31
1. INTRODUCTION TO K-2 & K-3 GRIDS 1.1 GRID DESCRIPTION 1.2 SAFETY-RELATED LOAD 1.3 ACCEPTANCE 2. OFFSITE POWER SYSTEMS 2.1 500kV Network 2.2 132kV Power System 2.3 LOAD FLOW STUDIES 3. AC POWER SYSTEMS 3.1 TYPE OF UNIT AUXILIARIES TO BE POWER SUPPLIED (GENERAL DESCRIPTION) 3.2 ELECTRICAL POWER SUPPLY FOR POWER STATION AUXILIARIES 3.3 DESCRIPTION OF THE 6.6KV DISTRIBUTION SWITCHBOARDS 3.4 380V SWITCHBOARD CONFIGURATION 3.5 ELECTRICAL POWER RESUPPLY DURING OUTAGE (ETR) 3.6 TRANSFER OF NORMAL ELECTRICAL POWER SUPPLIES AFTER FAULT DETECTION 3.7 EMERGENCY SUPPLY TO AUXILIARIES FROM ONSITE POWER SOURCES (DIESEL GENERATOR SETS) 3.8 TOTAL LOSS OF OFFSITE AND ONSITE ELECTRICAL POWER SUPPLIES ON A PLANT UNIT, RESUPPLY BY EMT AND EES SYSTEM 3.9 TESTS RELATIVE TO THE AC SYSTEMS 4. DC Power Supply Systems 4.1 CONFIGURATION AND OPERATION 4.2 SAFETY ANALYSIS OF DC POWER SYSTEM 5. Emergency Diesel Generator Set and Site Supplementary Power Supply Diesel Generator Set 5.1 THE SITE SUPPLEMENTARY POWER SUPPLY DIESEL GENERATOR SET (EMS) 5.2 INSTRUMENTATION, CONTROL AND PROTECTION RELATIVE TO EMERGENCY DIESEL GENERATOR SET 1

Final Report Npps

Embed Size (px)

Citation preview

Page 1: Final Report Npps

1. INTRODUCTION TO K-2 & K-3 GRIDS

1.1 GRID DESCRIPTION

1.2 SAFETY-RELATED LOAD

1.3 ACCEPTANCE

2. OFFSITE POWER SYSTEMS

2.1 500kV Network

2.2 132kV Power System

2.3 LOAD FLOW STUDIES

3. AC POWER SYSTEMS

3.1 TYPE OF UNIT AUXILIARIES TO BE POWER SUPPLIED (GENERAL DESCRIPTION)

3.2 ELECTRICAL POWER SUPPLY FOR POWER STATION AUXILIARIES

3.3 DESCRIPTION OF THE 6.6KV DISTRIBUTION SWITCHBOARDS

3.4 380V SWITCHBOARD CONFIGURATION

3.5 ELECTRICAL POWER RESUPPLY DURING OUTAGE (ETR)

3.6 TRANSFER OF NORMAL ELECTRICAL POWER SUPPLIES AFTER FAULT DETECTION

3.7 EMERGENCY SUPPLY TO AUXILIARIES FROM ONSITE POWER SOURCES (DIESEL GENERATOR SETS)

3.8 TOTAL LOSS OF OFFSITE AND ONSITE ELECTRICAL POWER SUPPLIES ON A PLANT UNIT, RESUPPLY BY EMT AND EES SYSTEM

3.9 TESTS RELATIVE TO THE AC SYSTEMS

4. DC Power Supply Systems

4.1 CONFIGURATION AND OPERATION

4.2 SAFETY ANALYSIS OF DC POWER SYSTEM

5. Emergency Diesel Generator Set and Site Supplementary Power

Supply Diesel Generator Set

5.1 THE SITE SUPPLEMENTARY POWER SUPPLY DIESEL GENERATOR SET (EMS)

5.2 INSTRUMENTATION, CONTROL AND PROTECTION RELATIVE TO EMERGENCY DIESEL GENERATOR SET

5.3 VITAL INSTRUMENTATION AND CONTROL POWER SUPPLY

1

Page 2: Final Report Npps

1.INTRODUCTION TO K-2 & K-3 GRIDS

2

Page 3: Final Report Npps

1.1 GRID DESCRIPTION

The new Karachi Nuclear Power Plant (K-2/K-3) will be constructed at site located

near K-1, in the southern coastal region of Pakistan on Arabian Sea.

