Thesis Defense Presentation by Wajahat Sammer Ansari (2012-NUST-MS-CE&M- 04) Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan. Thesis Supervisor: Dr. Muhammad Jamaluddin Thaheem Head, Department of Construction Engineering and Management, NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad G.E.C. Members: 1. Dr. Hamza Farooq Gabriel Head, Department of Water Resource Engineering and Management, NICE, National University of Sciences and Technology (NUST), Islamabad 2. Engr. Mansoor Ahmed Malik Deputy Director General, NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad 3. Engr. Shahnila Gul Department of Construction Engineering and

INVESTIGATION OF CONSULTANTS AND CONTRACTORS PERCEPTIONS OF OFFSITE CONSTRUCTION TECHNIQUES IN PAKISTAN CONSTRUCTION INDUSTRY

Embed Size (px)

DESCRIPTION

The problems in construction industry of pakistan

Citation preview

  • Department of Construction Engineering and Management, National Institute of Transportation (NIT), School of Civil and Environmental Engineering (SCEE), National University of Sciences and Technology (NUST), Islamabad, Pakistan.Thesis Supervisor:Dr. Muhammad Jamaluddin Thaheem Head, Department of Construction Engineering and Management,NIT, SCEE, National University of Sciences and Technology (NUST), IslamabadG.E.C. Members:Dr. Hamza Farooq Gabriel

    Head, Department of Water Resource Engineering and Management,NICE, National University of Sciences and Technology (NUST), Islamabad

    Engr. Mansoor Ahmed Malik

    Deputy Director General,NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad

    Engr. Shahnila Gul

    Department of Construction Engineering and Management,NIT, SCEE, National University of Sciences and Technology (NUST), Islamabad

    Title Slide

  • Introduction of Student*/33

    1.Name Wajahat Sammer Ansari2.Reg No. NUST201261002MSCEE15412F3.Discipline /DepartmentConstruction Engineering & Management (NIT), SCEE4.Date of Admission in Masters at NUST10 Sep 20125.MS Coursework CGPA3.25 / 4.006.Previous Qualification Matric73%FSc75%BE / BSc75%7.Employed atPakistan Institute of Engineering & Technology, Multan8.Progress of Research Paper: Title Submitted toSubmission Date

  • CONCLUSIONS AND RECOMMENDATIONSDATA ANALYSIS AND FINDINGS*/33CASE STUDY

  • */33Onsite Traditional Construction Case study

  • */33Offsite Construction Type of construction in which structures are built at different locations than the location where they are assembled (Haas and Fagerlund 2002).Case study

  • */33Benefits and Challenges of Onsite Traditional Construction as compared to Offsite Construction BenefitsNo need for careful transportationOnsite changes can be done easily The more expertise are available of traditional onsite construction

    (Tatum et.al., 1987 ; Warzsawski, 1990 ; Cart..et al, 2000 ;) ChallengesTakes more duration to complete project Can take High cost Decreases safety performance Can decrease product qualityCan do huge environmental impactIncreases skilled craft workers onsiteIncreases onsite labor congestionResults in low production

    (Cart..et al., 2000 ; Endicott, 2000 ; Waskett, 2001 ; Housing Form, 2002 ; Canadian Precast Concrete Institute, 2005)

    Case study

  • */33Benefits and Challenges of Offsite Construction as compared to Traditional onsite Construction BenefitsDecreases project construction time 65% decrease in project costs by use of offsite construction techniques Enhance onsite safety performance. Higher product quality can be achieved Reduce skilled labor on site 77% decrease has been observed site waste

    (AbouRizk and Halpin, 1992 ; Liska, 2002 ; Pasquire and Connolly, 2002 ; McGraw Hill Construction, 2011)

    ChallengesCareful pre- project planningTransportation restraints Can decrease operating cost Proper equipment's should be consider

    (Gann. 1996 ; Haas and Fagerlund, 2002 ; Blismas et al., 2005 ; Asiz, smith et al., 2006)

    Case study

  • Research Objectives:*/33Case study

  • Research Methodology:*/33

    T tests, ANOVA and Linear regressions

    Cost and duration comparison of onsite traditional construction and offsite construction in Pakistan

    Case study

  • Research Design:*/33Respondents ProfileAbout Offsite Construction (Based on Likert Scale)According to Koterlik (2001) for population equal or greater than 4000 the required returned minimum sample size is 119. For this study 140 responses are collected which is greater than 119 T tests, ANOVA and Linear RegressionCase StudyComparison of duration and cost of Project through onsite traditional and offsite construction in PakistanCase studyIntroduction & Literature Review

  • Questionnaire:*

  • */33Case studyIntroduction & Literature Review

  • */33

    Case studyIntroduction & Literature Review

  • */33Case studyIntroduction & Literature Review

  • */33Case studyIntroduction & Literature Review Linear relationship of consultants and contractors about offsite construction

    Model SummaryRR SquareAdjusted R SquareStd. Error of the Estimate.954.909.904.143.

    CoefficientsUnstandardized CoefficientsStandardized CoefficientstSig.BStd. ErrorBetaConsultants1.005.077.95413.064.000(Constant)-.063.381-.166.870

    Spearmans ranking correlation =0.999475

  • */33Case studyIntroduction & Literature Review

    Comparison of contractor categories (Scores out of 7)

  • */33Case studyIntroduction & Literature ReviewOverall Spearmans ranking correlation factor = 0.6843

    Spearmans correlation of contractor categories (Scores out of 7)

    Spearman's correlationTransportation restraints limit the use of offsite construction techniques0.9872452Reduces duration0.9995626Reduces workers0.9733882Increases productivity0.9872452Decreases onsite labor congestion0.9930015Reduces environmental impact of construction operations0.9930015Increases jobsite management efficiency0.9872452Reduces onsite disruption of other adjacent operations0.9974805Increases labor savings0.9922841Increases design cost0.9809465Project planning system the one of the barriers of offsite construction0.9489808Increase product quality0.9785671Limits design options0.9733882Increases project design efficiency0.9890648Limits changes in onsite work0.9820838Reduces project cost0.9809465Increases safety performance0.9760476Computer software for designing offsite construction techniques limits their uses0.9747354Increases overall cost savings0.9890648

  • */33Case studyIntroduction & Literature Review

    Comparison of consultant sectors (Scores out of 7)

  • */33Case studyIntroduction & Literature ReviewOverall Spearmans ranking correlation factor = 0.982766

    Spearmans ranking correlation of consultant sectors

    Spearmans correlationReduces onsite disruption of other adjacent operations0.99937Reduces duration0.99993Reduces workers0.993001Transportation restraints limit the use of offsite construction techniques0.999843Reduces environmental impact of construction operations0.999563Increases labor savings0.998583Increases jobsite management efficiency0.997481Increases productivity0.99993Increases project design efficiency0.99972Decreases onsite labor congestion0.99937Limits changes in onsite work0.999563Project planning system the one of the barriers of offsite construction0.99937Increases safety performance0.998583Increase product quality0.999983Limits design options1Increases design cost0.999143Reduces project cost0.999563Increases overall cost savings0.99993Computer software for designing offsite construction techniques limits their uses0.999843

  • */33Case studyIntroduction & Literature Review

    Comparison of contractor sectors (Scores out of 7)

    Chart1

    4.44.454.3

    4.85.76.35.5

    4.255.75

    3.64.62.74.5

    3.64.35.34.8

    4.65.855

    3.24.55.34.3

    3.64.354.5

    4.25.865.8

    4.25.85.75.8

    4.25.866

    3.65.155

    3.24.66.75

    3.84.54.73.5

    4.45.52.75.3

    4.65.565.5

    4.44.95.34.2

    4.25.86.35

    4.23.61.33.8

    4.23.61.33.8

    Residential

    Commercial

    Industrial

    Infrastructure

    Sheet1

    Ques 1Ques 2Ques 3Ques 4Ques 5Ques 6Ques 7Ques 8Ques 9Ques 10Ques 11Ques 12Ques 13

