10
Full Length Article Failure of hanging roofs in sublevel caving by shock collision and stress superposition Zong-Xian Zhang Department of Arctic Technology, University Center in Svalbard, Longyearbyen N-9171, Norway article info Article history: Received 6 April 2016 Received in revised form 25 May 2016 Accepted 22 June 2016 Available online 17 September 2016 Keywords: Shock wave collision Hanging roof Sublevel caving Rock fracture Hang-up Underground mining abstract Hanging roofs or high hang-ups, a common problem in sublevel caving mining, usually result in a large ore loss and undermine mining safety. This paper analyzed the formation of a hanging roof and showed that increased conning pressure and reduced free surface were its main characteristics. In order to break down a hanging roof, a new method based on shock wave collision and stress superposition was developed. In this method, two blastholes containing multi-primer at different positions are simulta- neously initiated at rst. By doing this, a new free surface and a swell room can be created. After these holes are red, a long delay time is given to the next blasthole so that the fragments from the rst two- hole blasting have enough time to fall down. This new method was applied to three hanging roofs in one production area, and all of them were successfully broken down. Field inspection indicated that almost no damage was caused in the nearby drifts/tunnels due to the new method. In addition, the far eld vibrations were found to be smaller than the maximum vibrations induced by some other blasts. Ó 2016 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by Elsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/ licenses/by-nc-nd/4.0/). 1. Introduction The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used mining method in metallic mines across the world. This method has many advantages regarding safety and mechanisation (Janelid and Kvapil, 1966). Because mining operation is carried out only in drifts, the safety of this method is relatively good, compared with other mining methods such as cut-and-ll, and room and pillar. However, sublevel caving has two main disadvantages: high ore loss and high dilution. Therefore, how to reduce ore loss is an important task for sublevel caving. Investigations including Janelid (1968), Kvapil (1982), Ren (1994), Stazhevskii (1996), Hustrulid (2000), Rustan (2000), Quinteiro et al. (2001a), Power (2004), Selldén and Pierce (2004), Zhang (2005, 2014a,b, 2016), Brunton et al. (2010), Wimmer (2010), Tawadrous (2015), and Nordqvist and Wimmer (2016) have indicated that rock blasting has a great impact on fragmen- tation and recovery. Furthermore, there is a great potential to in- crease ore recovery by improving blasting (Zhang, 2016). At the same time, unfortunately, there exist various problems in present underground blasting. One of such problems is the hanging roof in sublevel caving. In a normal condition, after a sublevel ring is blasted, the ore mass in the ring is completely destroyed into various sizes of fragments, and a new front face is formed. When ore extraction in the ring is completed, the new front face is partly occupied by the waste rocks (or mixed with ores). As a result, a large number of waste rocks move down to the drift oor and waste-rock boulders often partly block the draw point, as shown in Fig. 1a. However, sometimes, after a ring is blasted, the upper part of ore mass in the ring is either poorly fragmented or seriously conned. Under this circumstance, when extraction in the ring is nished or it cannot continue, the upper part of ore mass is hanged there and an empty room is formed below the upper part, as shown in Fig. 1b. This hanged part of ore mass is called hanging roof, also called remained roofor high hang-up(Hustrulid and Kvapil, 2008), which is similar to but not same as an ordinary hang-up in caving mining. An ordinary hang-up frequently happens in block caving and sublevel caving, and it may break up by itself during extraction. Different from an ordinary hang-up, a hanging roof does not break up by itself. A hanging roof is common and it results in a large ore loss in sublevel caving. As reported by Zhang and Naarttijavi (2006), the ore loss due to hanging roofs was up to 380,000 t in Malm- berget mine during two-year production. In addition, a hanging E-mail address: [email protected]. Peer review under responsibility of Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Contents lists available at ScienceDirect Journal of Rock Mechanics and Geotechnical Engineering journal homepage: www.rockgeotech.org Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895 http://dx.doi.org/10.1016/j.jrmge.2016.06.005 1674-7755 Ó 2016 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by Elsevier B.V. This is an open access article under the CC BY- NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).

Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Embed Size (px)

Citation preview

Page 1: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

lable at ScienceDirect

Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895

Contents lists avai

Journal of Rock Mechanics andGeotechnical Engineering

journal homepage: www.rockgeotech.org

Full Length Article

Failure of hanging roofs in sublevel caving by shock collision andstress superposition

Zong-Xian ZhangDepartment of Arctic Technology, University Center in Svalbard, Longyearbyen N-9171, Norway

a r t i c l e i n f o

Article history:Received 6 April 2016Received in revised form25 May 2016Accepted 22 June 2016Available online 17 September 2016

Keywords:Shock wave collisionHanging roofSublevel cavingRock fractureHang-upUnderground mining

E-mail address: [email protected] review under responsibility of Institute o

Chinese Academy of Sciences.

http://dx.doi.org/10.1016/j.jrmge.2016.06.0051674-7755 � 2016 Institute of Rock and Soil MechanicNC-ND license (http://creativecommons.org/licenses/

a b s t r a c t

Hanging roofs or high hang-ups, a common problem in sublevel caving mining, usually result in a largeore loss and undermine mining safety. This paper analyzed the formation of a hanging roof and showedthat increased confining pressure and reduced free surface were its main characteristics. In order tobreak down a hanging roof, a new method based on shock wave collision and stress superposition wasdeveloped. In this method, two blastholes containing multi-primer at different positions are simulta-neously initiated at first. By doing this, a new free surface and a swell room can be created. After theseholes are fired, a long delay time is given to the next blasthole so that the fragments from the first two-hole blasting have enough time to fall down. This new method was applied to three hanging roofs in oneproduction area, and all of them were successfully broken down. Field inspection indicated that almostno damage was caused in the nearby drifts/tunnels due to the new method. In addition, the far fieldvibrations were found to be smaller than the maximum vibrations induced by some other blasts.� 2016 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting byElsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/

licenses/by-nc-nd/4.0/).

1. Introduction

The modern sublevel caving, possibly developed in the ironmines of Sweden (Hustrulid and Kvapil, 2008), is a widely usedmining method in metallic mines across the world. This methodhas many advantages regarding safety and mechanisation (Janelidand Kvapil, 1966). Because mining operation is carried out only indrifts, the safety of this method is relatively good, compared withother mining methods such as cut-and-fill, and room and pillar.However, sublevel caving has two main disadvantages: high oreloss and high dilution. Therefore, how to reduce ore loss is animportant task for sublevel caving.