The power plant is connected with two different power sources:

i. 500kV for the power transmission and normal plant startup or shutdown.

ii. 132kV for the auxiliary supplies of the auxiliaries necessary for shutdown and

safety.

These two plants will deliver the generated power to WAPDA system through a common

switchyard (for K-2 and K-3), connected to Matiari grid by two 500kV double circuit

transmission lines.

The following interconnection scheme has been proposed for reliable dispersal of power

from future coastal power projects (K-2 & K-3) to the National Grid System under normal

and single line contingency conditions:

i. Two 500kV HVAC D/C transmission lines, approx. 200 + 200 =400 km long, on

twin bundled Greeley conductor from K-2/K-3 power plants to Matiari;

ii. ±600 kV H\TDC bipole (2x 2000 MW capacity), approx. 1000 km long, on six

bundle Bitterroot conductor from Matiari to Lahore South with HVDC convertor

station on both ends.

It is important to highlight that the interconnection of 1200 MW imported coal plant, lying

in coastal area nearby, has been proposed in one of the four 500kV circuits from K-2/K-3

power plant to Matiari.

Gross and Net Capacity of proposed Coal Plants

The gross and net capacity of these projects is given as under:

i. Gaddani Imported Coal project (Gross Capacity: 5x1320 = 6600 MW & Net

Capacity: 5x1200 MW = 6000 MW);

ii. Bin Qasim Imported Coal Project (Gross Capacity: 1320 MW & Net Capacity:1200

MW);

iii. Jamshoro Coal fired project (Gross Capacity: 1320 MW & Net Capacity:

1200MW);

iv. Thar Coal project (Net Capacity: 1200 MW);

3

Page 4: Final Report Npps

v. Maximum generation of the existing thermal power plants at Hubco, Jamshoro,

Kotri, Uch- 1, Uch-2 and Guddu power plant in south;

vi. Wind power plants generation with total gross capacity of 1756 MW in the

southern part of the system. The wind power has been planned to be evacuated to

the 132kV and 220kV network underneath Jamshoro. 8.1.2 Onsite Power Supply

Three sources of offsite power are provided to supply preferred power to the onsite

Class 1E systems through 500kV switching station and 132kV auxiliary switching station.

The main features of the distribution network are as follows:

i. The generator circuit breaker connections between the generator and the main

transformer enables to cut off fault current.

ii. The auxiliaries for each Unit are divided into groups depending on their safety and

operational function, including consideration of all the different operational

situations and foreseeable abnormal situations.

iii. The two Units are electrically independent. In case of an accident, the faulty Unit

must be able to respond to the accident regardless of the condition of the other Unit.

For this reason, each Unit has two independent diesel generator sets.

1.2 SAFETY-RELATED LOAD

Power supplies to the auxiliaries are designed to meet requirement of Unit availability

and, more importantly, of nuclear safety. Nuclear safety depends upon various factors on

the electric supply conditions of certain auxillary systems of NSSS.

The design of the electric power system has following features.

i. Electric power sources

The electric sources include two offsite power sources separately routed from the

main grid with common routing near the power plant due to the geographical

arrangement. Two onsite sources consisting of 100% redundant diesel generator

sets.

ii. Electric power supplies

The electric power supply system consists of two identical trains. These trains are

independent and are normally supplied by one of the offsite sources (the second source

ensures redundancy) and are backed up by the onsite sources in the event of main grid

failure.

4

Page 5: Final Report Npps

1.3 ACCEPTANCE

Power supplies have been designed based on the following criteria:

- They comprise two physically independent systems (not necessarily separately

routed) to ensure that simultaneous failure is minimized.

- The 132kV auxiliary power source is supplied by substation nearby;

- The quality of both sources is such that the auxiliaries supplied can be operated

or be started as soon as they are transferred from one source to the other.

- One supply for each of the two safeguard trains;

- No interconnections between trains of separate Units;

- Each power train supplies the electrical auxiliaries of each independent train of

the redundant mechanical systems (physical separation), so that loss of one

train does not lead to a loss of functions.

