 sqm = TK 0.786 lac
(vii) 6th Floor
(I) Concrete
Lintel for 10" wall
2 X 115 ' - 0 " = 230.00 rft
6 X 20 ' - 0 " = 120.00 rft
= 350.00 rft X 0 ' - 10 " X 0 ' - 6 "
= 145.83 cft
= 4.13 cum = TK 0.275 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
10 " lintel = 811.67 rft X1.83 rft = sft
= 137.99 sqm = TK 0.574 lac
( Total RCC in Lintel =
CE 51 h ( I ) Cornice , Railing , Drop walls , Louver, Fins etc.
7.4.8
( i ) GF
(I) Concrete
Railing , Stair void side 4 X 18 ' - 0 " = 72.00 rft
4 X 8 ' - 7 " = 34.33 rft
4 X 8 ' - 0 " = 32.00 rft
stair railing , basement stair 4 X 9 ' - 9 " = 39.00 rft
GF Stair : corner stair 4 X 11 ' - 8 " = 46.67 rft
1 X 3.1 X 3 ' - 8 " = 11.51 rft
short side stairs 2 X 4 X 11 ' - 8 " = 93.33 rft
long side stairs 2 X 4 X 11 ' - 8 " = 93.33 rft
2 X 3.1 X 5 ' - 6 " = 34.54 rft
middle stairs 4 X 11 ' - 8 " = 46.67 rft
2 X 28 ' - 2 " = 56.33 rft
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
Flower bed 2 X 15 ' - 0 " = 30.00 rft
Entry stair 2 X 4 ' - 4 " = 8.67 rft
Entry ramp 4 X 9 ' - 0 " = 36.00 rft
= 680.55 rft X 0 ' - 6 "
= 340.28 sft
Drop wall : void side 4 X 18 ' - 0 " = 72.00 rft
4 X 8 ' - 7 " = 34.33 rft
4 X 8 ' - 0 " = 32.00 rft
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
= 184.50 rft X 3 ' - 0 "
= 553.50 sft
Outer side of bldg 2 X 312 ' - 0 " = 624.00 rft
= 624.00 rft X 6 ' - 0 "
= 3744.00 sft
Total Railing & Dropwall = 4637.78 sft
= 4637.78 sft X 3 "
= 1159.44 cft
= 32.8361 cum = TK 1.973 lac@ TK
2718.77
/ cum
cft )
1485.35
664.24
@ TK 415.86 / sqm
393.5 / sqm
6010.00
@ TK
@ TK 6654.53
1485.35
/ cum
Page No 24
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
total quantity = 4637.78 sft X 2
= 9275.55 sft
= 861.72 sqm = TK 2.551 lac
( ii ) 1st Floor
(I) Concrete
Railing :Stair void side 4 X 18 ' - 0 " = 72.00 rft
4 X 8 ' - 7 " = 34.33 rft
4 X 8 ' - 0 " = 32.00 rft
lobby 1 X 30 ' - 0 " = 30.00 rft
short side stairs 2 X 4 X 11 ' - 8 " = 93.33 rft
long side stairs 2 X 4 X 11 ' - 8 " = 93.33 rft
2 X 3.1 X 5 ' - 6 " = 34.54 rft
middle stairs 4 X 11 ' - 8 " = 46.67 rft
2 X 28 ' - 2 " = 56.33 rft
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
= 538.71 rft X 0 ' - 6 "
= 269.35 sft
Drop wall : void side 4 X 18 ' - 0 " = 72.00 rft
4 X 8 ' - 7 " = 34.33 rft
4 X 8 ' - 0 " = 32.00 rft
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
= 184.50 rft X 3 ' - 0 "
= 553.50 sft
Outer side of bldg 2 X 312 ' - 0 " = 624.00 rft
= 624.00 rft X 6 ' - 0 "
= 3744.00 sft
Total Railing & Dropwall = 4566.85 sft
= 4566.85 sft X 3 "
= 1141.71 cft
= 32.33 cum = TK 1.956 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
= 4566.85 sft X 2
= 9133.71 sft
= 848.54 sqm = TK 2.638 lac
( iii ) 2nd Floor
(I) Concrete ( quantity same as 1st floor )= 32.33 cum = TK 1.969 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
( quantity same as 1st floor )= 848.542 sqm = TK 2.765 lac
( iv ) 3rd Floor
(I) Concrete ( quantity same as 1st floor )= 32.33 cum = TK 1.982 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
( quantity same as 1st floor )= 848.542 sqm = TK 2.891 lac
/ sqm@ TK
@ TK 6050.38 / cum
/ cum
@ TK 325.8
@ TK / cum
310.9
/ sqm
340.7 / sqm
@ TK
@ TK
@ TK
6090.76
6131.14
296.00 / sqm
Page No 25
( v ) 4th Floor
(I) Concrete ( quantity same as 1st floor )= 32.33 cum = TK 1.995 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
( quantity same as 1st floor )= 848.542 sqm = TK 3.017 lac
( vi ) 5th Floor
short side stairs 2 X 4 X 11 ' - 8 " = 93.33 rft
long side stairs 2 X 4 X 11 ' - 8 " = 93.33 rft
2 X 3.1 X 5 ' - 6 " = 34.54 rft
middle stairs 4 X 11 ' - 8 " = 46.67 rft
2 X 28 ' - 2 " = 56.33 rft
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
= 370.37 rft X 0 ' - 6 "
= 185.19 sft
drop wall
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
= 46.17 rft X 3 ' - 0 "
= 138.50 sft
Outer side of bldg 2 X 312 ' - 0 " = 624.00 rft
= 624.00 rft X 6 ' - 0 "
= 3744.00 sft
Total railing + drop wall = 4067.69 sft
= 4067.69 sft X 3 "
= 1016.92 cft
= 28.80 cum = TK 1.789 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
= 755.795 sqm = TK 2.800 lac
( Total Volume of RCC in cornice & dropwall =cft )
CE 51 I ( I ) Sun shade, false ceiling
7.4.9
GF
(I) Concrete 16 X 15 ' - 0 " = 240.00 rft X 2 ' - 0 " = sft
= 480.00 sft
= 480.00 sft X 3 "
= 120.00 cft
= 3.40 cum = TK 0.204 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
= 480.00 X
= 960.00 sft
= 89.19 sqm = TK 0.315 lac
2
6211.90 / cum
@ TK 353.00 / sqm
@ TK
@ TK
6171.52 / cum
355.6
480
/ cum6010.00
/ sqm
6743.22
@ TK
@ TK
@ TK
/ sqm
370.50
Page No 26
1St floor
(I) Concrete 20 X 15 ' - 0 " = 300.00 rft X 2 ' - 0 " = sft
= 600.00 sft
= 600.00 sft X 3 "
= 150.00 cft
= 4.25 cum = TK 0.257 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
= 600.00 X
= 1200.00 sft
= 111.48 sqm = TK 0.410 lac
2nd floor
(I) Concrete 24 X 15 ' - 0 " = 360.00 rft X 2 ' - 0 " = sft
= 720.00 sft
= 720.00 sft X 3 "
= 180.00 cft
= 5.10 cum = TK 0.310 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
= 720.00 X
= 1440.00 sft
= 133.78 sqm = TK 0.512 lac
3rd floor
(I) Concrete quantity same as 2nd Floor = 5.10 cum = TK 0.313 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
quantity same as 2nd Floor = 133.78 sqm = TK 0.532 lac
4th floor
(I) Concrete quantity same as 3rd Floor = 5.10 cum = TK 0.315 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
quantity same as 3rd Floor = 133.78 sqm = TK 0.552 lac
5th floor
(I) Concrete 40 X 15 ' - 0 " = 600.00 rft X 2 ' - 0 " = sft
= 1200.00 sft
= 1200.00 sft X 3 "
= 300.00 cft
= 8.50 cum = TK 0.528 lac
( ii ) Formwork / shuttering, prop and necessary supports etc ( steel )
= 1200.00 X
= 2400.00 sft
= 222.97 sqm = TK 0.953 lac
sub total= TK 858.400 lac
2
@ TK 6211.90 / cum
@ TK 412.60
1200
2
@ TK 382.80
@ TK 397.70
/ sqm
2
6090.76@ TK
/ sqm
600
/ sqm
@ TK 367.90
/ cum
@ TK 6171.52 / cum
/ sqm
@ TK 6131.14 / cum
@ TK 427.50 / sqm
720
@ TK 6050.38 / cum
Page No 27
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 900.8703 1102.76
Rate Total
Page No 28
7,040.00 9004.00 0.839 1.072544 10.0% 27.9%
259.00 320.00 0.513 0.633426 -18.8% 23.6%
636.17
7,090.00 9071.00 0.738 0.944004 10.1% 27.9%
Page No 29
278.00 345.00 0.482 0.598407 -16.7% 24.1%
7,140.00 9138.00 0.910 1.164481 10.2% 28.0%
297.00 370.00 0.603 0.750919 -14.9% 24.6%
Page No 30
7,190.00 9205.00 0.916 1.173019 10.3% 28.0%
316.00 395.00 0.641 0.801657 -13.1% 25.0%
7,240.00 9272.00 0.923 1.181557 10.3% 28.1%
335.00 420.00 0.680 0.852394 -11.5% 25.4%
7,290.00 9339.00 0.898 1.150422 10.4% 28.1%
Page No 31
354.00 445.00 0.707 0.888671 -10.0% 25.7%
7,356.00 9428.00 0.304 0.389384 10.5% 28.2%
382.00 483.00 0.527 0.666503 -8.1% 26.4%
6,922.00 8852.00 2.273 2.906655 15.2% 27.9%
Page No 32
240.00 298.00 2.068 2.567925 -18.9% 24.2%
6,972.00 8919.00 2.254 2.883869 15.2% 27.9%
259.00 323.00 2.198 2.740791 -16.7% 24.7%
7,022.00 8986.00 2.270 2.905533 15.3% 28.0%
278.00 348.00 2.359 2.952926 -14.7% 25.2%
7,072.00 9053.00 2.287 2.927196 15.3% 28.0%
297.00 373.00 2.520 3.165062 -12.8% 25.6%
Page No 33
7,122.00 9120.00 2.303 2.94886 15.4% 28.1%
316.00 398.00 2.681 3.377197 -11.1% 25.9%
7,172.00 9187.00 2.066 2.64584 15.5% 28.1%
335.00 423.00 2.532 3.197011 -9.6% 26.3%
6,922.00 8852.00 0.235 0.300833 15.2% 27.9%
278.00 337.00 0.248 0.300557 -21.2% 21.2%
Page No 34
6,972.00 8919.00 0.296 0.378887 15.2% 27.9%
297.00 362.00 0.331 0.403567 -19.3% 21.9%
7,022.00 8986.00 0.358 0.45808 15.3% 28.0%
316.00 387.00 0.423 0.517726 -17.5% 22.5%
7,072.00 9053.00 0.361 0.461495 15.3% 28.0%
335.00 412.00 0.448 0.551171 -15.8% 23.0%
7,122.00 9120.00 0.363 0.464911 15.4% 28.1%
354.00 437.00 0.474 0.584615 -14.2% 23.4%
7,172.00 9187.00 0.609 0.780544 15.5% 28.1%
373.00 462.00 0.832 1.0301 -12.7% 23.9%
sub total 943.3387 1156.478 9.89 22.6%
Page No 27
858.400 lac
12
CE 59
CE 59 b ( A ) 60 grade deformed bar wtih minimum fy = 415 Mpa, ultimate strength 620 Mpa
8.1.2 ( I ) GF
( A ) Pre cast pile
( Ref : Item 9 ) cft 2 = 1041.25 cft =
(B ) Pile cap
( Ref : Item 10 ) cft 4 = 1105.76 cft =
( Ref : Item 10 ) cft 2 = 432.22 cft =
(D) Basement wall
( Ref : Item 10 ) cft 2 = 99.15 cft =
(E) Slabs ( GF floor & roof slab )
( Ref : Item 10 ) cft 2 = 323.11 cft =
(F) Stair
( Ref : Item 10 ) cft 2 = 60.73 cft =
(G) Beam
( Ref : Item 10 ) cft 3 = 295.18 cft =
(H) Column upto GF
( Ref : Item 10 ) cft 4 = 184.45 cft =
(I) Column above GF
( Ref : Item 10 ) cft 3 = 133.80 cft =
(J) lift wall & shear wall
( Ref : Item 10 ) cft 2 = 49.70 cft =
(k) Lintel
( Ref : Item 11 ) cft 1 = 3.36 cft =
= quintal
@ TK5400.00 / quintal = TK 447.446 lac
% quintal7.48
8286.04
420.61 @
quintal
3313.51 @ % 110.45 quintal
297.335352.00 @ %
quintal
5270.00 @ % 409.89 quintal
655.9411807.00 @ %
quintal
4048.82 @ % 134.96 quintal
718.0221540.61 @ %
quintal
6610.00 @ % 220.33 quintal
24698.50 @ %
B.F = Tk
52062.50
Supplying, fabrication and fixing to details as per design deformed bar reinforcement in concrete in
accordance with BSTI standard in/c straightening and cleaning rust, if any, bending & binding in position
in/c supply of G.I. wires etc. complete in all respects and accepted by the Engineer.
2457.24
2313.89 quintal
quintal
(C) Basement
31593.13 @ %
960.50
@ %
Page No 28
( II ) 1st Floor
(A) Slabs
( Ref : Item 10 ) cft 2 = 154.19 cft =
(B) Stair
( Ref : Item 10 ) cft 2 = 35.45 cft =
(C) Beam
( Ref : Item 10 ) cft 3 = 142.45 cft =
(D) Column
( Ref : Item 10 ) cft 3 = 133.80 cft =
(E) lift wall & shear wall
( Ref : Item 10 ) cft 2 = 27.44 cft =
(F) Lintel
( Ref : Item 11 ) cft 1 = 2.94 cft =
= quintal
@ TK5419.06 / quintal = TK 59.762 lac
( III ) 2nd Floor
(A) Slabs
( Ref : Item 10 ) cft 2 = 154.19 cft =
(B) Stair
( Ref : Item 10 ) cft 2 = 35.45 cft =
(C) Beam
( Ref : Item 10 ) cft 3 = 142.45 cft =
(D) Column
( Ref : Item 10 ) cft 3 = 133.80 cft =
(E) lift wall & shear wall
( Ref : Item 10 ) cft 2 = 27.44 cft =
(F) Lintel
( Ref : Item 11 ) cft 1 = 3.60 cft =
= quintal
@ TK5438.12 / quintal = TK 60.052 lac
( IV ) 3rd Floor
(A) Slabs
( Ref : Item 10 ) cft 2 = 154.19 cft =
(B) Stair
( Ref : Item 10 ) cft 2 = 35.45 cft =
quintal%
%
quintal
%
quintal
1102.80
% 342.64
%
%
% 297.33
60.97
quintal
quintal
% 78.77 quintal
6.53
%
quintal
quintal
quintal
quintal
316.56
5352.00 @
@
2363.11 @
1829.22 @
367.47
10279.14 @
@
1829.22 @
5698.00 @
5352.00 @
5698.00
2363.11
449.97
@
@ %
10279.14 @ % 342.64
quintal
quintal297.33
60.97
8.00
78.77
% 316.56
1104.27
10279.14
2363.11
@ %
@ % 78.77
quintal
quintal
342.64
Page No 29
(C) Beam
( Ref : Item 10 ) cft 3 = 142.45 cft =
(D) Column
( Ref : Item 10 ) cft 3 = 133.80 cft =
(E) lift wall & shear wall
( Ref : Item 10 ) cft 2 = 27.44 cft =
(F) Lintel
( Ref : Item 11 ) cft 1 = 3.60 cft =
= quintal
@ TK5457.18 / quintal = TK 60.262 lac
( V ) 4th Floor
(A) Slabs
( Ref : Item 10 ) cft 2 = 154.19 cft =
(B) Stair
( Ref : Item 10 ) cft 2 = 35.45 cft =
(C) Beam
( Ref : Item 10 ) cft 3 = 142.45 cft =
(D) Column
( Ref : Item 10 ) cft 3 = 133.80 cft =
(E) lift wall & shear wall
( Ref : Item 10 ) cft 2 = 27.44 cft =
(F) Lintel
( Ref : Item 11 ) cft 1 = 3.60 cft =
= quintal
@ TK5476.24 / quintal = TK 60.473 lac
( VI ) 5th Floor
(A) Slabs
( Ref : Item 10 ) cft 2 = 129.40 cft =
(B) Stair
( Ref : Item 10 ) cft 2 = 24.13 cft =
(C) Beam
( Ref : Item 10 ) cft 3 = 114.25 cft =
2363.11
449.97 @
10279.14
@
1829.22 @
5698.00
5352.00
@
316.56
%
1104.27
%
quintal@
quintal
quintal
quintal
@ % 297.33
60.97
% 78.77
8.00
% 342.64
quintal% 316.56
% quintal
8.00
quintal
quintal
60.97
1104.27
quintal
@ % 53.63
8626.47 @ % 287.55
5698.00 @ %
quintal
quintal
1829.22 @ %
5352.00 @ % 297.33 quintal
4570.00 @ % 253.89
449.97 @
1608.93
quintal
Page No 30
(D) Column
( Ref : Item 10 ) cft 3 = 127.03 cft =
(E) lift wall & shear wall
( Ref : Item 10 ) cft 2 = 26.52 cft =
(F) Lintel
( Ref : Item 11 ) cft 1 = 3.48 cft =
= quintal
@ TK5495.30 / quintal = TK 51.877 lac
( VII ) 6th Floor
(A) Slabs
( Ref : Item 10 ) cft 2 = 26.10 cft =
(B) Beam
( Ref : Item 10 ) cft 3 = 28.13 cft =
(C) Column
( Ref : Item 10 ) cft 3 = 27.31 cft =
(D) lift wall & shear wall
( Ref : Item 10 ) cft 2 = 26.52 cft =
(E) Lintel
( Ref : Item 11 ) cft 1 = 1.17 cft =
= quintal
@ TK5532.56 / quintal = TK 13.429 lac
CE 59 a ( B ) 40 grade deformed bar wtih minimum fy = 276 Mpa, ultimate strength 482 Mpa
8.1.1
( I ) GF
(A) Cornice, railing, drop wall
( Ref : Item 11 ) cft 1 = 9.28 cft =
(B) Sun shade
( Ref : Item 11 ) cft 1 = 0.96 cft =
total = quintal
@ TK5256.00 / quintal = TK 1.196 lac
( II ) 1st Floor
(A) Cornice, railing, drop wall
( Ref : Item 11 ) cft 1 = 9.13 cft =
quintal
120.00 @
1740.00 @ %
@ %
1125.00 @ %
944.02
%
quintal
2.13
% 20.61
quintal
22.75
quintal
quintal
quintal
58.00
434.97 @ % 7.73
quintal
quintal
1768.11 @ % 58.94
% 282.28
quintal
5081.08 @
62.50
quintal1768.11
quintal
1092.50 @ % 60.69
145.83 @ % 2.59
1159.44 @
58.94
242.72
1141.71 @ % 20.30
Page No 31
(B) Sun shade
( Ref : Item 11 ) cft 1 = 1.20 cft =
total = quintal
@ TK5275.06 / quintal = TK 1.211 lac
( III ) 2nd Floor
(A) Cornice, railing, drop wall
( Ref : Item 11 ) cft 1 = 9.13 cft =
(B) Sun shade
( Ref : Item 11 ) cft 1 = 1.44 cft =
total = quintal
@ TK5294.12 / quintal = TK 1.244 lac
( IV ) 3rd Floor
(A) Cornice, railing, drop wall
( Ref : Item 11 ) cft 1 = 9.13 cft =
(B) Sun shade
( Ref : Item 11 ) cft 1 = 1.44 cft =
total = quintal
@ TK5313.18 / quintal = TK 1.248 lac
( V ) 4th Floor
(A) Cornice, railing, drop wall
( Ref : Item 11 ) cft 1 = 9.13 cft =
(B) Sun shade
( Ref : Item 11 ) cft 1 = 1.44 cft =
total = quintal
@ TK5332.24 / quintal = TK 1.253 lac
( VI ) 5th Floor
(A) Cornice, railing, drop wall
( Ref : Item 11 ) cft 1 = 8.14 cft =
(B) Sun shade
( Ref : Item 11 ) cft 1 = 2.40 cft =
total = quintal
@ TK5351.30 / quintal = TK 1.253 lac
Sub Total = TK 1619.105 lac
quintal
22.96
% 20.30
quintal
quintal150.00 @ % 2.67
quintal
23.50
% 3.20
% 20.30
1141.71 @
1141.71 @
180.00 @
180.00 @ % 3.20
180.00 @ % 3.20
1141.71 @ % 20.30
300.00 @ % 5.33
1016.92 @ % 18.08
quintal
23.41
quintal
23.50
quintal
quintal
23.50
quintal
Page No 32
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 943.3386852 1156.478041
7,258.00 8100.00 601.401 671.1690738 34.4% 11.6%
Rate Total
Page No 33
7,282.00 8132.00 80.306 89.68001024 34.4% 11.7%
7,306.00 8164.00 80.678 90.15264614 34.3% 11.7%
Page No 34
7,330.00 8196.00 80.943 90.50601271 34.3% 11.8%
7,354.00 8228.00 81.208 90.85937928 34.3% 11.9%
Page No 35
7,378.00 8260.00 69.650 77.97612134 34.3% 12.0%
7,425.00 8323.00 18.022 20.20191235 34.2% 12.1%
6,418.00 7240.00 1.460 1.646786803 22.1% 12.8%
Page No 36
6,442.00 7272.00 1.479 1.669926997 22.1% 12.9%
6,466.00 7304.00 1.519 1.716230078 22.1% 13.0%
6,490.00 7336.00 1.525 1.723749158 22.1% 13.0%
6,514.00 7368.00 1.531 1.731268238 22.2% 13.1%
6,538.00 7400.00 1.531 1.732483615 22.2% 13.2%
Sub Total 1,964.591 2,297.244 21.34 16.9%
Page No 32
B.F 1619.105 lac
13
(CE14)
04.1.
