Hot Crude Oil Storage.xls

Embed Size (px)

Citation preview

  • 7/22/2019 Hot Crude Oil Storage.xls

    1/13

    Art Montemayor Crude Oil Project August 12, 2002

    Rev: 0

    Summary of relief calculations for T-400 & T-405

    1. The Rainstorm with subsequent vacuum is the controlling case for relief.Since both tanks operate without Conservation Valves and with Open Vents, the vacuum demandfor the controlling case is more than sufficient for the worst pressure case (the Fire Case);

    2. The amount of open vent capacity required for the worst case (rainstorm) is to be handled byinstalling four (4) - 12" Open Vents on the roof of each tank; these vents should have a Flamearrestor under a 180o return. The vent outlet should have a Stainless Steel screen to keep outforeign objects and to resist corrosion.

    3. The flame arrestors should have a nominal capacity for 2.55 MM scfh each such that they do notcreate a pressure drop in excess of what the tank design vacuum can withstand at the existingatmospheric pressure.

    4. The four open vents should be located at equal 90o quadrant locations on the roof in order to allowequal distribution of created pressure or vacuum conditions.

    Page 1 of 13FileName: 161245513.xls.ms_office

    WorkSheet: Summary of Results

  • 7/22/2019 Hot Crude Oil Storage.xls

    2/13

    Art Montemayor Oil Recovery November 24, 2001

    Rev: 2(06/11/02)

    Stored Material

    Flash PointoF 350 (Estim.) in WC 55.36

    Boiling PointoF 360 (Estim.) oz/in

    20.50

    Latent Heat vap. Btu/lb 144.0 (Hexane) ft 50.0Mol. Wt. 274.0 ft 30.0

    Inflows

    Flow, GPM

    Value Units Note 1

    P-160/-170 -106C 100 PSIG 1,200

    P-165/-175 -107C 50 PSIG 1,200

    2,400

    or :

    or : 100 psi

    or :

    2,400

    1,500

    Outflows (See Note 1)

    Capacitygpm 2,500

    gpm 2,500

    gpm

    Total 5,000

    Notes:

    Tag

    10"-PL-138-A

    MAWP

    Max Vacuum

    DiameterMax fill

    Tag

    T - 400 & T - 405

    Transfer to Storage

    Transfer to Storage 10"-PL-055-A

    Total Inflows, gpm

    Tank Padding Calculation Sheet

    Attachment 1

    P &ID #

    115-XXX-

    01

    Max HeadService Line No.

    Data Entry

    Crude Oil Tank

    2) The above pump capacities are estimated due to a lack of pump performance curves.

    Sonic Flow in Pipe

    Pipe Flow at Maximum DP

    Other (Attach Method)

    Use for Relief (gpm)

    Normal Maximum (gpm)

    P-410

    P-420

    1) Pumps are at zero head flowrate (Max. gpm), and Control Valves have the max. trim size (Max. C v)

    Page 2 of 13Electronic FileName: 161245513.xls.ms_office

    WorkSheet: Data Entry

  • 7/22/2019 Hot Crude Oil Storage.xls

    3/13

    Art Montemayor Oil Recovery November 24, 2001

    Rev: 4(04/20/08)

    Flash PointoF 350 (Estim.) in. WC 55.4

    Boiling PointoF 360 (Estim.) oz/in

    20.5

    Latent Heat Vap. Btu/lb 144 (Hexane) ft 50.0

    Molecular Wt. 274 ft 30.0

    gal 440,620ft

    23,927.0

    12,861

    20,578 Fire BTU/hr-ft2

    4,735

    SCFH 690,425

    40,104

    SCFH 0

    SCFH 58,642

    Out SCFH 6,295

    In SCFH 10,491 MM Scfh 10.2

    N.A. in WC

    Required SCFH NAselected SCFH NA

    Fail Open SCFH 0

    Required SCFH N. A.

    Selected SCFH N. A. Regulator w/ " trim.