Investigations including Janelid (1968), Kvapil (1982), Ren(1994), Stazhevskii (1996), Hustrulid (2000), Rustan (2000),Quinteiro et al. (2001a), Power (2004), Selldén and Pierce (2004),Zhang (2005, 2014a,b, 2016), Brunton et al. (2010), Wimmer(2010), Tawadrous (2015), and Nordqvist and Wimmer (2016)have indicated that rock blasting has a great impact on fragmen-tation and recovery. Furthermore, there is a great potential to in-crease ore recovery by improving blasting (Zhang, 2016). At the

f Rock and Soil Mechanics,

s, Chinese Academy of Sciences. Prby-nc-nd/4.0/).

same time, unfortunately, there exist various problems in presentunderground blasting. One of such problems is the hanging roof insublevel caving.

In a normal condition, after a sublevel ring is blasted, the oremass in the ring is completely destroyed into various sizes offragments, and a new front face is formed. When ore extraction inthe ring is completed, the new front face is partly occupied by thewaste rocks (or mixed with ores). As a result, a large number ofwaste rocks move down to the drift floor and waste-rock bouldersoften partly block the draw point, as shown in Fig. 1a. However,sometimes, after a ring is blasted, the upper part of ore mass in thering is either poorly fragmented or seriously confined. Under thiscircumstance, when extraction in the ring is finished or it cannotcontinue, the upper part of ore mass is hanged there and an emptyroom is formed below the upper part, as shown in Fig. 1b. Thishanged part of ore mass is called hanging roof, also called“remained roof” or “high hang-up” (Hustrulid and Kvapil, 2008),which is similar to but not same as an ordinary hang-up in cavingmining. An ordinary hang-up frequently happens in block cavingand sublevel caving, and it may break up by itself during extraction.Different from an ordinary hang-up, a hanging roof does not breakup by itself. A hanging roof is common and it results in a large oreloss in sublevel caving. As reported by Zhang and Naarttijavi (2006),the ore loss due to hanging roofs was up to 380,000 t in Malm-berget mine during two-year production. In addition, a hanging

oduction and hosting by Elsevier B.V. This is an open access article under the CC BY-

Page 2: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Fig. 1. The draw points in a normal condition and a hanging roof condition. (a) The draw point picture in a normal condition taken from the drift floor onwhich the waste rocks rest;(b) the draw point picture in a hanging roof condition.

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895 887

roof may bring about a potential risk for the people working un-derground because it may come down with an air shock at anytime. Therefore, techniques for breaking down a hanging roof areneeded.

In the Malmberget mine, one method was often used to handlehanging roofs (Zhang and Naarttijavi, 2006). This method is calledold method in this paper and it is illustrated in Fig. 2. As shown inFig. 2, a hanging roof is formed, starting from ring 1 (R1). After R1 isblasted, its upper part remains. Then when extraction in R1 isfinished, R2 is blasted as usual. As this process continues, more andmore rings are blasted and the hanging roof becomes larger andthicker. After R12 is blasted, most of the ore mass in the ring ishanged. In order to keep a stable mining production and assure asafe work condition, several rings behind R12 have to be leftwithout blasting so that a new opening slot, as indicated in R17, ismade. This method can sustain mining production, but the orewithin several rings (e.g. R12-R16 in Fig. 2) has to be left as a per-manent ore loss since no blasting is involved. In order to reducesuch ore loss due to the old method, it is necessary to develop abetter method.

This paper will introduce a new method for breaking downhanging roofs. This new method was conceptually mentionedearlier (Zhang and Naarttijavi, 2006) but sufficient analysis waslacking. In this paper, the formation and characteristics of hangingroofs will be described. Then the principles of the newmethod willbe introduced. Finally, the applications of the new method to threehanging roofs will be in detail reported.

2. Formation and characteristics of hanging roofs

2.1. Formation of a hanging roof

The Malmberget mine is a large apatite-iron ore deposit, con-sisting of 20 ore bodies containing both magnetite and hematite.The iron content varies from 54% to 63%. The uniaxial compressivestrength of the ore ranges from 85 MPa to 140 MPa. The countryrocks consist of metamorphosed volcanic rocks such as gneissesand fine-grained feldspar-quartz rocks called leptites. The uniaxialcompressive strength of the red leptite varies from 170 MPa to220 MPa, and that of gray leptite ranges from 70 MPa to 160 MPa.Over the entire ore field, one structural group strikes and dips sub-parallel to the ore bodies (Quinteiro et al., 2001b).

The mining method is sublevel caving with a sublevel heightvarying from 20 m to 30 m. The production blastholes are 115 mmin diameter, each hole contains one primer, the dirft is 7 m wide

and 5.5 m high, the explosive is emulsion with a VOD (velocity ofdetonation) of 5000 m/s (Nordqvist and Wimmer, 2014), the delaytime between holes is 100 ms, and the P-wave velocity of the rock/ore mass is about 5100 m/s (Zhang, 2014c).

In the mine, a hanging roof may occur in either a large ore bodyor a very narrow ore body. In both ore bodies, hanging roofs can bedivided into two types. The first type, often found in narrow orebodies and shown in Fig. 2, occurs from the first production rings ina sublevel drift. A major reason for this type is an unsuccessful opencut, i.e. the blast surrounding the opening slot in the beginning of adrift does not create an opening large and high enough for the nextblasting. An unsuccessful open cut can be caused by various rea-sons, one of which is that the slot is too short to reach the top of thering. For example, as shown in Fig. 2, the slot (the slot is not shownbut it is assumed that the top of the slot is at the position SE) justreaches the position SE in front of the first ring, R1. In this case,when open cut is made, a certain upper part (roof) of R1 will be leftas shown in Fig. 2a. As soon as the roof of R1 is remained, it is easyto form a thicker hanging roof in R2 if it is blasted as usual. If R3 andother following rings are blasted one by one as usual, the hangingroof will become thicker and larger. As indicated in Fig. 2a, the roofsof R1 to R11 are all remained.

The second type of hanging roofs appears due to unsuccessfulblasting in several neighboring rings. This type is shown in Fig. 3.Different from the first type, the second type has a partly freesurface, which is parallel to the ring plane but is at least two bur-dens far from the ring to be blasted, as shown in Fig. 3a. In addition,the second type does not happen in the beginning of drift. Similarto the situation in the first type, when a ring is not well blasted andits roof is remained, if the next ring is blasted as usual, then thehanging roof becomes thicker and larger. Under this circumstance,if the next following ring is still blasted as usual, the hanging roofwill become much thicker until the last ring cannot be well blastedat all. For example, R13 in Fig. 3 cannot be destroyed as usual afterthe roof of R12 is remained.