10 " brick work in foundation
By the side of pile cap ( mark E of Item 6 A ) = ####### sft
By the side of basement wall( mark D of Item 6A ) = 7170 sft
side of basement ramp 60 ' X 10 ' - 0 " = 600.00 sft
= ####### sft X 10 "
= ####### cft
= 463.115 cum = TK 12.180 lac
14
(CE 16)
04.3.
(i) GF
= 734.33 rft X 0 ' - 10 " X 10 ' - 6 "
= 6425.42 cft
Deduction
aluminium sliding window = 1127.25 sft
aluminium composite fixed window = 605 sft
aluminium fixed fan light = 1336.83 sft
= 3069.08 sft X 10 "
= 2557.57 cft
Total volume = 3867.85 cft
= 109.54 cum = TK 3.328 lac
(ii) 1st floor
= 636.17 rft X 0 ' - 10 " X 10 ' - 6 "
= 5566.46 cft
Deduction
aluminium sliding window = 1608 sft
aluminium composite fixed window = 331 sft
aluminium fixed fan light = 1535.63 sft
= 3474.63 sft X 10 "
= 2895.52 cft
Total volume = 2670.94 cft
= 75.64 cum = TK 2.346 lac
(iii) 2nd floor
= 877.67 rft X 0 ' - 10 " X 10 ' - 6 "
= 7679.58 cft
Deduction
aluminium sliding window = 1711.50 sft
aluminium composite fixed window = 60.00 sft
aluminium fixed fan light = 1463.58 sft
= 3235.08 sft X 10 "
= 2695.9 cft
Total volume = 4983.68 cft
= 141.141 cum = TK 4.466 lac@ TK 3163.92 / cum
@ TK
@ TK 3038 / cum
3100.96 / cum
Brick works with 1st class bricks in cement sand ( F.M of sand 1.2 ) mortar (1:6) in foundation and
plinth, filling the joints/interstices fully with mortar, racking out the joints, cleaning and soaking the bricks at
least for 24 hours before use and curing at least for 7 days etc. all complete including cost of water,
electricity & other charges and accepted by the Engineer.
( Cement : CEM - II / A - M )
Wall length same as 10" Lintel area
Wall length same as 10" Lintel area
@ TK 2630.00 / cum
Wall length same as 10" Lintel area
Brick work with 1st class bricks in cement sand ( F.M. 1.2 ) mortar ( 1:4 ) in exterior walls in/c filling
the interstices with mortar, raking out joints, cleaning and socking the bricks at least for 24 hours before
use and washing of sand, necessary scaffolding, curing at least for 7 days etc. all complete including cost
of water, electricity & other charges (measurement to given as 250 mm width for one brick length and 375
mm for one brick and a half brick length). accepted by the Engineer.
( Cement : CEM - II / A - M )
Page No 33
(iv) 3rd floor
same as 2nd floor = 4983.68 cft
= 141.14 cum = TK 4.554 lac
(v) 4th floor
same as 3rd floor = 4983.68 cft
= 141.14 cum = TK 4.643 lac
(v1) 5th floor
= 811.67 rft X 0 ' - 10 " X 10 ' - 6 "
= 7102.08 cft
deduction
aluminium sliding window = 2589.00 sft
aluminium composite fixed window = 60.00 sft
aluminium fixed fan light = 2259.83 sft
= 4908.83 sft X 10 "
= 4090.69 cft
Total volume = 3011.39 cft
= 85.28 cum = TK 2.859 lac
(vii) 6th floor
Chillakota stair wall 2 X 110 ' - 0 " = 220.00 rft
6 X 20 ' - 0 " = 120.00 rft
(marked G) = 340.00 rft X 0 ' - 10 " X 10 ' - 6 "
= 2975.00 cft
Parapet wall 4 X 10 X 20 ' - 0 " = 800.00 rft X 0 ' - 10 " X 5 ' - 0 "
= 3333.33 cft
deduct window = 432.00 sftdoor = 136.67 sft
= 568.67 sft X 10 "
= 473.89 cft
Total = 5834.44 cft
= 165.23 cum = TK 5.686 lac
15
(CE 21b )
04.16.
(i) GF
= 550.25 rft X 12 ' - 0 "
= 6603 sft
Deduction doors
Partex single swing flush door 10 X 3 ' - 6 " = 35.00
Upvc plastic door 8 X 2 ' - 6 " = 20.00
(marked A) = 55.00 rft X 7 ' - 0 "
= 385 sft
Total volume = 6218.00 sft
= 577.67 sqm = TK 2.444 lac
/ cum
@ TK
@ TK 3289.84
@ TK
@ TK 423.00
@ TK
125 mm brick work with 1st class bricks in cement sand ( F.M.1.2 ) mortar ( 1:4 ) and making bond
with connected walls in/c necessary scaffolding, raking out joints, cleaning and soaking the bricks for at
least 24 hours before use and washing of sand curing at least for 7 days in all floors including cost of water,
electricity & other charges etc. all complete and accepted by the Engineer.
( Cement : CEM - II / A - M )
/ cum
/ sqm
3440.94 / cum
3226.88 / cum
3352.80
Wall length same as 5" Lintel area
Wall length same as 10" Lintel area
Page No 34
(ii) 1st floor
= 491.50 rft X 12 ' - 0 "
= 5898 sft
Deduction doors
Partex single swing flush door 6 X 3 ' - 6 " = 21.00
Upvc plastic door 9 X 2 ' - 6 " = 22.50
(marked D) = 43.50 rft X 7 ' - 0 "
= 304.5 sft
Total volume = 5593.50 sft
= 519.65 sqm = TK 2.258 lac
(iii) 2nd floor
= 404.50 rft X 11 ' - 6 "
= 4651.75 sft
Deduction doors
Partex single swing flush door 6 X 3 ' - 6 " = 21.00
Upvc plastic door 9 X 2 ' - 6 " = 22.50
(marked D) = 43.50 rft X 7 ' - 0 "
= 304.5 sft
Total volume = 4347.25 sft
= 403.87 sqm = TK 1.801 lac
(iv) 3rd floor
= 4347.25 sft
= 403.87 sqm = TK 1.848 lac
(v) 4th floor
= 4347.25 sft
= 403.87 sqm = TK 1.894 lac
(vi) 5th floor
= 464.50 rft X 12 ' - 0 "
= 5574 sft
Deduction doors
Partex single swing flush door 6 X 3 ' - 6 " = 21.00
Upvc plastic door 9 X 2 ' - 6 " = 22.50
(marked D) = 43.50 rft X 7 ' - 0 "
= 304.5 sft
Total volume = 5269.50 sft
= 489.55 sqm = TK 2.353 lac
@ TK 446.02 / sqm
/ sqm
Wall length same as 5" Lintel area
Quantity same as 2nd floor
Quantity same as 3rd floor
@ TK / sqm480.55
@ TK 457.53 / sqm
469.04@ TK
Wall length same as 5" Lintel area
@ TK 434.51 / sqm
Wall length same as 5" Lintel area
Page No 35
16
CE 20 b
04.13.
GF 2 X 195 ' - 0 " = 390.00 rft
2 X 115 ' - 0 " = 230.00 rft
= 620.00 rft X 12 ' - 6 "
= 7750.00 sft
= 719.993 sqm = TK 6.559 lac
1st Floor 2 X 195 ' - 0 " = 390.00 rft
2 X 115 ' - 0 " = 230.00 rft
= 620.00 rft X 3 ' - 0 "
= 1860.00 sft
= 172.798 sqm = TK 1.594 lac
17
CE 24 b
04.22.3
basement floor = 2000.00 sft
= 185.805 sqm = TK 1.714 lac
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Sub Total = TK 1671.764 lac
40 ' - 0 " X 50 ' - 0 "
@ TK
911 / sqm
922.51
Providing brick work in facing for 200 x 50 mm in superstructure with 200 x 50 x 50 mm machine made
hard pressed klinker facing bricks of approved quality pressed with 20 mm thick cement sand (F.M.1.2)
mortar (1:4), 10 mm thick cement mortar in adjacent sites in/c racking out joints and cutting the bricks to
required sizes wherever necessary with high class recessed pointing, cleaning and soaking the bricks for at
least 24 hours before use and washing of sand necessary scaffolding, curing at least for 7 days for all
floors up to 4th floor including cost of water, electricity & other charges etc. all complete and accepted by
the Engineer.
( Cement : CEM - II / A - M )
@ TK
Klinker paving bricks work in floor/ pavement with machine made pressed bricks of approved quality in
cement sand (F.M.1.2) mortar (1:4) on minimum 12 mm thick cement sand (F.M.1.2) mortar (1:4) in/c
raking out joints, cutting the bricks to required size soaking the same 24 hours before use wherever
necessary in/c high class flush pointing in cement mortar (1:2), cleaning, curing at least for 7 days etc. in/c
washing and screening of sand, cost of water, electricity & other charges complete and standard practice
accepted by the Engineer.
( Cement : CEM - II / A - M )
50 mm thick flat brick pavement with 200 X 100 X 50 mm klinker paving bricks in 1:4 cement sand mortar
having 200 X 100 mm face at top
/ sqm
@ TK 922.51 / sqm
Page No 36
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 1964.591 2297.244
1823.033
3,636.00 4688.00 16.839 21.71085 38.3% 28.9%
4,147.00 5264.00 4.543 5.76617 36.5% 26.9%
4,226.00 5370.00 3.197 4.062004 36.3% 27.1%
62.96 4,305.00 5476.00 6.076 7.728869 36.1% 27.2%
Rate Total
Page No 37
4,384.00 5582.00 6.188 7.878478 35.9% 27.3%
4,463.00 5688.00 6.299 8.028087 35.7% 27.4%
4,542.00 5794.00 3.874 4.941373 35.5% 27.6%
4,652.00 5942.00 7.687 9.818258 35.2% 27.7%
576.00 730.00 3.327 4.216964 36.2% 26.7%
Page No 38
590.00 749.00 3.066 3.89217 35.8% 26.9%
604.00 768.00 2.439 3.101717 35.4% 27.2%
618.00 787.00 2.496 3.178452 35.1% 27.3%
632.00 806.00 2.552 3.255187 34.7% 27.5%
646.00 825.00 3.162 4.038775 34.4% 27.7%
Page No 39
1,149.00 1423.00 8.273 10.24549 26.1% 23.8%
1,163.00 1442.00 2.010 2.49175 26.1% 24.0%
1,091.00 1362.00 2.027 2.530658 18.3% 24.8%
2048.646 2404.129 22.54 17.4%
Page No 36
B.F 1671.764 Lac
18
CE 120a
15.1.
(i) GF
for 10 " wall both side 2 X X 12 ' - 0 " = 17624.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 13206.00 sft
= 30830.00 sft
Deduction
aluminium sliding window = 1127.25 sft
= 605.00 sft
aluminium fixed fan light = 1336.83 sft
partex flush door = 227.78 sft
plastic door 8 X 2 ' - 6 " X 7 ' - 0 " = 140.00 sft
= 3436.86 sft
Net area = 27393.14 sft
= 2544.88 sqm / sqm = Tk 3.054 lac
(ii) 1st Floor
for 10 " wall both side 2 X X 12 ' - 0 " = 15268.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 11796.00 sft
= 27064.00 sft
Deduction
aluminium sliding window = 1608.00 sft
= 331.00 sft
aluminium fixed fan light = 1535.63 sft
partex flush door = 136.67 sft
plastic door 9 X 2 ' - 6 " X 7 ' - 0 " = 157.50 sft
= 3768.79 sft
Net area = 23295.21 sft
= 2164.18 sqm / sqm = Tk 2.713 lac
(iii) 2nd Floor
for 10 " wall both side 2 X X 12 ' - 0 " = 21064.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 9708.00 sft
= 30772.00 sft
Deduction
aluminium sliding window = 1711.50 sft
= 60.00 sft
aluminium fixed fan light = 1463.58 sft
partex flush door = 136.67 sft
plastic door 9 X 2 ' - 6 " X 7 ' - 0 " = 157.50 sft
= 3529.25 sft
Net area = 27242.75 sft
= 2530.91 sqm / sqm = Tk 3.308 lac
(iv) 3rd Floor Quantity same as 2nd floor = 27242.75 sft
= 2530.91 sqm / sqm = Tk 3.443 lac
(v) 4th Floor Quantity same as 3rd floor = 27242.75 sft
= 2530.91 sqm / sqm = Tk 3.579 lac
rft
rft
rft
734.33
550.25
aluminium composite fixed window
@ Tk 136.05
@ Tk 141.40
@ Tk 125.35
404.50
877.67
rft
636.17
Minimum 12 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement to wall both inner-and outer
surface, finishing the corner and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for
7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and accepted by the
Engineer.
( Cement : CEM - II / A - M )
aluminium composite fixed window
aluminium composite fixed window
491.50
@ Tk 120.00
rft
rft
@ Tk 130.70
Page No 37
(vi) 5th Floor
for 10 " wall both side 2 X X 12 ' - 0 " = 19480.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 11148.00 sft
= 30628.00 sft
Deduction
aluminium sliding window = 2589.00 sft
= 60.00 sft
aluminium fixed fan light = 2259.83 sft
partex flush door = 136.67 sft
plastic door 9 X 2 ' - 6 " X 7 ' - 0 " = 157.50 sft
= 5203.00 sft
Net area = 25425.00 sft
= 2362.04 sqm / sqm = Tk 3.466 lac
(vii) 6th Floor
for 10 " wall both side 2 X 350 ' - 0 " X 12 ' - 0 " = 8400.00 sft
parapet 4X 10 X 20 ' - 0 " X 10 ' - 10 " = 8666.67 sft
Deduct, windows = 432.00 sft
Deduct, Doors = 136.67 sft
= 16498.00 sft
= 1532.70 sqm / sqm = Tk 2.372 lac
19
CE 120 b
15.2.
GF 2 X ( 195 ' - 0 " + 115 ' - 0 " ) = 620.00 rft
= 620.00 rt X 2 ' - 0 "
= 1240.00 sft
= 115.20 sqm / sqm = Tk 0.159 lac
20
CE 120 c
15.3.
(i) GF
for 10 " wall inside 1 X X 0 ' - 6 " = 367.17 sft
for 5 " wall both side 2 X X 0 ' - 6 " = 550.25 sft
= 917.42 sft
Deduction
partex flush door 10 X 3 ' - 6 " X 0 ' - 6 " = 17.50 sft
plastic door 8 X 2 ' - 6 " X 0 ' - 6 " = 10.00 sft
= 27.50 sft
Net area = 889.92 sft
= 82.68 sqm @ Tk / sqm = Tk 0.123 lac
(ii) 1st Floor
for 10 " wall inside 1 X X 0 ' - 6 " = 318.08 sft
for 5 " wall both side 2 X X 0 ' - 6 " = 491.50 sft
= 809.58 sft
Deduction
partex flush door 6 X 3 ' - 6 " X 0 ' - 6 " = 10.50 sft
plastic door 9 X 2 ' - 6 " X 0 ' - 6 " = 11.25 sft
= 21.75 sft
Net area = 787.83 sft
= 73.19 sqm @ Tk / sqm = Tk 0.113 lac
aluminium composite fixed window
811.67 rft
rft
@ Tk 154.77
464.50
@ Tk 146.75
636.17 rft
491.50 rft
154.35
550.25 rft
149.00
Minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall (1:4) with cement up to
150 mm below ground level with neat cement finishing in/c washing of sand, finishing the edges and corners and curing at
least for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and accepted by the
Engineer.
( Cement : CEM - II / A - M )
@ Tk 138.00
Minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to dado (1:4) with cement up to 150
mm below ground level with neat cement finishing in/c washing of sand, finishing the edges and corners and curing at least
for 7 days, cost of water, electricity & other charges etc. all complete in all respect as per drawing and accepted by the
Engineer.
( Cement : CEM - II / A - M )
734.33 rft
Page No 38
(iii) 2nd Floor
for 10 " wall inside 1 X X 0 ' - 6 " = 438.83 sft
for 5 " wall both side 2 X X 0 ' - 6 " = 404.50 sft
= 843.33 sft
Deduction
partex flush door 6 X 3 ' - 6 " X 0 ' - 6 " = 10.50 sft
plastic door 9 X 2 ' - 6 " X 0 ' - 6 " = 11.25 sft
= 21.75 sft
Net area = 821.58 sft
= 76.33 sqm @ Tk / sqm = Tk 0.122 lac
(iv) 3rd Floor Quantity same as 2nd floor = 821.58 sft
= 76.33 sqm / sqm = Tk 0.126 lac
(v) 4th Floor Quantity same as 3rd floor = 821.58 sft
= 76.33 sqm / sqm = Tk 0.130 lac
(vi) 5th Floor
for 10 " wall inside 1 X X 0 ' - 6 " = 405.83 sft
for 5 " wall both side 2 X X 0 ' - 6 " = 464.50 sft
= 870.33 sft
Deduction
partex flush door 6 X 3 ' - 6 " X 0 ' - 6 " = 10.50 sft
plastic door 9 X 2 ' - 6 " X 0 ' - 6 " = 11.25 sft
= 21.75 sft
Net area = 848.58 sft
= 78.84 sqm / sqm = Tk 0.139 lac
(vii) 6th Floor
for 10 " wall inside 1 X 350 ' - 0 " X 0 ' - 6 " = 175.00 sft
Deduct, Doors 6 X 3 ' - 6 " X 0 ' - 6 " = 10.50 sft
= 164.50 sft
= 15.28 sqm / sqm = Tk 0.028 lac
21
CE 120 d
15.4.
