23
IENG 217 Cost Estimating for Engineers Project Estimating

IENG 217 Cost Estimating for Engineers Project Estimating

Embed Size (px)

Citation preview

Page 1: IENG 217 Cost Estimating for Engineers Project Estimating

IENG 217Cost Estimating for

Engineers

Project Estimating

Page 2: IENG 217 Cost Estimating for Engineers Project Estimating

Hoover Dam U.S. Reclamation Service opened debate

1926 Six State Colorado River Act, 1928 Plans released 1931, RFP Bureau completed its estimates 3 bids, 2 disqualified Winning bid by 6 companies with bid price

at $48,890,955 Winning bid $24,000 above Bureau

estimates

Page 3: IENG 217 Cost Estimating for Engineers Project Estimating

Project Methods Power Law and sizing CERs Cost estimating relationships Factor

Page 4: IENG 217 Cost Estimating for Engineers Project Estimating

Power Law and Sizing In general, costs do not rise in strict proportion

to size, and it is this principle that is the basis for the CER

1m0 exponent,g correlatinm

size designreference Q

equipmentofsizedesign

Qsize designreference for cost

Qdesignnew for cost

r

r

c

c

r

m

r

cr

Q

C

C

where

Q

QCC

Page 5: IENG 217 Cost Estimating for Engineers Project Estimating

Power Law and Sizing

design of tindependen items of costC

designnew to coupledindex inflationI

designreference to coupledindex inflation

i

c

r

ir

c

m

r

cr

I

where

CI

I

Q

QCC

Page 6: IENG 217 Cost Estimating for Engineers Project Estimating

Power Law and Sizing Ten years ago BHPL built a 100 MW

coal generation plant for $100 million. BHPL is considering a 150 MW plant of the same general design. The value of m is 0.6. The price index 10 years ago was 180 and is now 194. A substation and distribution line, separate from the design, is $23 million. Estimate the cost for the project under consideration.

Page 7: IENG 217 Cost Estimating for Engineers Project Estimating

Class Problem

Page 8: IENG 217 Cost Estimating for Engineers Project Estimating

CER1

2

.

.

C KQ

C C CQ

Q

N

m

f vc

r

m

s

FHG

IKJ

K empirical constant

Q capacity expressed as design dimension

m=correlatingcoefficient

C fixed costs

C variable costs

3. C=KQ

f

v

m

m

r

cvf Q

QCCC

Page 9: IENG 217 Cost Estimating for Engineers Project Estimating

Factor Method Uses a ratio or percentage approach; useful for

plant and industrial construction applications

C C f C f

C selected major equipment

f factors for estimatingmajor items

f factor for estimating indirect

c ii

n

e I

e

i

I

( )( )

11

where

C cost of design

cost of

expenses

Page 10: IENG 217 Cost Estimating for Engineers Project Estimating

Factor Method

Basic Item Cost

Factor

Page 11: IENG 217 Cost Estimating for Engineers Project Estimating

Adjustment for Inflation

C CI

I

where

C t of itemat benchmark time

C t of itemincurrent time

I index of benchmark year

I index for current time

r cr

c

r

c

r

c

FHG

IKJ

cos

cos

c

rcr I

ICC

Page 12: IENG 217 Cost Estimating for Engineers Project Estimating

Example; Plant Project

Page 13: IENG 217 Cost Estimating for Engineers Project Estimating

Example; Plant Project

Ir = 100.0Ic = 114.1

Major Process Design Equipment Current Cost

Benchmark Cost

Rising Film Reactor $2,900,000 $2,541,630Ozonation Reactor $700,000 $613,497 Total $3,600,000 $3,155,127

Page 14: IENG 217 Cost Estimating for Engineers Project Estimating

Example; Plant Project

4.1

1.7

1.1

Page 15: IENG 217 Cost Estimating for Engineers Project Estimating

Example; Plant Project

Item Current Cost Current Index

Major Item Bench

fi Benchmark Cost

Project Strt Index

Project Strt Cost

Midwest Index

Plant Strt Cost

Equipment $3,600,000 114.1 $3,155,127 1.0 $3,155,127 134.0 $4,227,870 $4,227,870Major Process Item Bld Erection 1.7 $5,363,716 134.0 7,187,379 1.000 7,187,379 Direct Materials 4.1 $12,936,021 134.0 17,334,268 1.000 17,334,268 Eng. Costs 1.1 $3,470,640 134.0 4,650,657 1.000 4,650,657Building Site 1,250,000Process Building 2,100,000Railroad Spur 40,000Utilities 650,000 Total $37,440,175

Page 16: IENG 217 Cost Estimating for Engineers Project Estimating

Other Project Methods

Expected Value Range Percentile Simulation

Page 17: IENG 217 Cost Estimating for Engineers Project Estimating

Expected Value

Suppose we have the following cash flow diagram.

NPW = -10,000 + A(P/A, 15, 5)

1 2 3 4 5

A A A A A

10,000

MARR = 15%

Page 18: IENG 217 Cost Estimating for Engineers Project Estimating

Expected Value

Now suppose that the annual return A is a random variable governed by the discrete distribution:

A

p

p

p

2 000 1 6

3 000 2 3

4 000 1 6

, /

, /

, /

Page 19: IENG 217 Cost Estimating for Engineers Project Estimating

Expected Value

A

p

p

p

2 000 1 6

3 000 2 3

4 000 1 6

, /

, /

, /

For A = 2,000, we have

NPW = -10,000 + 2,000(P/A, 15, 5)

= -3,296

Page 20: IENG 217 Cost Estimating for Engineers Project Estimating

Expected Value

A

p

p

p

2 000 1 6

3 000 2 3

4 000 1 6

, /

, /

, /

For A = 3,000, we have

NPW = -10,000 + 3,000(P/A, 15, 5)

= 56

Page 21: IENG 217 Cost Estimating for Engineers Project Estimating

Expected Value

A

p

p

p

2 000 1 6

3 000 2 3

4 000 1 6

, /

, /

, /

For A = 4,000, we have

NPW = -10,000 + 4,000(P/A, 15, 5)

= 3,409

Page 22: IENG 217 Cost Estimating for Engineers Project Estimating

Expected Value

There is a one-for-one mapping for each value of A, a random variable, to each value of NPW, also a random variable.

A 2,000 3,000 4,000

p(A) 1/6 2/3 1/6

NPW -3,296 56 3,409

p(NPW) 1/6 2/3 1/6

Page 23: IENG 217 Cost Estimating for Engineers Project Estimating

Expected Value

E[Return] = (1/6)-3,296 + (2/3)56 + (1/6)3,409

= $56

A 2,000 3,000 4,000

p(A) 1/6 2/3 1/6

NPW -3,296 56 3,409

p(NPW) 1/6 2/3 1/6