2.2. Characteristics of a hanging roof

2.2.1. Stress stateFor an ordinary ring to be blasted, its front face is partly covered

by the waste rocks with different sizes. For example, in Fig. 3 theboundary between the front face of R8 (one ordinary ring) and thecaved waste rocks is a partly free surface, meaning that the hori-zontal stress, along X-direction, applied to the front face of R8 isvery small or negligible. However, the horizontal stress from the

Page 3: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Fig. 2. Diagram of the first type of hanging roofs. (a) Transverse section taken through the sublevel drift; (b) cross-section AeA along the plane of R10; (c) plane section BeB. Thehanging roof begins at open cut (before R1) and ends at R12. Taking R10 for example, when it is blasted, the confinement to the ring in X-direction is increased from zero to a certainvalue, and the actual burden is 4 times greater than the original burden at the level BeB, see Fig. 2a and c.

Fig. 3. Diagram of the second type of hanging roofs. (a) Transverse section taken through the production drift; (b) cross-section AeA along the plane of R10; (c) plane section BeB.The hanging roof begins at R8 and ends at R12. Taking R10 for example, when it is blasted, the confinement to the ring in X-direction is increased from zero to a certain value,compared with an ordinary case, and the actual burden becomes double of the original one.

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895888

intact rockmass (above the upper surface in Fig. 3c) in Y-direction isnot zero. In addition, it is assumed that the horizontal stress in Y-direction from thewaste rock below the boundary JK in Fig. 3c is notzero since the flow ability of the waste rock along JK is smaller thanthat along IJ where waste rock (also ore fragments) can flow downduring extraction. In brief, the rock in an ordinary ring bears two

directional loads, one in vertical direction (Z-axis in Figs. 2 and 3)and the other in horizontal direction (Y-axis).

In the first type of hanging roofs, such as one of roofs of R1eR12in Fig. 2, the partly free surface in front of the ring to be blasted doesnot exist at all. The ore mass in the left and above the position SE(shown in Fig. 2) is mostly an insufficiently fragmentedmass. In this

Page 4: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895 889

case, for the ring to be blasted, there are three directional stressesacting on the rock mass in the ring. Two horizontal stresses in X-and Y-directions can be considered to be equal to the in-situstresses in this mining area. In the second type of hanging roofs,the partly free surface in front of the ring (e.g. R10 in Fig. 3) to beblasted disappears. There is one partly free surface (e.g. at R8 inFig. 3), but it is far from the ring in question (e.g. R10).

As a conclusion, the rock mass in a hanging roof bears threedirectional loads, while that in an ordinary ring does two direc-tional ones.

2.2.2. Free surfaceIn an ordinary ring, there is a partly free surface in the front of

ring, as described above. This surface is approximately parallel tothe plane of the ring. Such a plane is indicated by the dashed lineswith ring numbers in Fig. 2. It is this partly free surface that makesthe blast-induced compressive waves partly reflected into tensilewaves. In other words, this partly free surface plays an importantrole in rock fracture and fragmentation. However, in the first type ofhanging roofs, such a partly free surface does not exist anymore. Inthe second type of hanging roofs, this partly free surface is at leasttwo burdens far from the ring to be blasted. In this case, when acompressive wave arrives at the partly free surface, its amplitudewill be much smaller than that in an ordinary ring due to waveattenuation. As a consequence, the tensile wave reflected from thepartly free surface will be small, giving rise to little spalling or evenno spalling in the ring if it is blasted as usual. In other words, theusual blast method fails to break down a hanging roof. In order todestroy a hanging roof, higher amplitude of stress wave must besupplied.

2.2.3. Confining pressureAsmentioned above, in an ordinary ring, the rock bears only two

directional loading, i.e. the stress in one horizontal direction,defined as h1 direction, is nearly zero, i.e. sh1o z 0, here subscriptletter “o” means ordinary rings. In a hanging roof, the rock bearsthree directional loading, and the stress in the same horizontaldirection h1 is greater than zero, i.e. sh1r > 0, here “r” meanshanging roof. It is assumed that the stresses in another horizontaldirection, defined as h2 direction, are equal to each other in both anordinary ring and a hanging roof, i.e. sh2o ¼ sh2r.

The magnitudes and orientations of two horizontal stresses inMalmberget mining area can be estimated by using the followingformulae (Sandström and Nordlund, 2004):

sh1 ¼ 0:037z (1)

sh2 ¼ 0:028z (2)

where z is the vertical distance or depth from the surface, i.e.z ¼ 0 m on the surface.

Eq. (1) is for the maximum horizontal principal stress in MPa(East-West), and Eq. (2) is for the minimum horizontal principalstress in MPa (North-South). Note that the calculated stresses byusing Eqs. (1) and (2) fall in the range of the empirical formula byBrown and Hoek (1978).

Since mining activity and underground structures affect thelocal stress state, it is difficult to determine the exact stressmagnitude and orientation in a hanging roof. To break down ahanging roof, it is better to take themaximum horizontal stress intoconsideration and assume that both horizontal stresses in two di-rections are equal. Accordingly, Eq. (1) is used to estimate themaximum horizontal stress. In this study, for the three hangingroofs to be discussed later, their depths are z1 ¼ 440 m, z2 ¼ 437 m,

and z3 ¼ 480 m, respectively. Accordingly, their maximum hori-zontal stresses, i.e. the confining pressures, are as follows:

(1) For the first hanging roof at JS4402-r52:

sh1 ¼ 0:037z1 ¼ 16:3 MPa (3a)

(2) For the second hanging roof at JH4376-r7:

sh2 ¼ 0:037z2 ¼ 16:2 MPa (3b)

(3) For the third hanging roof at JS4801-r20:

sh3 ¼ 0:037z3 ¼ 17:8 MPa (3c)

2.3. Rock fracture under confining pressure

The above description indicates that, in order to break down ahanging roof, two factors must be considered: increased confiningpressure and reduced free surface. To consider the effect of increasedconfining pressure on rock fracture,weneed to know the influenceofconfining pressure on the strengths and fracture toughness of rock.