    S. No.Role in Construction IndustryType/Field of BusinessName of CompanyNo. of Projects per YearJob TitleYear(s) in Current PositionExperienceAgeHow does your Company Identify Risks?Which of the following Qualitative Risk Assessment Techniques does your company apply?Which of the following Quantitative Risk Assessment Techniques does your company apply?Does your company currently use Project Risk Management Software?If yes, please indicate which of these Risk Management Software Programs/add-ons does your company use.To what level do you need to process the input data before introducing/inputting in the Risk Software?What type of input you provide to the Risk Software?Is the output of the Risk Software readily understandable or needs to be translated/worked upon?What type of output do you get from the Risk Software?If NO, Please indicate the reason/s for NOT using Risk Management Software.Please rate in order of importance from 1 (most important) to 5 (least important) the following attributes of Risk Management Software/Software add-ons.Please rate in order of importance from 1 (most important) to 5 (least important) the following functions of Risk Management Software.How does your company monitor and control Risks?Client

    Consultant

    Contractor

    Ability to CustomizeUsability/User FriendlinessExtended Functionality/Variety of FunctionsCompatibility with other ProgramsTechnical SupportImportability/Exportibility into other PM Software SystemReportingProbability SimulationRisk/Treatment DatabaseRisk/Treatment ManagementQues 1Ques 4Ques 9Ques 12

    Documentation reviewYesProbabilistic Achievement in Cost and Time Objectives1

    BrainstormingNoProbabilistic Analysis of the Project2

    InterviewingPrioritized List of Quantified Risks3

    1ConsultantConstructionThe Architects20Resident Engineer1.53460Documentation reviewRisk Probability and Impact AssessmentSensitivity AnalysisYesCrystal Ball (Excel)Entirely dataRisk DatabaseNoProbabilistic Analysis of the Project5442254523Earned Value AnalysisRoot Cause IdentificationTrends in Quantitative Analysis Results4

    Cause and Effect DiagramRisk Data Quality AssessmentExpected Monetary ValuePrimavera Risk Analysis (Primavera)Entirely dataRoles and Responsibilities, Risk Categories, RBSNoProbabilistic Achievement in Cost and Time ObjectivesReserve analysisChecklist AnalysisQues 55

    System or Process Flow ChartModeling and SimulationsProject Schedule Management PlanNoTrends in Quantitative Analysis ResultsProject Risk Response AuditsAssumptions AnalysisCrystal Ball (Excel)

    Influence DiagramsProject Cost Management PlanNoTechnical Performance MeasurementCause and Effect Diagram@Risk (Excel)Ques 10

    2ClientCivil ConstructionDHA Karachi500Asst Executive Engineer2529Documentation reviewRisk Probability and Impact AssessmentInterviewingYesPrimavera Risk Analysis (Primavera)Entirely dataProject Schedule Management PlanNoProbabilistic Achievement in Cost and Time Objectives4132525413Technical Performance MeasurementSystem or Process Flow ChartRiskyProject (Microsoft Project, Primavera)Bugs/errorsQues 13

    3ConsultantCivil ConstructionThe Consultant100Resident Engineer2627Documentation reviewRisk Probability and Impact AssessmentInterviewingYesPrimavera Risk Analysis (Primavera)Entirely dataProject Schedule Management PlanNoProbabilistic Achievement in Cost and Time Objectives45543Technical Performance MeasurementInfluence Diagrams@Risk (Microsoft Project)Limits of SoftwareAdditional Risk response planning

    4ContractorCivil ConstructionNida Traders3Chief Executive42260Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planningDelphi TechniquePrimavera Risk Analysis (Primavera)CostProject Risk Response Audits

    BrainstormingRisk urgency assessmentNot necessaryReserve analysisSWOT AnalysisPredict!Not sufficiently tailored for BusinessEarned Value Analysis

    Assumptions AnalysisStatus meetingsPareto ChartRisk+ (Microsoft Project)Difficulty of useTechnical Performance Measurement

    5ContractorCivil and ElectricalNoble Enterprises5Chief Executive72363Documentation reviewRisk Probability and Impact AssessmentInterviewingYesPrimavera Risk Analysis (Primavera)No needProject Scope StatementNoTrends in Quantitative Analysis ResultsAdditional Risk response planningOthersNot necessaryReserve analysis

    BrainstormingRisk Data Quality AssessmentExpert JudgmentProject Schedule Management PlanNoReserve analysisIncompatibility with existing softwareStatus meetings

    Assumptions AnalysisRisk urgency assessmentExpected Monetary ValueProject Cost Management PlanNoTechnical Performance MeasurementQues 2Ques 6Perceived lack of Support

    Modeling and SimulationsStatus meetingsRisk Probability and Impact AssessmentEntirely dataLack of product knowledge

    6ContractorCivil ConstructionSyed Associates4Chief Executive43758Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planningProbability and Impact MatrixPart of the dataPerceived unreliability

    BrainstormingRisk urgency assessmentNot necessaryReserve analysisRisk Data Quality AssessmentNo needLack of user friendliness

    Status meetingsRisk Categorization

    7ClientConstructionCivil Aviation Authority3General Manager51235Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentYesRisk+ (Microsoft Project)Part of the dataProject Schedule Management PlanYesProbabilistic Analysis of the Project5534455444Project Risk Response AuditsRisk urgency assessment

    BrainstormingTechnical Performance MeasurementOthersQues 7

    8ContractorConstructionAB Associates2Site Engineer3323Assumptions AnalysisRisk CategorizationInterviewingNoNot necessaryStatus meetingsRisk DatabaseQues 11

    InterviewingProject Scope Statement1

    SWOT AnalysisQues 3Roles and Responsibilities, Risk Categories, RBS2

    9ContractorConstructionKAYBEE Constructors12Supervisor2222Documentation reviewRisk Data Quality AssessmentInterviewingYes@Risk (Excel)Entirely dataRisk DatabaseYesProbabilistic Analysis of the Project4455544344Status meetingsInterviewingRisk Register3

    InterviewingExpert Judgment@Risk (Microsoft Project)Entirely dataProject Schedule Management PlanYesPrioritized List of Quantified RisksProbability DistributionsProject Schedule Management Plan4

    Checklist AnalysisSensitivity AnalysisExpert JudgmentProject Cost Management Plan5

    Assumptions AnalysisSensitivity Analysis

    SWOT AnalysisExpected Monetary ValueQues 8

    Influence DiagramsDecision Tree AnalysisYes

    10ContractorConstructionFWO50Trainee Engineer1122Documentation reviewRisk Data Quality AssessmentExpert JudgmentNoLack of user friendlinessTechnical Performance MeasurementModeling and SimulationsNo

    11ClientConstructionPakistan Cricket BoardAsst. Engineer1125Documentation reviewRisk urgency assessmentInterviewingyes@Risk (Excel)Entirely dataProject Scope StatementNoTrends in Quantitative Analysis Results221124511Additional Risk response planning

    Checklist Analysis@Risk (Microsoft Project)Entirely data

    12ClientConstructionFWO50Project Engineer1328Cause and Effect DiagramRisk Probability and Impact AssessmentExpert JudgmentYesCrystal Ball (Excel)Entirely dataRisk DatabaseNoProbabilistic Analysis of the Project3144454321Additional Risk response planning

    Root Cause IdentificationRisk CategorizationSensitivity AnalysisRisk RegisterNoTrends in Quantitative Analysis ResultsEarned Value Analysis

    Reserve analysis

    13ContractorConstructionAMA Builders & Dev.5Asst. Engineer2528SWOT AnalysisProbability and Impact MatrixInterviewingYesRiskyProject (Microsoft Project, Primavera)Part of the dataRisk DatabaseYesProbabilistic Analysis of the Project4534435442Status meetings

    Prioritized List of Quantified Risks

    14ConsultantConstructionOsmania Consultants5+Asst. Resident Engg.21041Documentation reviewRisk Probability and Impact AssessmentInterviewingYesCrystal Ball (Excel)Entirely dataRisk DatabaseYesProbabilistic Analysis of the Project5145535555Additional Risk response planning

    InterviewingSensitivity AnalysisPrimavera Risk Analysis (Primavera)Entirely dataRisk RegisterYesTrends in Quantitative Analysis ResultsTechnical Performance Measurement

    Checklist AnalysisModeling and SimulationsProject Cost Management PlanYesStatus meetings