    Valve Fail Open SCFH N. A.

    Inflow (Pressure) SCFH 85,515

    Fire (Pressure) SCFH 690,425

    Outflow (Vacuum) SCFH 10,232,913

    1)

    2)

    3)

    4)

    MAWP

    Diameter

    This flowrate assumes the valve's Cv determines the capacity

    Consider this only if the tank vents to a vacuum source or header

    Normal Operation

    Outflows, SCFH

    Blow-Through From Upstream

    Refer to API-2000; 5th

    Ed., April 1998; Table 2A for thermal breathing requirements.

    Tank Pressure & Vacuum ProtectionDesign Sheet - Based on Data Entry Sheet

    Notes:

    Required Capacity

    Stored Material:

    Wetted Area

    Max fill Height

    Max fill Volumenflows, SCFH (see API 2000; table 1A)

    Attachment 2

    Pool Fire Case

    T - 400 & T - 405Crude Oil

    Max Vacuum

    Tank:

    Rain Storm CoolingVacuum (Note 3)

    Relief Scenario Unit Heat Input

    Flashing Feed (Note 4)Thermal Breathing, Note 1

    Pump Inflow + Out Breathing + Flashing Feed

    Consider this when using emission vapor control system

    Pumps' outflows + in Breathing + condensed vapor during rainstorm

    Blanket Gas Valve set at 7" WC

    With vent system Pressure Drop of 9 in WC

    Vent Valve set at

    sum of outflows + in Breathing + fail open vent valve

    Pressure and Vacuum Relief Cases

    Fisher Model

    Normal max inflow + out breathing

    These two Crude Oil Storage Tanks (T-400 & T-405) should be equipped with 4- 12" roof nozzles located

    at a convenient location. The nozzle should have a Flame arrestor sized for 2,500,000 Scfh and a 180o

    return with a protective stainless steel screen.

    Fire Case calculations are according to API Standard 2000, 5th

    Ed., Section 4.3.3.2.1

    Internal vapor condensation during a Tropical rainstorm is a special case detailed in this worksheet.

    The Hot Crude Oil introduced into these tanks goes through a Vapor Separator where some flash vapor is

    removed and routed to vapor disposal; however some additional vapor remains in equilibrium with the

    crude and flashes inside the main tank that is vented directly to the atmosphere.

    Page 3 of 13

    Electronic FileName: 161245513.xls.ms_office

    WorkSheet: Design Basis

  • 7/22/2019 Hot Crude Oil Storage.xls

    4/13

    Art Montemayor Oil Recovery November 24, 2001

    Rev: 2(06/11/02)

    TANK:

    in. W.C. Rated at in. W.C.

    Required SCFH

    Selected Size SCFH (Note 2) Total 0

    oz/inRequired SCFH 10,232,913

    Selected Capacity SCFH (Note 2) Total 0

    Set at in. W.C. Rated at in. WC

    Required SCFH 0

    Selected Size SCFH N. A. Total

    Set at oz/in Rated at in. WC

    Required SCFH 424,263

    Selected Size SCFH N. A. Total

    Tag Size, in Cv

    N. A. 2 66.7

    N. A.

    N. A.

    N. A.

    N. A.

    1)

    2)

    3)

    section 4.2.5.14, "Uninsulated Tanks"

    Attachment 3

    Fisher 1190

    zero (if Con vent has capacity) or Worst case w/o Con Vent

    each from catalog; total number

    Manufacturer Model

    T - 400 & T - 405

    Conservation Vent

    Blanket Gas Regulator

    Nitrogen Valve

    Conservation Vent

    Emergency Pressure Relief, Note 1

    These tanks are designed taking into consideration the recommendations of API Standards 2000, 5th Ed.;

    Selected Equipment:

    Emergency Vacuum Relief

    zero (if Con vent has capacity) or Worst case w/o Con Vent

    each from catalog; total number

    Emergency Vent

    Storage Tank Pressure/Vacuum Equipment Specifications

    Vacuum Side set at 0.5 oz/in2 Vacuum, rated at

    Pressure side set at

    zero (if tank has Vent Valve and Emergency vent) or worst case

    each from catalog; total number

    Outflow Case

    each from catalog; total number

    A Conservation vent (PVSV) is not recommended for these two crude oil storage tanks.