GF outside 2 X 190 ' - 0 " X 2 ' - 0 " = 760.00 sft
2 X 110 ' - 0 " X 2 ' - 0 " = 440.00 sft
= 1200.00 sft
= 111.48 sqm / sqm = Tk 0.122 lac
@ Tk 175.75
@ Tk 183.77
@ Tk 165.05
@ Tk 170.40
404.50
811.67 rft
rft
159.70
464.50 rft
877.67 rft
Minimum 12 mm thick cement sand (F.M. 1.2) plaster (1:6) having with fresh cement to wall both inner-and outer
surface, finishing the corner and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for 7 days,
cost of water, electricity and other charges etc all complete as per drawing and accepted by the Engineer.
( Cement : CEM - II / A - M )
@ Tk 109.00
Page No 39
22
CE 120 e
15.5.
(i) GF
Basement floor ceiling
1 X 196 ' - 0 " X 116 ' - 0 " = 22736.00 sft
3.14 X 25 ' - 0 " X 25 ' - 0 " = 1962.50 sft
Basement floor column face
Column C1 32 X ( 3 ' - 0 " + 3 ' - 0 " ) = 192.00 rft
Column C2 28 X ( 3 ' - 0 " + 2 ' - 3 " ) = 147.00 rft
Column C3 4 X ( 1 ' - 3 " + 2 ' - 6 " ) = 15.00 rft
Column C4 14 X ( 1 ' - 0 " + 2 ' - 1 " ) = 43.17 rft
= 397.17 rft X 10 ' 0 X 2
= 7943.33 sft
Basement floor lift wall 4 X 75 ' - 0 " X 10 ' - 6 " = 3150.00 sft
Basement floor RCC wall 2 X ( 190 ' - 0 " + 60 ' - 0 " ) = 500.00 rft
2 X 3.14 X 25 ' - 0 " = 157.00 rft
= 657.00 rft X 10 ' 0 X 2
= 13140.00 sft
Ramp bottom face 1 X 61 ' - 0 " X 18 ' - 4 " = 1118.33 sft
Basement stair bottom , slab2 X 11 ' - 8 " X 3 ' - 0 " = 70.00 sft
landing 0.5 X 3.14 X 4 ' X 4 ' = 25.12 sft
= 95.12 sft
Basement ceiling beam side
Long direction 4 X 190 ' - 0 " X 1 ' - 6 " = 1140.00 sft
2 X 219 ' - 0 " X 2 ' - 0 " = 876.00 sft
Short direction 10 X 80 ' - 0 " X 1 ' - 6 " = 1200.00 sft
21 X 30 ' - 0 " X 1 ' - 6 " = 945.00 sft
2 X 78 ' - 6 " X 1 ' - 6 " = 235.50 sft
= 4396.50 sft X 2 ( 2 sides of beam )
= 8793.00 sft
( Total plaster in basement floor = sft )
GF ceiling, col, lift wall, stair
Ceiling quantity same as GF roof slab = 19720.39 sft
GF column face
Column C1 32 X ( 2 ' - 9 " + 2 ' - 9 " ) = 176.00 rft
Column C2 28 X ( 2 ' - 9 " + 2 ' - 0 " ) = 133.00 rft
Column C3 4 X ( 1 ' - 3 " + 2 ' - 6 " ) = 15.00 rft
Column C4 18 X ( 1 ' - 0 " + 2 ' - 1 " ) = 55.50 rft
= 379.50 rft X 12 ' X 2
= 9108.00 sft
GF lift wall 4 X 75 ' - 0 " X 12 ' - 6 " = 3750.00 sft
58938.29
Minimum 6 mm thick cement sand (F.M. 1.2) plaster (1:4) with fresh cement (conforming to BDS 232) to ceiling
R.C.C. columns, beams, surface of stair case, sunshades, cornices, railings, drop wall, louvers, fins and finishing
the corners and edges in/c washing of sand cleaning the surface, scaffolding and curing at least for 7 days, cost of
water, electricity & other charges etc. all complete in all respect as per drawing and direction of the engineer-in-
charge.
( Cement : CEM - II / A - M )
Page No 40
GF ceiling beam side
Long direction 4 X 190 ' - 0 " X 1 ' - 6 " = 1140.00 sft
2 X 219 ' - 0 " X 2 ' - 0 " = 876.00 sft
Short direction 10 X 84 ' - 0 " X 1 ' - 6 " = 1260.00 sft
14 X 30 ' - 0 " X 1 ' - 6 " = 630.00 sft
3.1 X 25 ' - 0 " X 1 ' - 6 " = 117.75 sft
= 4023.75 sft X 2 ( 2 sides of beam )
= 8047.50 sft
Stair case slab bottom & landing
Short side stair 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 3 ' - 0 " = 28.26 sft
long side stair 4 X 11 ' - 8 " X 4 ' - 8 " = 217.78 sft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " = 68.38 sft
Middle stair 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
Corner stair 2 X 11 ' - 8 " X 3 ' - 6 " = 81.67 sft
landing 0.5 X 3.1 X 3 ' - 6 " X 3 ' - 6 " = 19.23 sft
= 845.85 sft
Railing, drop wall = 4637.78 sft X 2
= 9275.55 sft
Sun shade = 480.00 sft X 2
= 960.00 sft
Total plaster area in GF = 110645.58 sft (mark B)
= 10283.05 sqm / sqm = Tk 10.180 lac
(ii) 1st Floor
Ceiling = 20558.28 sft
column face
Column C1 32 X ( 2 ' - 9 " + 2 ' - 9 " ) = 176.00 rft
Column C2 28 X ( 2 ' - 9 " + 2 ' - 0 " ) = 133.00 rft
Column C3 4 X ( 1 ' - 3 " + 2 ' - 6 " ) = 15.00 rft
Column C4 18 X ( 1 ' - 0 " + 2 ' - 1 " ) = 55.50 rft
= 379.50 rft X 12 ' 0 X 2
= 9108.00 sft
lift wall 4 X 75 ' - 0 " X 12 ' - 6 " = 3750.00 sft
ceiling beam side
Long direction 4 X 190 ' - 0 " X 1 ' - 6 " = 1140.00 sft
2 X 219 ' - 0 " X 2 ' - 0 " = 876.00 sft
Short direction 10 X 80 ' - 0 " X 1 ' - 6 " = 1200.00 sft
15 X 30 ' - 0 " X 1 ' - 6 " = 675.00 sft
Semi circular 2 X 3.1 X 25 ' - 0 " X 1 ' - 6 " = 235.50 sft
stair landing beam 2 X 11 ' - 0 " X 1 ' - 6 " = 33.00 sft
= 4159.50 sft X 2 ( 2 sides of beam )
= 8319.00 sft
Stair case slab bottom & landing
Short side stair 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 3 ' - 0 " = 28.26 sft
long side stair 4 X 11 ' - 8 " X 4 ' - 8 " = 217.78 sft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " = 68.38 sft
Middle stair 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
= 744.95 sft
@ Tk 99.00
quantity same as 1st Flor roof slab ,
mark B of Item 2
Page No 41
Railing, drop wall = 4566.85 sft X 2
= 9133.71 sft
Sun shade = 600.00 sft X 2
= 1200.00 sft
Total plaster area in 1st Floor = 52813.93 sft (mark C )
= 4908.36 sqm / sqm = Tk 5.122 lac
(iii) 2nd Floor
Ceiling = 20558.28 sft
column face
Column C1 32 X ( 2 ' - 9 " + 2 ' - 9 " ) = 176.00 rft
Column C2 28 X ( 2 ' - 9 " + 2 ' - 0 " ) = 133.00 rft
Column C3 4 X ( 1 ' - 3 " + 2 ' - 6 " ) = 15.00 rft
Column C4 18 X ( 1 ' - 0 " + 2 ' - 1 " ) = 55.50 rft
= 379.50 rft X 12 ' 0 X 2
= 9108.00 sft
lift wall 4 X 75 ' - 0 " X 12 ' - 6 " = 3750.00 sft
ceiling beam side quantity same as 1st Floor = 8319.00 sft
Stair case slab bottom & landing
Short side stair 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 3 ' - 0 " = 28.26 sft
long side stair 4 X 11 ' - 8 " X 4 ' - 8 " = 217.78 sft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " = 68.38 sft
Middle stair 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
= 744.95 sft
Railing, drop wall = 4566.85 sft X 2
= 9133.71 sft
Sun shade = 720.00 sft X 2
= 1440.00 sft
Total plaster area in 2nd Floor = 53053.93 sft (mark D )
= 4930.66 sqm / sqm = Tk 5.409 lac
(iv) 3rd Floor quantity same as 2nd floor = 53053.93 sft
= 4930.66 sqm / sqm = Tk 5.673 lac
(v) 4th Floor quantity same as 3rd floor = 53053.93 sft
= 4928.83 sqm / sqm = Tk 5.934 lac
(vi) 5th Floor
Ceiling : = 17252.94 sft
@ Tk
@ Tk
@ Tk 109.70
104.35
120.40
quantity same as 2nd Floor roof slab ,
mark C of Item 2
quantity same as 5th Floor roof slab ,
mark D of Item 2
115.05@ Tk
Page No 42
column face
Column C1 32 X ( 2 ' - 9 " + 2 ' - 9 " ) = 176.00 rft
Column C2 28 X ( 2 ' - 9 " + 2 ' - 0 " ) = 133.00 rft
Column C3 4 X ( 1 ' - 3 " + 2 ' - 6 " ) = 15.00 rft
Column C4 6 X ( 1 ' - 0 " + 2 ' - 1 " ) = 18.50 rft
= 342.50 rft X 12 ' 0 X 2
= 8220.00 sft
lift wall 4 X 75 ' - 0 " X 12 ' - 6 " = 3750.00 sft
ceiling beam side
Long direction 4 X 190 ' - 0 " X 1 ' - 6 " = 1140.00 sft
2 X 190 ' - 0 " X 1 ' - 6 " = 570.00 sft
Short direction 20 X 20 ' - 0 " X 1 ' - 6 " = 600.00 sft
20 X 20 ' - 0 " X 1 ' - 6 " = 600.00 sft
4 X 30 ' - 0 " X 1 ' - 6 " = 180.00 sft
= 3090.00 sft X 2 ( 2 sides of beam )
= 6180.00 sft
Stair case slab bottom & landing
Short side stair 4 X 11 ' - 8 " X 3 ' - 0 " = 140.00 sft
landing 3.1 X 3 ' - 0 " X 3 ' - 0 " = 28.26 sft
long side stair 4 X 11 ' - 8 " X 4 ' - 8 " = 217.78 sft
landing 3.1 X 4 ' - 8 " X 4 ' - 8 " = 68.38 sft
Middle stair 4 X 11 ' - 8 " X 5 ' - 0 " = 233.33 sft
landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
= 744.95 sft
Railing, drop wall = 4067.69 sft X 2
= 8135.37 sft
Sun shade = 1200.00 sft X 2
= 2400.00 sft
Total plaster area in 5th floor = 46683.27 sft ( mark E )
= 4336.98 sqm / sqm = Tk 5.454 lac
(vii) 6th Floor
Ceiling 1 X 116 ' - 0 " X 30 ' - 0 " = 3480.00 sft
column face
Column C1 8 X ( 2 ' - 9 " + 2 ' - 9 " ) = 44.00 rft
Column C2 4 X ( 2 ' - 9 " + 2 ' - 0 " ) = 19.00 rft
Column C3 4 X ( 1 ' - 3 " + 2 ' - 6 " ) = 15.00 rft
Column C4 2 X ( 1 ' - 0 " + 2 ' - 1 " ) = 6.17 rft
= 84.17 rft X 12 ' 0 X 2
= 2020.00 sft
ceiling beam side
3 X 110 ' - 0 " X 1 ' - 6 " = 495.00 sft
4 X 30 ' - 0 " X 1 ' - 6 " = 180.00 sft
3 X 30 ' - 0 " X 2 ' - 0 " = 180.00 sft
= 855.00 sft X 2 ( 2 sides of beam )
= 1710.00 sft
Total Plaster in 6th Floor = 7210.00 sft ( mark F )
= 669.83 sqm / sqm = Tk 0.896 lac
@ Tk 125.75
@ Tk 133.77
Page No 43
23
CE 122
15.8.
GF quantity same as Facing brick work = 7750.00 sft
= 719.99 sqm / sqm = Tk 0.569 lac
1st Floor quantity same as Facing brick work = 1860.00 sft
= 172.80 sqm / sqm = Tk 0.146 lac
24
(CE 124)
15.10.
7 X 20 X 15 ' - 0 " = 2100.00 rft
= 640.24 rm / rm = Tk 0.301 lac
25
CE 127
15.13.
5th Floor roof 1 X 195 ' - 0 " X 115 ' - 0 " = 22425.00 sft
= 22425.00 sft X 4 "
= 7475.00 cft
211.70 cum / cum = Tk 11.269 lac
Tk 1745.712 lac
Providing drip course/ Nosing/ throating at the edge of sunshade or cornice with cement sand (F.M. 1.2) mortar (1:2)
with fresh cement (conforming to BDS 232) in/c. scaffolding, curing at least for 7 days, cost of water, electricity & other
charges etc. all complete in all respect as per drawing accepted by the Engineer.
( Cement : CEM - II / A - M )
@ Tk 5323.00
@ Tk 47.00
=
SubTotal =
Rule pointing to brick wall with cement sand (F.M. 1.2) mortar (1:2) with fresh cement (conforming to BDS 232) and
raking out the joints, scaffolding, curing at least for 7 days, cost of water, electricity & other charges etc. all complete in all
respect as per drawing and accepted by the Engineer.
( Cement : CEM - II / A - M )
@ Tk 79.00
@ Tk 84.35
Average 100 mm thick finished lime terracing with 20 mm down graded 1st class brick chips (Khoa), surki from 1st class
bricks and lime (stone lime brought at site, not being powdered in open air and to be slaked in presence of engineer-in-
charge and to be measured in volume three days after slaking for using in the mix) in the proportion 7:2:2 (brick chips : surki
: lime) including preparation of the mix on the ground by making a suitable platform under proper polythene cover. Cutting
the mix twice daily with limewater (1:10) at least for 7 days until the mix attain desirable consistency. Laying the mix in
proper slope, beating the same with standard ‘koppa’ for minimum 7 days to gain maximum consolidation, making ghoondy
and neat finishing with lime Surki mortar (1:2) and curing for 21 days providing polythene cover after each day work and
cleaning etc. complete in all respect accepted by the Engineer.
( Cement : CEM - II / A - M )
Page No 44
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 2048.646 2404.13
151.00 175.00 3.843 4.45 25.8% 15.9%
158.00 184.00 3.419 3.98 26.0% 16.5%
165.00 193.00 4.176 4.88 26.2% 17.0%
172.00 202.00 4.353 5.11 26.4% 17.4%
179.00 211.00 4.530 5.34 26.6% 17.9%
Rate Total
Page No 45
186.00 220.00 4.393 5.20 26.7% 18.3%
196.00 234.00 3.004 3.59 26.6% 19.4%
174.00 202.00 0.200 0.23 26.1% 16.1%
188.00 216.00 0.155 0.18 26.2% 14.9%
195.00 225.00 0.143 0.16 26.3% 15.4%
Page No 46
202.00 234.00 0.154 0.18 26.5% 15.8%
209.00 243.00 0.160 0.19 26.6% 16.3%
216.00 252.00 0.165 0.19 26.8% 16.7%
223.00 261.00 0.176 0.21 26.9% 17.0%
233.00 275.00 0.036 0.04 26.8% 18.0%
137.00 161.00 0.153 0.18 25.7% 17.5%
Page No 47
Page No 48
125.00 152.00 12.854 15.63 26.3% 21.6%
Page No 49
132.00 161.00 6.479 7.90 26.5% 22.0%
139.00 170.00 6.854 8.38 26.7% 22.3%
146.00 179.00 7.199 8.83 26.9% 22.6%
153.00 188.00 7.541 9.27 27.1% 22.9%
Page No 50
160.00 197.00 6.939 8.54 27.2% 23.1%
170.00 211.00 1.139 1.41 27.1% 24.1%
Page No 51
100.00 120.00 0.720 0.86 26.6% 20.0%
107.00 129.00 0.185 0.22 26.9% 20.6%
59.00 73.00 0.378 0.47 25.5% 23.7%
8,319.00 10258.00 17.611 21.72 56.3% 23.3%
2145.604 2521.4787 22.91 17.5%SubTotal =
Page No 44
B.F 1745.712 lac
26
CE 44-I a
06.8.1
(i) GF
male gen toilet 1 X 19 ' - 7 " X 14 ' - 6 " = 283.96 sft
Female gen toilet 1 X 19 ' - 7 " X 14 ' - 6 " = 283.96 sft
= 567.92 sft
= 52.76 sqm / sqm = TK 0.457 lac
(ii) 1st Floor
male gen toilet 1 X 19 ' - 7 " X 14 ' - 6 " = 283.96 sft
Female gen toilet 1 X 19 ' - 7 " X 14 ' - 6 " = 283.96 sft
= 567.92 sft
= 52.76 sqm / sqm = TK 0.459 lac
(iii) 2nd Floor
male gen toilet 1 X 19 ' - 7 " X 14 ' - 6 " = 283.96 sft
Female gen toilet 1 X 19 ' - 7 " X 14 ' - 6 " = 283.96 sft
= 567.92 sft
= 52.76 sqm / sqm = TK 0.461 lac
(iv) 3rd Floor Quantity same as 2nd floor = 567.9167 sft
= 52.76 sqm / sqm = TK 0.464 lac
(v) 4th Floor Quantity same as 3rd floor = 567.9167 sft
= 52.76 sqm / sqm = TK 0.466 lac
(vi) 5th Floor Quantity same as 4th floor = 567.9167 sft
= 52.76 sqm / sqm = TK 0.468 lac
(Marked A) ( total floor tiles in toilet in all floors = 3407.50 sft )
27
CE 44 -IIb
06.9.2
(i) GF
2 X 27 ' - 6 " X 28 ' - 0 " = 1540.00 sft
2 X 3 ' - 11 " X 6 ' - 6 " = 50.92 sft
1 X 28 ' - 0 " X 28 ' - 0 " = 784.00 sft
1 X 19 ' - 0 " X 5 ' - 0 " = 95.00 sft
deduct, middle stair -1 X 23 ' - 2 " X 11 ' - 10 " = -274.14 sft
= 2195.78 sft
= 203.99 sqm / sqm = TK 3.770 lac
(ii) 1st Floor area same as GF = 2195.78 sft
= 203.99 sqm / sqm = TK 3.778 lac
886.2
1848.00
@ Tk 1851.84
Supplying, fitting and fixing mirror polished floor tiles (local made) on 20 mm thick cement sand (F.M.1.2)
mortar (1:4) base and raking out the joints with white cement and colored pigment including cutting and laying tiles
in proper way and finishing with care etc, all complete and accepted by the Engineer.
( Cement : CEM - II / A - M )
Size : GP ( mirror polished ) 396 mm X 396 mm floor tiles
@ Tk
@ Tk
@ Tk
@ Tk
@ Tk 867.00
@ Tk 870.84
@ Tk
GP Homogeneous 305 mm X 305 mm floor tiles in Toilet
Supplying, fitting and fixing unglazed homogeneous floor tiles (local made) on 20 mm thick cement sand
(F.M.1.2) mortar (1:4) base and raking out the joints with white cement and colored pigment including cutting and
laying tiles in proper way and finishing with care etc, all complete and accepted by the Engineer.
( Cement : CEM - II / A - M )
Size : GP Homogeneous 305 mm X 305 mm .