References

[1] HAP 102-2004, Safety Code on Nuclear Power Plant Design

RCC-E Design and Construction Rules for Electrical Components of nuclear Island

2.OFFSITE POWER SYSTEMS

5

Page 6: Final Report Npps

The Nuclear power plants (K-2/K-3) will be connected with two independent offsite power

sources, one at 500kV and other at 132kV in National Transmission and Dispatch Company

(NTDC) and Karachi Electric Supply Corporation (KESC) System respectively.

Each Unit (K-2/K-3) will generate power at 24kV and this power will be stepped-up to

500kV by the Main Transformers (MTs) independently. The 500kV network will also

supply power for normal plant startup or shutdown.

The 132kV network will be used as a standby power supply source.

2.1 500kV Network

The power generated by the plants (K-2/K-3) will be delivered to NTDC System through a

500kV switchyard (common for K-2 and K-3), connected via two 500kV double circuit

transmission lines from K-2/K-3 to Matiari.

For dispersal of power from K-2/K-3, 3x500kV circuits to Matiari will be installed, which is

about 200 km from plant site and lx 500kV circuit for looping in and out on Bin Qasim

Power Project which is about 140 km from plant site will be installed. The 500kV

electrical system is classified as Non-Class 1 E System.

The 500kV system constitutes a preferred source (offsite) for supplying power to plants

auxiliaries including Class 1E loads. The system will supply electrical power for start up,

safe shut-down as well as operation of emergency systems and the engineered safety features,

in accordance with IEEE 765-2006 standard.

The 500kV transmission lines from Matiari and Bin Qasim Power Project, and the 132kV

system will be physically separate and independent from each other, and designed in such a

way that the probability of simultaneous faults in the offsite power supply circuits (500kV

and 132kV system), due to operating conditions, postulated accidents and atmospheric

conditions is reduced to minimum.

6

Page 7: Final Report Npps

The 500kV system will supply power for start-up, emergency reactor shut-down,

containment isolation, reactor core cooling, and containment and reactor heat removal and all

those services required for preventing significant release of radioactive material to the

environment in accordance with IEEE 765-2006 and GB/T 13177-2008 standard.

The 500kV system will be provided with the instrumentation necessary for the

indication and continuous monitoring of its operational status, to ensure that any change in

the system, which could impair its functions is detected by the operator in the control room

in accordance with IEEE 765-2006.

All the circuit breakers of the 500kV system will operate manually/automatically from the

grid control building of K-2/K-3.All the components of the 500kV system will be designed

and installed in accordance with the requirements of latest applicable IEEE/ANSI, IEC and

other applicable standards .The limiting conditions for operation (LCOs) will be met in

accordance with USNRC Regulatory Guide 1.93-2012.

2.2 132kV Power System

The 132kV power system will act as a standby offsite power source and provide power

to the required plant emergency loads for safe shut-down of the plant(s) in case of

unavailability of 500kV network and outage of main generator(s).

The 132kV power system is classified as Non Class-i E System .The system will be

designed to be available within a few seconds following a loss of coolant accident to assure

that the core cooling, containment integrity and other vital safety functions are maintained.

The 132kV system will be designed to facilitate the periodic inspection and testing of

important areas and features - such as wiring, insulation, connections and switchboards to

assess the continuity of the systems and the condition of their components in accordance

with 1 OCFR5O Appendix A, General Design Criteria No. 18.

The 132kV power system will have sufficient capacity to provide the required loads during

start-up and the normal operation of the plant .A 500kV switchyard will be constructed

with all the required auxiliaries for dispersal of power from Units K-2/K-3 to Matiari and

Bin Qasim Power Project as shown in Figure.