Experimental studies including Lindholm et al. (1974), Gowd andRummel (1977), Schmidt andHuddle (1977),Whittaker et al. (1992),Thallak et al. (1993), Vasarhelyi (1997), Al-Shayea et al. (2000),Backers et al. (2002), Funatsu et al. (2004), and Liu et al. (2014) haveshown that rock compressive strength and fracture toughness in-crease with increasing confining pressure. Unfortunately, thestudies on fracture toughness only deal with static or quasi-staticloading. Similarly, the experiments on dynamic tensile strengthwith different confining pressures are few. Since compressivestrength and tensile strength of rock have an approximately linearrelation, it is assumed that the dynamic tensile strength of rockincreases with increasing confining pressure, too. Because there areno measured data on the iron ore available, we need estimate thedynamic strength of the ore under different confining pressures.Two results for basalt (with a statically uniaxial compressivestrength of 369MPa) (Lindholm et al.,1974) and amphibolite (with astatically uniaxial compressive strength of 140MPa) (Liu et al., 2014)may be taken as references. According to the results in Lindholmet al. (1974) and Liu et al. (2014), as confining pressure isincreased to 20MPa, the dynamic strength of the basalt is increasedby5% and that of the amphibolite increased by45% approximately. Itis assumed that the ore mass in the hanging roofs to be discussed ismore close to the amphibolite. Thus, in order to destroy the hangingroofs, we have to apply a 45% higher stress to overcome the higherstrength caused by the higher confining pressure.

3. Shock wave collision and stress superposition

As described above, a higher stress (as well as more energy) isrequired to break down a hanging roof due to the increasedconfinement and reduced free surface. This may be realized bydrilling more and larger boreholes to charge more explosive. Un-fortunately, it is not allowed to perform any drilling operation in orclose to a hanging roof in the mine. Because of this limitation, it isnecessary to look for another way. A possible and easy way is tomake use of shock wave collision and stress superposition.

3.1. Shock wave collision

According to one-dimensional (1D) shock wave theory (Cooper,1996; Zhang, 2016), when one shock wave with pressure P1 meets

Page 5: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895890

another shock wave with pressure P2, the final shock pressure P3produced is greater than the sum of the initial two shock pressures,i.e.

P3 > P1 þ P2 (4)

This is called shock wave collision. Note that a shock wavecollision is different from an elastic wave collision. For example, astwo shock waves each with a 15 GPa pressure travel towards eachother in TNT (cast), their collision can result in a 47.5 GPa pressure,much higher than the sum of the initial two pressures (Zhang,2016). In 1D condition, as an elastic wave with stress s1 meetsanother one with stress s2, the final stress s3 produced is equal tothe sum of the stresses of the initial two elastic waves, i.e.

s3 ¼ s1 þ s2 (5)

Take a single blasthole for example, as shown in Fig. 4. In thishole, there are two primers at locations D1 and D2. There is no freesurface surrounding the hole that is fully charged. It is assumedthat: (1) a shockwave from a detonating blasthole quickly decays toan elastic wave in the rock mass, so shock wave collision will beonly considered in the blasthole, while elastic wave superpositionwill occur in the rock mass; (2) the detonation velocity of theexplosive and the P-wave velocity of the rock mass are equal toeach other; (3) in order to simplify the analysis, only P-wave isconsidered while S-wave is neglected. Under these conditions,when the two primers are simultaneously initiated, the detonationfrom both primers will travel in two directions: up and down in thehole. When the detonation front from D1 propagates down to D2,its front in upward direction will come to F1. At the same time,when the detonation front from D2 propagates up to D1, its front indownward direction will come to F2. At the same moment, thefronts of the P-waves starting fromD1 and D2will travel outward inthe rock mass. These fronts are indicated in Fig. 4. Now a summaryon the stress distribution in the rock mass can be made as follows:

(1) There is a superposition region of the two P-waves startingfrom the two primers, which is enclosed by curve E1-D1-E2-D2-E1. In this region, the stress (in a certain direction and at aspecific point) is greater than either the initial stress (at the

Front of P-wave

Front of P-wave

D1

D2

O

F1

F2

E2E1 B1 B2

Fig. 4. Two fronts of P-waves starting from two primers at D1 and D2 when theexplosive between F1 and F2 is detonated. At the same moment, the front of the shock-collision-induced P-wave starting from position O arrives at D1, D2, B1 and B2.

same direction and same point) caused by the wave startingfrom D1 or the initial stress from D2.

(2) In the superposition region E1-D1-E2-D2-E1, there are threeareas. The first is the circular area, and the diameter of whichis D1-D2 or B1eB2. In this area, a shock wave collisionhappens between D1 and D2 in the hole, and the collisionbegins at location O. According to Eq. (4), this shock collisionresults in that the final shock pressure is greater than thesum of the initial two shock pressures. Accordingly, the finalstress produced by the shock collision in this circular areamust be greater than the sum of the initial two stresses eachfrom one primer. With elapsed time, this circular area ex-pands outward.

(3) In the superposition region E1-D1-E2-D2-E1, the two otherareas are E1-D1-B1-D2-E1 and D1-E2-D2-B2-D1. In theseareas, only elastic wave superpositionmay occur, i.e. the finalstress after superposition is greater than either of the initialtwo stresses but less than or equal to the sum of the twoinitial stresses.

As a result, if two primers are placed at two places in a blastholeand they are initiated simultaneously, the stresses at a certain pointin some region will be two times greater than the stresses at thesame position caused by a single primer. Since a normal productionblasthole contains only one primer in the mine, it is possible tobreak down the hanging roof by placing multiple primers in one ormore holes in a ring. However, there are more factors to beconsidered, such as loading rate effect on rock fracture.

3.2. Elastic wave superposition

If we place four primers at different positions D1eD4 in twoblastholes and all of them are initiated simultaneously, as shown inFig. 5, after a certain period of time, four fronts of P-waves startingfrom every primer location come to the positions indicated by fourcircles in Fig. 5a. There is an intensive stress superposition regionsurrounded by D1-D3-D4-D2. Within this region, there are foursmaller regions where stresses coming from 3 P-waves start atthree primers. These regions are marked with number 3. If onlyelastic wave superposition is considered, the final stress at anarbitrary point in these regions will be less than or equal to threetimes of the stress at the same place from any one primer deto-nation. In addition to these small regions, there is another areaenclosed by area QRST in the central part of Fig. 5a. In this area, thefinal stress at an arbitrary point results from the superposition offour initial stresses from four primers. Similarly, if only elastic wavesuperposition is considered, the final stress at a certain point in thisarea may reach four times of the stress at the same point due to oneprimer detonation. Obviously, if the shock collision is considered,the final stresses in some parts of this area will be greater than fourtimes of the stresses at the same positions. If we take two sectionsAeA and BeB from Fig. 5a, then we find that the area QRST isactually a three-dimensional zone. On section AeA this zone is thearea enclosed by URVT and on section BeB it is the area surroundedby QUSV. Enclosed in this zone are two smaller zones induced byshock collision. The two smaller zones are indicated by the dashedcircles. In these two zones, the total stress at a certain point may begreater than four times of the stress caused by one single primerdetonation.