874.68
878.52
882.36
Side stair and lift front stair
corridor
Page No 45
(iii) 2nd Floor area same as 1st Floor = 2195.78 sft
= 203.99 sqm / sqm = TK 3.785 lac
(iv) 3rd Floor Quantity same as 2nd floor = 2195.778 sft
= 203.99 sqm / sqm = TK 3.793 lac
(v) 4th Floor Quantity same as 3rd floor = 2195.778 sft
= 203.99 sqm / sqm = TK 3.801 lac
(vi) 5th Floor Quantity same as 4th floor = 2195.778 sqm
= 203.99 sqm / sqm = TK 3.809 lac
28
CE 42 b
06.6.2
(i) GF
male gen toilet 9 X 3 ' - 6 " X 7 ' - 0 " = 220.50 sft
10 X 4 ' - 9 " X 7 ' - 0 " = 332.50 sft
8 X 2 ' - 0 " X 7 ' - 0 " = 112.00 sft
4 X 4 ' - 2 " X 7 ' - 0 " = 116.67 sft
4 X 6 ' - 10 " X 7 ' - 0 " = 191.33 sft
1 X 15 ' - 0 " X 7 ' - 0 " = 105.00 sft
Basement lift wall 4 X 36 ' - 8 " X 10 ' - 0 " = 1466.67 sft
Female gen toilet 9 X 3 ' - 6 " X 7 ' - 0 " = 220.50 sft
10 X 4 ' - 9 " X 7 ' - 0 " = 332.50 sft
8 X 2 ' - 0 " X 7 ' - 0 " = 112.00 sft
4 X 4 ' - 2 " X 7 ' - 0 " = 116.67 sft
4 X 6 ' - 10 " X 7 ' - 0 " = 191.33 sft
1 X 15 ' - 0 " X 7 ' - 0 " = 105.00 sft
= 3622.67 sft
= 336.55 sqm / sqm = TK 3.056 lac
(ii) 1st Floor
male gen toilet 9 X 3 ' - 6 " X 7 ' - 0 " = 220.50 sft
10 X 4 ' - 9 " X 7 ' - 0 " = 332.50 sft
8 X 2 ' - 0 " X 7 ' - 0 " = 112.00 sft
4 X 4 ' - 2 " X 7 ' - 0 " = 116.67 sft
4 X 6 ' - 10 " X 7 ' - 0 " = 191.33 sft
1 X 15 ' - 0 " X 7 ' - 0 " = 105.00 sft
Female gen toilet 9 X 3 ' - 6 " X 7 ' - 0 " = 220.50 sft
10 X 4 ' - 9 " X 7 ' - 0 " = 332.50 sft
8 X 2 ' - 0 " X 7 ' - 0 " = 112.00 sft
4 X 4 ' - 2 " X 7 ' - 0 " = 116.67 sft
4 X 6 ' - 10 " X 7 ' - 0 " = 191.33 sft
1 X 15 ' - 0 " X 7 ' - 0 " = 105.00 sft
= 2156.00 sft
= 200.30 sqm / sqm = TK 1.826 lac911.84
@ Tk
Supplying , fitting and fixing glazed wall tiles ( local made ) on 20 mm thick cement sand ( F.M 1.2 ) mortar
(1:3) base and raking out the joints with white cement including cutting , laying and hire charge of machine and
finishing with care etc including water, electricity and other charges complete in all respect and accepted by the
Engineer.
( Cement : CEM - II / A - M )
Size : Coloured wall tiles of different sizes
1855.68
1859.52
1863.36
1867.20@ Tk
@ Tk
@ Tk
@ Tk
908.00
@ Tk
Page No 46
(iii) 2nd Floor Quantity same as 1st floor = 2156.00 sft
= 200.30 sqm / sqm = TK 1.834 lac
(iv) 3rd Floor Quantity same as 2nd floor 2156.00 sft
= 200.30 sqm / sqm = TK 1.842 lac
(v) 4th Floor Quantity same as 3rd floor 2156.00 sft
= 200.30 sqm / sqm = TK 1.849 lac
(vi) 5th Floor Quantity same as 3rd floor = 2156.00 sft
= 200.30 sqm / sqm = TK 1.857 lac
( Total wall tiles area =
29
CE 27 c
05.1.4
( I ) GF
Basement floor 2 X 30 ' - 0 " X 15 ' - 0 " = 900.00 sft
2 X 30 ' - 0 " X 25 ' - 0 " = 1500.00 sft
deduct -4 X 12 ' - 0 " X 9 ' - 0 " = -432.00 sft
Basement stair :landing 0.5 X 3.14 3 ' X 3 ' = 14.13 sft
Tread 22 X 3 ' - 0 " X 0 ' - 10 " = 55.00 sft
short side stair :landing 1 X 3.14 3 ' X 3 ' = 28.26 sft
Tread 44 X 3 ' - 0 " X 0 ' - 10 " = 110.00 sft
middle stair :landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
Tread 44 X 5 ' - 0 " X 0 ' - 10 " = 183.33 sft
long side stair :landing 1 X 3.14 4.67 ' X 4.67 ' = 68.48 sft
Tread 44 X 4 ' - 8 " X 0 ' - 10 " = 171.11 sft
corner stair :landing 0.5 X 3.14 3.5 ' X 3.5 ' = 6.01 sft
Tread 22 X 3 ' - 6 " X 0 ' - 10 " = 64.17 sft
= 2725.68 sft
= 253.22 sqm / sqm = TK 2.059 lac
(ii ) 1st floor
short side stair :landing 1 X 3.14 3 ' X 3 ' = 28.26 sft
Tread 44 X 3 ' - 0 " X 0 ' - 10 " = 110.00 sft
middle stair :landing 1 X 11 ' - 10 " X 4 ' - 10 " = 57.19 sft
Tread 44 X 5 ' - 0 " X 0 ' - 10 " = 183.33 sft
long side stair :landing 1 X 3.14 4.67 ' X 4.67 ' = 68.48 sft
Tread 44 X 4 ' - 8 " X 0 ' - 10 " = 171.11 sft
= 618.38 sft
= 57.45 sqm / sqm = TK 0.469 lac
@ Tk
816.84
X
@ Tk
915.68
@ Tk 923.36
927.2
10 mm thick finished and 12 mm laying thickness situ mosaic work on floor with one part of 10 mm machine
crushed well graded dust free and properly washed marble chips and one part of mixture containing white cement
and grey cement in proportion ( 9:1 ) in/c. preparation of mix. and laying the same over minimum 25 mm thick
artificial patent stone flooring in/c making suitable panel, compacting, curing at least for 7 days, cutting with pumic
stone (No. 40, No. 80, No.120)/cutting with mosaic machine and finishing with Minar stone & spreading oxalic acid
in/c breaking brick chips, screening, washing mosaic chips and supply of all necessary materials& water,
electricity & other charges in all respect accepted by the Engineer.
( Cement : CEM - II / A - M )
With Indian chips and without glass strip approved by the Engineer.
813.00
X
X
X
X
X
@ Tk
@ Tk
14402.67 sft )
919.52
@ Tk
Page No 47
(iii) 2nd floor area same as 1st Floor = 618.38 sft
= 57.45 sqm / sqm = TK 0.471 lac
(iv) 3rd floor area same as 2nd Floor = 618.38 sft
= 57.45 sqm / sqm = TK 0.474 lac
(v) 4th floor area same as 3rd Floor = 618.38 sft
= 57.45 sqm / sqm = TK 0.476 lac
(vi) 5th floor area same as 4th Floor = 618.38 sft
= 57.45 sqm / sqm = TK 0.478 lac
30
CE 31 a
05.5.1
( I ) GF
Basement 4 X 30 ' - 0 " X 1 ' - 6 " = 180.00 sft
4 X 25 ' - 0 " X 1 ' - 6 " = 150.00 sft
Basement stair rise 24 X 3 ' - 0 " X 0 ' - 6 " = 36.00 sft
railing 4 X 11 ' - 8 " X 1 ' - 11 " = 89.44 sft
short side stair : Railing 8 X 11 ' - 8 " X 1 ' - 11 " = 178.89 sft
landing side railing 2 X 3.14 4.67 ' X 1 ' - 11 " = 29.33 sft
Rise 48 X 3 ' - 0 " X 0 ' - 6 " = 72.00 sft
middle stair : Railing 8 X 11 ' - 8 " X 1 ' - 11 " = 178.89 sft
Rise 48 X 5 ' - 0 " X 0 ' - 6 " = 120.00 sft
long side stair : Railing 8 X 11 ' - 8 " X 1 ' - 11 " = 178.89 sft
Rise 48 X 4 ' - 8 " X 0 ' - 6 " = 112.00 sft
corner stair :landing 4 X 11 ' - 8 " X 1 ' - 11 " = 89.44 sft
Rise 24 X 3 ' - 6 " X 0 ' - 6 " = 42.00 sft
= 1456.88 sft
= 135.35 sqm / sqm = TK 1.167 lac
(ii) 1st Floor
short side stair : Railing 8 X 11 ' - 8 " X 2 ' - 3 " = 210.00 sft
landing side railing 2 X 3.14 4.67 ' X 2 ' - 3 " = 58.66 sft
Rise 48 X 3 ' - 0 " X 0 ' - 6 " = 72.00 sft
middle stair : Railing 8 X 11 ' - 8 " X 2 ' - 3 " = 210.00 sft
Rise 48 X 5 ' - 0 " X 0 ' - 6 " = 120.00 sft
long side stair : Railing 8 X 11 ' - 8 " X 2 ' - 3 " = 210.00 sft
Rise 48 X 4 ' - 8 " X 0 ' - 6 " = 112.00 sft
= 992.66 sft
= 92.22 sqm / sqm = TK 0.798 lac865.84
@ Tk
@ Tk 828.36
X
@ Tk 832.20
@ Tk 824.52
862.00
X
@ Tk
@ Tk 820.68
10 mm thick finished and laying thickness 12.5 mm situ mosaic work on wall with one part of 10 mm machine crushed
well graded dust free and properly washed marble chips and one part of mixture containing white cement and grey cement
in proportion (9:1) including preparation of mix and laying the same on 12 mm thick cement plaster (1:4) to wall, compacting,
curing at least for 7 days, cutting with pumic stone (No. 40, No. 80, No. 120) including finishing the corners and edges and
also finishing with Minar stone and supplying all necessary materials in & water, electricity & other charges in all respect
accepted by the Engineer.
( Cement : CEM - II / A - M )
With Indian chips
Page No 48
(iii) 2nd Floor Quantity same as 1st floor = 992.66 sft
= 92.22 sqm / sqm = TK 0.802 lac
(iv) 3rd Floor Quantity same as 2nd floor = 992.6552 sft
= 92.22 sqm / sqm = TK 0.806 lac
(v) 4th Floor Quantity same as 3rd floor = 992.6552 sft
= 92.22 sqm / sqm = TK 0.809 lac
(vi) 5th Floor Quantity same as 4th floor = 992.6552 sft
= 92.22 sqm / sqm = TK 0.813 lac
31
(CE 40 )
06.2.
(i) GF
Entrance platform 1 X 9 ' - 7 " X 28 ' - 4 " = 271.53 sft
Lobby 1 X 30 ' - 0 " X 40 ' - 0 " = 1200.00 sft
Front entrance stair tread 4 X 28 ' - 4 " X 0 ' - 10 " = 94.44 sft
side entrance platform 4 X 7 ' - 6 " X 10 ' - 0 " = 300.00 sft
side entrance stair tread 4 X 4 X 7 ' - 6 " X 0 ' - 10 " = 100.00 sft
= 1965.97 sft
= 182.64 sqm / sqm = TK 10.747 lac
32
CE 38 b
06.4.
GF backside entrance 4 X 5 ' - 10 " X 0 ' - 10 " = 19.44 sft
= sqm / sqm = TK 0.135 lac
33
CE 39 b
06.3.2
( i ) GF
Entrance stair rise 5 X 28 ' - 4 " X 0 ' - 6 " = 70.83 sft
Entrance side stair rise 20 X 7 ' - 6 " X 0 ' - 6 " = 75.00 sft
Backside entrance stair rise 5 X 5 ' - 10 " X 0 ' - 6 " = 14.58 sft
Flower bed side wall 2 X 15 ' - 0 " X 2 ' - 3 " = 67.50 sft
Lift wall sides 4 X 22 ' - 6 " X 12 ' - 6 " = 1125.00 sft
= 1352.92 sft
= 125.74 sqm
/ sqm = TK 7.093 lac
873.52
@ Tk
877.36
@ Tk
1.81
5641.00@ Tk
@ Tk
7483.00
5884.00
@ Tk
Supplying and setting 12 mm thick De carrara/Ariston/ Venous marble stone (Italy) or equivalent of
approved quality/texture & size on wall over 12 mm thick cement sand (F.M.1.2) mortar (1:2) in/c. cutting the
marble stone to desired size, grinding and finishing the edges, setting on position keeping correct horizontal and
vertical alignment filling the joints with white cement and coloring pigments including supplying all necessary
equipments/ materials and finishing the top by pumic stone and necessary auxiliary materials & water, electricity &
other charges complete in all respect and accepted by the Engineer.
( Cement : CEM - II / A - M )
@ Tk 881.2
Marble stone flooring with 18 mm thick European origin marble stone of approved quality, texture & size
over 25 mm thick cement sand (F.M.1.2) mortar (1:2) in/c. placing cement slurry below the stone, cutting the
marble stone to desired size, grinding and finishing the edges, setting in position in proper level filling the gaps
with white cement and coloring pigments including supplying all necessary equipments/materials and finishing the
top by pumic stone and necessary auxiliary materials & water, electricity & other charges complete in all respect
and accepted by the Engineer.
( Cement : CEM - II / A - M )
Marble stone flooring with 20 mm thick grey or colored marble stone ( SAARC countries origin ) of
approved quality, texture & size over 25 mm thick cement sand (F.M.1.2) mortar (1:2) in/c placing cement slurry
below the stone, cutting the marble stone to desired size, grinding, polishing and finishing the edges setting in
position in proper level, filling the gaps with white cement and coloring pigments including supplying all necessary
equipments/materials and finishing the top by pumic stone and necessary auxiliary materials & water, electricity &
other charges all complete in all respect and accepted by the Engineer.
( Cement : CEM - II / A - M )
869.68
@ Tk
Page No 49
( ii ) 1st Floor
Lift wall front & back face 4 X 22 ' - 6 " X 12 ' - 6 " = 1125.00 sft
= 104.55 sqm
@ Tk / sqm = TK 5.902 lac
( iii ) 2nd Floor
Lift wall front & back face 4 X 22 ' - 6 " X 12 ' - 6 " = 1125.00 sft
= 104.55 sqm
@ Tk / sqm = TK 5.906 lac
( iv ) 3rd Floor
Lift wall front & back face 4 X 22 ' - 6 " X 12 ' - 6 " = 1125.00 sft
= 104.55 sqm
@ Tk / sqm = TK 5.910 lac
( v ) 4th Floor
Lift wall front & back face 4 X 22 ' - 6 " X 12 ' - 6 " = 1125.00 sft
= 104.55 sqm
@ Tk / sqm = TK 5.914 lac
( vi ) 5th Floor
Lift wall front & back face 4 X 22 ' - 6 " X 12 ' - 6 " = 1125.00 sft
= 104.55 sqm
@ Tk / sqm = TK 5.918 lac
34
CE 26 f
04.31.
1 X 110 ' - 0 " X 190 ' - 0 " = 20900.00 sft
2 X 0.5 X 3.1 X 25 ' - 0 " X 25 ' - 0 " = 1962.50 sft
Deduction -2 X 15 ' - 0 " X 30 ' - 0 " = -900.00 sft
-2 X 25 ' - 0 " X 30 ' - 0 " = -1500.00 sft
= 20462.50 sft
= 1901.01 sqm
@ Tk / sqm = TK 5.855 lac
1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft
0.5 X 3.14 25 ' X 25 ' X 2 = 1962.5 sft
= 24698.50 sft
Deduction
Mid lift & stair block 1 X 30 ' - 0 " X 150 ' - 0 " = 4500.00 sft
mid stair block 1 X 30 ' - 0 " X 80 ' - 0 " = 2400.00 sft
toilet 2 X 20 ' - 0 " X 15 ' - 0 " = 600.00 sft
= 7500.00 sft
Net Area = 24698.50 - sft
= 17198.50 sft
= 1597.78 sqm
@ Tk / sqm = TK 4.921 lac308.00
(ii) Ground Floor
(semi circular portion )
38 mm thick artificial patent stone ( 1:1.5:3 ) flooring with cement, best quality coarse sand (50% quantity of
Sylhet sand or coarse sand of equivalent F.M. 2.2 and 50% best local sand of FM 1.2) & 12 mm down well graded
stone chips , in/c breaking chips, screening, laying the concrete in alternate panels, compacting and finishing the
top with neat cement and curing at least 7 days in all floors in/c cost of water, electricity & other charges etc. all
complete in all respect and accepted by the Engineer.
( Cement : CEM - II / A - M )
(i) Basement floor
308.00
X
7500.00
( - )
5660.20
5656.36
5648.68
5652.52
5644.84
Page No 50
1 X 116 ' - 0 " X 196 ' - 0 " = 22736.00 sft
0.5 X 3.14 25 ' X 25 ' = 981.25 sft
= 23717.25 sft
Deduction :
0.5 X 11 ' - 4 " X 10 ' - 0 " = 56.67 sft
0.5 X 11 ' - 4 " X 10 ' - 0 " = 56.67 sft
0.5 X 28 ' - 4 " X 5 ' - 10 " = 82.64 sft
Mid lift & stair block 1 X 30 ' - 0 " X 110 ' - 0 " = 3300.00 sft
Side stair block 1 X 30 ' - 0 " X 80 ' - 0 " = 2400.00 sft
Toilet 2 X 15 ' - 0 " X 20 ' - 0 " = 600.00 sft
lobby void 1 X 30 ' - 0 " X 20 ' - 0 " = 600.00 sft
= 7095.97 sft
Net Area = 23717.25 - sft
(mark A ) = 16621.28 sft
= 1544.15 sqm
@ Tk / sqm = TK 4.934 lac
area same as 1st Floor = 16621.28 sft
1 X 30 ' - 0 " X 20 ' - 0 " = 600.00 sft
= 17221.28 sft
= 1599.90 sqm
@ Tk / sqm = TK 5.296 lac
area same as 2nd floor = 17221.28 sft
= 1599.90 sqm
@ Tk / sqm = TK 5.480 lac
area same as 3rd floor = 17221.28 sft
= 1599.90 sqm
@ Tk / sqm = TK 5.664 lac
4 X 86 ' - 0 " X 46 ' - 0 " = 15824.00 sft
deduct, toilet -2 X 15 ' - 0 " X 20 ' - 0 " = -600.00 sft
(mark D) = 15224.00 sft
= 1414.34 sqm
@ Tk / sqm = TK 5.170 lac
1 X 117 ' - 0 " X 30 ' - 0 " = 3510.00 sft
= 326.09 sqm
@ Tk / sqm = TK 1.242 lac
Sub Total = TK 1879.196 lac
(vii) 5th Floor
add , lobby void
319.51
331.02
( iii ) 1st Floor
(semi circular portion ) X
365.55
380.90
(void at Dept of Forensic
medicine )
( - )
7095.97
(iv) 2nd Floor
( viii ) 6th Floor ( chillakota )
(v) 3rd Floor
(vi ) 4th Floor
354.04
342.53
Page No 51
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 2145.604069 2521.479
1,084.00 1321.00 0.572 0.696969 25.0% 21.9%
1,089.00 1327.00 0.575 0.700135 25.1% 21.9%
1,094.00 1333.00 0.577 0.703301 25.1% 21.8%
1,099.00 1339.00 0.580 0.706466 25.1% 21.8%
1,104.00 1345.00 0.582 0.709632 25.1% 21.8%
1,109.00 1351.00 0.585 0.712798 25.1% 21.8%
1,890.00 1565.00 3.855 3.192486 2.3% -17.2%
1,895.00 1571.00 3.866 3.204726 2.3% -17.1%
Rate Total
Page No 52
1,900.00 1577.00 3.876 3.216965 2.4% -17.0%
1,905.00 1583.00 3.886 3.229205 2.4% -16.9%
1,910.00 1589.00 3.896 3.241445 2.5% -16.8%
1,915.00 1595.00 3.906 3.253684 2.6% -16.7%
1,007.00 1107.00 3.389 3.725652 10.9% 9.9%
1,012.00 1113.00 2.027 2.229309 11.0% 10.0%
Page No 53
1,017.00 1119.00 2.037 2.241327 11.1% 10.0%
1,022.00 1125.00 2.047 2.253344 11.1% 10.1%
1,027.00 1131.00 2.057 2.265362 11.2% 10.1%
1,032.00 1137.00 2.067 2.27738 11.3% 10.2%
887.00 1215.00 2.246 3.076647 9.1% 37.0%
892.00 1221.00 0.512 0.70145 9.2% 36.9%
Page No 54
897.00 1227.00 0.515 0.704897 9.3% 36.8%
902.00 1233.00 0.518 0.708344 9.4% 36.7%
907.00 1239.00 0.521 0.711791 9.5% 36.6%
912.00 1245.00 0.524 0.715238 9.6% 36.5%
963.00 1321.00 1.303 1.787944 11.7% 37.2%
968.00 1327.00 0.893 1.223758 11.8% 37.1%
Page No 55
973.00 1333.00 0.897 1.229292 11.9% 37.0%
978.00 1339.00 0.902 1.234825 12.0% 36.9%
983.00 1345.00 0.907 1.240358 12.0% 36.8%
988.00 1351.00 0.911 1.245891 12.1% 36.7%
4,885.00 5125.00 8.922 9.360468 -17.0% 4.9%
6,932.00 7269.00 0.125 0.13131 -7.4% 4.9%
4,189.00 5039.00 5.267 6.335824 -25.7% 20.3%
Page No 56
4,194.00 5045.00 4.385 5.274744 -25.7% 20.3%
4,199.00 5051.00 4.390 5.281018 -25.7% 20.3%
4,204.00 5057.00 4.395 5.287291 -25.6% 20.3%
4,209.00 5063.00 4.401 5.293564 -25.6% 20.3%
4,214.00 5069.00 4.406 5.299837 -25.6% 20.3%
364.00 416.00 6.920 7.908213 18.2% 14.3%
364.00 416.00 5.816 6.646763 18.2% 14.3%
Page No 57
378.00 435.00 5.837 6.717072 18.3% 15.1%
392.00 454.00 6.272 7.263527 18.4% 15.8%
406.00 473.00 6.496 7.567507 18.5% 16.5%
420.00 492.00 6.720 7.871487 18.6% 17.1%
434.00 511.00 6.138 7.227298 18.7% 17.7%
453.00 537.00 1.477 1.751087 18.9% 18.5%
2278.601542 2669.836 21.25 17.2%
Page No 51
B.F 1879.196 lac
35
CE 166 b
22.3.