    Cause and Effect Diagram

    15ConsultantConstructionEA Consulting pvt. Ltd.5Design Engineer1224Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentYesCrystal Ball (Excel)Part of the dataRoles and Responsibilities, Risk Categories, RBSYesProbabilistic Analysis of the Project3232244554Additional Risk response planning

    BrainstormingRisk Data Quality AssessmentExpected Monetary ValueRiskyProject (Microsoft Project, Primavera)Part of the dataProject Scope StatementYesTrends in Quantitative Analysis ResultsTechnical Performance Measurement

    Checklist AnalysisRisk+ (Microsoft Project)Part of the dataProject Cost Management PlanYes

    16ConsultantConstructionAssociated Consultancy Centre Pvt. Ltd.10Trainee Engineer1123Documentation reviewRisk Data Quality AssessmentExpert JudgmentNoCostStatus meetings

    BrainstormingRisk urgency assessmentLack of product knowledge

    Checklist Analysis

    SWOT Analysis

    17ConsultantConstructionAssociated Consultancy Centre Pvt. Ltd.10Trainee Engineer2224Documentation reviewRisk Probability and Impact AssessmentProbability DistributionsNoLack of product knowledgeStatus meetings

    18ContractorConstructionWaliullah Construction Company5Site Engineer2428Documentation reviewRisk Probability and Impact AssessmentInterviewingNoLack of product knowledgeStatus meetings

    Checklist AnalysisRisk Data Quality AssessmentExpert Judgment

    19ClientConstructionPhilip Morris International100Project Engineer2325Cause and Effect DiagramRisk CategorizationExpert JudgmentNoLack of product knowledgeStatus meetings

    20ContractorConstructionAtif Nazar Associates2Site Engineer1124Root Cause IdentificationRisk CategorizationExpert JudgmentNoCostTechnical Performance Measurement

    21ContractorConstructionArma Construction Company2Site Engineer1540InterviewingRisk Data Quality AssessmentInterviewingNoLack of product knowledgeTechnical Performance Measurement

    22ConsultantConstructionEngineering Associates Ltd.5Site Engineer3529Documentation reviewRisk Data Quality AssessmentProbability DistributionsNoLack of product knowledgeReserve analysis

    23ClientOil and GasPakistan Petroleum Limited10Deputy Engineer6629Documentation reviewRisk Probability and Impact AssessmentInterviewingYesRiskyProject (Microsoft Project, Primavera)Part of the dataRisk DatabaseYesProbabilistic Analysis of the Project5424555455Additional Risk response planning

    Checklist AnalysisSensitivity AnalysisRisk RegisterYesProbabilistic Analysis of the ProjectStatus meetings

    24ClientOil and GasPakistan Petroleum Limited10Deputy Engineer2837Documentation reviewProbability and Impact MatrixExpert JudgmentNoNot necessaryStatus meetings

    Checklist AnalysisExpected Monetary ValueLack of product knowledgeReserve analysis

    25ConsultantOil and GasExterran Services5Construction Manager12558Documentation reviewProbability and Impact MatrixInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    26ConsultantOil and GasExterran Services5Business Dev Manager21438Documentation reviewProbability and Impact MatrixExpert JudgmentNoNot sufficiently tailored for BusinessAdditional Risk response planning

    Assumptions AnalysisRisk Data Quality AssessmentInterviewingNot necessaryStatus meetings

    Root Cause Identification

    27ConsultantOil and GasExterran Services5Supervisor31135Documentation reviewProbability and Impact MatrixExpert JudgmentNoPerceived lack of SupportAdditional Risk response planning

    BrainstormingRisk Data Quality AssessmentInterviewingCostStatus meetings

    SWOT Analysis

    28ContractorConstructionSKB6M D152040Checklist AnalysisRisk CategorizationDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Root Cause Identification

    29ContractorConstructionExecutive Engg Services4M D91842InterviewingRisk CategorizationInterviewingNoNot necessaryStatus meetings

    30ContractorConstructionMalani Construction Company5Site Engineer2225InterviewingProbability and Impact MatrixInterviewingNoLimits of SoftwareStatus meetings

    31ContractorConstructionSKB6Site Engineer3528Root Cause IdentificationRisk Data Quality AssessmentExpert JudgmentNoLack of user friendlinessAdditional Risk response planning

    32ConsultantConstructionEA Consulting pvt. Ltd.5Senior Engineer3832Documentation reviewRisk Probability and Impact AssessmentInterviewingYesRiskyProject (Microsoft Project, Primavera)Part of the dataRisk DatabaseYesProbabilistic Achievement in Cost and Time Objectives5444354455Technical Performance Measurement

    33ContractorConstructionExecutive Engg Services3Site Engineer2325Documentation reviewRisk Data Quality AssessmentExpert JudgmentNoCostProject Risk Response Audits

    34ConsultantConstructionEA Consulting pvt. Ltd.5Resident Engineer2835Root Cause IdentificationRisk Data Quality AssessmentExpected Monetary ValueYesRiskyProject (Microsoft Project, Primavera)Entirely dataRisk DatabaseYesProbabilistic Achievement in Cost and Time Objectives3543545335Technical Performance Measurement

    35ContractorConstructionWaliullah Construction Company5Site Engineer3530Root Cause IdentificationRisk CategorizationExpected Monetary ValueNoBugs/errorsEarned Value Analysis

    Cost

    36ConsultantConstructionDesign and Consult Engineering Services2Supervisor2530SWOT AnalysisRisk Probability and Impact AssessmentModeling and SimulationsNoCostEarned Value Analysis

    37ContractorConstructionMJ Construction Company1Project Manager2830SWOT AnalysisRisk Probability and Impact AssessmentProbability DistributionsNoDifficulty of useStatus meetings

    Lack of user friendliness

    38ContractorConstructionIqbal Malik & Company3Chief Executive52555Documentation reviewRisk CategorizationExpert JudgmentNoCostReserve analysis

    BrainstormingDifficulty of use

    39ContractorConstructionSBS and Sons5M D32250Documentation reviewRisk CategorizationExpert JudgmentNoCostReserve analysis

    BrainstormingDifficulty of use

    40ContractorConstructionBarkat Ali Khaki & Co.3Senior Engineer51242Checklist AnalysisRisk CategorizationDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Root Cause Identification

    41ContractorConstructionThadani Enterprises5Resident Engineer31538Checklist AnalysisRisk CategorizationDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Root Cause Identification

    42ContractorConstructionBilal Builders5Site Engineer3530Root Cause IdentificationRisk CategorizationExpected Monetary ValueNoBugs/errorsEarned Value Analysis

    Cost

    43ContractorConstructionUzair Engineering Works3Chief Executive42260Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    BrainstormingRisk urgency assessmentNot necessaryReserve analysis

    44ContractorConstructionImtiaz Construction Company2Site Engineer1540InterviewingRisk Data Quality AssessmentInterviewingNoLack of product knowledgeTechnical Performance Measurement

    45ContractorConstructionAl Sultan & Jamal Construction Company5Site Engineer3530Root Cause IdentificationRisk CategorizationExpected Monetary ValueNoBugs/errorsEarned Value Analysis

    Cost

    46ConsultantDesign and ConstructionNESPAK20Site Engineer1124InterviewingRisk Data Quality AssessmentExpert JudgmentNoCostStatus meetings

    Not necessary

    47ConsultantDesign and ConstructionNESPAK20Resident Engineer12558Documentation reviewProbability and Impact MatrixInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    48ConsultantDesign and ConstructionNESPAK20Asst Resident Engineer21844Documentation reviewProbability and Impact MatrixInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    49ContractorConstruction of RoadsIqbal and Sons-Site Engineer1224Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryReserve analysis

    System or Process Flow ChartRisk CategorizationSensitivity AnalysisStatus meetings

    SWOT AnalysisModeling and Simulations

    50ContractorConstructionMemonai Enterprises2Site Engineer1124System or Process Flow ChartRisk Data Quality AssessmentDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Checklist AnalysisProject Risk Response Audits

    51ContractorConstructionSN Construction Company2Asst. Project Manager1327BrainstormingRisk Probability and Impact AssessmentInterviewingNoNot necessaryStatus meetings