3.3. Loading rate effect on rock fracture

Experimental investigations including Olsson (1991), Zhanget al. (1999, 2001), Cho et al. (2003), Dai et al. (2010), and Xia andYao (2015) have shown that rock strengths and fracture

Page 6: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Fig. 5. Stress distribution surrounding four simultaneously initiated primers due to shock collision and stress superposition. (a) Transverse section taken through two holes blastedat the same time; (b) section AeA; (c) section BeB. The dashed circles are the regions affected by shock collision. The numbers in the figure represent the quantity of stress wavesfrom different primers. The shadow areas represent a high stress superposition zone in which the total stress at a certain point can be up to or greater than four times of the stressfrom one single primer position.

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895 891

toughness increase with increasing loading rates under dynamicloading condition. When shock collision in the same hole andelastic wave collision between holes happen, the loading rate in therock mass surrounding the blastholes will increase. According toprevious experimental studies summarized in Zhang (2016), underdynamic loading condition, the relation between strain rate _3andtensile strength sTd of rock and that between loading rate _k andmode I fracture toughness KId of rock can be expressed as

sTd ¼ C01 _3a (6)

KId ¼ C02 _kb

(7)

where C01 and C02 are the coefficients; and constants a and b areequal to 0.33 and 0.67e0.76, respectively. Let _31 and _k1 be thestrain rate and loading rate under the condition of a single primerin a blasthole, and corresponding strength and toughness be sTd1and KId1, respectively. As four primers are placed in two holes asshown in Fig. 5, we assume that the maximum strain rate andloading rate in the high stress superposition zone are approxi-mately four times as great as _31 and _k1, respectively. Then we mayestimate from Eqs. (6) and (7) that the tensile strength and thefracture toughness will be 1.58 and 2.51e2.86 times as great assTd1 and KId1, respectively. This means that, to break down thehanging roof, a higher stress is required to overcome the higherstrength and greater toughness.

As a consequence, if the rock strength or fracture toughness isincreased by up to 3.31 times due to increased confining pressureand increased loading rate, it is possible to break down the hangingroof by placing four primers at different positions in two neigh-boring blastholes.

4. New method and its applications

4.1. New method for breaking down hanging roofs

On the basis of the above analysis, the stresses at any point insome region between two neighboring blastholes containing fourprimers with the same delay time can be greater than four times ofthe stresses at the same point caused by a single primer in ablasthole. That is to say, a much high stress can be achieved bymaking use of shock collision and elastic wave superposition,without increase in explosive charge. Although four primers at twoholes are good enough to overcome the higher rock strengths andgreater fracture toughness caused by the greater confinement andhigher loading rate in a hanging roof, it is better to use more thanfour primers at the two holes so as to certainly break down thehanging roof. Accordingly, the ring nearest the hanging roof, forexample R13 in Figs. 2 and 3, is chosen to do this special blasting. Insuch a ring, multiple primers are placed at different positions intwo neighboring blastholes, and all these primers are initiated atthe same time. This special blast method is called new method for

Page 7: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895892

breaking down hanging roofs. The newmethod consists of two keyissues:

(1) To place several primers at different positions in twoneighboring holes. All primers in the two holes are initiatedat the same time. If NONEL or pyro-technic detonators areused, the zero delay time should be chosen.

(2) The delay time between the above two holes and the nexthole to be fired must be very long so that the fragments fromthe two hole blasting have enough time to completely falldown before the next hole is initiated.

Fig. 7. Blast plan for breaking down the hanging roof close to ring JH4376-r7. The smallsquares show the detonator numbers and their positions. The circles and the numbershave the same meanings as that in Fig. 6.

4.2. Breaking down the first hanging roof

The first hanging roof was formed before ring JS4402-r52 (r52 inshort) in a sublevel drift named JS4402 located in a small andnarrow ore body. This is a second type of hanging roof. Ore ex-tractions in two nearest rings r51 and r50 were less than 50%because their roofs were remained. The newmethodwas applied toring r52 and the photograph in Fig. 1b was taken before ring r52had been charged. The blast plan of r52 is shown in Fig. 6. Two holes#6 and #7 were blasted simultaneously. A total of 7 primers wereplaced at different locations in the two holes and they were initi-ated at the same time. Every primer contained one NONEL deto-nator. Considering that the initiation error of NONEL detonatorsincreases with increasing delay time, zero-delay-time detonatorswere used in the 7 primers. Thus, according to the above analysis,the blast-induced stresses in some area between the two holescould reach 7 times greater than the stresses in a normal produc-tion blast in which only one primer is placed in each hole.

As stated above, in order to have enough time to let fragmentsfrom the first two holes fall down, a delay time of 500 ms wasassigned to the next initiation e hole #8. If blasting in holes #6e#8is successful, a free surface and an empty roomwill be created. If so,the rest of holes in the ring may be blasted one by one as in normalproduction blasting. For this reason, a delay time of 100 ms or

Fig. 6. Blast plan for breaking down the roof in the ring JS4402-r52. The primer po-sitions are marked with stars and delay times indicated. The primers in each hole havethe same delay time. The primers in holes #6 and #7 were fired first. The circlesindicate the fronts of compressive waves starting from each primer in holes #6 and #7after a certain time of initiation. The numbers between the two holes show how manycompressive waves are overlapped.

200 ms was used between these holes, as shown in Fig. 6. Note thatthree primers were placed in each of holes #8e#9 and #1e#5. Thisis to assure that the roof is certainly broken down.

After the blast of r52, the hanging roof came down and oreextraction in r52 reached 110%, a normal value in the mine.

4.3. Breaking down the second hanging roof

The second hanging roof belongs to the first type and it wasformed from the open cut in the drift JH4376. Ore extractions in thefirst 6 rings were lower than 80% on average and the extraction inthe last ring r6 (in short)was only 23%. This hanging roof was brokendown by blasting ring r7. Different from the first hanging roof, thesecond onewas formed from the beginning of the drift, similar to thesituation shown in Fig. 2. In this case, the front free surface wasreduced to nearly zero for ring r7. Considering this increasedconfinement, two long holes were chosen as the first simultaneousinitiation, and a total of 8 primers were placed in the two holes, asshown in Fig. 7. In addition, since the increased confinement couldresult in longer time for rock fragments to fall down, a long delaytime of 3 s was given to the next initiation e hole #4. As a result, thehanging roofwas broken down and the ore extraction came back to anormal level in ring r7 and other following rings.