    For technical calculations and process analysis determining the type and degree of tank pressure and vacuum

    protection, refer to included worksheets "Condensing Vapor".

    A Fire hatch or Emergency Vent is not required since the open 12" vents on this tank have sufficient capacityfor the controlling case (vacuum) and this is sufficiently large for the worst pressure case also.

    Notes:

    Emergency Vacuum

    Page 4 of 13

    Electronic FileName: 161245513.xls.ms_office

    WorkSheet: Requisition Info

  • 7/22/2019 Hot Crude Oil Storage.xls

    5/13

    Art Montemayor Oil Recovery November 24, 2001

    Rev: 4(04/20/08)

    Storage Tank:

    Fluid:

    1 Liquid movement in 20,578 20,578 N.A. N.A.

    2 Liquid movement out N.A. N.A. N.A. 40,104 N.A.

    3 Out Breathing (Vapor out) 6,295 N.A. N.A. N.A.

    4 In Breathing (Vapor In) 10,491 N.A. 10,491 N.A.

    5 Fire Exposure 690,425 N.A. N.A. N.A.

    6 Pressure Transfer Blow-through N.A. N.A. N.A. N.A. N.A.

    7 Blanket Gas Failure - Blocked N.A. N.A. N.A. N.A.

    8 Blanket Gas Failure - Open N. A. N. A. N.A. N.A. N.A.

    9 Steam Coil Rupture N.A. N.A. N.A. N.A. N.A.

    10 Vent System Failure - Blocked N.A. N.A. N.A. N.A. N.A.

    11 Chemical Reaction N.A. N.A. N.A. N.A. N.A.12 Flashing Feed (Note 2) N.A.

    13 Steam-Out N.A. N.A. N.A. N.A. 13,566,429

    26,873 700,916 50,595 13,566,429 0

    876,145

    63,244

    Air density = 0.0807 lb/ft3 at 32 oF and 14.696 psiaBlanket gas density = 0.33425 lb/ft

    3at 109

    oF and 79.7 psia

    Blanket gas Molecular Weight = 25.237

    Blanket gas density = 0.083877 lb/ft3

    at 109oF and 20 psia

    Blanket gas specific gravity = 1.0394 lb/ft3

    at 109oF and 20 psia

    case because an open, atmospheric vent is employed which is designed for the controlling vacuum case.

    Note 2: Although the crude oil feed is flashing into the tank, this case is not a credible pressure

    steaming out the tank. The open vents capacity plus the roof manway should suffice for the steam out.

    cfh (Includes 25% contingency)

    cfh (Includes 25% contingency)

    Note 1: The steam-out case is calculated in this Workbook; relief protection is recommended

    Controlling Vacuum Case Design Capacity =

    T - 400 & T - 405

    Attachment 4

    Case Contributions:

    in the form of a properly sized nozzle (or roof-located manway) that is required to be left open while

    Other

    Vacuum ScenarioPressure Scenario

    Steam-Out

    (Note 1)

    OutflowInflow Fire Case

    Controlling Pressure Case Design Capacity =

    Crude Oil

    Total Volumetric Flow:

    Safety Scenario Relief Rates, CFH

    Liquid

    Overflow

    Page 5 of 13

    Electronic FileName: 161245513.xls.ms_office

    WorkSheet: Case Summaries

  • 7/22/2019 Hot Crude Oil Storage.xls

    6/13

    Art Montemayor Storage Tank Pressure Relief

    Over-Pressurization Scenario Contributions

    November 22, 2001

    Rev: 2(06/11/2002)

    1 2 3 4 5 6 7 8 9 10 11 12

    No. Event Press. Vacuum Press. Press. Press. Press. Press. Press. Press. Press. Press. Press.