    52ClientMonitoring of ProjectsPnD Dept. Sindh1500Monitoring & Evaluation Officer41640Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    53ClientMonitoring of ProjectsPnD Dept. Sindh1500Planning Officer T&C21035BrainstormingRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    Documentation review

    54ClientMonitoring of ProjectsPnD Dept. Sindh1500Planning Officer PP&H21236BrainstormingRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    Documentation review

    55ContractorConstructionExecutive Engineering Services5Executive Director81541Assumptions AnalysisRisk Probability and Impact AssessmentExpert JudgmentNoLack of user friendlinessAdditional Risk response planning

    56ContractorMechanicalConstructionAU Engineering Services4Chief Executive53061Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoCostStatus meetings

    BrainstormingRisk CategorizationExpected Monetary ValueDifficulty of useReserve analysis

    Assumptions Analysis

    57ContractorConstruction Inst & Elec.Delta Engineering8Project Incharge52050Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoCostStatus meetings

    BrainstormingRisk CategorizationExpected Monetary ValueDifficulty of useReserve analysis

    58ClientMonitoring of ProjectsWorks n Services Sindh700Asst Executive Engineer51538Documentation reviewRisk Probability and Impact AssessmentInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    59ClientMonitoring of ProjectsWorks n Services Sindh700XEN32052Documentation reviewRisk Probability and Impact AssessmentInterviewingNoCostStatus meetings

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    Additional Risk response planning

    60ClientMonitoring of ProjectsPak PWD1500Asst Executive Engineer21136InterviewingNoNot sufficiently tailored for BusinessStatus meetings

    61ConsultantConstructionEuro Consultants100Sr. Field Engineer1732NoLack of product knowledge

    62ContractorEPCEtimaad Engineering20Site Manager31034Documentation reviewOthersExpert JudgmentNoCostStatus meetings

    BrainstormingNot necessaryReserve analysis

    63ContractorPlant ConstructionDescon Engineering15Civil Engineer1930Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryStatus meetings

    Risk Categorization

    64ConsultantConstructionNDC25Asst Resident Engineer2729Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryStatus meetings

    65ClientConstructionDHA Karachi100Asst Executive Engineer5831Documentation reviewExpert JudgmentNoLack of product knowledgeStatus meetings

    66ConsultantIrrigationEngineering Associates30Jr. Engineer1630Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryTechnical Performance Measurement

    65666666Bugs/errors

    134.95384615382.886363636410.454545454535.9545454545Limits of Software

    382.23851337352.32510620868.735747633311.6453117912Cost

    Not sufficiently tailored for Business

    Difficulty of use

    Not necessaryAdditional Risk response planning

    Incompatibility with existing softwareProject Risk Response Audits

    Perceived lack of SupportEarned Value Analysis

    Lack of product knowledgeTechnical Performance Measurement

    Perceived unreliabilityReserve analysis

    Lack of user friendlinessStatus meetings

    43.16666666673.33333333333.33333333333.92307692314.08333333334.615384615443.46153846153.4615384615

    11.64224532181.073086741.30267789461.25575597830.99620491990.50636968350.77459666921.50639661751.4500221042

    Sheet2

    Question 1

    Documentation Review

    Brainstorming

    Delphi Technique

    Interviewing

    Root Cause Identification

    SWOT Analysis

    Checklist Analysis

    Assumptions Analysis

    Pareto Chart

    Cause And Effect Diagram

    System Or Process Flow Chart

    Influence Diagrams

    None

    Other

    Question 2

    Risk Probability and Impact Assessment

    Probability and Impact Matrix

    Risk Data Quality Assessment

    Risk Categorization

    Risk Urgency Assessment

    None

    Other

    Question 3

    Interviewing

    Probability Distributions

    Expert Judgment

    Sensitivity Analysis

    Expected Monetary Value

    Decision Tree Analysis

    Modeling and Simulations

    None

    Other

    Question 4

    Yes

    No

    Question 5

    Crystal Ball (Excel)

    @Risk (Excel)

    Risky Project (MS Project, Primavera)

    @Risk (Excel)

    Primavera Risk Analysis (Primavera)

    Predict!

    Risk+ (Microsoft Project)

    None

    Other

    Question 6

    Entirely Data

    Part of Data

    No Need

    Question 7

    Risk database

    Project scope statement

    Roles and responsibilities, risk categories, RBS

    Risk register

    Project schedule management plan

    Project cost management plan

    None

    Other

    Question 8

    Yes

    No

    Question 9

    Probabilistic analysis of the project

    Probabilistic achievment in cost and time objectives

    Prioritized list of quantified risks

    Trends in quantitative analysis results

    None

    Other

    Question 10

    Bugs/errors

    Limits of software

    Cost

    Not sufficiently tailored for business

    Difficulty of use

    Not necessary

    Incompatibility with existing software

    Perceived lack of support

    Lack of product knowledge

    Perceived unreliability

    Lack of user friendliness

    None

    Other

    Question 11

    Ability to customize

    Usability/ user friendliness

    Extended functionality /variety of functions

    compatibility with other programs

    Technical support

    Cost

    Question 12

    Importability / exportability to PM software

    Reporting

    Probability simulation

    Risk/treatment database

    Risk treatment management

    None

    Other

    Question 13

    Additional Risk Response Planning

    Project Risk Response Audits

    Earned Value Analysis

    Technical Performance Measurement

    Reserve Analysis

    Status Meetings

    None

    Other

    Question

    High

    Medium

    Low

    Not at all

    N/A

    Sheet3

    Years in Current PositionMeanStd DevExperienceMeanStd DevAgeMeanStd DevRoleClientConsultantContractorProj/YearMeanStd DevRisk IdentificationDocumentation ReviewBrainstormingDelphi TechniqueInterviewingRoot Cause IdentificationSWOT AnalysisChecklist AnalysisAssumptions AnalysisPareto ChartCause And Effect DiagramSystem Or Process Flow ChartInfluence DiagramsOtherPercentQualitative TechniqueRisk Probability and Impact AssessmentProbability and Impact MatrixRisk Data Quality AssessmentRisk CategorizationRisk Urgency AssessmentOtherPercentQuantitative TechniqueInterviewingProbability DistributionsExpert JudgmentSensitivity AnalysisExpected Monetary ValueDecision Tree AnalysisModeling and SimulationsPercentUse of SoftwareYES CountNO CountSoftwareCrystal Ball (Excel)@Risk (Excel)RiskyProject (Microsoft Project, Primavera)@Risk (Microsoft Project)Primavera Risk Analysis (Primavera)Predict!Risk+ (Microsoft Project)PercentPreProc LevelEntire DataPart of DataNo NeedPercentInput typeRisk databaseProject scope statementRoles and responsibilities, risk categories, RBSRisk registerProject schedule management planProject cost management planPercentOutput UnderstandabilityYesNoPercentOutput TypeProbabilistic analysis of the projectProbabilistic achievment in cost and time objectivesPrioritized list of quantified risksTrends in quantitative analysis resultsPercentReason of Not Using SoftwareBugs/errorsLimits of softwareCostNot sufficiently tailored for businessDifficulty of useNot necessaryIncompatibility with existing softwarePerceived lack of supportLack of product knowledgePerceived unreliabilityLack of user friendlinessPercentAbility to CustomizeUsability/User FriendlinessExtended Functionality/Variety of FunctionsCompatibility with other ProgramsTechnical SupportImportability/Exportibility into other PM Software SystemReportingProbability SimulationRisk/Treatment DatabaseRisk/Treatment ManagementMonitor and ControlAdditional Risk Response PlanningProject Risk Response AuditsEarned Value AnalysisTechnical Performance MeasurementReserve AnalysisStatus MeetingsPercent

    1.52.88636363642.32510620863410.45454545458.73574763336035.954545454511.6453117912Consultant14193320139.2380952381382.2385133735Documentation review411601411812704320118Risk Probability and Impact Assessment30817176179Sensitivity Analysis233386104589Yes1452Crystal Ball (Excel)425250220Entirely data127120Risk Database83236426No141226Probabilistic Analysis of the Project9526223119251901200474MeanStd DevMeanStd DevMeanStd DevMeanStd DevMeanStd DevMeanStd DevMeanStd DevMeanStd DevMeanStd DevMeanStd DevEarned Value Analysis1781118142997

