30
1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 1 ILC Report Barry Barish Caltech / GDE 1-Dec-06 RDR Design Freeze

ILC Report

  • Upload
    akiva

  • View
    39

  • Download
    0

Embed Size (px)

DESCRIPTION

ILC Report. Barry Barish Caltech / GDE 1-Dec-06. RDR Design Freeze. Progress toward RDR. Baseline to a RDR. 2006. July. Dec. Jan. Frascati. Bangalore. Vancouver. Valencia. Freeze Configuration Organize for RDR. Review Design/Cost Methodology. Review Initial Design / Cost. - PowerPoint PPT Presentation

Citation preview

Page 1: ILC Report

1-Dec-06 HEPAP Univ. Subpanel

Global Design Effort 1

ILC Report

Barry Barish

Caltech / GDE

1-Dec-06RDR Design Freeze

Page 2: ILC Report

1-Dec-06 HEPAP Univ. Subpanel

Global Design Effort 2

Progress toward RDR

Page 3: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 3

Baseline to a RDR

Jan July Dec 2006

Freeze ConfigurationOrganize for RDR

Bangalore

Review Design/Cost Methodology

Review InitialDesign / Cost Review Final

Design / CostRDR Document

Design and Costing PreliminaryRDR

Released

Frascati Vancouver Valencia

Page 4: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 4

System July 18, 2006 - Cost Estimates received for Regionaldescription common e- e+ DR RTML ML BDS Exp Am Asia Eure- Source √e+ Source √DR √RTML √Main LinacBDS √Com, Op, ReliabControl System √ √ √ √ √ √ √Cryogenics √ √ √ * √ √ √ *Convent. Facilities √ √ √ √ √ √ √ * √ √ √ √Installation √ √ √ √ √ √ √Instrumentation √ √ √ √ √ √ √Cavities √ √ √Cryomodules √ √ √ √ √ √ √RF √ √ √ √ √ √ √ √ √Magnets & PS √ * √ *Dumps & Collim √ √ √ √ √Vacuum √ √ √ √ √ √Accel Phys

√ = complete, √ * = almost complete, missing something minor

Vancouver Cost Data

Page 5: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 5

ILC Estimate by Area Systems -17july06

Main Linac DRs Beam Deliv RTML e+ Source Exp. Halls e- Source General

Costs by Area System

Page 6: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 6

ILC Estimate by Technical & Global Systems - 22july06

Conventional Facilities

Dumps & Collimators

CM & Cavities

Instrumentation

RF

Vacuum

Installation

Magnets

Cryogenics

Controls

Costs by Technical & Global System

Page 7: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 7

Optimizing Cost to Performance

RDR MB CCB

214mr IRs supported central injectors supported Removal of service tunnel rejected

conventional e+ source rejected

RF unit modifications (24 26 cav/klys) supported submitted

reduced RF in DR (6 9mm z) supported in prep

DR race-track lattice (CFS) supported in prep

reduced static cryo overhead supported in prep

removal linac RF overhead supported in prep

single-stage bunch compressor rejected

e- source: common pre-accelerator supported in prep

Page 8: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 8

Vancouver Costs for BDS

• Cost drivers– CF&S– Magnet

system– Vacuum

system– Installation– Dumps &

Collimators

Total Cost

Additional costs for IR20 and IR2

Page 9: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 9

2/20 mrad 14/14 mrad

• Motivation – Reduce costs

• 2 mrad beam line expensive, risky, especially extraction line• Common collider hall

– Advantages• Improved radiation conditions in the extraction lines• Better performance of downstream diagnostics• Easier design and operation of extraction optics and magnets• Reduced back scattering from extraction line elements

– Disadvantages• Impact on physics (appears minor at present). • Simpler incoming beam optics

• R&D on small crossing angles will continue as alternative

Page 10: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 10

On-surface Detector Assembly• Vancouver WBS considered the underground halls

sized at 32m (W) x 72m (L) each to allow underground assembly of the largest considered detector.