    1 Liquid Movement in and Breathing Out Yes No No No No Note 2 Note 2 No Note 2 No No No

    2 Liquid Movement Out and Breathing In No Yes No No No Note 2 Note 2 No Note 2 No No No

    3 Fire Exposure No No Yes No No No No No No No No No

    4 Pressure Transfer Blow Through No No No No No No No No No No No No

    5 Blanket Gas Regulator Failure No No No No No No No No No No No No6 Failure or Loss of Control - Heat Transfer Devices No No No No No No No No No No No No

    7 Failure of Internal Heating / Cooling Coils No No No No No No No No No No No No

    8 Failure of Vent Treatment System No No Note 1 No No No No No No No No No

    9 Failure of Utilities (Steam, Nitrogen, air, CWS) No No No No No No No No No No No No

    10 Chemical Reaction No No Note 3 No No Note 3 Note 3 No Note 3 Note 3 No Note 3

    11 Liquid Overfill No No No No No No No No No No Yes No

    12 Flashing Liquid Feed Yes No No No No No No No No No No Yes

    13 Steam Out (Note 4) N. A. N. A. N. A. N. A. N. A. N. A. N. A. N. A. N. A. N. A. N. A. N. A.

    1)

    2)

    3)

    4)

    omments on scenarios for Tank T - 400 & T - 405:

    Steam Out is a special case that is handled and calculated independently in this Workbook; a properly sized nozzle is usually specified to be left open for this case.

    Consider Event when calculating CASE:

    Consider this event if the fluids involved normally, or potentially, can cause a reaction

    This event is when the vent valve feeding tank vapors to a vapor treatment system fails closed.

    Either or both liquid movement events could be applicable dep

    otes:

    Event No. 11 is not considered a credible scenario since the tank has been designed according to API Standard 2000, 5th Ed.; article 4.2.5.10

    Event No. 10 is not considered a credible scenario since the compounds and fluids with potential for introduction into the tank do not react with each other or polimerize.

    Event No. 4 is not considered a credible scenario since all liquid transfer into tank is done by pumping, not pressure transfer.

    Event No. 6 is not considered a credible scenario since this tank does not incorporate a heat transfer device or internal coil.

    Event No. 7 is not considered a credible scenario since this tank does not incorporate an internal coil that could rupture.

    Event No. 8 is not considered a credible scenario since this tank does not incorporate a Vapor Treating System.

    Page 6 of 13Electronic FileName: 161245513.xls.ms_office

    WorkSheet: OverPressure Scenarios

  • 7/22/2019 Hot Crude Oil Storage.xls

    7/13

    Art Montemayor Storage Tank Pressure Relief May 14, 2002

    Rev: 2(06/11/2002)

    Event Inflow / Outflow

    Liquid Movement in and Breathing Out Inflow

    Liquid Movement Out and Breathing In Outf low

    Exposure to Pool Fire with subsequent

    tank contents' vaporization

    Inflow

    Pressure Transfer Blow-through Inflow

    Inert Gas Pad/Purge Regulator Failure Inf low

    Failure or loss of Control Heat Transfer

    Devices

    Either or both

    Failure of Internal Heating/Cooling Coils Either or both

    Failure of Vent Treatment System Outflow

    Failure of Utilities (Air, Steam, Cooling

    Water, N2, etc.)