    21.212121212128.787878787950Cause and Effect Diagram34.745762711913.5593220339011.86440677979.32203389836.779661016910.16949152545.932203389803.38983050852.54237288141.69491525420100Risk Data Quality Assessment37.974683544310.126582278521.518987341821.51898734187.59493670891.2658227848100Expected Monetary Value25.84269662923.370786516942.69662921356.741573033711.23595505624.49438202255.617977528110021.212121212178.7878787879Primavera Risk Analysis (Primavera)2010251025010100Entirely data60355100Roles and Responsibilities, Risk Categories, RBS30.769230769211.53846153857.692307692311.538461538523.076923076915.3846153846100No53.846153846246.1538461538100Probabilistic Achievement in Cost and Time Objectives40.909090909122.72727272739.090909090927.27272727271004.05405405411.351351351425.67567567572.70270270276.756756756825.675675675701.351351351427.02702702705.4054054054100413.16666666671.64224532183.33333333331.073086743.33333333331.30267789463.92307692311.25575597834.08333333330.99620491994.61538461540.506369683540.77459666923.46153846151.50639661753.46153846151.4500221042Reserve analysis17.52577319598.247422680411.340206185618.556701030914.432989690729.8969072165100

    System or Process Flow Chart62.121212121224.2424242424021.212121212116.666666666712.121212121218.181818181810.606060606106.06060606064.54545454553.03030303030178.7878787879Modeling and Simulations66Project Schedule Management PlanNoTrends in Quantitative Analysis ResultsProject Risk Response Audits

    Influence DiagramsProject Cost Management PlanNoTechnical Performance Measurement

    2529Client500Documentation reviewRisk Probability and Impact AssessmentInterviewingYesPrimavera Risk Analysis (Primavera)Entirely dataProject Schedule Management PlanNoProbabilistic Achievement in Cost and Time ObjectivesTechnical Performance Measurement

    2627Consultant100Documentation reviewRisk Probability and Impact AssessmentInterviewingYesPrimavera Risk Analysis (Primavera)Entirely dataProject Schedule Management PlanNoProbabilistic Achievement in Cost and Time ObjectivesTechnical Performance Measurement

    42260Contractor3Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    BrainstormingRisk urgency assessmentNot necessaryReserve analysis

    Assumptions AnalysisStatus meetings

    72363Contractor5Documentation reviewRisk Probability and Impact AssessmentInterviewingYesPrimavera Risk Analysis (Primavera)No needProject Scope StatementNoTrends in Quantitative Analysis ResultsAdditional Risk response planning

    BrainstormingRisk Data Quality AssessmentExpert JudgmentProject Schedule Management PlanNoReserve analysis

    Assumptions AnalysisRisk urgency assessmentExpected Monetary ValueProject Cost Management PlanNoTechnical Performance Measurement

    Modeling and SimulationsStatus meetings

    43758Contractor4Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    BrainstormingRisk urgency assessmentNot necessaryReserve analysis

    Status meetings

    51235Client3Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentYesRisk+ (Microsoft Project)Part of the dataProject Schedule Management PlanYesProbabilistic Analysis of the ProjectProject Risk Response Audits

    BrainstormingTechnical Performance Measurement

    3323Contractor2Assumptions AnalysisRisk CategorizationInterviewingNoNot necessaryStatus meetings

    Interviewing

    SWOT Analysis

    2222Contractor12Documentation reviewRisk Data Quality AssessmentInterviewingYes@Risk (Excel)Entirely dataRisk DatabaseYesProbabilistic Analysis of the ProjectStatus meetings

    InterviewingExpert Judgment@Risk (Microsoft Project)Entirely dataProject Schedule Management PlanYesPrioritized List of Quantified Risks

    Checklist AnalysisSensitivity Analysis

    Assumptions Analysis

    SWOT Analysis

    Influence Diagrams

    1122Contractor50Documentation reviewRisk Data Quality AssessmentExpert JudgmentNoLack of user friendlinessTechnical Performance Measurement

    1125ClientDocumentation reviewRisk urgency assessmentInterviewingyes@Risk (Excel)Entirely dataProject Scope StatementNoTrends in Quantitative Analysis ResultsAdditional Risk response planning

    Checklist Analysis@Risk (Microsoft Project)Entirely data

    1328Client50Cause and Effect DiagramRisk Probability and Impact AssessmentExpert JudgmentYesCrystal Ball (Excel)Entirely dataRisk DatabaseNoProbabilistic Analysis of the ProjectAdditional Risk response planning

    Root Cause IdentificationRisk CategorizationSensitivity AnalysisRisk RegisterNoTrends in Quantitative Analysis ResultsEarned Value Analysis

    Reserve analysis

    2528Contractor5SWOT AnalysisProbability and Impact MatrixInterviewingYesRiskyProject (Microsoft Project, Primavera)Part of the dataRisk DatabaseYesProbabilistic Analysis of the ProjectStatus meetings

    Prioritized List of Quantified Risks

    21041Consultant5+Documentation reviewRisk Probability and Impact AssessmentInterviewingYesCrystal Ball (Excel)Entirely dataRisk DatabaseYesProbabilistic Analysis of the ProjectAdditional Risk response planning

    InterviewingSensitivity AnalysisPrimavera Risk Analysis (Primavera)Entirely dataRisk RegisterYesTrends in Quantitative Analysis ResultsTechnical Performance Measurement

    Checklist AnalysisModeling and SimulationsProject Cost Management PlanYesStatus meetings

    Cause and Effect Diagram

    1224Consultant5Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentYesCrystal Ball (Excel)Part of the dataRoles and Responsibilities, Risk Categories, RBSYesProbabilistic Analysis of the ProjectAdditional Risk response planning

    BrainstormingRisk Data Quality AssessmentExpected Monetary ValueRiskyProject (Microsoft Project, Primavera)Part of the dataProject Scope StatementYesTrends in Quantitative Analysis ResultsTechnical Performance Measurement

    Checklist AnalysisRisk+ (Microsoft Project)Part of the dataProject Cost Management PlanYes

    1123Consultant10Documentation reviewRisk Data Quality AssessmentExpert JudgmentNoCostStatus meetings

    BrainstormingRisk urgency assessmentLack of product knowledge

    Checklist Analysis

    SWOT Analysis

    2224Consultant10Documentation reviewRisk Probability and Impact AssessmentProbability DistributionsNoLack of product knowledgeStatus meetings

    2428Contractor5Documentation reviewRisk Probability and Impact AssessmentInterviewingNoLack of product knowledgeStatus meetings

    Checklist AnalysisRisk Data Quality AssessmentExpert Judgment

    2325Client100Cause and Effect DiagramRisk CategorizationExpert JudgmentNoLack of product knowledgeStatus meetings

    1124Contractor2Root Cause IdentificationRisk CategorizationExpert JudgmentNoCostTechnical Performance Measurement

    1540Contractor2InterviewingRisk Data Quality AssessmentInterviewingNoLack of product knowledgeTechnical Performance Measurement

    3529Consultant5Documentation reviewRisk Data Quality AssessmentProbability DistributionsNoLack of product knowledgeReserve analysis

    6629Client10Documentation reviewRisk Probability and Impact AssessmentInterviewingYesRiskyProject (Microsoft Project, Primavera)Part of the dataRisk DatabaseYesProbabilistic Analysis of the ProjectAdditional Risk response planning

    Checklist AnalysisSensitivity AnalysisRisk RegisterYesProbabilistic Analysis of the ProjectStatus meetings

    2837Client10Documentation reviewProbability and Impact MatrixExpert JudgmentNoNot necessaryStatus meetings

    Checklist AnalysisExpected Monetary ValueLack of product knowledgeReserve analysis

    12558Consultant5Documentation reviewProbability and Impact MatrixInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    21438Consultant5Documentation reviewProbability and Impact MatrixExpert JudgmentNoNot sufficiently tailored for BusinessAdditional Risk response planning

    Assumptions AnalysisRisk Data Quality AssessmentInterviewingNot necessaryStatus meetings