• Conventional Facilities Schedule gives detector hall is ready for detector assembly 5 yrs from project start– If so, cannot fit our goal of “7years until first beam” and

“8years until physics run”

• Surface assembly allows to save 2-2.5 years and allows to fit into this goal– The collider hall size may be smaller (~40-50%) in this

case – A building on surface is needed, but savings may be

still substantial

• Optimization needs to be done

Page 11: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 11

CMS assembly approach• Assembled on the surface in parallel with underground work• Allows pre-commissioning before lowering• Lowering using dedicated heavy lifting equipment• Potential for big time saving• Reduce size of underground hall required

On-surface assembly

Page 12: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 12

Cost details of new 14/14 baseline

Total cost

1.000

0.3680.316 0.316

0

0.2

0.4

0.6

0.8

1

1.2

Total Common add for IR A add for IR B

a.u.

Updates from CF&SMagnets to be included

Should we go to a single IR and push

pull system and save 30% of BCD costs?

Page 13: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 13

Push-Pull Evaluation

• Initiated by GDE & WWS at the end of September• Detailed list of questions to be studied developed:

• Large group of accelerator and detector colleagues, from ILC and other projects, is participating in design and discussion of these question

• The task force of detector experts was formed to contribute to detailed evaluation of the whole set of technical issues

http://www-project.slac.stanford.edu/ilc/acceldev/beamdelivery/rdr/docs/push-pull/

Page 14: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 14

Cost Reductions Logged

Our efforts at Valencia identified another 4.91%!

05

10

152025

initia

l

BDS

14/1

4 + m

uon

1 e+ r

ing

ML RF

DR 9m

m +

e+ so

urce

RTML

CF&S

Sha

fts+

Centrariz

ed D

R

BDS

1IR

Cooli

ng+M

isc

Energy

?

Lumino

sity?

%

Accumulated Cost Savings Each Cost Savings

Page 15: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 15

ILC Documents

• Several reports for different audiences

• Brochure – non-technical audiences, ready now• “Quantum Universe” level booklet ~30 pages

• Executive Summary ~ 30 pages • Physics motivation, accelerator and detectors

• RDR Report ~ 300 pages• high level description of the accelerator

• DCR Report ~ 250 pages• physics and detectors

Page 16: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 16

RDR Report

• RDR is a high level description of the accelerator, CFS, sites and costs

• A snapshot of what we propose to build– not a history of R&D, design evolution, and

alternatives

• Editors: – Nan Phinney (SLAC), Nobu Toge (KEK), Nick Walker

(DESY)

• Original schedule was complete draft now, but has been pushed back because of cost iterations

Page 17: ILC Report

1-Dec-06 HEPAP Univ. Subpanel

Global Design Effort 17

Reviewing RDR & Costs

Page 18: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 18

Plans until Beijing (Feb. '07)

November December January February

Valencia

Further cost consolidationCCR preparation & submission

Cost & Design Freeze 30/11

Prepare for Full Cost Review

SLAC Cost Review 14-16/12

MAC 10-12/01/07

Final cost corrections and documentation

Agency cost briefings

Beijing: RDR draft published

RDR final editing

RDR prepare 1st drafts

2006 2007

Page 19: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 19

Charge for MAC Review

• On Wednesday 10, Thursday 11 and Friday 12 (until noon) January 2007, there will be an ILC MAC meeting at the Cockcroft Institute, Daresbury, UK. The major item for the meeting is the ILC cost and overall design, with specific MAC tasks:

– Review the soundness of the overall RDR concept, identify any areas of concern, note what R&D is still needed, and comment on whether the performance parameters can be met.

– Review the cost methodology and identify any areas of concern.

• This will be the first occasion at which costs will be presented outside of the GDE.

Page 20: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 20

What Happens after Beijing?