    Either or both

    Chemical Reaction Inflow

    Liquid Overfill Inflow

    Flashing Liquid Inflow

    Determination

    for use when calculati

    Page 7 of 13FileName: 161245513.xls.ms_office

    WorkSheet: Inflow-Outflow

  • 7/22/2019 Hot Crude Oil Storage.xls

    8/13

    Art Montemayor Storage Tank Pressure Relief May 14, 2002

    Rev: 2(06/11/2002)

    Calculate Inflow or Outflow by:

    termine the Maximum flow, at zero head, for each pump that can be lined up to the tank. For sources

    t are not pump driven, calculate the maximum flow for the flow limiting element. For Control valves,

    e the largest trim for the valve body and add the capacity of any bypass valves. The total inflow is the

    m from all of these sources. The total inflow can be reduced if engineering judgment indicates that it is

    kely that all of the sources will be feeding into the tank simultaneously. The total inflow can also be

    uced if the pressure drop in the line(s) between the inlet manifold(s) and tank exceeds the available

    ssure drop. The available pressure drop is the highest pressure sources dead head pressure.

    termine the Maximum flow, at zero head, for each pump that can take suction from the tank. The

    tflow is the sum of all of these; even installed spare(s).

    not consider inflow for fire case since there is ample time to shutoff the inflow before the fire case fully

    velops. (see also API-2000 3.4.3.1.4) Do consider the failure of the blanketing gas regulator (if

    plicable) since these instuments typically fail open and the heat from a fi re could cause it to fail.

    e Case 1

    e Case 1

    e Case 1 if the failure can cause the tank to vent. Use Case 2 if the failure can create a vacuum in the

    k.

    e Case 1 if the failure can cause the tank to vent. Use Case 2 if the failure can create a vacuum in the

    k.

    e case 2

    e Case 1 if the failure can cause the tank to vent. Use Case 2 if the failure can create a vacuum in the

    k.

    e Case 1

    Project Tanks will be designed according to API Standard 2000, 5th Ed.; article 4.2.5.10

    en introducing flashing liquids, always include the flashed vapor in the total relief capacity.

    Inflows and Outflows for Storage Tanks

    Normal and Emergency Venting Requirements

    Page 8 of 13FileName: 161245513.xls.ms_office

    WorkSheet: Inflow-Outflow

  • 7/22/2019 Hot Crude Oil Storage.xls

    9/13

    Art Montemayor Project

    Crude Oil Storage Vacuum Relief

    June 03, 2001

    Rev: 0

    50.00 feet

    32.00 feet

    62,832 Ft3

    47,124 Ft3

    = 9,817 Ft3

    56,941 Ft3

    Assume that the blanket vapor regulator fails in the closed position and that the flashing feed continues to enter

    the Crude Oil storage tank, effectively sweeping out the non-condensibles through the PVSV pressure side.

    Under these conditions, it is feasible for the vapor space to essentially become water vapor ("steam") rich

    in composition after a prolonged period of saturated Crude Oil entering the tank proper and flashing.

    It is at this critical moment that a credible tropical rainstorm could develop and drench the area for hours.

    From the process simulation run of Nov 27, 2001 the Crude Oil Flash vapor produced in the storage tank due to

    adiabatic expansion is:

    208oF

    14.7 psia

    0.040864 Lb/ft3

    1.407 MM Scfd = 1.773 MM Acfd

    19.788

    3,058 Lb/hr

    Mole %

    92.96

    7.04

    The storage tank surface area capable of cooling-condensing the vapors when the tank is 25% full is:

    3,770 ft2

    1,991 ft2

    5,760 ft2

    In accordance with API Standard 2000, paragraph 4.2.5.14 - "Uninsulated Tanks":

    Tank's Water Vapor volume @ 25% full =

    Cylindrical tank section with fuel gas blanket =

    Conical roof volume with fuel gas blanket = (3.1416 r2) (h) / 3

    out by their respective booster pumps and a sudden rainstorm develops.

    of the water vapor in the vapor space which will can be at a temperature between 180oF to 220

    oF.

    The concern for this scenario occuring is due to the partial vacuum hazard created by the condensation

    is equal to the rate of condensed water vapor during the rainstorm due to heat transfer through the tank's roof

    Tank Height =

    Since the Crude Oil Storage is being fed with a flashing crude oil feed that is adding water vapor ,

    there is a possibility that a partial vacuum can be created as the continuing tanks' operation is being pumped

    The storage tanks could normally be filled with a minimum of approximately 25% of the total available

    tank height.

