Innovation &
Technology Produced by: Corporate Communications
EMP – 4 project innovates with
mechanized cylindrical mast
foundations
Railway SBG’s EMP-4 project team
has successfully initiated casting of Cylindrical
Foundations at Sakun-Kishangarh section of
Package-B on 15-Feb-17.
Conventionally, Indian Railway OHE Mast
Foundations are cast-in-situ manually which is
labor intensive as well as requiring large
quantities of concrete. The concept of
mechanized cylindrical foundation was
introduced to increase productivity (10-12
foundations/day/ equipment which is upto 4
times faster than manual methods) and to reduce
the quantity of concrete required.
EMP-4 team designed and developed a Mast
Guided Auger attachment mounted on a high
capacity tractor enabling expeditious execution of
dimensionally accurate cylindrical foundations.
The design, mock-up testing and approval of
cylindrical foundations involved simulations of
different loads to meet the stringent design
requirements of high-rise OHE, a large mast
implantation and a very narrow formation bed
leaving less space for foundations on the
formation. This major innovation will help the
team expedite the project’s requirement of about
42000 foundations.