Front Entrance door inGF
2 X 4 ' - 2 " X 7 ' - 0 " = 58.33 sft
= 5.42 sqm / sqm = Tk 0.808 lac
36
analysis
Front Entrance door inGF
1 X 43 ' - 6 " X 24 ' - 0 " = 1044.00 sft
deduct, glass door -2 X 4 ' - 2 " X 7 ' - 0 " = -58.33 sft
= 985.67 sft
= 91.60 sqm / sqm = Tk 5.990 lac
37
CE 76 e
11.1.5
Single swing door ( per swing 3'-4")
GF 10 X 17 ' - 6 " = 175.00 rft
1st Floor 6 X 17 ' - 6 " = 105.00 rft
2nd Floor 6 X 17 ' - 6 " = 105.00 rft
3rd Floor 6 X 17 ' - 6 " = 105.00 rft
4th Floor 6 X 17 ' - 6 " = 105.00 rft
5th Floor 6 X 17 ' - 6 " = 105.00 rft
6th Floor 6 X 17 ' - 6 " = 105.00 rft
= 805.00 rft X 0 ' 6 " X 0 ' "
= 83.85 cft
= 2.37 cum / cum = Tk 3.161 lac
38
CE 86 a
12.7.1
GF 10 X 3 ' - 4 " X 6 ' - 10 " = 227.78 sft
1st Floor 6 X 3 ' - 4 " X 6 ' - 10 " = 136.67 sft
2nd Floor 6 X 3 ' - 4 " X 6 ' - 10 " = 136.67 sft
3rd Floor 6 X 3 ' - 4 " X 6 ' - 10 " = 136.67 sft
4th Floor 6 X 3 ' - 4 " X 6 ' - 10 " = 136.67 sft
5th Floor 6 X 3 ' - 4 " X 6 ' - 10 " = 136.67 sft
6th Floor 6 X 3 ' - 4 " X 6 ' - 10 " = 136.67 sft
= 1047.78 sft
= 97.34 sqm / sqm = Tk 3.165 lac
@ Tk
@ Tk 133119.00
6539.00
Supplying , fitting, fixing of swing door shutter provided by 10 mm thick Tempered Clear glass ( foreign made )
in/c locking arrangements, shutter closer, handle & other necessary fittings etc, all complete in all respect and
accepted by the Engineer.
Supplying , fitting, fixing of fixed 10 mm thick Tempered Clear glass ( foreign made ) with 15.75 mm , 14.81 mm fixed
glass protector aluminium section and other necessary fitting, fixtures complete in all respect as per direction of the
engineer in charge.
Supplying and making door and window frames (Chowkat) for all floors with matured natural seasoned wood of
required size including painting two coats of coal tar to the surface in contact with wall, fitting and fixing in position etc.
all complete and accepted by the Engineer.
(All sizes of wood are finished).
Door frame of Chittagong Teak wood
Supplying, fitting & fixing 36 mm thick & having density 400 kg/cum. solid particle board single leaf flush door for all
floors for internal use made of well matured mechanical seasoned garjan/other approved wooden frame having
finished size 35 x 50 mm around upon which 1.4 mm thick veneer (total two Nos. of veneers one of 0.7 mm
horizontally and another of 0.7 mm vertically made of Burma Teak/Champa/Chapalish /Garjan wood) with necessary
screws are pested on each side by mechanized process and provided with best quality 4 Nos. 100 mm iron hinges, 2
Nos. best quality 12 mm iron dia 300 mm and 225 mm long iron tower and socket bolts, 2 (two) Nos. heavy type nickel
plated handles, 1 No. hatch-bolt, hinged cleats, buffer blocks etc. complete and accepted by the Engineer.
Burma Teak veneered.
2.5
14906.00
@ Tk
3251.00@ Tk
Page No 52
39
Analysis
GF 2 X 2 ' - 0 " X 2 ' - 0 " = 8.00 sft
1st Floor 2 X 2 ' - 0 " X 2 ' - 0 " = 8.00 sft
2nd Floor 2 X 2 ' - 0 " X 2 ' - 0 " = 8.00 sft
3rd Floor 2 X 2 ' - 0 " X 2 ' - 0 " = 8.00 sft
4th Floor 2 X 2 ' - 0 " X 2 ' - 0 " = 8.00 sft
5th Floor 2 X 2 ' - 0 " X 2 ' - 0 " = 8.00 sft
= 48.00 sft
= 4.46 sqm / sqm = Tk 0.101 lac
40
CE 111 d
14.6.2.3
GF
12 X 15 ' - 0 " X 4 ' - 6 " = 810.00 sft
2 X 16 ' - 8 " X 4 ' - 6 " = 150.00 sft
2 X 9 ' - 7 " X 4 ' - 6 " = 86.25 sft
3 X 6 ' - 0 " X 4 ' - 6 " = 81.00 sft
= 1127.25 sft ( Total length = rft )
1st floor
14 X 15 ' - 0 " X 4 ' - 6 " = 945.00 sft
3 X 16 ' - 8 " X 4 ' - 6 " = 225.00 sft
4 X 6 ' - 0 " X 4 ' - 6 " = 108.00 sft
2 X 12 ' - 11 " X 4 ' - 6 " = 116.25 sft
3 X 10 ' - 0 " X 4 ' - 6 " = 135.00 sft
2 X 8 ' - 9 " X 4 ' - 6 " = 78.75 sft
= 1608.00 sft ( Total length = rft )
2nd floor
16 X 15 ' - 0 " X 4 ' - 6 " = 1080.00 sft
4 X 6 ' - 5 " X 4 ' - 6 " = 115.50 sft
4 X 16 ' - 8 " X 4 ' - 6 " = 300.00 sft
8 X 6 ' - 0 " X 4 ' - 6 " = 216.00 sft
= 1711.50 sft ( Total length = rft )
3rd floor = 1711.50 sft
4th floor = 1711.50 sft
same as 2nd floor
same as 3rd floor
Extra rate for punching in veneered board door shutter and Supplying, fitting & fixing fixed glass on punched
veneered board door shutter providing 25 mm wide & 12 mm thick wooden bit/frame of Teak chambal wood , 5 mm foreign
made clear glass in/c nails, putty, etc, all complete in all respect in all floors as per design and direction of the engineer in
charge.
@ Tk
Supplying, fitting and fixing of Aluminium sliding window as per the U.S. Architectural Aluminium Manufacturer’s
Association (AAMA) standard specification having 1.5 mm thick outer bottom (size 75.50 mm, 32mm), 1.5 mm thick
outer top (size 75.50 mm, 16.80 mm), 1.5 mm thick shutter top (size 33 mm.26.80, 22 mm), 1.5 mm thick shutter
bottom (size 60mm, 24.40 mm), 1.5 mm thick outer side(size 75.50 mm,19.90 mm), 1.5 mm thick sliding fixed side
(size 31 mm, 26 mm),1.5 mm thick shutter lock (size 49.20 mm 26.20 mm) & 1.5 mm thick inter lock (size 34.40 mm,
32.10 mm) sections all Aluminium members (Total weight kg/sqm) will be anodized to Aluminium Bronze/Silver color
with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc. including all accessories like
sliding door key lock, sliding door wheel, sliding door mohiar, sliding door neoprene, bolts & nuts in/c sealants, keeping
provision for fitting 5 mm thick glass including labour charge for fitting of accessories, making grooves & mending good
damages, carriage, and electricity complete in all respect as per drawing and accepted by the Engineer.
Size : 900 mm X 1400 mm ( total weight minimum 7.409 kg ) , Colour : Silver colour.
250.50
2269.00
357.33
380.33
Page No 53
5th floor
28 X 15 ' - 0 " X 4 ' - 6 " = 1890.00 sft
8 X 16 ' - 8 " X 4 ' - 6 " = 600.00 sft
4 X 5 ' - 6 " X 4 ' - 6 " = 99.00 sft
= 2589.00 sft ( Total length = rft )
Total = 10458.75 sft
= 971.64 sqm / sqm = Tk 35.105 lac
41
CE 112 b
14.8.3
GF 1 X 28 ' - 4 " X 6 ' - 0 " = 170.00 sft
1 X 7 ' - 4 " X 6 ' - 0 " = 44.00 sft
4 X 6 ' - 0 " X 6 ' - 0 " = 144.00 sft
2 X 10 ' - 5 " X 6 ' - 0 " = 125.00 sft
5 X 2 ' - 6 " X 6 ' - 0 " = 75.00 sft
1 X 7 ' - 10 " X 6 ' - 0 " = 47.00 sft
= 605.00 sft ( Total length = rft )
1st floor
1 X 5 ' - 10 " X 6 ' - 0 " = 35.00 sft
1 X 7 ' - 9 " X 6 ' - 0 " = 46.50 sft
1 X 6 ' - 3 " X 6 ' - 0 " = 37.50 sft
1 X 8 ' - 6 " X 6 ' - 0 " = 51.00 sft
1 X 7 ' - 10 " X 6 ' - 0 " = 47.00 sft
5 X 2 ' - 6 " X 6 ' - 0 " = 75.00 sft
1 X 6 ' - 6 " X 6 ' - 0 " = 39.00 sft
= 331.00 sft ( Total length = rft )
2nd floor 4 X 2 ' - 6 " X 6 ' - 0 " = 60.00 sft
= 60.00 sft ( Total length = rft )
3rd floor = 60.00 sft
4th floor = 60.00 sft
5th floor 4 X 2 ' - 6 " X 6 ' - 0 " = 60.00 sft
6th floor 12 X 6 ' - 0 " X 6 ' - 0 " = 432.00 sft ( Total length = rft )
Total = 1608.00 sft
same as 2nd floor
72.00
( mark A )
55.17
10.00
100.83
same as 3rd floor
3613.00
Supplying, fitting and fixing of Aluminium fixed composite window as per the U.S. Architectural Aluminium
Manufacturer’s Association (AAMA) standard specification having 1.5 mm thick outer bottom (size 75.50 mm, 32 mm,
0.695 kg/m), 1.5 mm thick outer top (size 75.50mm, 26.80 mm, 0.78 kg/m), 1.5 mm thick shutter top (size 33 mm,
26.80 mm, 0.536 kg/m), 1.5 mm thick shutter bottom (size 60 mm, 24.40 mm, 0.736 kg/m), 1.5 mm thick outer side
(size 75.50 mm, 19.90 mm, 0.616 kg/m), 1.5 mm thick sliding fixed side (size 31 mm, 26 mm, 0.422 kg/m), 1.5 mm
thick shutter lock (size 49.20 mm, 26.20 mm, 0.661 kg/m), 1.5 mm thick inter lock (size 34.40 mm, 32.10 mm 0.665
kg/m) 1.5 mm thick bottom cover (size 37.78 mm, 31.78 mm, 0.313 kg/m), 1.5 mm thick grouve cover (76.20 mm,
38.10 mm, 0.912 kg/m), 1.5 mm thick grouve cover ( size 57.15 mm, 15.80 mm, 0.452 kg/m) and 1.5 mm thick top &
side (size 76.20 mm, 38.10 mm, 0.3 kg/m) sections all Aluminium members (Total weight 12.297 kg) will be anodized
to Bronze/Silver color with a coat not less than 15 micron in thickness and density of 4 mg per square cm etc.
including all accessories
like sliding door key lock, sliding door wheel, sliding door mohiar, sliding door neoprene, bolts & nuts in/c sealants,
keeping provision for fitting 5mm thick glass including labour charge for fitting of accessories, making grooves &
mending good damages, carriage, and electricity complete in all respect as per drawing and accepted by the
Engineer.
Size: 1500mm x 2100 mm , Colour : Silver colour.
( mark A )
@ Tk
575.33
Page No 54
= 149.39 sqm / sqm = Tk 3.992 lac@ Tk 2672.00
Page No 55
42
CE 115b
14.11.3
(Basement) 24 X 12 ' - 0 " X 3 ' - 3 " = 936.00 sft
GF 4 X 15 ' - 0 " X 3 ' - 3 " = 195.00 sft
1 X rft X 3 ' - 3 " = 814.13 sft
1 X rft X 3 ' - 3 " = 327.71 sft
Total = 1336.83 sft
1st Floor 4 X 15 ' - 0 " X 3 ' - 3 " = 195.00 sft
1 X rft X 3 ' - 3 " = 1161.33 sft
1 X rft X 3 ' - 3 " = 179.29 sft
= 1535.63 sft
2nd Floor 4 X 15 ' - 0 " X 3 ' - 3 " = 195.00 sft
1 X rft X 3 ' - 3 " = 1236.08 sft
1 X rft X 3 ' - 3 " = 32.50 sft
= 1463.58 sft
3rd Floor area same as 2nd floor = 1463.58 sft
4th Floor area same as 2nd floor = 1463.58 sft
5th Floor 4 X 15 ' - 0 " X 3 ' - 3 " = 195.00 sft
1 X rft X 3 ' - 3 " = 1869.83 sft
1 X rft X 3 ' - 3 " = 195.00 sft
= 2259.83 sft
Total = 10459.04 sft
= 971.67 sqm / sqm = Tk 28.023 lac
43
CE 113 b
14.9.3
GF - 5 th Floor rft X 3 ' - 3 " = 325.00 sft
= 30.19 sqm / sqm = Tk 1.742 lac
575.33
60.00
100.83
357.33
55.17
10.00
Supplying fitting and fixing of Aluminium fixed fan light as per the U.S. Architectural Aluminium Manufacturer’s
Association (AAMA) standard specification mm, 0.313 kg/m) 1.5 mm thick bottom cover (size 76.2 mm, 38.10 mm,
0.76 kg/m) & 2.5 mm thick grouve cover section (size 57.15mm, 15.80 mm, 0.425 kg/m) and 1.5 thick top & side
section (76.20 mm, 16 mm, 38.10 mm, 0.961 kg/m) fixed with above mentioned frames and all Aluminium members
(Total weight 5.365kg) will be anodized to Aluminium Bronze/Silver color with a coat not less than 15 micron in
thickness and density of 4 mg per square cm etc. including all accessories, neoprene, sealant, nut & bolt etc. complete
in all respect as per drawing and accepted by the Engineer.
Colour : Silver colour.
380.33
Supplying, fitting and fixing of Aluminium top hung/casement windows as per the U.S. Architectural Aluminium
Manufacturer’s Association (AAMA) standard specification having 1.5 mm thick casement outer (size 38.86 mm, 36.36
mm, 0.395kg/m), 1.9 mm thick casement shutter (size 47.62 mm, 28.57 mm, 0.692 kg/m), & 1.245 mm thick shutter
glass clip (size 15.87 mm, 27 mm, 0.188 kg/m) sections of all Aluminium members will (Total weight 7.584 kg) be
anodized to Aluminium Bronze/Silver color with a coat not less than 15 micron in thickness and density of 4 mg per
square cm etc. including all accessories 4-bar hinge, casement handle, bolts & nuts keeping provision for fitting 5 mm
thick glass including labour charge for fitting of accessories, making grooves & mending good damages, carriage, and
electricity complete in all respect as per drawing and accepted by the Engineer.
Colour : Silver colour.
250.50
2884.00@ Tk
@ Tk
100.00
5768.00
Page No 56
44
CE 107b
14.2.3
GF 1 X 4 ' - 0 " X 7 ' - 0 " = 28.00 sft
1st Floor 1 X 4 ' - 0 " X 7 ' - 0 " = 28.00 sft
2nd Floor 1 X 4 ' - 0 " X 7 ' - 0 " = 28.00 sft
3rd Floor 1 X 4 ' - 0 " X 7 ' - 0 " = 28.00 sft
4th Floor 1 X 4 ' - 0 " X 7 ' - 0 " = 28.00 sft
5th Floor 1 X 4 ' - 0 " X 7 ' - 0 " = 28.00 sft
= 168.00 sft
= 15.61 sqm / sqm = Tk 0.798 lac
45
CE 109 b
14.4.3
GF 1 X 4 ' - 0 " X 7 ' - 0 " = 126.00 sft
1st Floor 1 X 4 ' - 0 " X 7 ' - 0 " = 210.00 sft
= 336.00 sft
= 31.22 sqm / sqm = Tk 0.683 lac
46
CE 104 a13.4.1
Quantity same as aluminium sliding window = 10458.75 sft
Quantity same as aluminium composite fixed window = 1608.00 sft
Quantity same as aluminium fixed fanlight = 10459.04 sft
= 22525.79 sft
= 2092.70 sqm / sqm = Tk 38.129 lac1822.00@ Tk
5112.00@ Tk
Supplying fitting and fixing of Aluminium composite swing doors as per the U.S. Architectural Aluminium
Manufacturer’s Association (AAMA) standard specification having 1.8 mm thick wall frame size 101.60 mm. 44.45 mm.