    Total (100%) Tank cylindrical Volume =

    This situation would be in the worse circumstance if the tank were almost empty at the moment the rain

    commences. The rate of atmospheric air required to maintain the tank at the minimum design pressure

    Pressure

    Cone top roof surface area =

    Total Surface Area =

    Vapor Flowrate

    Total Molecular Weight

    Total Flowrate

    Crude Oil Tank Diameter =

    Tanks T-400 & T-405

    Non-condensables

    Cylindrical surface area =

    and wall in contact with the internal vapor.

    Vapor Density

    Temperature

    Total Stream Composition:

    Water

    Page 9 of 13

    FileName: 161245513.xls.ms_office

    WorkSheet: Condensing Vapor

  • 7/22/2019 Hot Crude Oil Storage.xls

    10/13

    Art Montemayor Project

    Crude Oil Storage Vacuum Relief

    June 03, 2001

    Rev: 0

    Where,

    Q =

    U =

    A =

    DT =

    500

    Q = 368,666,833 Btu/hr

    379,951 lb/hr

    = 190 ton/hr

    26.799 ft3/lb

    ft3/hr

    = 244.4 MM Acfd

    = 169,705 ft3/min

    = 2,828 ft3/sec

    Although the above scenario is agravated by the Crude Oil pumped out by the booster pumps at a maximum

    rate of 40,100 cfh (approximately 1.0 MM cfd) this effect will be short-lived due to the fact that as the tank

    develops a vacuum condition, the booster pumps will loose their prime and cease to pump. Additionally, the

    amount of vacuum contributed by the pump-out in this scenario only contributes approximately 0.5% of thetotal vacuum rate.

    Where,

    vs =

    k = 1.40

    g =

    P' =

    V = 13.10

    Therefore, vs = 1,118 ft/sec

    2.53 ft

    3.25

    Sonic velocity of air, ft/sec

    The maximum possible velocity in the Tank's vacuum relief nozzle is:

    Specific volume of steam at 14.696 psia =

    mean temperature difference between both fluids,oF

    For a condensing system, an overall heat transfer coefficient of 250 to 700 Btu/hr-ft2-oF is considered

    as very credible. The actual temperature of the rain water could be an estimated 60oF.

    If an overall condensing heat transfer coefficient of

    For a heat transfer rate heat equation, use:

    Heat transfer rate, Btu/hr

    Overall heat transfer coefficient, Btu/hr-ft2-oF

    Heat transfer surface, ft2

    Btu/hr-ft2-oF is used,

    There is more than ample cooling rain capability to easily condense all of the incoming 3,000 lb/hr of flash vapor

    (1.77 MM Acfd) containing only 7 % volume of non-condensibles.

    Vacuum rate inside tank = 10,182,317

    Steam condensation rate =

    Required nozzle area for sonic velocity =

    Quantity of 12" ID open vents required =

    Ratio of specific heats for air =

    acceleration of gravity, 32.2 ft/sec2

    Absolute pressure, psia

    Specific volume of air, ft3/lb =

    TAUQ D=

    VPgkTRgkvs == 144

    Page 10 of 13

    FileName: 161245513.xls.ms_office

    WorkSheet: Condensing Vapor

  • 7/22/2019 Hot Crude Oil Storage.xls

    11/13

    Art Montemayor Oil Recovery January 26, 2002

    Rev: 0

    In order to have safe vessel entry for inspection and repairs of the tank, OSHA requires it be clean of

    chemicals. Tanks are normally subjected to cleaning with live steam for this purpose and this procedure

    can introduce the hazard of sudden, uncontrolled vacuum developed due to steam condensation during a

    rain storm.