    Root Cause Identification

    31135Consultant5Documentation reviewProbability and Impact MatrixExpert JudgmentNoPerceived lack of SupportAdditional Risk response planning

    BrainstormingRisk Data Quality AssessmentInterviewingCostStatus meetings

    SWOT Analysis

    152040Contractor6Checklist AnalysisRisk CategorizationDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Root Cause Identification

    91842Contractor4InterviewingRisk CategorizationInterviewingNoNot necessaryStatus meetings

    2225Contractor5InterviewingProbability and Impact MatrixInterviewingNoLimits of SoftwareStatus meetings

    3528Contractor6Root Cause IdentificationRisk Data Quality AssessmentExpert JudgmentNoLack of user friendlinessAdditional Risk response planning

    3832Consultant5Documentation reviewRisk Probability and Impact AssessmentInterviewingYesRiskyProject (Microsoft Project, Primavera)Part of the dataRisk DatabaseYesProbabilistic Achievement in Cost and Time ObjectivesTechnical Performance Measurement

    2325Contractor3Documentation reviewRisk Data Quality AssessmentExpert JudgmentNoCostProject Risk Response Audits

    2835Consultant5Root Cause IdentificationRisk Data Quality AssessmentExpected Monetary ValueYesRiskyProject (Microsoft Project, Primavera)Entirely dataRisk DatabaseYesProbabilistic Achievement in Cost and Time ObjectivesTechnical Performance Measurement

    3530Contractor5Root Cause IdentificationRisk CategorizationExpected Monetary ValueNoBugs/errorsEarned Value Analysis

    Cost

    2530Consultant2SWOT AnalysisRisk Probability and Impact AssessmentModeling and SimulationsNoCostEarned Value Analysis

    2830Contractor1SWOT AnalysisRisk Probability and Impact AssessmentProbability DistributionsNoDifficulty of useStatus meetings

    Lack of user friendliness

    52555Contractor3Documentation reviewRisk CategorizationExpert JudgmentNoCostReserve analysis

    BrainstormingDifficulty of use

    32250Contractor5Documentation reviewRisk CategorizationExpert JudgmentNoCostReserve analysis

    BrainstormingDifficulty of use

    51242Contractor3Checklist AnalysisRisk CategorizationDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Root Cause Identification

    31538Contractor5Checklist AnalysisRisk CategorizationDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Root Cause Identification

    3530Contractor5Root Cause IdentificationRisk CategorizationExpected Monetary ValueNoBugs/errorsEarned Value Analysis

    Cost

    42260Contractor3Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    BrainstormingRisk urgency assessmentNot necessaryReserve analysis

    1540Contractor2InterviewingRisk Data Quality AssessmentInterviewingNoLack of product knowledgeTechnical Performance Measurement

    3530Contractor5Root Cause IdentificationRisk CategorizationExpected Monetary ValueNoBugs/errorsEarned Value Analysis

    Cost

    1124Consultant20InterviewingRisk Data Quality AssessmentExpert JudgmentNoCostStatus meetings

    Not necessary

    12558Consultant20Documentation reviewProbability and Impact MatrixInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    21844Consultant20Documentation reviewProbability and Impact MatrixInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    1224Contractor-Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryReserve analysis

    System or Process Flow ChartRisk CategorizationSensitivity AnalysisStatus meetings

    SWOT AnalysisModeling and Simulations

    1124Contractor2System or Process Flow ChartRisk Data Quality AssessmentDecision Tree AnalysisNoLack of product knowledgeTechnical Performance Measurement

    Checklist AnalysisProject Risk Response Audits

    1327Contractor2BrainstormingRisk Probability and Impact AssessmentInterviewingNoNot necessaryStatus meetings

    41640Client1500Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    21035Client1500BrainstormingRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    Documentation review

    21236Client1500BrainstormingRisk Probability and Impact AssessmentExpert JudgmentNoLack of product knowledgeAdditional Risk response planning

    Documentation review

    81541Contractor5Assumptions AnalysisRisk Probability and Impact AssessmentExpert JudgmentNoLack of user friendlinessAdditional Risk response planning

    53061Contractor4Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoCostStatus meetings

    BrainstormingRisk CategorizationExpected Monetary ValueDifficulty of useReserve analysis

    Assumptions Analysis

    52050Contractor8Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoCostStatus meetings

    BrainstormingRisk CategorizationExpected Monetary ValueDifficulty of useReserve analysis

    51538Client700Documentation reviewRisk Probability and Impact AssessmentInterviewingNoCostProject Risk Response Audits

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    32052Client700Documentation reviewRisk Probability and Impact AssessmentInterviewingNoCostStatus meetings

    InterviewingExpert JudgmentNot necessaryEarned Value Analysis

    Additional Risk response planning

    21136Client1500InterviewingNoNot sufficiently tailored for BusinessStatus meetings

    1732Consultant100NoLack of product knowledge

    31034Contractor20Documentation reviewOthersExpert JudgmentNoCostStatus meetings

    BrainstormingNot necessaryReserve analysis

    1930Contractor15Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryStatus meetings

    Risk Categorization

    2729Consultant25Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryStatus meetings

    5831Client100Documentation reviewExpert JudgmentNoLack of product knowledgeStatus meetings

    1630Consultant30Documentation reviewRisk Probability and Impact AssessmentExpert JudgmentNoNot necessaryTechnical Performance Measurement

    ANOVA

    RISK IDENTIFICATION Techniques

    DatasetGlobalLocal

    Documentation Review19341

    Anova: Single FactorBrainstorming16716

    Delphi Technique160

    SUMMARYInterviewing8914

    GroupsCountSumAverageVarianceRoot Cause Identification9411

    Documentation Review223411711552SWOT Analysis898

    Brainstorming218391.511400.5Checklist Analysis12812

    Delphi Technique2168128Assumptions Analysis667

    Interviewing210351.52812.5Pareto Chart150

    Root Cause Identification210552.53444.5Cause And Effect Diagram644

    SWOT Analysis29748.53280.5System Or Process Flow Chart603

    Checklist Analysis2140706728Influence Diagrams182

    Assumptions Analysis27336.51740.5None00

    Pareto Chart2157.5112.5Other140

    Cause And Effect Diagram268341800

    System Or Process Flow Chart26331.51624.5

    Influence Diagrams22010128

    None2000

    Other214798

    ANOVA

    Source of VariationSSdfMSFP-valueF crit

    Between Groups31259.1785714286132404.55219780220.75059322330.69443941112.5072633745

    Within Groups44849.5143203.5357142857

    Total76108.678571428627

    QUALITATIVE ANALYSIS Techniques

    DatasetGlobalLocal

    Anova: Single FactorRisk Probability and Impact Assessment17630

    Probability and Impact Matrix1038

    SUMMARYRisk Data Quality Assessment6317

    GroupsCountSumAverageVarianceRisk Categorization13217

    Risk Probability and Impact Assessment220610310658Risk Urgency Assessment546

    Probability and Impact Matrix211155.54512.5None180

    Risk Data Quality Assessment280401058Other11

    Risk Categorization214974.56612.5

    Risk Urgency Assessment260301152

    None2189162

    Other2210

    ANOVA

    Source of VariationSSdfMSFP-valueF crit

    Between Groups15651.857142857162608.64285714290.75597184850.6254763733.8659688531