The criterion of operation is as under:

a) Voltage Limits: ±5% under normal and ±10% under contingency conditions.

b) Transmission: 100% under normal and N-i contingency line loading conditions

7

Page 8: Final Report Npps

2.3 LOAD FLOW STUDIES

2.3.1 Peak Load January 2021

Load flow study for the peak load of January 2021 under normal system condition has been

carried out with the induction of 2x 1100 MW, K-2 and K-3 nuclear power plants and is

attached as Exhibit #1. As per load flow study, the power flows on the circuits emanating

from K-2/K-3 plants and in their vicinity are as under:

Transmission Line Power Flow

K-2/K-3 - Matiari three 500kV S/C 3 x 755.7 MW

K-2/K-3 - Bin Qasim 500kV S/C 232.6 MW

Bin Qasim - Matiari 500kV S/C 967.4 MW

Matiari - Lahore-South ±600 kV HVDC bipole 2 x 1650 MW

Matiari - Jamshoro S/C 205.1 MW

Matiari - Moro S/C 523.4 MW

Matiari - Gadani D/C 2 x 175.8 MW

Gadani - Lahore-South ±600 kV HVDC bipole 2 x 1650 MW

Gadani - Faisalabad-West ±600 kV HVDC bipole 2 x 1650 MW

Jamshoro - Dadu (circuit #1) 522.2 MW

Jamshoro - Dadu (circuit #2) 579.5 MW

Dadu - Shikarpur (circuit #1) 358.1 MW

Dadu - Shikarpur (circuit #2) 396.0 MW

Lahore South - Lahore Old (circuit #1) 764.4 MW

Lahore South - Lahore Old (circuit #2) 1104.0 MW

Lahore South - Lahore North D/C 2 x 1118.4 MW

Lahore South - Gujranwala S/C 850.8 MW

Lahore South - Sahiwal S/C 377.0 MW

8

Page 9: Final Report Npps

2.3.2 Peak Load Aug/Sep 2021

Transmission Line Power Flow

K-2/K-3 NPPs - Matiari three 500kV S/C 3 x 755.8 MW

K-2/K-3 NPPs - Bin Qasim 500kV S/C 232.3 MW

Bin Qasim - Matiari 500kV S/C 967.2 MW

Matiari - Lahore-South ±600 kV HVDC bipole 2 x 1650 MW

Matiari - Jamshoro S/C 42.9 MW

Matiari - Moro S/C 554.2 MW

Matiari - Gadani D/C 2 x 241.7 MW

Gadani - Lahore-South ±600 kV HVDC bipole 2 x 1700 MW

Gadani - Faisalabad-West ±600 kV HVDC bipole 2 x 1700 MW

Jamshoro - Dadu (circuit #i)575.9 MW

Jamshoro - Dadu (circuit #2) 638.8 MW

Dadu - Shikarpur (circuit #i) 370.2 MW

Dadu - Shikarpur (circuit #2) 409.8 MW

Lahore South - Lahore Old (circuit #i) 788.4 MW

Lahore South - Lahore Old (circuit #2) i i38.4 MW

Lahore South - Lahore North D/C 2 x 875.5 MW

Lahore South - Gujranwala S/C 55i.5 MW

Lahore South - Sahiwal S/C 877.5 MW

9

Page 10: Final Report Npps

3. AC POWER SYSTEMS

3.1 TYPE OF UNIT AUXILIARIES TO BE POWER SUPPLIED (GENERAL

DESCRIPTION)

The power station auxiliaries are divided into four types:

a) The 'plant unit auxiliaries': those auxiliaries necessary for normal operation of the

plant unit. When the unit is shut down, the auxiliaries can be shut down. For

example: Reactor coolant pumps, Auxiliary equipment of the unit, circulating water

pumps, feed water pump, Condensate pump.

b) The 'permanent auxiliaries': Which are used more particularly during plant unit

shutdown, some are used during unit operation. For example: Compressed air

production and distribution system, Electrical equipment of the nuclear auxiliary,

Electrical equipment of the fuel building, Auxiliary steam distribution system,

Electrical equipment of the PX building

c) The 'emergency power-supplied auxiliaries': which are necessary from a nuclear

safety point of view and protect the important plant unit equipment, including the

safeguard auxiliaries and the safeguard important equipment auxiliaries. The

safeguard auxiliaries: Which can protect, limit and reduce the leakage of radioactive

materials to environment. For example: Reactor Coolant system, Containment Spray

system, Containment Cleanup system, Auxiliary Feed water system

d) The 'site common auxiliaries': Which are the general auxiliaries common to the two

plant units and have no relation to the electrical power generation as well as they

will not affect the unit operation.