4.4. Breaking down the third hanging roof

The third hanging roof is of the first type of hanging roof formedfrom the open cut in the drift JS4801. Ore extraction in the first 19rings (r1-r19 in short) was only 45% on average. The third roof wasbroken down by blasting ring JS4801-r20. This roof is very similarto the second one. The last ring before ring 20 is the ring 19 inwhich the final extraction was only 5%, i.e. most of the ore mass inring 19 was remained. Two pictures in Fig. 8 were taken while ring20 was being charged. Fig. 8b indicates that the ore mass close tothe brow (top contour of the drift) is hanging there, although theore mass looks fractured. However, it is difficult to judge how theore mass inside ring 19 had been fractured. In brief, ring 20 washighly confined.

Page 8: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895 893

In terms of the above description, a similar blast plan as in thesecond hanging roof was employed. As a consequence, the thirdhanging roof was broken down, too. In addition, the ore extractionin ring 20 reached 119%.When the loading in ring 20was finished, aphotograph was taken, as shown in Fig. 9, fromwhich we can see acertain burden for ring 21 was intact and the brow damage is muchless than that for ring 20.

Fig. 9. The top of the drift JS4801 after ring JS4801-r20 was blasted. There was nodamage in the right top of drift. There was spalling in the left top of drift.

5. Effect of new method on stability of nearby structures andvibrations in far field

5.1. Stability of nearby structures

After each hanging roof was broken down, an investigation wasmade on the stability of structures in the mine. In the far field ofeach drift where a hanging roof was located, no damage in the roofand walls of the drift was found. No damage was observed in otherneighboring drifts, either.

In the drifts close to the hanging roofs, no damage was found inthe tops of drifts JS4402 and JH4376. Fig. 10 indicates that the shot-crete in both top andwalls of drift JS4402 is complete, i.e. no damage.Differently but not strangely, small spallingwas found in the left sideof drift JS4801 where the third hanging roof was located. We can seefrom Fig. 8a that before the roof was broken down, therewas alreadyspalling in the left top of drift, but no damage in the right side. Afterthe hanging roof was broken down, as shown in Fig. 9, therewas stillno damage in the right side, while the new spalling in the left side

Fig. 8. Photographs taken when ring 20 was charged. (a) Photograph taken after theexplosive and the primers were loaded; (b) photograph showing the brow area wherethe upper part indicates some collars of blastholes in ring 20 and the lower part doesthe seriously compacted fragments in ring 19. The compacted fragments were hangingthere after the extraction was finished in ring 19.

was observed. Probably, the previous spalling shown in Fig. 8a is oneof main factors that cause the new spalling.

Another positive result is that the brow damage was reduced bybreaking down the third hanging roof. As indicated in Fig. 8a, theburden for ring 20 was completely broken off before the hangingroof was destroyed. Note that the boreholes observed in Fig. 8b areall under the hanging roof, and the picture was taken under theroof. However, a burden with several collars can be clearly seen inFig. 9 after the hanging roof was broken down, implying that thebrow damage was decreased when the roof was destroyed.

5.2. Vibrations in far field

In Malmberget City, a vibrationmonitor is all time installed at thebasement of one house. Any vibrations above the trigger level of themonitor can be recorded. Among the three hanging roofs, the secondone at JH4376-r7 was nearest to the monitor, while the other two atJS4402-r52 and JS4801-r20were relatively far from themonitor. As aconsequence, the ground vibrations from production blasts in thedrift JH4376 were always recorded by the monitor.

Fig. 11 shows the maximum vertical particle velocity per weekrecorded by the monitor in the city from 2000 to 2010 (Zhang,2012). When the second hanging roof was broken down inJH4376-r7 on April 1, 2004, the maximum vertical particle velocitywas found to be 5.85 mm/s. This value is much lower than twonearest high vibrations, one is 15.8 mm/s caused by a failed opencut in the drift JH4376 happening on March 28, 2004, and the otheris 16.2 mm/s occurring onMay 17, 2004 due to a simultaneous blastof two rings in two different drifts. It should be noted that, in thefailed open cut blast, several blastholes were connected oneanother, resulting in the explosive charged in the connected holesbeing initiated together. Similarly, in the simultaneous initiation oftwo rings, the measured vibrations came from the superposition oftwo vibration waves from the two rings.

Since the monitor was relatively far from the other two hangingroofs at JS4402-r52 and JS4801-r20, there were no measured vi-brations available.

6. Discussion

6.1. Safety of new method

As mentioned above, no damage was found in the far field rockstructures when the three hanging roofs were broken down. Inaddition, no damage was observed in the near field drifts when thefirst and second roofs were destroyed. Only in the near field of drift

Page 9: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Fig. 10. No damage in the top and walls of drift JS4402 after the hanging roof atJS4402-r52 was broken down.

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895894

JS4801 was spalling observed in the left side of the drift, probablydue to the previous damage. Moreover, the maximum vibrationduring breaking down the hanging roof at JH4376-r7 was found tobe much smaller than that during simultaneous blasting of tworings. These results indicate that the new method is safe for bothnearby structures and far field vibrations. Two possible reasons are:

(1) much energy included in the high stresses caused by shockcollision and elastic wave superposition might be consumedin fracturing the rock close to and between the two first-initiated holes, e.g. in the regions enclosed by the dashedcircles and shadowed areas in Figs. 5 and 6. As a conse-quence, the waves propagating to the rock outside the twoholes and the far field will significantly decrease.

(2) As soon as going into rock mass, a shock wave will rapidlydecay to an ordinary stress wave or elastic wave. A support tothe first reason is that when shock collision was applied toproduction blasts in which two primers were placed atdifferent positions in each hole and theywere initiated at thesame time, the brow damagewas largely reduced rather thanincreased (Zhang, 2011, 2014a).

6.2. Quantity of primers and delay time

It is necessary to do a further study on the quantity of theprimers in the first two holes. The similar thing is for the delay time

Fig. 11. Ground vibrations measured at the

between the first initiation and the next one. In practice, if it isdifficult to determine the confining pressure and the falling speedof fragments, seven or eight primers in the first two holes and adelay time longer than 1 s between the first two holes and the nexthole are suggested.