    Within Groups2415573450.7142857143

    Total39806.857142857113

    QUANTITATIVE ANALYSIS Techniques

    DatasetGlobalLocal

    Anova: Single FactorInterviewing11723

    Probability Distributions753

    SUMMARYExpert Judgment17038

    GroupsCountSumAverageVarianceSensitivity Analysis766

    Interviewing2140704418Expected Monetary Value8910

    Probability Distributions278392592Decision Tree Analysis494

    Expert Judgment22081048712Modeling and Simulations805

    Sensitivity Analysis282412450None50

    Expected Monetary Value29949.53120.5Other10

    Decision Tree Analysis25326.51012.5

    Modeling and Simulations28542.52812.5

    None252.512.5

    Other210.50.5

    ANOVA

    Source of VariationSSdfMSFP-value

    Between Groups16433.111111111182054.13888888890.73564990750.6620437035

    Within Groups25130.592792.2777777778

    Total41563.611111111117

    USE OF SOFTWARE

    DatasetGlobalLocal

    Anova: Single FactorYES5614

    NO21152

    SUMMARY

    GroupsCountSumAverageVariance

    YES27035882

    NO2263131.512640.5

    ANOVA

    Source of VariationSSdfMSFP-value

    Between Groups9312.2519312.251.37729709740.3613996051

    Within Groups13522.526761.25

    Total22834.753

    REASON FOR NOT USING SOFTWARE

    Anova: Single FactorDatasetGlobalLocal

    Bugs/errors163

    SUMMARYLimits of software401

    GroupsCountSumAverageVarianceCost8319

    Bugs/errors2199.584.5Not sufficiently tailored for business742

    Limits of software24120.5760.5Difficulty of use165

    Cost2102512048Not necessary5719

    Not sufficiently tailored for business276382592Perceived unreliability120

    Difficulty of use22110.560.5Lack of user friendliness124

    Not necessary27638722None140

    Incompatibility with existing software214798Other110

    Perceived lack of support214772

    Lack of product knowledge28040800

    Perceived unreliability212672

    Lack of user friendliness216832

    None214798

    Other2115.560.5

    ANOVA

    Source of VariationSSdfMSFP-value

    Between Groups6511.846153846112542.65384615380.94060.539170767

    Within Groups750013576.9230769231

    Total14011.846153846225

    MONITORING and CONTROL Techniques

    DatasetGlobalLocal

    Anova: Single FactorAdditional Risk Response Planning10617

    Project Risk Response Audits1388

    SUMMARYEarned Value Analysis8311

    GroupsCountSumAverageVarianceTechnical Performance Measurement10318

    Additional Risk Response Planning212361.53960.5Reserve Analysis3314

    Project Risk Response Audits2146738450Status Meetings20129

    Earned Value Analysis294472592

    Technical Performance Measurement212160.53612.5

    Reserve Analysis24723.5180.5

    Status Meetings223011514792

    None2000

    Other273.524.5

    ANOVA

    Source of VariationSSdfMSFP-value

    Between Groups2067672953.71428571430.70301422960.6722819828

    Within Groups3361284201.5

    Total5428815

    Linear Regression

    RISK IDENTIFICATION Techniques

    GlobalLocalLocalGlobal

    Documentation Review1934141193

    Brainstorming1671616167

    Interviewing89141489

    Checklist Analysis1281212128

    Root Cause Identification94111194

    SWOT Analysis898889

    Assumptions Analysis667766

    Cause And Effect Diagram644464

    System Or Process Flow Chart603360

    Influence Diagrams182218

    Delphi Technique160016

    Pareto Chart150015

    Other140014

    None0000

    Correlation Coefficient R0.8910087636Correlation Coefficient R0.8910087636

    QUALITATIVE ANALYSIS Techniques

    GlobalLocalLocalGlobal

    Risk Probability and Impact Assessment1763030176

    Risk Categorization1321717132

    Risk Data Quality Assessment63171763

    Probability and Impact Matrix10388103

    Risk Urgency Assessment546654

    Other1111

    None180018

    Correlation Coefficient R0.888873242Correlation Coefficient R0.888873242

    QUANTITATIVE ANALYSIS Techniques

    LocalGlobal

    GlobalLocal38170

    Expert Judgment1703823117

    Interviewing117231089

    Expected Monetary Value8910676

    Sensitivity Analysis766580

    Modeling and Simulations805449

    Decision Tree Analysis494375

    Probability Distributions75305

    None50

    Correlation Coefficient R0.9132357809

    Correlation Coefficient R0.9132357809

    MONITORING and CONTROL Techniques

    GlobalLocalLocalGlobal

    Status Meetings2012929201

    Technical Performance Measurement1031818103

    Additional Risk Response Planning1061717106

    Reserve Analysis33141433

    Earned Value Analysis83111183

    Project Risk Response Audits13888138

    Other7007

    None0000

    Correlation Coefficient R0.8205123376

    Correlation Coefficient R0.8205123376

    REASON FOR NOT USING SOFTWARE

    GlobalLocalLocalGlobal

    Cost83191983

    Not necessary57191957

    Difficulty of use165516

    Bugs/errors163316

    Not sufficiently tailored for business742274

    Limits of software401140

    Perceived lack of support131113

    Incompatibility with existing software140014

    Correlation Coefficient R0.6371515468Correlation Coefficient R0.6371515468

    Linear Regression

    Local

    Global

    Local

    Spearman's Correlation

    Global

    Local

    Global

    t-test

    Global

    Local

    Global Calculation

    Local

    Global

    Graphs

    Global

    Local

    Sheet8

    Global

    Global

    Local

    Sheet7

    Local

    Global

    Local

    Sheet5

    Global

    Global

    Local

    Sheet6

    Global

    Local

    Sheet4

    Global

    Global

    Local

    RISK IDENTIFICATION TechniquesRankingC1Rank

    Reduces duration6.21

    GlobalLocalGlobal RankLocal Rankdidi2Limits design options62

    Documentation Review193411100Increases jobsite management efficiency62

    Brainstorming167162200Increases productivity5.73CommercialConsultantsContractorsdidi26 x di2nn(n2-1)

    Interviewing89145324Reduces environmental impact of construction operations5.73Reduces onsite disruption of other adjacent operations11000703429301

    Checklist Analysis1281234-11Transportation restraints limit the use of offsite construction techniques5.73Reduces duration11000703429301233

    Root Cause Identification941145-11Increases project design efficiency5.73Reduces workers54116703429300.91428571436 x 1398

    SWOT Analysis8986600Decreases onsite labor congestion5.73Transportation restraints limit the use of offsite construction techniques312424703429300.6571428571n70

    Assumptions Analysis6677700Increases labor savings5.73Reduces environmental impact of construction operations22000703429301n(n2-1)342930

    Cause And Effect Diagram6448800Reduces workers5.34Increases labor savings413954703429300.22857142860.9959233663

    System Or Process Flow Chart6039900Reduces onsite disruption of other adjacent operations5.34Increases jobsite management efficiency422424703429300.6571428571

    Influence Diagrams182101000Reduces project cost4.75Increases productivity21116703429300.9142857143

    Delphi Technique160111100Increases overall cost savings4.75Increases project design efficiency13-2424703429300.6571428571

    Pareto Chart150121200Limits changes in onsite work4.36Decreases onsite labor congestion22000703429301

    Other140131300Increases design cost4.36Limits changes in onsite work18-74929470342930-3.2

    None00141400Computer software for designing offsite construction techniques limits their uses4.36Project planning system the one of the barriers of offsite construction210-86438470342930-4.4857142857

    Increase product quality47Increases safety performance59-4169670342930-0.3714285714

    6Increases safety performance3.38Increase product quality49-52515070342930-1.1428571429

    6 x 36Project planning system the one of the barriers of offsite construction39Limits design options57-2424703429300.6571428571

    n14Increases design cost46-2424703429300.6571428571

    n(n2-1)2730Reduces project cost26-4169670342930-0.3714285714

    Increases overall cost savings15-4169670342930-0.3714285714

    0.0131868132Computer software for designing offsite construction techniques limits their uses37-4169670342930-0.3714285714

    0.9868131868233

    QUALITATIVE ANALYSIS Techniques

    GlobalLocalGlobal RankLocal Rankdidi2

    Risk Probability and Impact Assessment176301100

    Risk Categorization132172200

    Risk Data Quality Assessment63174311

    Probability and Impact Matrix103834-11

    Risk Urgency Assessment5465500

    Other117611

    None18067-11

    4

    6 x 24

    n7

    n(n2-1)336Spearman's correlationCACBC1C2C3C4C5C6didi26 x di2nn(n2-1)

    Transportation restraints limit the use of offsite construction techniques17352443-277294374703429300.9872452104

    0.0714285714Rreduces duration21111111-525150703429300.9995625929

    0.9285714286Reduces workers313481862-3915219126703429300.973388155

    Increases productivity46364453-277294374703429300.9872452104

    Decreases onsite labor congestion53374314-204002400703429300.9930014872

    QUANTITATIVE ANALYSIS TechniquesReduces environmental impact of construction operations64343336-204002400703429300.9930014872ResidentialConsultantsContractorsdidi26 x di2nn(n2-1)