83.21 mm). 2.33 mm thick shutter size (54 mm, 46 mm), 0.99 mm thick door glass bit (size 16.54 mm. 14.49mm .115
kg/m), 2.5 mm thick clousure section (size 101.60 mm, 42.93 mm 1.5 mm), 106.60 mm clousure cover (0.45 kg/m), 4
mm thick floor bottom (size 101.60 mm. 12.70 mm 1 kg/m),1.8 mm thick shutter bottom (size 82.6 mm, 43.99 mm,
0.60 kg/m), 1.8 mm thick shutter top (size 51 mm, 43.99 mm, 1.88 kg/m) & 2.3 mm to 4.01 mm thick handle (size
101.60 mm, 38.10 mm, 25.40 mm short, 1.35 kg/m) section of all aluminum members will be anodized to Aluminium
Bronze/Silver colour with a coat not less than 15 micrones in thickness and density of 4 mg per square cm etc.
including all accessories like swing door clousure, swing door lock, swing door mohiar, labor charge, fabrication, fitting
fixing in position, carriage & electricity charge keeping provision for fitting 5 mm thick glass including neoprene. sealant
etc. complete in all respect
as per drawing and accepted by the Engineer. (Total weight min 23 kg/m2) , Silver colour.
@ Tk 2187.00
Supplying, fitting and fixing of Aluminium sliding doors as per the U.S. Architectural Aluminium Manufacturer’s
Association (AAMA) standard specification having 1.5 mm thick outer bottom (size 75.50 mm, 17.79 mm, 0.528 kg/m),
1.5 mm thick outer top (size 75.50 mm, 26.80 mm, 0.78 kg/m) 1.5 mm thick shutter top (size 33 mm, 26.80 mm, 0.536
kg/m), 1.5 mm shutter bottom (size 60 mm, 24 mm, 0.736 kg/m), 1.5 mm thick outer side(size 75.50 mm, 19.90
mm,0.616 kg/m) 1.5 mm thick shutter lock (size 49.20 mm, 26.20 mm, 0.661 kg/m), 1.5 mm thick inter lock (size 34.40
mm, 32.10 mm, 0.665 kg/m), 1.5 mm thick shutter divider (size 31.75 mm, 0.535 kg/m) sections all Aluminium
members (Total weight 14.789 kg) will be anodized to Aluminium Bronze/Silver colour with a coat not less than 15
micrones in thickness and density of 4 mg per square cm etc. including all accessories like handle, sliding door key
lock , sliding door wheel, sliding door mohiar, sliding door neoprene, bolts & nuts in/c sealants, keeping provision for
fitting 5mm thick glass including labour charge for fitting of accessories, making grooves & mending good damages,
carriage, and electricity
complete in all respect as per drawing and accepted by the Engineer.
Size: 2100 mm x 2100mm , Colour : Silver colour.
Supplying fitting, fixing window grills of any design made with 25 x 6 mm F.I. bar in/c fabrication, welding, cost of
electricity workshop charges, carriage, cutting grooves, mending good the damages, tools & plants etc. complete for all
floors as per direction of the engineer-in-charge. (Total weight per sqm should be min 42.88 kg. & add or deduct @
Tk.9.04 for each kg. excess or less respectively)
Page No 57
47
(CE 106 )
13.8.
Mid void 24 X 8 ' - 0 " X 6 ' - 0 " = 1152.00 sft
24 X 8 ' - 7 " X 6 ' - 0 " = 1236.00 sft
24 X 20 ' - 0 " X 6 ' - 0 " = 2880.00 sft
stair side 24 X 7 ' - 9 " X 6 ' - 0 " = 1116.00 sft
24 X 3 ' - 11 " X 6 ' - 0 " = 564.00 sft
= 6948.00 sft
= 645.48 sqm / sqm = Tk 8.985 lac
48
CE 116 b
14.12.3
quantity same as aluminium top hung window = 10459.04 sft
deduct, basement top hung window area = 936.00 sft
net area = 9523.04 sft
= 884.71 sqm / sqm = Tk 47.297 lac
49
CE 117 b
14.14.1
Quantity BF from aluminium swing door = 168.00 sft
Quantity BF from aluminium sliding door = 336.00 sft
Quantity BF from aluminium sliding window = 10458.75 sft
Quantity BF from aluminium fixed composite window = 1608.00 sft
Quantity BF from aluminium fixed fanlight = 10459.04 sft
= 23029.79 sft
= 2139.52 sqm / sqm = Tk 12.687 lac
50
CE 117 d
= 100.00 sqm / sqm = Tk 3.113 lac
51
CE 171
22.9.
GF 8 X 16 ' - 6 " =
1st Floor 9 X 16 ' - 6 " =
2nd Floor 9 X 16 ' - 6 " =
3rd Floor 9 X 16 ' - 6 " =
4th Floor 9 X 16 ' - 6 " =
5th Floor 9 X 16 ' - 6 " =
=
= / rm = Tk 1.093 lac
1392.00
@ Tk 593.00
@ Tk 5346.00
Supplying fitting and fixing of Aluminium fixed louver as per the U.S. Architectural Aluminium Manufacturer’s
Association (AAMA) standard specification having 1.5mm thick wall frame (size 76.20 mm, 38.10 mm, 0.707 kg/m), 5
mm thick louver section (size 55.02 mm, 37.39 mm, 0.22kg/m) & 2.50 mm thick louver outer section (size 39.67 mm,
15.06 mm, 0.265 kg/m) and inner inclined Aluminium louver section fixed with above mentioned frame and all
Aluminium members (Total weight 7.992 kg) will be anodized to Aluminium Bronze/silver color with a coat not less than
15 micron in thickness and density of 4 mg per square cm etc. including all accessories, neoprene, sealant, nuts &
bolts etc. complete in all respect as per drawing and accepted by the Engineer.
Colour : Silver colour.
Supplying, fitting and fixing in Aluminium door frames Partitions/ windows distortion free foreign made 5 mm thick
glass of approved quality and shade including cost of fitting fixing all necessary accessories etc. complete in all
respect as per drawing and direction of the engineer-in-charge.
Clear glass.
Supplying, fitting and fixing or pesting screen colour paper on glass pan approved and accepted by the Engineer.
148.50 rft
148.50 rft
@ Tk 3113.00
rm
132.00
874.50 rft
@ Tk
148.50 rft
266.62
rft148.50
148.50 rft
410.00
@ Tk
rft
Supplying, fitting, fixing of uPVC plastic door/window frame having specific gravity 1.35 - 1.45, and other physical,
chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacurer standards or ASTM, BS/ISO/IS
standards fitted & fixed in brick wall/ R.C.C wall with 6 nos GI clamp, 4nos inner joint GI clamp, 2 nos outer GI joint
clamp, 16 nos revit making necessary grooves & and mending good the damages, finishing, curing, carraige etc
complete in all respect accepted by the Engineer.
Supplying, fitting and fixing of verandah grills made of 3/8" dia M.S rod placed @ 3 " c/c both ways fitted with outer frame
of M.S. Angle 1" X 1" X 1/4 " as per drawing and approved and accepted by the Engineer.
Page No 58
52
CE 172 b
22.10.2
GF 8 nos
1st Floor 9 nos
2nd Floor 9 nos
3rd Floor 9 nos
4th Floor 9 nos
5 th Floor 9
total 53 nos each = Tk 1.827 lac
53
CE 77 a
11.2.
GF to 5th floor 46 X 2 X 3 = 276 nos each = Tk 0.135 lac
54
CE 100
12.25
Total no of hasp bolt = each = Tk 0.140 lac
55
CE 99 a12.22.
= each = Tk 0.354 lac
56
CE 99 a
12.22.
= each = Tk 0.354 lac
57
CE 99 c
12.24.
= each = Tk 0.134 lac
58
CE 99 b
12.23.1 = each = Tk 0.528 lac
59
CE 98 a
12.21.1 46 X 3 ' - 6 " X 7 ' - 0 " = 1127.00 sft
= 104.70 sqm / sqm = Tk 0.161 lac
Sub Total = Tk 2077.700 lac
Supplying, fitting and fixing of best quality magnetic door shock absorber in/c all necessary tools and
accessories etc. all complete approved and accepted by the Engineer.
Supplying, fitting , fixing of "King Brand" ( made in Korea / equivalent ) hydraulic door closer ( big
size ) including all necessary tools and accessories etc all complete approved and accepted by the Engineer.
305.00
20 nos
nos
1055.00
Supplying, fitting & fixing best quality heavy type 19 mm dia and to 300 mm long brass hasp bolt including
cutting grooves in door shutter and frames, screws etc all complete approved and accepted by the Engineer.
267.00
20 nos @ Tk
@ Tk
50 nos
154.00
Extra cost for using brass fittings in place of iron fittings in doors for all floors approved and accepted by the
Engineer.
@ Tk
46
Supplying, fitting , fixing of "King Brand" ( made in Korea / equivalent ) hydraulic door closer ( big size )
including all necessary tools and accessories etc all complete approved and accepted by the Engineer.
1768.00
@ Tk 1768.00
@ Tk
50 nos @ Tk
Supplying, fitting and fixing MORTICE door lock approved and accepted by the Engineer.
Supplying , fitting and fixing M.S. Flat bar clamp of 225 X 38 X 6 mm size having bifurcated ends to door and
window frames with necessary screws and uncasing inside the wall with cement concrete ( 1:2:4 ) etc. Complete and
accepted by the Engineer.
= @ Tk
@ Tk 49.00
3447.00
Supplying, fitting, fixing of uPVC/hollow or solid plastic door shutter having specific gravity 1.35 - 1.45, thckness
1.7 mm-2.2 mm, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved
manufacurer standards or ASTM, BS/ISO/IS standards of different sizes fitted fixed with uPVC plastic door frame
weigning 5.82 kg/m2 with at least 3 nos hinges by min 64 nos Ø 3.17 mm & 3.97 mm 12.7 mm long revits, 12 nos 25.4
mm screws, Ø 9.38 mm, 150 mm long tower bolts 2 nos, 146 mm plastic handle by revit 2 nos, plastic inner joint
234.95 mm x 127 mm clamp, 76.2 mm x 57.15 mm, 25 mm dia 1 no hasbolt, special type roundlock, carraying the
same to the site & local carraige etc. complete in all respect accepted by the Engineer.
760 mm X 2130 mm uPVC plastic shutter ( solid )
Page No 59
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 2278.6015 2669.836
10,173.00 10399.00 0.552 0.563762 -31.8% 2.2%
1,084.00 0.993 0 -83.4% -100.0%
190,899.00 214544.00 4.533 5.09499 43.4% 12.4%
3,755.00 4156.00 3.655 4.045489 15.5% 10.7%
Rate Total
Page No 60
Page No 61
2,879.00 3120.00 27.974 30.31522 -20.3% 8.4%
Page No 62
2,193.00 2436.00 3.276 3.639064 -17.9% 11.1%
Page No 63
2,665.00 2975.00 25.895 28.90714 -7.6% 11.6%
6,945.00 7994.00 2.097 2.413647 20.4% 15.1%
Page No 64
4,817.00 5193.00 0.752 0.810502 -5.8% 7.8%
1,823.00 2030.00 0.569 0.633668 -16.6% 11.4%
2,266.00 2570.00 47.421 53.78232 24.4% 13.4%
Page No 65
1,842.00 2070.00 11.890 13.36154 32.3% 12.4%
4,803.00 5674.00 42.493 50.19857 -10.2% 18.1%
787.00 856.00 16.838 18.31429 32.7% 8.8%
176.00 217.00 0.469 0.578556 -57.1% 23.3%
Page No 66
2,737.00 2960.00 1.451 1.5688 -20.6% 8.1%
60.00 73.00 0.166 0.20148 22.4% 21.7%
317.00 322.00 0.146 0.14812 3.9% 1.6%
1,931.00 2014.00 0.386 0.4028 9.2% 4.3%
1,931.00 2014.00 0.386 0.4028 9.2% 4.3%
190.00 215.00 0.095 0.1075 -28.8% 13.2%
1,218.00 1293.00 0.609 0.6465 15.5% 6.2%
360.00 382.00 0.377 0.399957 133.8% 6.1%
2471.6227 2886.373 18.96 16.8%
Page No 58
B F 2077.700 lac
60
CE 131 b16.4.
1st floor to 4th floor 2 X 190 ' - 0 " X 60 ' - 0 " = 22800.00 sft
2 X 60 ' - 0 " X 60 ' - 0 " = 7200.00 sft
semi circular 2 X 78 ' - 6 " X 60 ' - 0 " = 9420.00 sft
5th floor 2 X 190 ' - 0 " X 12 ' - 0 " = 4560.00 sft
22 X 20 ' - 0 " X 12 ' - 0 " = 5280.00 sft
2 X 30 ' - 0 " X 12 ' - 0 " = 720.00 sft
6th floor 2 X 110 ' - 0 " X 12 ' - 0 " = 2640.00 sft
2 X 30 ' - 0 " X 12 ' - 0 " = 720.00 sft
= 53340.00 sft
= 4955.41 sqm / sqm = Tk 5.055 lac
61CE 133 b
16.8.2
Walls
(i) GF
for 10 " wall inside 1 X X 12 ' - 0 " = 8812.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 13206.00 sft
= 22018.00 sft
Deduction
aluminium sliding window = 1127.25 sft
aluminium composite fixed window = 605.00 sft
aluminium fixed fan light = 1336.83 sft
partex flush door = 227.78 sft
plastic door 8 X 2 ' - 6 " X 7 ' - 0 " = 140.00 sft
= 3436.86 sft
Net area = 18581.14 sft
(ii) 1st Floor
for 10 " wall inside 1 X X 12 ' - 0 " = 7634.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 11796.00 sft
= 19430.00 sft
Deduction
aluminium sliding window = 1608.00 sft
aluminium composite fixed window = 331.00 sft
aluminium fixed fan light = 1535.63 sft
partex flush door = 136.67 sft
plastic door 9 X 2 ' - 6 " X 7 ' - 0 " = 157.50 sft
= 3768.79 sft
Net area = 15661.21 sft
(iii) 2nd Floor
Plastic emulsion paint of approved best quality and colour delivered from authorized local agent of the
manufacturer in a sealed container, applying to wall and ceiling in two coats over lime putty of specified brand
applied on primer or sealer elapsing specified time for drying/recoating including cleaning drying, making free from
dirt, grease, wax, removing all chalked & scaled materials, fungus, mending good the surface defects, sand paparing
the surface and necessary scaffolding, spreading by brush/ roller/spray etc. all complete in all floor accepted by the
Engineer.
lime putty to be applied as per manufacturer instructions approved and accepted by the Engineer.
rft
636.17 rft
734.33 rft
491.50
550.25
on exterior surface applying as per manufacturer instruction 3 coat of Weather coat of approved quality and
colour delivered from authorized local agent of the manufacturer in a sealed container complete in all respect in all
floors and accepted by the Engineer.
@ Tk 102.00
rft
Page No 59
for 10 " wall inside 1 X X 12 ' - 0 " = 10532.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 9708.00 sft
= 20240.00 sft
Deduction
aluminium sliding window = 1711.50 sft
aluminium composite fixed window = 60.00 sft
aluminium fixed fan light = 1463.58 sft
partex flush door = 136.67 sft
plastic door 9 X 2 ' - 6 " X 7 ' - 0 " = 157.50 sft
= 3529.25 sft
Net area = 16710.75 sft
(iv) 3rd Floor
Quantity same as 2nd floor = 16710.75 sft
(v) 4th Floor
Quantity same as 3rd floor = 16710.75 sft
(vi) 5th Floor
for 10 " wall inside 1 X X 12 ' - 0 " = 9740.00 sft
for 5 " wall both side 2 X X 12 ' - 0 " = 11148.00 sft
parapet wall 4X10 X X 10 ' - 10 " = 8666.67 sft
= 29554.67 sft
Deduction
aluminium sliding window = 2589.00 sft
aluminium composite fixed window = 60.00 sft
aluminium fixed fan light = 2259.83 sft
partex flush door = 136.67 sft
plastic door 9 X 2 ' - 6 " X 7 ' - 0 " = 157.50 sft
= 5203.00 sft
Net area = 24351.67 sft
(vii) 6th Floor
for 10 " wall both side 2 X 350 ' - 0 " X 12 ' - 0 " = 8400.00 sft
Deduct, windows = 432.00 sft
Deduct, Doors = 136.67 sft
= 7831.33 sft
Total wall area to be painted = 116557.60 sft
Ceiling, column, lift wall etc
GF Ref , mark B of Item 16 = 110645.58 sft
deduct , basement plaster area = 58938.29
1st Floor Ref , mark C of Item 16 = 52813.93 sft
2nd Floor Ref , mark D of Item 16 = 53053.93 sft
3rd Floor same as 2nd floor = 53053.93 sft
4th Floor same as 3rd floor = 53053.93 sft
5th Floor Ref , mark E of Item 16 = 46683.27 sft
6th Floor Ref , mark F of Item 16 = 7210.00 sft
= 317576.28 sft
404.50 rft
877.67 rft
rft
20.00 rft
rft
464.50
811.67
Page No 60
Total wall + ceiling and others = 434133.88 sft
deduct wall tiles area = 14402.67 sft
Net area = 419731.21 sft
= 38993.98 sqm / sqm = Tk 56.151 lac
62
CE 132
16.7
Basement floor = 58938.29 sft
= 5475.50 sqm / sqm = Tk 4.545 lac
63
CE 129
16.1.
GF 1 X 40 ' - 0 " X 40 ' - 0 " = 1600.00 sft
1st Floor 1 X 40 ' - 0 " X 40 ' - 0 " = 1600.00 sft
= 3200.00 sft
= 297.29 sqm / sqm = Tk 0.025 lac
64
CE 137
16.14 single swing 46 X 3 ' - 4 " X 7 ' - 0 " = 1073.33 sft
= 1073.33 sft X
= 2683.33 sft
= 249.29 sqm / sqm = Tk 0.239 lac
65
CE 131d
16.6.
area same as window grill area = 22525.79 sft
2092.70 sqm / sqm = Tk 2.114 lac
@ Tk 144.00
@ Tk
Approved best quality and colour synthetic polyvinyl distemper delivered from authorized local agent of the
manufacturer in a sealed container, applying to wall & ceiling in 2 coats over a coat of brand specified primer or
sealer elapsing specified time for drying/ recoating matt finish including cleaning and sand papering making the
surface free from loose and flaky materials, dirt, grease, wax, polish, scraping all chalked & scaled materials,
applying the paint by brush/rooller and necessary scaffolding etc. all complete in all floor accepted by the Engineer.
@ Tk 101.00
Painting to door and window frames and shutters in two coats with approved best quality and colour of
synthetic enamel paint delivered from authorized local agent of the manufacturer in a sealed container, having
highly water resistant, high bondibilty, flexible, using specfic brand thinner applied by brass/roller/spray over a coat of
priming elapsing time for drying including surface cleaning from dust, oil or dirt, smoothening, finishing and polishing
with sand paper and necessary tools, scaffolding, testing charges etc. all complete in all floors approved and
accepted by the Engineer.
French polishing to door and window frames and shutters three coats over a coat of priming including putty,
cleaning finishing and polishing with sand paper etc. all complete in all floor accepted by the Engineer.
@ Tk 96.00
White washing by three coats, lime mixture prepared at least 12 hours before use, slacking stone lime, supply of
gums, blue, stirring thoroughly, removing the floating materials from the mixer, surface cleaning to free from all
foreign materials before application of each coat, applying one vertical & one horizontal wash for each coat &
successive coat is to be applied after drying up of previous coat in/c hair brass, providing necessary scaffolding and
cleaning plinth, floors, doors, windows, portions & ventilators by washing, rubbing, oiling if necessary after white
wash for all floors in/c cost of water, electricity & other charges etc. complete in all respect accepted by the Engineer.
2.5
8.50
83.00
@ Tk
Page No 61
66
CE 61
08.4.