3.2 ELECTRICAL POWER SUPPLY FOR POWER STATION AUXILIARIES

a) Power supply for the 'plant unit auxiliaries':

- When the unit is in normal operation, the auxiliaries are supplied from the

generator by the unit step down transformers;

- When the unit is shut down, the auxiliaries are supplied from the main offsite

power supply source by the unit step down transformers.

b) Power supply for the 'permanent auxiliaries':

10

Page 11: Final Report Npps

- In normal operation, the auxiliaries are supplied from the generator by the unit

step down transformers; when the unit shut down, the auxiliaries are supplied

from the main offsite power supply source by the main transformer and unit

step down transformers;

- When the unit step down transformers fail, it can be supplied from the auxiliary

power source by stand-by auxiliary transformers.

d) Power supply for the 'site common auxiliaries'

The electrical equipment which used to supply the electrical power to all the auxiliaries

mentioned above are designed and installed according as the rules in specialty.

The power station auxiliaries required for normal operation are supplied by 6 group 6.6kV

distribution switchboards: ESA, ESD, ESE and ESF for 'plant unit auxiliaries'; ESB and

ESC for 'permanent auxiliaries'.

The choice of incoming cables and breakers which connect with two unit step-down

transformers must ensure the power supply for any power station auxiliaries at the same time

in any operation.

The power supply changeover from unit step down transformers to stand-by auxiliary

transformers is a slow, sequential and automatic transfer mode. A 1.5 seconds time delay

allows for the magnetic motor flux to decay. The changeover usually occurs automatically

and it can be performed manually either from main control room (MCR) or remote shutdown

station (IRS).

When all of the offsite power sources fail, the EMA and EMB are fed by EDG sets. An under

voltage set at 0.8 Un (time-lagged 0.9s) has been detected on EMA and EMB's busbars is

one of the condition which initiates EDG sets start

3.3 DESCRIPTION OF THE 6.6KV DISTRIBUTION SWITCHBOARDS

The normal and emergency 6.6kV distribution switchboards are identical.

The circuit breaker cabinets/panels are fitted with circuit breakers which rated current is 31

50A, 1 600A or 1 250A. The contactor cabinets/panels feed the power to 6.6kV auxiliaries

which rated power less than 750kW (rated current less than 80A). All the fuses' rated current

is 250A of all fused contactors.

11

Page 12: Final Report Npps

- Train A switchboard: identified by an orange label, engraved in white;

- Train B switchboard: identified by a green label, engraved in

white.

All of the 6.6kV distribution switchboards are installed in Safety Buildings, train A

switchboards are installed on level 1 7.OOm of NL building, train B switchboards are installed

on level 1 7.50m of NR building. It is physically separated of two trains because of the

installation in different buildings.

The electrical rooms for these 6.6kV distribution switchboards are designed against water

ingress, flood, missiles and seismic events for the connection between transformers and

switchboards.

3.4 380V SWITCHBOARD CONFIGURATION

The 380V switchboards are fed by the 6.6kV/400V transformers. The 6.6kV/400V

transformer is fit together with 3 80V switchboards and fed by fused contactor outgoing

circuit of 6.6kV switchboard.

The 3 80V auxiliaries of the normal network are distributed between several functional

switchboards which are supplied from the 6.6kV switchboards.

380V distribution switchboards used for BOP are supplied by busbar ESH and ES!.

The rating of the switchboards and 6.6kV/400V transformers and the distribution

arrangement enable all the emergency power-supplied auxiliaries to be fed adequately

whatever the operating condition might be.

3.4.1 Nuclear Island 380V Switchboards

The 380V normal and safeguard switchboards used for Nuclear Island auxiliaries are

identical. The following table shows the switching devices used, with their relevant

protections:

12

Page 13: Final Report Npps

Type of equipment Protections

Contactors Thermal and fuse (or breaker)

Circuit breakers Magnetic and thermal

Reversible contactors Thermal and fuse (or breaker)

Each switchboard is fed via a dry type, 6.6kV/400V, 800kVA transformer with adjustable off

circuit taps at ± 2.5% .