    Diameter = 50 ft

    Height = 32 ft

    5,027 ft2

    1,991 ft2

    7,017 ft2

    Where,

    Q =

    U =

    A =

    DT =

    as very credible. A tropical rain storm at any given time is considered as a design criteria that should be

    500

    Q = 5.E+08 Btu/hr

    506,229 lb/hr

    = 253 ton/hr

    26.799 ft /lb

    ft3/hr

    = 226,107 ft3/min

    = 3,768 ft3/sec

    Where,

    vs =

    k = 1.40

    g =

    P' =V = 13.10

    Therefore, vs = 1,118 ft/sec

    3.37 ft

    32 inch diameter

    Cylindrical surface area =

    Cone top roof surface area =

    Total Surface Area =

    For a heat transfer rate heat equation, use:

    instantaneous cloud burst in the rainy season. The actual rain water temperature could be an estimated 60oF.

    strictly observed because of historical, empirical meteorological data. It is very possible to suffer an

    Ratio of specific heats for air =

    Steam condensation rate =

    Specific volume of steam at 14.696 psia =

    Volumetric displacement inside tank =

    Heat transfer rate, Btu/hr

    Overall heat transfer coefficient, Btu/hr-ft2-oF

    mean temperature difference between both fluids,oF

    For a condensing system, an overall heat transfer coefficient of 250 to 700 Btu/hr-ft2-oF is considered

    Heat transfer surface, ft2

    If an overall condensing heat transfer coefficient of

    Required nozzle area for sonic velocity =

    This calculation is for vacuum protection of Crude Oil Storage tanks, T-400 & T-405:

    The maximum possible velocity in the Tank's vacuum relief nozzle is:

    A nozzle to allow safe operation =

    acceleration of gravity, 32.2 ft/sec2

    Absolute pressure, psiaSpecific volume of air, ft

    3/lb =

    Btu/hr-ft2-oF is used,

    13,566,429

    Sonic velocity of air, ft/sec

    TAUQ D=

    VPgkTRgkvs == 144

    Page 11 of 13FileName: 161245513.xls.ms_office

    WorkSheet: Steam Out

  • 7/22/2019 Hot Crude Oil Storage.xls

    12/13

    TANKS

    CLIENT: DOC No 1

    JOB: Revision: B of : 1

    TANK DATA SHEET

    TAG No T-400 Oil Shipping TankGENERAL

    SERVICE: Crude Oil VOLUME: Bbls = 470,014 Gallons

    TYPE: EMPTY WEIGHT:

    INSULATION: Personnel Protection FILLED WITH WATER:

    EXTERNAL PAINT: Per Spec 4001 OPERATING WEIGHT:

    INTERNAL PAINT: Per Spec 4001 DIMENSIONS:

    TRACING: None Diameter 50 feet

    Height 32 feet

    REF. P&ID:

    DESIGN DATACODE: API 650 Latest Edition

    RX: Per API 650

    HEAT TREATMENT: Per API 650

    DESIGN PRESSURE INT.:

    CORROSION: 0.125"

    AMBIENT TEMP 32-120F

    MATERIALSSHELL: A-36

    BOTTOM: A-36

    ROOF: A-36

    PIPES: A53/A106 SMLS

    FORGED: A-105

    STUDS: A193 Gr B7 Fluorocarbon Coated

    NUTS: A194 2H Hvy Hex Nuts Fluorocarbon Coat'd

    GASKETS: Flexitallic CG or equal

    SUPPORTS:

    FITTINGSLADDER: Per API 650 Tables 3-20 and 3-21 LEVEL GAGE

    ROOF PROTECTION Per API 650 INSPECTION NOZZLE

    CLEANOUT EMERGENCY NOZZLE

    NOZZLES

    Mark QTY SIZE TYPE Series Locate SERVICEA 1 8" Thief Hatch

    B 1 2" RF 150 Gas Blanket

    C 1 RF 150 PVSV + Flame Arrestor (Contractor to Size)