GF 40 nos
1st Floor 42 nos
2nd Floor 64 nos
3rd Floor 64 nos
4th Floor 64 nos
5th Floor 64 nos
338 nos each = Tk 0.206 lac
67
CE 157 d
20.7.4
GF 2 X 2 X 12 X 3 ' - 0 " = 144.00 rft
2 X 2 X 12 X 4 ' - 8 " = 224.00 rft
2 X 2 X 12 X 3 ' - 6 " = 168.00 rft
2 X 2 X 12 X 5 ' - 0 " = 240.00 rft
1st Floor 2 X 2 X 12 X 3 ' - 0 " = 144.00 rft
2 X 2 X 12 X 4 ' - 8 " = 224.00 rft
2 X 2 X 12 X 5 ' - 0 " = 240.00 rft
2nd Floor 2 X 2 X 12 X 3 ' - 0 " = 144.00 rft
2 X 2 X 12 X 4 ' - 8 " = 224.00 rft
2 X 2 X 12 X 5 ' - 0 " = 240.00 rft
3rd Floor 2 X 2 X 12 X 3 ' - 0 " = 144.00 rft
2 X 2 X 12 X 4 ' - 8 " = 224.00 rft
2 X 2 X 12 X 5 ' - 0 " = 240.00 rft
4th Floor 2 X 2 X 12 X 3 ' - 0 " = 144.00 rft
2 X 2 X 12 X 4 ' - 8 " = 224.00 rft
2 X 2 X 12 X 5 ' - 0 " = 240.00 rft
5th Floor 2 X 2 X 12 X 3 ' - 0 " = 144.00 rft
2 X 2 X 12 X 5 ' - 0 " = 240.00 rft
= 3592.00 rft
= 1095.12 rm /rm = 8.947 lac
68
CE 230 b1
26.31
60 X 72 ' - 0 " =
= /rm = Tk 4.096 lac
Sub Total = Tk 2159.078 lac
4320 rft
Supplying fan hook of 16 mm diameter M.S. Rod ( one meter straight length ) having rounded hook at the middle
of bar in proper size so as to be concealed within fan cup including fabrication and fitting fixing in all floors accepted
by the Engineer.
Supplying 100 mm inside diameter best quality uPVC rain water down pipe fitting, fixed in positon with head and
shoes, bends, min.20 mm width F.I bar clamp and nails, and including all accessories such as round grating /
doomed roof grating bands, sockets approved and accepted by the Engineer.
@ Tk
817.00@ Tk
61.00
rm1317.07
Providing nosing to the Nose of tread of stair including supplying 3 nos of 75 mm long 12 mm X 3 mm F.I bar
clamp with bifurcated ends in each treads including fitting and fixing with the angle by welding including fitting and
fixing the angle by cutting grooves in RCC , fixing and finishing and the same with CC ( 1:2:4 ) etc., cost of electricity
all complete and accepted by the Engineer.
Providing 1.5 " X 1.5 " X 1/4 " brass angle to the nosing of stair case.
@ Tk 311.00
Page No 62
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 2471.623 2886.373
138.00 166.00 6.838 8.225975 35.3% 20.3%
Rate Total
Page No 63
Page No 64
161.00 186.00 62.780 72.52881 11.8% 15.5%
105.00 122.00 5.749 6.680111 26.5% 16.2%
12.00 15.00 0.036 0.044593 41.2% 25.0%
178.00 230.00 0.444 0.573362 85.4% 29.2%
123.00 150.00 2.574 3.139046 21.8% 22.0%
Page No 65
81.00 95.00 0.274 0.3211 32.8% 17.3%
888.00 966.00 9.725 10.57888 8.7% 8.8%
552.00 524.00 7.270 6.901463 77.5% -5.1%
2567.313 2995.366 18.91% 16.7%
Page no 62
B.F 2159.078 lac
69
CE 140
17.2.
2 X 200 ' - 0 " =
1 X 150 ' - 0 " =
=
= / rm = TK 2.146 lac
70
CE 139
17.1
Ramp front 1 X 30 ' - 0 " =
1 X 120 ' - 0 " =
2 X 40 ' - 0 " =
=
= / rm = TK 0.438 lac
71
CE 141
17.3.
left and right side 2 X 192 ' - 0 " =
front and back side 2 X 122 ' - 0 " =
= X 5'-0"
=
= / sqm = TK 1.266 lac
80.00
rft
3140.00 sft
384.00
244.00
Constructing surface drain of 600 mm (Av) depth and 225 mm clear width at the bottom and 525 mm at the top having 125
mm thick cement concrete (1:2:4) curb up to 300 mm from the bottom over one layer of polythene on top brick flat soling and the
side slopes of the remaing 300 mm height provided with 125mm thick lst class brick work in cement mortar (1:6) in/c minimum
12mm thick cement sand ( F.M 1.2 ) plaster (1:3) in/c neat cement finishing the surfaces and back of the drain up to 150 mm
below ground level with fresh cement , curing at least for 7 days in/c excavation of all kinds of soil, back filling with fine sand
(F.M. 0.8) consolidating and dressing, in/c cost of water, electricity, other charges etc complete and accepted by the Engineer.
( Cement : CEM - II / A - M )
Constructing surface drain of 300 mm clear width and depth up to 300 mm in brick masonry with 125 mm thick check wall in
cement mortar (1:6) over av. 75 mm thick cement concrete base (1:3:6) over one layer of brick flat soling. The surface having
minimum 12mm thick cement sand ( F.M 1.2 ) plaster (1:3) and neat cement finishing with cement , curing at least for 7 days
in/c excavation in all kinds of soil, back filling with fine sand (F.M. 0.8), consolidating and dressing, cost of water, electricity,
other charges etc complete and accepted by the Engineer.
( Cement : CEM - II / A - M )
Providing apron with 50 mm thick cement concrete (1:2:4) with cement (conforming to BDS 232), coarse sand and picked
jhama chips in/c breaking chips and one layer brick flat soling at bottom with lst class or picked jhama bricks in/c cutting earth
for preparation of bed and filling the interstices with local sand (F.M. 0.8) in/c finishing, dressing, curing at least for 7 days etc. all
complete, in/c cost of water, electricity, other charges accepted by the Engineer.
( Cement : CEM - II / A - M )
624.00@ Tk70.12 rm
291.71
1280.00@ Tk
@ Tksqm
400.00
550.00 rft
rft
434.00
167.68 rm
628.00 rft
rft
rft230.00
rft
150.00 rft
30.00 rft
rft
120.00
Page no 63
72
CE 155 c
20.4.
( i ) GF
main entry 5 X 4 ' - 0 " = 20.00 rft
stair railing , basement stair 4 X 9 ' - 9 " = 39.00 rft
GF Stair : corner stair 4 X 11 ' - 8 " = 46.67 rft
3.14 X 3 ' - 8 " = 11.51 rft
short side stairs 8 X 11 ' - 8 " = 93.33 rft
long side stairs 8 X 11 ' - 8 " = 93.33 rft
2 X 3.14 X 5 ' - 6 " = 34.54 rft
middle stairs 4 X 11 ' - 8 " = 46.67 rft
2 X 28 ' - 2 " = 56.33 rft
= 441.39 rft
( ii ) 1st Floor
short side stairs 8 X 11 ' - 8 " = 93.33 rft
long side stairs 8 X 11 ' - 8 " = 93.33 rft
2 X 3.14 X 5 ' - 6 " = 34.54 rft
middle stairs 4 X 11 ' - 8 " = 46.67 rft
2 X 28 ' - 2 " = 56.33 rft
= 324.21 rft
( iii ) 2nd Floor
( quantity same as 1st floor )= 324.21
( iv ) 3rd Floor
( quantity same as 2nd floor )= 324.21
( v ) 4th Floor
( quantity same as 3rd floor )= 324.21
( vi ) 5th Floor
short side stairs 8 X 11 ' - 8 " = 93.33 rft
long side stairs 8 X 11 ' - 8 " = 93.33 rft
2 X 3.14 X 5 ' - 6 " = 34.54 rft
middle stairs 4 X 11 ' - 8 " = 46.67 rft
2 X 28 ' - 2 " = 56.33 rft
= 324.21 rft
Total = 2062.42 rft
= 2062.42 X sft
= 6187.26 sft =
= 574.81 sqm = /sqm = TK 35.460 lac
Supplying, fitting and fixing 12 mm dia G.I pipe stair railing of any standard height of any design & shape with 50 x 50 x 6 mm
M.S. plate at the base f 12 mm dia G.I. Pipe and fitted andfixed by welding. Placing the pipes vertically @ 125 mm c/c (2 Nos. in
each steps) 150 mm ecbeded into the R.C.C tread of stair case after cutting grooves and mending good the damages with C.C.
& providing 38 x 6 mm F.I. bar on the top of G.I. pipe to provide wooden/G.I. pipe hand rail of any design in/c polishing painting
etc. all complete and accepted by the Engineer. ( Exposed area of railing will be considered for measurement. rate is excluding
cost of paint)
Supplying , fitting and fixing stainless steel ( S S ) stair railing of standard height with 2 mm thick 2.5 " dia pipe for hand - rail as
per drawing and accepted by the Engineer.
3 ' - 0"
@ Tk 6169.00
Page no 64
73
CE 156c
20.6
( i ) GF
Railing , Stair void side 4 X 18 ' - 0 " = 72.00 rft
4 X 8 ' - 7 " = 34.33 rft
4 X 8 ' - 0 " = 32.00 rft
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
Flower bed 2 X 15 ' - 0 " = 30.00 rft
= 214.50 rft
( ii ) 1st Floor
Railing :Stair void side 4 X 18 ' - 0 " = 72.00 rft
4 X 8 ' - 7 " = 34.33 rft
4 X 8 ' - 0 " = 32.00 rft
lobby 1 X 30 ' - 0 " = 30.00 rft
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
= 214.50 rft
( iii ) 2nd Floor
( quantity same as 1st floor excluding lobby)= 184.50 rft
( iv ) 3rd Floor
( quantity same as 2nd floor )= 184.50 rft
( v ) 4th Floor
( quantity same as 3rd floor )= 184.50 rft
( vi ) 5th Floor
stair side 2 X 11 ' - 8 " = 23.33 rft
2 X 11 ' - 5 " = 22.83 rft
= 46.17 rft
Total = 1028.67
rft
= 1028.67 X sft
= 2571.67 sft
= 238.914 sqm /sqm = TK 15.847 lac
74
CE 186 a
24.4
2 X 340 ' - 0 " X 20 ' - 0 " = 13600.00 sft
2 X 120 ' - 0 " X 20 ' - 0 " = 4800.00 sft
= 18400.00 sft
= 1709.40 sqm /sqm = TK 2.889 lac
75
CE 186 b
24.5.
2 X 340 ' - 0 " X 20 ' - 0 " = 13600.00 sft
2 X 120 ' - 0 " X 20 ' - 0 " = 4800.00 sft
= 18400.00 sft
= 1709.40 sqm /sqm = TK 4.718 lac
@ Tk
Supplying , fitting and fixing verandah railing with 2 mm thick 50 mm , 25 mm and 20 mm diameter stainless steel pipes as per
approved design and accepted by the Engineer.
@ Tk 276.00
Brick on edges pavement in herring bone bond with lst class or picked jhama bricks as per alignment, camber and grade
over 12 mm thick sand cushion (F.M. 0.50) including filling the joints with the same sand including cost of all materials and
accepted by the Engineer.
169.00
Single layer brick flat soling in road work with lst class or picked jhama bricks as per alignment, camber and grade including
filling joints with sand (F.M. 0.50) etc. complete as per direction of the engineer-in-charge including cost of all materials and
accepted by the Engineer.
2 ' - 6"
@ Tk 6633.00
Page no 65
76
CE 187
24.7.
2 X 920 ' - 0 " = 1840.00 rft
= 560.98 rm / rm = TK 0.224 lac
77
CE 152
19.6.
Front entrance 2 X 18 ' - 0 " X 10 ' - 0 " = 360.00 sft
= 33.44 sqm /sqm = TK 1.059 lac
78
CE 147 a
19.1.1
Side entrance 2 X 7 ' - 9 " X 7 ' - 0 " = 108.50 sft
1 X 7 ' - 6 " X 7 ' - 0 " = 52.50 sft
1 X 7 ' - 3 " X 7 ' - 0 " = 50.75 sft
= 211.75 sft
= 19.67 sqm /sqm = TK 0.414 lac
79
analysis
Basement floor
56 X 4 X 3 ' - 0 " = 672.00 rft
= 204.88 rm / rm = TK 0.512 lac
@ Tk
Brick on end edging (75 mm across the road) with lst class or picked jhama bricks and filling the gaps with fine sand (F.M.
0.50) in/c cutting trenches. true to level & grade, removing earth, refilling and ramming the sides properly including cost of all
materials and accepted by the Engineer.
40.00@ Tk
3165.00
Supplying. fitting and fixing of rolling shutter of any design & shape made of 24 SWG G.P, sheet unit minimum 69 mm width
having 10 mm & 12 mm dia Circular folding at ends ,rolled in machine, locked together properly to form rolling shutter, top of
the shutter to be fitted w with circular spring box made of 22 BWG sheet, containing best quality spring made in China, nutted
with 38 mm G.I. pipe at one end and the other end nutted to shutter in/c fitting the G.I. pipe again with 375 x 300 x 6 mm pankha
at ends with side guide channel (side channel consist of 50 x 100 x 6 mm M.S. plate with 2 x 19 x 3 mm F.I. bar, middle
channel consist of 2 x 150 mm x 6 mm M.S. plate with 2 x19 mm x 6 mm Fixed to wall or coloumn with clamps embeded in
R.C.C. part by cement concrete (1:2:4) in/c cutting holes (minimumm 3 x 25 mm x6 mm) mending the damages, finishing,
curing, bottom end of shutter fitted to folded G.P. sheet (min 125 mm width in two layers), which is again fitted to 25 x 25 x 3 mm
angle, providing handle (with F.I. bar 25 x 6 mm riveted) and locking arrangement in both sides, painting two coats with
approved colour and brand of synthetic enamel paint over a coat of priming etc. complete in all respect as per
drawing design accepted by the Engineer.
( Rate is excluding cost of paint)
Manufacturing, supplying, fitting and fixing collapsible gate of any design & shape made of 3/4" x 3/8" x 1/8" channel
placed @ 112 mm c/c vertically and connecting the same with each other by 20 x 3 mm M.S flat bar scissors 525 mm/ 600 mm
long provided in 3 rows in/c cutting the different M.S. members to required sizes, fabricating, welding, riveting with required size
rivets, providing requried size wheels, pulling handles on both sides, suitable locking arrangement, electrodes, greees and
finally placing the same in position in between 2 (two) Nos. 50 x 50 x 6 mm M.S. Tee rail made by welding 2 Nos. 50 x 6 mm
M.S. flat bar fitted and fixed at top and bottom with R.C.C. lintel/roof slab. floors and side wall with required Nos. 150 mm to 225
mm long 38 x 6 mm M.S. flat bar clamps one end welded with the gate member and the other end bifurcated and embedded in
C.C. at the respective point in/c cutting holes and mending good the damages by pouring concrete (1:2:4) into the holes &
finishing, etc complete, painting 2 (two) coats with approved best quality synthetic enamel paint over a coat of anticorrosive
painting, both end carraige, in/c greesing, electodes, curing etc. complete as per drawing & design
and accepted by the Engineer. (Rate is excluding cost of paint)
Supplying fitting and fixing of 62 mm X 62mm X 10 mm M.S angle each of 3'-0" height in each of four corner of column ,
placing in position with clamping with royal plug or any other means as per design , mending good the damages, etc. all complete in
all
@ Tk 250.00
@ Tk 2104.00
Page no 66
80
CE 56 a
26.31
GF to 1st Floor exposed column ( double ht column )
8 X 2 ' - 0 " X 2 ' - 0 " = 32.00 sft X 10 '
= 320.00 cft
= 9.06 cum / cum = TK 0.008 lac
81
CE 56 c
26.31
GF to 1st Floor exposed col 8 X ( 2' + 2' ) X 2 X 10 ' = 640.00 sft
= 59.46 sqm / sqm = TK 0.010 lac
82
CE 56 d
26.31
waffle roof beams
= 58.87 cft
= 1.67 cum / sqm = TK 0.002 lac
83
CE 56 f
26.31
= 157.00 sft
= 14.59 sqm / sqm = TK 0.006 lac
84
CE 56 g
26.31
= 39.10 cum / cum = TK 0.037 lac
85
CE 56 h
26.31
= 434.83 sqm / sqm = TK 0.100 lac
86
CE 67
26.31
In Column / Beam 100 X 25 X 0 ' - 6 " = 1250.00 inch /inch = TK 0.045 lac
quantity same as mark A of item 10 (D)
39.00
@ Tk
Extra rate over the rate of concrete ( materials, consumables and laying / placing concrete ) of RCC works in Tee beams, Ell beams
and rectangular beams where the free height of the structure exceeds 4 meter ( Rate is considered for each additional meter height
)
1/2 X 3.14 X 25'-0" X 1'-0" X 1'-6"
Extra rate over the rate of formwork / shuttering ( steel ) of RCC works in Columns , Capitals, lift walls and walls where the free
height of the structure exceeds 4 meter ( Rate is considered for the height of each additional 4 ( four ) meter or part)
@ Tk 92.00
@ Tk 16.00
Extra rate over the rate of concrete ( materials, consumables and laying / placing concrete ) of RCC works in floor/roof slab,
cantilever slab, waffle slab and drop panels where the free height of the structure exceeds 4 meter ( rate is considered for each
additional meter height )
3.57
Providing and making welded splice by welding of minimum 300 mm length at the lap of main reinforcement in re-bar cage to be
placed in bore-hole / where necessary by electric arc welding with highly oxidized electrodes making the joint prominent and accepted
by the Engineer. ( Rate is inclusive of all materials labour, tools, plants, electricity and all equipment )
@ Tk
Extra rate over the rate of concrete ( materials, consumables and laying / placing concrete ) of RCC works in Columns, Capitals, lift
walls and walls where the free height of the structure exceeds 4 meter ( Rate is considered for the height of each additional 4 ( four )
meter or part)
94.00
Extra rate over the rate of formwork / shuttering ( steel ) of RCC works in Tee beams, Ell beams and rectangular beams where
the free height of the structure exceeds 4 meter ( Rate is considered for each additional meter height )
1/2 X 3.14 X 25'-0" X ( 1'-0" + 3'-0" )
@ Tk
@ Tk 94.00
Extra rate over the rate of formwork / shuttering for RCC works in floor/roof slab, cantilever slab, waffle slab and drop panels
where the free height of the structure exceeds 4 mm ( rate is considered for each additional meter height )
quantity same as mark B of item 10 (D) @ Tk 23.00
Page no 67
87
CE 118
14.15
= 942.00 sft
= 87.51 sqm / sqm = TK 5.725 lac
88
CE 1c
01.1.3
1 office ( L.S ) = TK 3.506 lac
Grand Total lac
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
6542.00
Mirpur, Dhaka
Engineer's site office of minimum 38 sqm plinth area with providing security fencing, 5 kva stand by Generator , IBM compatible PC
with monitor, uninterrupted power supply ( UPS ), Laserjet printer ( minimum 25 ppm ) , furniture, first aid box, safety helmet, level /
theodolite / EDM, consumables, stationaries etc
Sub Divisional Engineer
Mirpur PWD Sub Division 2 Mirpur PWD Sub Division 2
2233.489
6 X 2 X 3.14 X ( 12.5 / 12 ) X 24'-0"
@ Tk
Sub-Assistant Engineer (Estimator )
Mirpur PWD Division, Dhaka
Sub-Assistant Engineer 1
Mirpur, Dhaka
Supplying , fitting and fixing of 4 mm thick Aluminium composite Panel ( European origin ) in column , beam and wall surface providing
with minimum 50 X 50 X 1.5 mm aluminium section including supply of necessary hardwares, consumables, scaffolding etc. approved
and accepted by the Engineer.
Before commencing the work, the Contractor shall submit sample of aluminium composite panel, aluminium sections, hardware and
consumables along with evidence of origin / brand / manufacturer, catalogue and method statement for executing the work to the
Engineer for approval. However, Engineer's approval shall not relieve the Contractor of his responsibilities and obligations under
contract.