6.3. Reasons for hanging roofs and hang-ups

It is of importance to investigate every reason for hanging roofsin detail in the future. However, some possible reasons can belisted as follows: (1) too short opening slot in a sublevel drift, asdescribed in Section 2; (2) too small charged lengths in some holesin a ring, which result in that the stresses and energy transmittedto the upper part of the ring are not strong enough to make suf-ficient fragmentation in the upper part; (3) an improper blast plansuch as incorrect primer placement; (4) detonation failure in someholes in a ring; (5) an increasing confinement to the ore flow(Hustrulid and Kvapil, 2008; Castro et al., 2014); (6) other un-known reasons.

6.4. Breaking down a hanging roof or a high hang-up at good time

Even though a spalling in a drift surface can happen far fromexplosive charge, e.g.10e20m, a short distance between the chargeand the drift surface resulted in larger volume of rock fracture inthe surface, according to field investigation and spalling theory(Zhang, 2014c, 2016). Therefore, as soon as a hanging roof occurs, itshould be broken down as early as possible so that the distancebetween the nearest free (or partly free) surface and the ring to beblasted is kept as small as possible. If a hang-up does not break upby itself, it may be broken down by using the new method.

7. Conclusions

A hanging roof makes the ore mass in a ring to be blasted bearthree directional loadings. In other words, the confining pressure tothe rock mass in the hanging roof is increased from zero to a certainvalue. This increase in confining pressure requires a higher stress ormore energy to break down the hanging roof. In addition, thereduced free surface makes tensile rock fracture decreased. Based onthese facts, a newmethod for breaking downa hanging roof has beendeveloped. This new method has been used to break down all threehanging roofs met in one mining area in the Malmberget mine.

The new method is easy to be used, very cheap and efficient. Byusing this new method, a large ore loss due to the old method canbe avoided.

Malmberget City from 2000 to 2010.

Page 10: Failure of hanging roofs in sublevel caving by shock ... · The modern sublevel caving, possibly developed in the iron mines of Sweden (Hustrulid and Kvapil, 2008), is a widely used

Z.-X. Zhang / Journal of Rock Mechanics and Geotechnical Engineering 8 (2016) 886e895 895

The new method is safe for either nearby structures or the farfield, regarding rock damage and ground vibrations.

Conflict of interest

The author wishes to confirm that there are no known conflictsof interest associated with this publication and there has been nosignificant financial support for this work that could have influ-enced its outcome.

Acknowledgements

The author is grateful to LKAB, his former colleagues AndersJohnsson and Matthias Wimmer, and the miners in Malmbergetmine for support.

References

Al-Shayea NA, Khan K, Abduljauwad SN. Effects of confining pressure and tem-perature on mixed-mode (IeII) fracture toughness of a limestone rock. Inter-national Journal of Rock Mechanics and Mining Sciences 2000;37(4):629e43.

Backers T, Stephansson O, Rybacki E. Rock fracture toughness testing in ModeIIdpunch-through shear test. International Journal of Rock Mechanics andMining Sciences 2002;39(6):755e69.

Brown ET, Hoek E. Trends in relationships between measured in-situ stresses anddepth. International Journal of Rock Mechanics and Mining Sciences & Geo-mechanics Abstracts 1978;15(4):211e5.

Brunton ID, Fraser SJ, Hodgkinson JH, Stewart PC. Parameters influencing full scalesublevel caving material recovery at the Ridgeway gold mine. InternationalJournal of Rock Mechanics and Mining Sciences 2010;47(4):647e56.

Castro RL, Fuenzalida MA, Lund F. Experimental study of gravity flow underconfined conditions. International Journal of Rock Mechanics and Mining Sci-ences 2014;67:164e9.

Cho SH, Ogata Y, Kaneko K. Strain-rate dependency of the dynamic tensile strengthof rock. International Journal of Rock Mechanics and Mining Sciences2003;40(5):763e77.

Cooper PW. Explosives engineering. New York: Wiley-VCH; 1996.Dai F, Xia K, Tang L. Rate dependence of the flexural tensile strength of Laurentian

granite. International Journal of Rock Mechanics and Mining Sciences2010;47(3):469e75.

Funatsu T, Seto M, Shimada H, Matsui K, Kuruppu M. Combined effects of increasingtemperature andconfiningpressure on the fracture toughness of clay bearing rocks.International Journal of Rock Mechanics and Mining Sciences 2004;41(6):927e38.

Gowd TN, Rummel F. Effect of fluid injection on the fracture behavior of porousrock. International Journal of Rock Mechanics and Mining Sciences & Geo-mechanics Abstracts 1977;14(4):203e8.

Hustrulid W, Kvapil R. Sublevel caving e past and future. In: Proceedings of the 5thinternational conference and exhibition on mass mining. Luleå: Luleå Univer-sity Press; 2008. p. 107e32.

Hustrulid WA. Method selection for large scale underground mining. In: Pro-ceedings of the 3rd international conference and exhibition on mass mining.Melbourne: Australasian Institute of Mining and Metallurgy; 2000. p. 29e56.

Janelid I. Sublevel caving: how to use it; what are advantages, problems. WorldMining 1968;21(9):76e8.

Janelid I, Kvapil R. Sublevel caving. International Journal of Rock Mechanics andMining Sciences & Geomechanics Abstracts 1966;3(2):129e53.

Kvapil R. The mechanics and design of sublevel caving systems. In: Hustrulid WA,editor. Underground mining methods handbook. Littleton, USA: Society ofMining Engineers of the American Institute of Mining, Metallurgical, and Pe-troleum Engineers; 1982. p. 880e97.

Lindholm US, Yeakley LM, Nagy A. The dynamic strength and fracture properties ofdresser basalt. International Journal of Rock Mechanics and Mining Sciences &Geomechanics Abstracts 1974;11(5):181e91.

Liu S, Xu J, Lv X. Influence of confining pressure and impact loading on mechanicalproperties of amphibolite and sericite-quartz schist. Earthquake Engineeringand Engineering Vibration 2014;13(2):215e22.

Nordqvist A, Wimmer M. Holistic approach to study gravity flow at the Kirunasublevel caving mine. In: Proceedings of the 7th international conference andexhibition on mass mining, Sydney; 2016.

Nordqvist A, Wimmer M. Large scale field test of gravity flow at the Kiruna mine. In:Proceedings of Aachen international mining symposia, 2014, Stolberg (Ger-many). Stolberg: Druckservice Zillekens; 2014. p. 621e36.