3.4.2 Conventional Island 380V Switchboards

The switchboards are used for the turbine essential auxiliaries and the standby lighting for the

Conventional Island and Balance of Plant. The switchboards are used under emergency

conditions and are fed from Nuclear Island switchboard EMA (power train A).

The following table shows the switching devices used with their relevant protections.

Type of equipment Protections

Contactors (motors < 50 kW) Fuse (or breaker)and Thermal

Contactors (motors> 50 kW) Fuse (or breaker)and Thermal

• •

Each non-emergency power-supplied switchboard is fed via a dry type, 6.6kV/400V,

630kVA or 800kVA transformer with adjustable taps at ±2.5%.

3.5 ELECTRICAL POWER RESUPPLY DURING OUTAGE (ETR)

During 6.6kV or 380V switchboard's maintenance, the ETR system enables to reenergize

the 380V auxiliaries.

Description of the ETR system

- 380V AC equipment connected with EED

13

Page 14: Final Report Npps

- 380V AC equipment connected with ERA

- 110V DC equipment connected with EDG

- Uninterrupted 220V AC equipment conneted with ERI

3.6 TRANSFER OF NORMAL ELECTRICAL POWER SUPPLIES AFTER FAULT DETECTION

The detection of a network fault, as well as the actions taken by the turbo generator set

protections, leads to the following operating situations:

a) In case of mechanical faults or internal electrical faults of main generator, then

the main generator shut down, the generator circuit breaker trip. The ESA, ESD,

ESE, ESF can be supplied by main offsite power source through main

transformer;

b) The network faults cause the opening of the 500kV circuit breaker. When the

house loading operation has been successful, the ESA, ESD, ESE and ESF can be

supplied by main generator through generator circuit breaker and two unit

stepdown transformers;

The house loading is initiated by the detection of 'low rotate speed of reactor coolant pump',

when the voltage drops rapidly. However, when the reactor coolant pumps maintain their

speed, but the other motors might be tripped, the house loading order is initiated by a voltage

drop criterion.

The voltage must recover according to RCC-E (C 2133 B 'General Unit Auxiliary Restart), or

an emergency shutdown signal is given, which leads to a turbine trip and the opening of the

generator circuit breaker.

3.7 EMERGENCY SUPPLY TO AUXILIARIES FROM ONSITE POWER SOURCES (DIESEL

GENERATOR SETS)

Each of the two diesel generator sets providing internal emergency electrical power supply is

able to fulfill the following functions:

14

Page 15: Final Report Npps

(a) In case of a loss of the external power sources, to supply the emergency power-

supplied auxiliaries and enable a safe shutdown of the plant Unit without damage

to the equipment, for instance, to ensure the cooling of the reactor.

(b) In case of loss of the external power sources and with a simultaneous reactor

coolant accident (such as a loss of primary coolant), to supply without any time

limit for the reactor core emergency cooling.

For this reason, a load shedding and reloading program is provided to perform the following

functions:

The rating of the diesel generator set is based on the power balances occurring after three

types of accidents, all of them causing the switchover to the diesel generator set, and which

involve automatic shutdown of the plant Unit. The three types of accidents are:

a) Loss of voltage signal

b) Loss of voltage and safety injection signals.

c) Loss of voltage plus safety injection plus high-high pressure in the containment.

One diesel generator set supplies the 6.6kV EMA busbar; the other diesel generator set

supplies the 6.6kV EMB busbar. Both, EMA and EMB supply the safeguard auxiliaries.

These auxiliaries are systematically redundant. Stopping the diesel generator set is only

possible locally after resetting from the control room.

3.8 TOTAL LOSS OF OFFSITE AND ONSITE ELECTRICAL POWER SUPPLIES ON A PLANT

UNIT, RESUPPLY BY EMT AND EES SYSTEM

In case of total loss of offsite and onsite electrical power supplies on a plant Unit, different

means are provided.

For the short term, the EES system is used giving enough energy to the test pump and other

actuators necessary to keep the plant Unit on a safe condition.

For the long term and for the resupply of emergency-supplied switchboards the following

means are provided, in decreasing order of priority:

a) Resupply from the network;

b) Resupply from the plant Unit diesel generator sets;

c) Resupply from the site supplementary diesel generator set.