• Public Release of Draft RDR and Preliminary Costing at Beijing– Cost Reviews, etc– Finalize RDR by Summer 2007?

• Enter into Engineering Design Phase– Planning underway internally– Design will evolve through value engineering

and R&D program– General Goal is to have Construction Proposal

ready by 2010

Page 21: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 21

Proposed RDR Review Process

Page 22: ILC Report

1-Dec-06 HEPAP Univ. Subpanel

Global Design Effort 22

Siting Aspects of RDR&

Candidate Sites

Page 23: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 23

Site Aspects of RDR

• Three Samples Sites– ILC Conventional Facilities Group: Jean-Luc Baldy (CERN), Vic

Kuchler (Fermilab) and Atsushi Enomoto (KEK) + Support Group

– Sample Site Analysis - Europe (CERN); Japan (?); US (Fermilab) also, TESLA for reference and Russia unsolicited

– Conventional Facilities are expensive! Make narrow definition for “host costs” - goal ~ 25% of total.

Page 24: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 24

ILC Estimate by Technical & Global Systems - 22july06

Conventional Facilities

Dumps & Collimators

CM & Cavities

Instrumentation

RF

Vacuum

Installation

Magnets

Cryogenics

Controls

Costs by Technical & Global System

Page 25: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 25

Site Aspects of RDR

• Three Samples Sites– ILC Conventional Facilities Group: Jean-Luc Baldy (CERN), Vic

Kuchler (Fermilab) and Atsushi Enomoto (KEK) + Support Group

– Sample Site Analysis - Europe (CERN); Japan (?); US (Fermilab) also, TESLA for reference and Russia unsolicited

– Conventional Facilities are expensive! Make narrow definition for “host costs” - goal ~ 25% of total.

• Costing Regional – Best estimates in “own” system of costing. They are close to equal, meaning the RDR siting chapter can concentrate on requirements, technical features, cost drivers, safety issues, other issues etc.

• Need “true” candidate sites within ~ 1-2 years for realistic engineering design. How do we solicit candidate sites

Page 26: ILC Report

1-Dec-06 HEPAP Univ. Subpanel

Global Design Effort 26

CoordinatingGlobal R&D

Page 27: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 27

The ‘S’ R&D Task Forces

S0High-Gradient Cavities

S1High-Gradient Cryomodule

S2Test Linac

S3Damping Ring

S4Beam Delivery

S5…Sn

To address priority R&D items, RDB has convened several ‘task forces’.

S0-S3 will report on Friday AM GDE plenary

Page 28: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 28

The ‘S’ R&D Task Forces

• Addresses current ‘poor’ yield for EP cavities

• Primary goal: establish parameters for routinely producing 35 MV/m EP’d cavities– required 80% yield

S0High-Gradient Cavities

S1High-Gradient Cryomodule

S2Test Linac

S3Damping Ring

S4Beam Delivery

S5…SnH. Hayano, T. Higo, L. Lilje, J. Mammosser, H. Padamsee, M. Ross, K. Saito

Page 29: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 29

Summary

• Status of Costing– First costing available at Vancouver (July)– Cost to performance optimization

• Status & Plans for design modifications– Several proposals accepted and some rejected– Changes having physics impact (Valencia)– Complete RDR by Beijing Meetings

• Global planning for critical R&D beginning– Formation of ‘S’ task forces

Page 30: ILC Report

1-Dec-06 HEPAP Univ. Subpanel Global Design Effort 30

Some Key Issues

• The RDR– The RDR is a snapshop of the concept and scope of

the costs; NOT A MATURE DESIGN– It is an “optimized concept” for the physics scope

(ILCSC parameters) without doing detailed engineering (value engineering) and future R&D (demonstrations and alternatives)

– Engineering Design will be more cost effective, lower risk and maintain the physics scope.

• Next Phase – Expensive– Resources and Organization ???– Involve University Community in Acc Design/ R&D– Detector R&D Road map - collaborations/detectors