OlssonWA. The compressive strength of tuff as a function of strain rate from 10�6 to103/s. International Journal of Rock Mechanics and Mining Sciences & Geo-mechanics Abstracts 1991;28(1):115e8.

Power G. Full scale SLC draw trials at ridgeway gold mine. In: Proceedings of the 4thinternational conference and exhibition on mass mining. Santiago: Instituto deIngenieros de Chile; 2004. p. 225e30.

Quinteiro CR, Larsson L, Hustrulid WA. Theory and practice of very large scalesublevel caving in underground mining methods. In: Hustrulid WA, Bullock RL,editors. Underground mining methods: engineering fundamentals and inter-national case studies. Englewood: Society for Mining, Metallurgy, and Explo-ration; 2001a. p. 381e4.

Quinteiro C, Quinteiro M, Hedstrom O. Underground iron ore mining at LKAB,Sweden. In: Hustrulid WA, Bullock RL, editors. Underground mining methods:engineering fundamentals and international case studies. Englewood: Societyfor Mining, Metallurgy, and Exploration; 2001b. p. 361e8.

Ren FY. Ore flow theory. Beijing: China Metallurgical Industry Press; 1994 (inChinese).

Rustan A. Gravity flow of broken rock e what is known and unknown. In: Pro-ceedings of the 3rd international conference and exhibition on mass mining.Melbourne: Australasian Institute of Mining and Metallurgy; 2000. p. 557e67.

Sandström D, Nordlund E. Analys av det primära spänningstillståndet i LKABMalmberget. Luleå: Luleå University of Technology; 2004 (in Swedish).

Schmidt RA, Huddle CW. Effect of confining pressure on fracture toughness ofIndiana limestone. International Journal of Rock Mechanics and Mining Sci-ences & Geomechanics Abstracts 1977;14(5e6):289e93.

Selldén H, Pierce M. PFC3D modeling of flow behavior in sublevel caving. In: Pro-ceedings of the 4th international conference and exhibition on mass mining.Santiago: Instituto de Ingenieros de Chile; 2004. p. 201e14.

Stazhevskii SB. Features of flow of broken rock in extraction of ores with sublevelcaving. Journal of Mining Science 1996;32(5):403e16.

Tawadrous A. Blasting, material flow and ore dilution in sublevel caving mining:state-of-the-art review. Blasting and Fragmentation 2015;9:25e40.

Thallak S, Holder J, Gray KE. The pressure dependence of apparent hydro-fracturetoughness. International Journal of Rock Mechanics and Mining Sciences &Geomechanics Abstracts 1993;30(7):831e5.

Vasarhelyi B. Influence of pressure on the crack propagation under Mode I loadingin anisotropic gneiss. Rock Mechanics and Rock Engineering 1997;30(1):59e64.

Whittaker BN, Singh RN, Sun G. Rock fracture mechanics: principles, design andapplications, developments in geotechnical engineering. Elsevier; 1992.

Wimmer M. Gravity flow of broken rock in sublevel caving (SLC) e state-of-the-art.Swebrec Report 2010:P1. Luleå: Luleå University of Technology; 2010.

Xia K, YaoW.Dynamic rock tests using split Hopkinson (Kolsky) bar systeme a review.Journal of Rock Mechanics and Geotechnical Engineering 2015;7(1):27e59.

Zhang ZX. Increasing ore extraction by changing detonator positions in LKABMalmberget mine. Fragblast 2005;9(1):29e46.

Zhang ZX, Kou SQ, Yu J, Yu Y, Jiang LG, Lindqvist PA. Effects of loading rate on rockfracture. International Journal of Rock Mechanics and Mining Sciences1999;36(5):597e611.

Zhang ZX, Naarttijavi T. Applying fundamental principles of stress waves to pro-duction blasting in LKAB Malmberget mine. In: Proceedings of the 8th inter-national conference on rock fragmentation by blasting. Sandiago: Santiago deChile; 2006. p. 369e74.

Zhang ZX, Yu J, Kou SQ, Lindqvist PA. Effects of high temperatures on dynamic rockfracture. International Journal of Rock Mechanics and Mining Sciences2001;38(2):211e25.

Zhang ZX. Blast-induced dynamic rock fracture in the surfaces of tunnels. Inter-national Journal of Rock Mechanics and Mining Sciences 2014c;71:217e23.

Zhang ZX. Controlling vibrations caused by underground blasts in LKAB Malm-berget mine. Blasting and Fragmentation 2012;6:63e72.

Zhang ZX. Effect of double-primer placement on rock fracture and ore recovery.International Journal of Rock Mechanics and Mining Sciences 2014a;71:208e16.

Zhang ZX. Impact of blasting on resource recovery, mining profit, safety, and theenvironment. Blasting and Fragmentation 2014b;8:101e12.

Zhang ZX. Reducing eyebrow break caused by rock blasting in Malmberget mine.Blasting and Fragmentation 2011;5:1e10.

Zhang ZX. Rock fracture and blasting: theory and applications. Oxford: Elsevier/Butterworth-Heinemann; 2016.

Zong-Xian Zhang is currently Professor of Rock Mechanicsat the University Center in Svalbard (UNIS), Norway. Heobtained his BS degree from Xi’an University of Architec-ture and Technology, China in 1982; M.Sc. degree from theUniversity of Science and Technology Beijing (USTB), Chinain 1986; and Ph.D. degree from the Luleå University ofTechnology (LTU), Sweden in 2001. From 1982 to 1983 hedid research at Northwestern Institute of Mining andMetallurgical Technology, Baiying, China; from 1986 to1997 he worked at the USTB as Research Assistant (1986e1988), Lecturer (1988e1992) and Associate Professor(1992e1997); from 2001 to 2002 he worked at the LTU asSenior Research Engineer; from 2002 to 2013 he joinedmining company LKAB as Senior Research Engineer; in

2013 he joined the UNIS as Associate Professor and from 2014 as Professor. Hisresearch covers rock drilling, rock fracture under different loading rates and varioustemperatures, rock excavation by boring machine, stress waves in rock, rock blasting,sublevel caving, vibration control, etc. His publications include 2 books and 70 articles.His new book is Rock Fracture and Blasting: Theory and Applications published byElsevier Science in 2016. By using stress wave, shock wave and rock fracture theories,he has successfully solved a number of problems and developed several methods inrock blasting, vibration control, and mining production.