15

Page 16: Final Report Npps

The EES system is composed of two SBO diesel generator sets (800kw, EESO 1

OAP,EESO 11 AP) for per plant unit, one SBO diesel generator is standby for the other.

In the event of a simultaneous loss of voltage on the emergency power-supplied busbars

(EMA and EMB), EESO1OAP of this plant Unit starts up automatically and supplies the

hydrotest pump control cabinet (EESOO1AR) through EESO1OAR. Then the RIS test pump

automatically starts up and supplies water to the reactor coolant pump seals at the flowrate of 6

m3/h.

3.9 TESTS RELATIVE TO THE AC SYSTEMS

a) In-factory checking. Earthquake resistance capability

b) Checking and testing during commissioning

c) Checking and testing during operation

The general, practice is that the Class 1E items of equipment are not designed differently

from other items of equipment which have to perform a function connected to the process.

All these items of equipment are designed according to the technical specifications issued for

each type of electrical equipment and are relative to:

a) Motors (motor size, minimum accelerating voltage, motor starting torque, motor

insulation, temperature monitoring devices);

b) Motor valve actuators (motor size, minimum accelerating torque, coupling, motor

circulation);

c) 6.6kV power cables;

d) 1000 V power cables;

e) MV/LV distribution transformers.

3.9.1 ELECTRICAL POWER SUPPLY SAFETY ANALYSIS

The following analysis proves that the electrical power supply and distribution network

complies with all requirements relating to offsite power supplies and onsite AC power

supply:

16

Page 17: Final Report Npps

a) All permanent and emergency power supplied auxiliaries (for safety and safeguard

purposes) may be supplied from two external power

b) The electrical power is supplied by two, almost independent (500kV and 132kV)

networks via the plant switch-yard

c) The high-voltage, medium-voltage, and control supply network has been designed

so that it is possible to come back to the available source of supply despite the

downgraded condition of the network ;The following steps are taken to reduce the

probability of total loss of the electrical power supply sources as a consequence of

loss of power generated by the plant Unit, opening of the generator circuit

breaker ,loss of power coming from the offsite 500kV network house loading ,loss

of power supplied from onsite sources.

e) Each safeguard train is powered by the non-safety electrical distribution system

which has access to the main generator and two offsite networks.

f) In normal operation, there is no interconnections between the redundant safety

power trains of the same plant Unit;

g) Each power train supplies the electrical auxiliaries of the same independent train

of the redundant mechanical systems (physical separation), so that loss of one

power train does not lead to a loss of function;

h) Each busbar supplying a single train is provided with both offsite power supplied

and a separate onsite power supply;

i) The diesel generator sets are started automatically

j) Changeover of the emergency power-supplied auxiliaries from the offsite to the

onsite sources is automatic with loss of voltage on the busbars; the return to

normal power and subsequent diesel shutdown is manually controlled.

17

Page 18: Final Report Npps

4. DC Power Supply Systems

The DC power systems supply all the control and signal systems and the vital, permanent,

and classified 220V AC production, through DC/AC inverters (Figure 8.3-3).

Several independent DC systems are provided as follows:

a) The 220V DC network: ETU, which feeds the three inverters of system EAE;

b) The 110V DC networks:

EDA (train A), EDB (train B), EDG and EDP, feed in particular the control

circuits of contactors and circuit breakers and the EAG, EAH, EAF, EAP DC/AC

inverter.

c) Two 220V DC networks:

ETE (train A) and ETF (train B) which supply the valves, instrument and control

device relevant with passive safety system.

Train A safety related actuators' control are supplied by train A DC power and

Train B safety related actuators' control are supplied by train B DC power.

The turbine direct-current auxiliaries are fed by a specific 220V DC network

(ETC).

4.1 CONFIGURATION AND OPERATION

The physical identification color of train A is orange, train B is green, and the others are

colorless.

The independence criterion for DC system is following,

Each DC system includes:

a) One lead-acid battery;

b) One (for system EDP) or two battery chargers ensuring the battery charging and

the normal feeding of the consumers;

c) One distribution switchboard with incoming & outgoing circuit-breakers.

18

Page 19: Final Report Npps

Each distribution switchboard includes:

a) One protected busbar;

b) Incoming and outgoing breakers and switches;

c) Control and signal relaying systems.