    D 1 10" RF 150 Inlet

    E 1 2" RF LSH

    F 1 2" RF 150 TIT

    G 1 2" RF 150 LIT

    H 1 2" RF 150 LSL

    I 1 12" RF 150 Outlet

    J 1 4" RF 150 Drain

    K 8 2" RF 150 Sample points

    M 2 2" RF 150 Level Gauge

    N 1 6" RF 150 Foam

    MH 1 36"x36" Flush Manway

    MH 3 24" FF Manway

    Fill Rate 45,000 BPD

    Empty Rate 45,000 BPD

    NOTES

    Platform to be provided as follows: Minimum 4' X 4' Grating Platform at Thief Hatch connected by walkway to

    stairs. Construction per API 650 Table 3-19

    All nozzle orientations to be defined later

    150

    11,191

    Sheet:

    BASIC DATA SHEET

    Fixed Cone Roof

    AO115-EPF-01-112A1

    2 PSIG @ 240 F

    MHMHMH

    M

    MH

    MH

    A

    ACB

    D

    E

    F

    G

    H

    N

    I

    J

    K

    M

    7/31/2013

  • 7/22/2019 Hot Crude Oil Storage.xls

    13/13

    TANKS

    CLIENT:DOC No

    1JOB: Revision:B of : 1

    TANK DATA SHEET

    TAG No T-405 Oil Shipping TankGENERAL

    SERVICE: Crude Oil Bbls = 470,014 Gallons

    TYPE: Fixed Cone Roof EMPTY WEIGHT:

    INSULATION: Personnel Protection FILLED WITH WATER:

    EXTERNAL PAINT: Per Spec 4001 OPERATING WEIGHT:

    INTERNAL PAINT: Per Spec 4001 DIMENSIONS:

    TRACING: None Diameter 50

    Height 32

    REF. P&ID:

    DESIGN DATACODE: API 650 Latest Edition

    RX: Per API 650

    HEAT TREATMENT: Per API 650

    DESIGN PRESSURE INT.:

    CORROSION: 0.125"

    AMBIENT TEMP 32-120F

    MATERIALSSHELL: A-36

    BOTTOM: A-36

    ROOF: A-36

    PIPES: A53/A106 SMLS

    FORGED: A-105

    STUDS: A193 Gr B7 Fluorocarbon Coated

    NUTS: A194 2H Hvy Hex Nuts Fluorocarbon Coat'd

    GASKETS: Flexitallic CG or equal

    SUPPORTS:

    FITTINGSLADDER: Per API 650 Tables 3-20 and 3-21 LEVEL GAGE

    ROOF PROTECTION Per API 650 INSPECTION NOZZLE

    CLEANOUT EMERGENCY NOZZLE

    NOZZLES

    Mark QTY SIZE TYPE Series Locate SERVICEA 1 8" Thief Hatch

    B 1 2" RF 150 Gas Blanket

    C 1 RF 150 PVSV + Flame Arrestor (Contractor to Size)

    D 1 10" RF 150 Inlet

    E 1 2" RF LSH

    F 1 2" RF 150 TIT

    G 1 2" RF 150 LIT

    H 1 2" RF 150 LSL

    I 1 12" RF 150 Outlet

    J 1 4" RF 150 Drain

    K 8 2" RF 150 Sample points

    M 2 2" RF 150 Level Gauge

    N 1 6" RF 150 Foam

    MH 1 36"x36" Flush ManwayMH 3 24" FF Manway

    Fill Rate 45,000 BPD

    Empty Rate 45,000 BPD

    NOTES

    Platform to be provided as follows: Minimum 4' X 4' Grating Platform at Thief Hatch connected by walkway to

    stairs. Construction per API 650 Table 3-19

    All nozzle orientations to be defined later

    BASIC DATA SHEET

    AO115-EPF-01-112A2

    2 PSIG @ 240 F

    150

    11,191VOLUME:

    Sheet:

    MH

    M

    MHMH

    M

    MH

    B CA

    D

    E

    F

    G

    H

    I

    J

    N

    K

    M