Page no 68
2008 2011 2008 2011 Increase Increase
06 to 08 08 to 11
BF 2567.31291 2995.366
1,663.00 2000.00 2.789 3.353659 29.9% 20.3%
818.00 1010.00 0.574 0.708232 31.1% 23.5%
581.00 723.00 1.695 2.109086 33.9% 24.4%
Rate Total
Page no 69
5,664.00 5839.00 32.557 33.56318 -8.2% 3.1%
Page no 70
7,862.00 8717.00 18.783 20.8261 18.5% 10.9%
243.00 327.00 4.154 5.589744 43.8% 34.6%
396.00 535.00 6.769 9.145299 43.5% 35.1%
Page no 71
61.00 83.00 0.342 0.46561 52.5% 36.1%
4,033.00 4818.00 1.349 1.611371 27.4% 19.5%
2,675.00 3066.00 0.526 0.603145 27.1% 14.6%
Page no 72
Page no 73
5,313.00 5455.00 4.650 4.773885 -18.8% 2.7%
364,472.00 427192.00 3.645 4.27192 4.0% 17.2%
2645.145 3082.4 18.43% 16.5% 0.380078
Page no 34
Rate Analysis for Item No 4 (b)
Supplying , fitting & fixing of Tempered glass ( fixed )
considering 1 no of glass ( 3' - 0" X 7' - 0" ) = sft
A. Cost of Materials
(i) Tempered glass in/c 5% wastage : 22.05 sft @ Tk 300.00 / sft = Tk 6615.00
(ii) Protector bit : 21.00 sft @ Tk 6.00 / sft = Tk 126.00
(iii) Alu. Fixed Section ( CE 117 b ) silver color : 24.00 sft @ Tk 167.30 / sft = Tk 4015.20
Tk 10756.20Contractor's Profit 10 % = Tk 1075.62Overhead expenses 3.50% = Tk 376.47
Tk 12208.29Vat 4.50 % = Tk 549.37
Grand Total = Tk 12757.66
Rate per sft = Tk 607.51
Rate per sqm = Tk 6539.21
Say Tk /= per sqm
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
Mirpur, Dhaka
Sub-Assistant Engineer (Estimator )
Mirpur PWD Division, Dhaka
21.00
6539
Sub-Assistant Engineer 1Mirpur PWD Sub Division 2
Mirpur, Dhaka
Sub Divisional EngineerMirpur PWD Sub Division 2
Page no 35
Rate Analysis for Item No 27
Providing weather coat
sft
(i) Cost of weather coat ( 4 liter covers 350 sft area ) : 1.14 @ Tk 162.50 / Liter = Tk 185.71
(ii) Cost of wall primer : 0.80 @ Tk 156.00 / Liter = Tk 124.80
(iii) Painter : 1.50 nos @ Tk 160.00 /person = Tk 240.00
(iv) Ordinary labour : 1.50 nos @ Tk 100.00 /person = Tk 150.00
(iv) Scaffolding, carrying, cleaning, sand papering, making the surface defect free etc: ( L.S ) = Tk 50.00
Tk 750.51
Add 10% contractors profit , 3.50% overhead charge = 13.50 % Tk 101.32
= Tk 851.83
Vat = 4.50 % = Tk 38.33
Grand Total = Tk 890.17
Rate per sft = Tk 8.90
Rate per sqm = Tk 95.82
Say Tk / sqm
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
Sub-Assistant Engineer 1 Sub Divisional EngineerMirpur PWD Sub Division 2
Mirpur, Dhaka Mirpur, Dhaka
Sub-Assistant Engineer (Estimator )
96.00
Mirpur PWD Division, Dhaka
100.00Taking
Liter
Liter
Mirpur PWD Sub Division 2
Page no 36
Page no 37
Rate analysis for Item no 55
Manufacturing, supplying, fitting and fixing of stainless steel pipe stair railing
Taking 29'-0" X 3'-0" = sft
A. Cost of material
(i) 2.5" dia SS pipe ( foreign made )
Horizontal 1 X 13 ' 6 " = 13.50 rft
1 X 0 ' 8 " = 0.67 rft
1 X 13 ' 4 " = 13.33 rft
Vertical X 3 ' 3 " = 1.63 rft
= 29.13 rft
5% wastage = 1.4563 rft
30.58 rft @ Tk 190.00 / rft = Tk 5810.44
(ii) 1" dia SS pipe ( foreign made )
Vertical 10 X 2 ' 11 1/2 " = 29.58 rft
10 X 3 ' 1 1/2 " = 31.25 rft
= 60.83 rft
5% wastage = 3.0417 rft
63.88 rft @ Tk 70.00 / rft = Tk 4471.25
(iii) 3/4" dia SS pipe ( foreign made )
Horizontal 10 X 13 ' 10 " = 138.33 rft
5 X 1 ' 0 " = 5.00 rft
= 143.33 rft
5% wastage = 7.1667 rft
150.50 rft @ Tk 55.00 / rft = Tk 8277.50
(iv) 2.5" dia SS ball top ( 2 nos/4) 0.50 nos @ Tk 625.00 each = Tk 312.50
(v) 2.5" dia SS pipe socket ( 2 nos/4) 0.50 nos @ Tk 160.00 each = Tk 80.00
(vi) 2.5" dia SS Elbow 5.00 nos @ Tk 600.00 each = Tk 3000.00
(vii) 1" dia SS Elbow 10.00 nos @ Tk 200.00 each = Tk 2000.00
(viii) 15 mm thick SS base plate ( 3" X 8" ) 10.00 nos @ Tk 120.00 each = Tk 1200.00
(ix) Anchor 23.00 nos @ Tk 35.00 each = Tk 805.00
B. Cost of labour
: 87.00 @ Tk 120.00 / sft = Tk 10440.00
: 87.00 @ Tk 20.00 / sft = Tk 1740.00
(iii) Carrying charge from market to workshop and workshop to site : 87.00 @ Tk 6.00 / sft = Tk 522.00
: 87.00 @ Tk 6.00 / sft = Tk 522.00
sub total = Tk 39180.69
Add 10% contractors profit , 3.50% overhead charge 13.50 % Tk 5289.39
Tk 44470.08
Vat 4.50 % Tk 2001.15
Total = Tk 46471.23
Rate per sft = Tk 534.15
Rate per sqm = Tk 5749.61
say Tk 5750 / sqm
Assistant Engineer (Staff Officer ) Executive Engineer
(ii) Polishing work including polish materials, labour, hire charge of
polish machine
sft
Sub Divisional Engineer
Mirpur PWD Sub Division 2 Mirpur PWD Sub Division 2
(iv) Labour charge for fitting , fixing including groove cutting and
mending good the damages
sft
Mirpur, Dhaka
Sub-Assistant Engineer (Estimator )
Mirpur, Dhaka
87.00
Sub-Assistant Engineer 1
0.5
(i) Cost of labour for fabrication including welding rod, hire charge of
welding machine, grinding machine etc
sft
sft
Page no 38
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
Rate analysis for Item no 56
Manufacturing, supplying, fitting and fixing of stainless steel pipe stair railing
Taking 16'-3" X 3'-0" = sft
A. Cost of material(i) 2.5" dia SS pipe ( foreign made )
Horizontal 1 X 16 ' 4 " = 16.33 rft
5% wastage = 0.8167 rft
17.15 rft @ Tk 190.00 / rft = Tk 3258.50
(ii) 1" dia SS pipe ( foreign made )Vertical 8 X 2 ' 9 1/2 " = 22.33 rft
5% wastage = 1.1167 rft
23.45 rft @ Tk 70.00 / rft = Tk 1641.50
(iii) 3/4" dia SS pipe ( foreign made )
Horizontal 6 X 16 ' 4 " = 98.00 rft
5% wastage = 4.9 rft
102.90 rft @ Tk 55.00 / rft = Tk 5659.50
(iv) M.S flat bar 1" X 1/4" = 5.00 rft
= 4.25 lb ( 0.85 lb per rft )
5% wastage = 0.21 lb
4.46 lb @ Tk 15.43 / lb = Tk 68.86
(v) Anchor 3 X 6 = 18.00 nos
1 X 8 = 8.00 nos
= 26.00 nos @ Tk 35.00 each = Tk 910.00
(vi) 2.5" dia side Cap 2.00 nos @ Tk 70.00 each = Tk 140.00
(vii) 3/4" dia side Cap 12.00 nos @ Tk 30.00 each = Tk 360.00
(viii) 15 mm thick SS base plate ( 3" X 8" ) 4.00 nos @ Tk 120.00 each = Tk 480.00
B. Cost of labour
: 48.75 @ Tk 120.00 / sft = Tk 5850.00
: 48.75 @ Tk 25.00 / sft = Tk 1218.75
(iii) Carrying charge from market to workshop and workshop to site : 48.75 @ Tk 8.00 / sft = Tk 390.00
: 48.75 @ Tk 7.50 / sft = Tk 365.63
sub total = Tk 20342.73
Add 10% contractors profit , 3.50% overhead charge 13.50 % Tk 2746.27
Tk 23089.00
Vat 4.50 % Tk 1039.01
Total = Tk 24128.01
Rate per sft = Tk 494.93
Rate per sqm = Tk 5327.46
say Tk 5327 / sqm
Mirpur PWD Sub Division 2
Sub-Assistant Engineer 1 Sub Divisional Engineer
Mirpur PWD Sub Division 2
Mirpur, Dhaka Mirpur, Dhaka
(iv) Labour charge for fitting , fixing including groove cutting and
mending good the damages
sft
(i) Cost of labour for fabrication including welding rod, hire charge of
welding machine, grinding machine etc
sft
(ii) Polishing work including polish materials, labour, hire charge of
polish machine
sft
48.75
sft
Mirpur PWD Division, Dhaka
Page no 39
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
Rate analysis for Item no 57
Manufacturing, supplying, fitting and fixing of stainless steel pipe stair Hand rail
Taking 1 X 10'-0" = rft
A. Cost of material
(i) 2.5" dia SS pipe ( foreign made )
Inclined 1 X 10 ' 0 " = 10.00 rft
5% wastage = 0.5 rft
10.50 rft @ Tk 190.00 / rft = Tk 1995.00
(ii) Anchor 1 X 2 = 2.00 nos @ Tk 35.00 each = Tk 70.00
(iii) 2.5" dia side Cap 1 X 2 = 2.00 nos @ Tk 70.00 each = Tk 140.00
(iii) 15 mm thick SS base plate ( 3" X 8" ) 2.00 nos @ Tk 120.00 each = Tk 240.00
B. Cost of labour
: 10.00 @ Tk 120.00 / rft = Tk 1200.00
: 10.00 @ Tk 25.00 / rft = Tk 250.00
(iii) Carrying charge from market to workshop and workshop to site : 10.00 @ Tk 8.00 / rft = Tk 80.00
: 10.00 @ Tk 7.50 / rft = Tk 75.00
sub total = Tk 4050.00
Add 10% contractors profit , 3.50% overhead charge 13.50 % Tk 546.75
Tk 4596.75
Vat 4.50 % Tk 206.85
Total = Tk 4803.60
Rate per rft = Tk 480.36038
Rate per rm = Tk 1575.582
say Tk 1576 / rm
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
Mirpur PWD Sub Division 2
Mirpur, Dhaka
rft
Sub Divisional Engineer
Mirpur PWD Sub Division 2
rft(iv) Labour charge for fitting , fixing including groove cutting and
mending good the damages
Sub-Assistant Engineer 1
Mirpur, Dhaka
Sub-Assistant Engineer (Estimator )
Mirpur PWD Division, Dhaka
(ii) Polishing work including polish materials, labour, hire charge of
polish machine
rft
(i) Cost of labour for fabrication including welding rod, hire charge of
welding machine, grinding machine etc
10.00
rft
Sub-Assistant Engineer (Estimator )
Mirpur PWD Division, Dhaka
Page no 40
Rate Analysis for Item no 5
Supplying, fitting and fixing of Alico bond
sft
A. Cost of Materials
(i) Alico bon in/c 5% wastage : 50.40 @ Tk 275.00 / sft = Tk 13860.00
(ii) 2" X 1.5 " Aluminium box in/c 5% wastage : 48.48 @ Tk 95.00 / rft = Tk 4605.60
(iii) Rubber gaskit 3/4" X 3/4" : 48.48 @ Tk 6.00 / rft = Tk 290.88
(iv) Silicon, screw, Royel plugs etc : ( L.S ) = Tk 350.00
Sub Total "A" Tk 19106.48
B. Labour cost
(i) Fitting, fixing : 48.00 @ Tk 90.00 / sft = Tk 4320.00
(ii) Scaffolding in/c materials : 48.00 @ Tk 3.00 / sft = Tk 144.00
Sub Total "B" Tk 4464.00
C. Carrying cost : ( L.S ) = Tk 150.00
Sub total A + B + C = Tk 23720.48
Add 10% contractors profit , 3.50% overhead charge = 13.50 % = Tk 3202.26
= Tk 26922.74
Add 4.50% VAT = Tk 1211.52
Grand Total Tk 28134.27
Rate per sft = Tk 586.13
Rate per sqm = Tk 6309.11
Say Tk 6309.00 / sqm
sft
rft
Considering 16'-0"X3'-0" = 48.00
Sub-Assistant Engineer 1 Sub Divisional Engineer
Mirpur PWD Sub Division 2 Mirpur PWD Sub Division 2
Mirpur, Dhaka Mirpur, Dhaka
rft
sft
sft
Page no 41
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
Rate analysis for Item no 16 (b )
Supplying, fitting and fixing of fixed glass on door shutter
sft
A. Cost of material
(i) Teak chambal wood for bit
Bit all around the glass 8 X 2 ' 0 " = 16.00 rft
Bit in middle of glass ( cross ) 4 X 2 ' 0 " = 8.00 rft
= 24.00 rft X 1" X 0.5 "
= 0.083 cft
5% wastage = 0.0415 cft
0.12 cft @ Tk 1010.00 / cft = Tk 125.75
(ii) 5 mm glass 1 X 2 ' 0 " X 2 ' 0 " = 4.00 sft
5% wastage = 0.2 sft
4.20 sft @ Tk 100.00 / sft = Tk 420.00
(iii) Cost of nails, screw, putty etc (L.S) = Tk 40.00
B. Labour cost
(i) Carpenter : 0.50 @ Tk 150.00 each = Tk 75.00
(ii) Carpenter helper : 0.50 @ Tk 100.00 each = Tk 50.00
Sub Total Tk 710.75
Add 10% contractors profit , 3.50% overhead charge = 13.50 % = Tk 95.95
= Tk 806.70
Vat = 4.5 % = Tk 36.30
Grand Total Tk 843.00
Rate per sft = Tk 210.75
Rate per sqm = Tk 2268.50
Say Tk 2269 / sqm
Considering 01 X 2' -0" X 2' - 0" = 4
Mirpur PWD Division, Dhaka
Sub-Assistant Engineer (Estimator )
nos
nos
Page no 42
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
Rate analysis for Item no 4(a)
Analysis of Item 4
Supplying , fitting & fixing of Tempered glass swing door shutter
considering 1 no of glass ( 3' - 0" X 7' - 0" ) door = sft
A. Cost of Materials
: 1.00 nos @ Tk 21000.00 each = Tk 21000.00
B. Cost of Labor
fitting , fixing : 1.00 nossft @ Tk 3500.00 each = Tk 3500.00
C. Cost of carrying : ( L.S) = Tk 500.00
Tk 25000.00
Contractor's Profit 10 % = Tk 2500.00
Overhead expenses 3.50% = Tk 875.00
Tk 28375.00
Vat 4.50 % = Tk 1276.88
Grand Total = Tk 29651.88
Rate per sft = Tk
Rate per sqm = Tk
21.00
1412
15199
Mirpur PWD Sub Division 2
Mirpur, Dhaka
Sub Divisional EngineerSub-Assistant Engineer 1
Sub-Assistant Engineer (Estimator )
Mirpur PWD Division, Dhaka
Mirpur PWD Sub Division 2
Sub-Assistant Engineer 1
Mirpur, Dhaka
(i) Tempered glass door in/c all fitting and fixturers such as door
closer, handle, bottom lock, bottom fittings, top fittngs etcin/c 5%
wastage
Sub Divisional Engineer
Page no 43
Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, DhakaMirpur PWD Division, Dhaka
Sub-Assistant Engineer (Estimator )
Mirpur, Dhaka
Mirpur PWD Sub Division 2 Mirpur PWD Sub Division 2
Mirpur, Dhaka
Page no 44
Page no 45
Page no 46
Page no 47
Page no 48
Page no 49
Page no 50
Page no 51
Page no 52
Page no 53
( TK in lac )
SL NO ITEMAMOUNT
1 Civil construction work of Academic Building 2233.489
2Internal Sanitary & water supply works of Academic
Building34.644
3 Construction of Pump House 4.429
4Construction of 50,000 gallon capacity underground
water reservoir18.693
5
Sinking of 38 mm dia Test and Observation Well &
Installation of 150 mm X 300 mm dia shrouded
production well with G.I pipe
15.142
6 Internal Electrification work of Academic Building
Total 2291.255
Sub-Assistant Engineer 1 Sub Divisional Engineer
Mirpur PWD Sub Division 2 Mirpur PWD Sub Division 2
Mirpur, Dhaka Mirpur, Dhaka
Sub-Asstt Engineer (Estimator ) Assistant Engineer (Staff Officer ) Executive Engineer
Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka Mirpur PWD Division, Dhaka
ABSTRACT OF COST
Construction of IBRAHIM MEDICAL COLLEGE at Darussalam, Mirpur, Dhaka.
Sub Head : Construction of Academic Building with Ancillary works.
Construction of Ibrahim medical college
Calculation of depth of earth filling
1st line 97.27 + 96.09 + 96.14 + 94.21 + 93.04 + 93.12 + 94.37 + 93.75 + 92.72 + 93.49 + 93.33 + 93.49 = 1131.02
2nd line 96.94 + 95.15 + 95.49 + 93.59 + 92.76 + 92.01 + 88.30 + 88.06 + 88.56 + 89.48 + 90.34 + 93.51 = 1104.19
3rd line 96.91 + 95.18 + 93.57 + 93.46 + 91.91 + 89.01 + 86.83 + 88.67 + 90.91 + 90.86 + 90.31 + 91.21 = 1098.83
4th line 96.71 + 94.21 + 94.01 + 93.06 + 91.88 + 90.90 + 90.72 + 86.76 + 91.49 + 91.44 + 91.57 + 91.88 = 1104.63
5th line 96.21 + 93.22 + 92.87 + 91.62 + 90.86 + 90.91 + 86.50 + 87.71 + 92.39 + 88.39 + 90.44 + 93.04 = 1094.16
6th line 96.05 + 93.54 + 91.93 + 90.98 + 90.65 + 88.05 + 87.34 + 89.41 + 92.59 + 92.39 + 92.26 + 93.01 = 1098.20
7th line 96.61 + 92.25 + 90.80 + 89.79 + 88.24 + 87.53 + 87.88 + 92.36 + 94.09 + 93.69 + 93.84 + 95.10 = 1102.18
8th line 95.65 + 89.69 + 89.52 + 90.63 + 88.38 + 88.70 + 92.75 + 93.44 + 93.99 + 94.20 + 95.14 + 97.22 = 1109.31
9th line 95.75 + 90.39 + 90.14 + 90.94 + 91.02 + 91.74 + 93.54 + 94.59 + 94.65 + 98.02 + 98.60 + 98.05 = 1127.43
Total = 9969.95
= 92.31 ft
Avg Depth of filling = 100.00 - 92.31 ft
= 7.69 ft
9969.95
9 X 12Avg RL =
Sub Head : Civil Construction of College Building
( Estimated cost :Tk 2233.489 lac only )
Construction of IBRAHIM MEDICAL COLLEGE