The NI DC system relevant equipment are located in electrical rooms of electrical building

(LR) and safety building (SR) separately

Battery chargers, inverters, and switchboards are installed at level +8.50m of LR and SR

buildings, batteries are installed at level +4.80m of LR and SR buildings in order to shorten

distance with related switchboards so that reducing the voltage drop and possibility of fault

in cables.

4.2 SAFETY ANALYSIS OF DC POWER SYSTEM

The safety analysis of DC power system is following RCC-E 2005 C 1440.

a) The auxiliaries and their DC equipment are supplied by the busbars associated in

such a way that loss of electrical power on one train of auxiliaries does not affect

equipment on another train;

b) Each redundant DC power source consists of a battery and one or two battery

chargers and is connected to the same power train of emergency AC power supply

during normal operation;

c) The sizing criteria of DC power supply are also met. If the AC power supply to the

battery chargers is interrupted for one hour, the energy stored by the batteries is

sufficient to ensure adequate power to operate equipment and necessary

disconnecting devices, the 72h DC and UPS power system can ensure the need of

19

Page 20: Final Report Npps

5. Emergency Diesel Generator Set and Site

Supplementary Power Supply Diesel Generator Set

The diesel generator sets is provided with an engine and an alternator, and one alternator is driven by

one engine. Each generator set is fitted with an electronic speed regulation system.

Each cylinder is supplied by a separate fuel injection pump; failure of a single injection pump will

not cause shutdown of the diesel generator set.

Each generator is designed to be capable of withstanding the following faults:

a) Three-phase or two-phase short-circuits at the generator terminals due to an external fault.

b) Over speed operation

c) Over voltage

Ventilation of the diesel generator set room is designed so that the temperature of the room will not

exceed 49°C.

5.1 THE SITE SUPPLEMENTARY POWER SUPPLY DIESEL GENERATOR SET (EMS)

EMS system is consisting of site supplementary power supply diesel generator set, and it does not

perform the safety related function.

The site supplementary power supply diesel generator set shall be connected to the relevant

emergency distribution boards (EMA, EMB) system by EMT system.

The diesel generator sets for train A and train B are installed in two separate buildings:

a) One nearby electrical building (power train A, EMP);

b) Other nearby fuel building (power train B, EMQ).

The site supplementary power supply diesel generator set and its auxiliary systems concerning fuel

oil, cooling, starting, lubrication, are installed in another separate buildings on site.

20

Page 21: Final Report Npps

The general characteristic of diesel engine and generator for the site supplementary power are to be

determined .The diesel buildings are not designed to withstand plane crashes due to the small target

area of these buildings and the shadowing effect of other buildings, and thus a low probability of

occurrence

5.2 INSTRUMENTATION, CONTROL AND PROTECTION RELATIVE TO EMERGENCY DIESEL

GENERATOR SET

To monitor the operability of EDG, the instrumentation devices on local panel include:

voltmeter ,ampere meter ,frequency ,meter ,wattmeter ,varmeter ,excitation voltmeter and excitation

ammeter

In emergency situation, diesel generator may actuate on

a) Over speed (automatic);

b) Voltage loss (automatic);

c) Emergence manual shutdown.

Excluding emergency operation, tripping of the diesel generating set occurs for any of the following:

Electrical protection may actuate i-e differential, overload, overcurrent,loss of field, reverse power,

overvoltage , undervoltage ,over frequency ,under frequency,stator earth fault ,generator winding

temperature ,over speed ,excitation fault and manual emergency.

The engines protection may damage i-e Cooling water jacket high-high temperature ,Lube oil high

temperature ,Exhaust gas high/low temperature ,Low level of heating water jackets in the

system ,Low level of main fuel storage tank and a daily tank ,Emergency air valve closed

5.3 VITAL INSTRUMENTATION AND CONTROL POWER SUPPLY

a) A charger fed by a 380V AC emergency-supplied switchboard

b) An inverters of 10 kVA for each power supply;

c) A static transfer switch, loads will be transferred to bypass regulating transformer while

inverter loses its AC power;

d) An AC switchboard;

21

Page 22: Final Report Npps

22