    Increases jobsite management efficiency73286546-277294374703429300.9872452104Reduces onsite disruption of other adjacent operations14-3954703429300.9998425335

    GlobalLocalGlobal RankLocal Rankdidi2Reduces onsite disruption of other adjacent operations8243344-12144864703429300.9974805354Reduces duration11000703429301

    Expert Judgment170381100Increases labor savings96322863-214412646703429300.9922841396Reduces workers24-2424703429300.9999300149

    Interviewing117232200Increases design cost105685667-3310896534703429300.9809465489Transportation restraints limit the use of offsite construction techniques24-2424703429300.9999300149

    Expected Monetary Value89103300Project planning system the one of the barriers of offsite construction11149811698-54291617496703429300.9489808416Reduces environmental impact of construction operations34-116703429300.9999825037317

    Sensitivity Analysis7665411Increase product quality128759756-3512257350703429300.9785670545Increases labor savings440007034293016 x 1902

    Modeling and Simulations80545-11Limits design options13827611108-3915219126703429300.973388155Increases jobsite management efficiency532424703429300.9999300149n70

    Decision Tree Analysis4947611Increases project design efficiency1412354555-256253750703429300.9890648237Increases productivity6241696703429300.9997200595n(n2-1)342930

    Probability Distributions75367-11Limits changes in onsite work159687296-3210246144703429300.9820838072Increases project design efficiency660007034293010.9944536786

    None508800Reduces project cost16115581073-3310896534703429300.9809465489Decreases onsite labor congestion6241696703429300.9997200595

    Increases safety performance17108777105-3713698214703429300.9760475899Limits changes in onsite work7341696703429300.9997200595

    4Computer software for designing offsite construction techniques limits their uses18106869116-3814448664703429300.9747353687Project planning system the one of the barriers of offsite construction8441696703429300.9997200595

    6 x 24Increases overall cost savings1995310782-256253750703429300.9890648237Increases safety performance963954703429300.9998425335

    n818045Increase product quality10641696703429300.9997200595

    n(n2-1)5046 x 108270Limits design options1073954703429300.9998425335

    n70Increases design cost11741696703429300.9997200595

    0.0476190476RankingCBRankn(n2-1)342930Reduces project cost126636216703429300.9993701338

    0.9523809524Rreduces duration6.110.6842795906Increases overall cost savings123981486703429300.9985828012

    Reduces onsite disruption of other adjacent operations62Computer software for designing offsite construction techniques limits their uses135864384703429300.9988802379

    Increases jobsite management efficiency5.83317

    MONITORING and CONTROL TechniquesDecreases onsite labor congestion5.83Consultants RankingResidentialRank

    Reduces environmental impact of construction operations5.74Reduces onsite disruption of other adjacent operations6.11Consultants RankingResidentialCommercialIndustrialInfrastructuredidi26 x di2nn(n2-1)InfrastructureConsultantsContractorsdidi26 x di2nn(n2-1)

    GlobalLocalGlobal RankLocal Rankdidi2Increases design cost5.65Reduces duration6.11Reduces onsite disruption of other adjacent operations1133-636216703429300.9993701338Reduces onsite disruption of other adjacent operations32116703429300.9999825037

    Status Meetings201291100Increases productivity5.56Reduces workers62Reduces duration1111-2424703429300.9999300149Reduces duration11000703429301

    Technical Performance Measurement103184224Increases labor savings5.56Transportation restraints limit the use of offsite construction techniques62Reduces workers2589-204002400703429300.9930014872Reduces workers9541696703429300.9997200595

    Additional Risk Response Planning106173300Transportation restraints limit the use of offsite construction techniques5.37Reduces environmental impact of construction operations5.93Transportation restraints limit the use of offsite construction techniques2311-3954703429300.9998425335Transportation restraints limit the use of offsite construction techniques11000703429301

    Reserve Analysis33146424Increase product quality5.28Increases labor savings5.74Reduces environmental impact of construction operations3242-525150703429300.9995625929Reduces environmental impact of construction operations22000703429301

    Earned Value Analysis83115500Limits design options5.28Increases jobsite management efficiency5.45Increases labor savings4454-981486703429300.9985828012Increases labor savings45-116703429300.9999825037

    Project Risk Response Audits138826-416Limits changes in onsite work5.19Increases productivity5.36Increases jobsite management efficiency5458-12144864703429300.9974805354Increases jobsite management efficiency8441696703429300.9997200595

    Other707700Increases overall cost savings5.19Increases project design efficiency5.36Increases productivity6233-2424703429300.9999300149Increases productivity37-41696703429300.9997200595

    None008800Increases safety performance510Decreases onsite labor congestion5.36Increases project design efficiency6136-41696703429300.9997200595Increases project design efficiency65116703429300.9999825037

    Computer software for designing offsite construction techniques limits their uses4.710Limits changes in onsite work57Decreases onsite labor congestion6264-636216703429300.9993701338Decreases onsite labor congestion43116703429300.9999825037

    24Reduces project cost4.611Project planning system the one of the barriers of offsite construction4.88Limits changes in onsite work7174-525150703429300.9995625929Limits changes in onsite work48-41696703429300.9997200595

    6 x 144Increases project design efficiency4.512Increases safety performance4.79Project planning system the one of the barriers of offsite construction8248-636216703429300.9993701338Project planning system the one of the barriers of offsite construction810-2424703429300.9999300149

    n8Reduces workers4.113Increase product quality4.610Increases safety performance9567-981486703429300.9985828012Increases safety performance77000703429301

    n(n2-1)504Project planning system the one of the barriers of offsite construction3.714Limits design options4.610Increase product quality10425-116703429300.9999825037Increase product quality56-116703429300.9999825037

    Increases design cost4.211Limits design options10532000703429301Limits design options28-636216703429300.9993701338

    0.2857142857Reduces project cost412Increases design cost11477-749294703429300.9991426822Increases design cost752424703429300.9999300149

    0.7142857143Increases overall cost savings412Reduces project cost12232525150703429300.9995625929Reduces project cost27-525150703429300.9995625929

    Computer software for designing offsite construction techniques limits their uses3.313Increases overall cost savings121632424703429300.9999300149Increases overall cost savings39-636216703429300.9993701338

    REASON FOR NOT USING SOFTWAREComputer software for designing offsite construction techniques limits their uses13367-3954703429300.9998425335Computer software for designing offsite construction techniques limits their uses711-41696703429300.9997200595

    Spearman's Correlationconsultant Rankcontractor Rankdidi26 x di2nn(n2-1)190

    GlobalLocalGlobal RankLocal Rankdidi2Rreduces duration5.61875110007034293019856 x 1140

    Cost83191100Transportation restraints limit the use of offsite construction techniques5.5692307692220007034293016 x 5910n70

    Not necessary57193211Reduces onsite disruption of other adjacent operations5.553846153833000703429301n70n(n2-1)342930

    Difficulty of use1656339Reduces environmental impact of construction operations5.461538461544000703429301n(n2-1)3429300.9966757064

    Bugs/errors1635411Increases labor savings5.307692307755000703429301RankingCommercialRank0.9827661622

    Not sufficiently tailored for business74225-39Decreases onsite labor congestion5.246153846266000703429301Limits changes in onsite work71

    Limits of software40146-24Increases productivity5.215384615477000703429301Reduces duration71Contractors RankingResidentialCommercialIndustrialInfrastructuredidi26 x di2nn(n2-1)IndustrialConsultantsContractorsdidi26 x di2nn(n2-1)

    Perceived lack of support1318711Increases jobsite management efficiency5.046153846288000703429301Reduces onsite disruption of other adjacent operations71Offsite construction techniques reduces the overall project schedule1111-2424703429300.9999300149Reduces onsite disruption of other adjacent operations33000703429301

    Incompatibility with existing software14078-11Increases project design efficiency4.923076923199000703429301Increases project design efficiency71Offsite construction techniques increases overall labour productivity2165-10100600703429300.9982503718Reduces duration11000703429301

    Reduces workers4.86153846151012-2424703429300.9999300149Increases overall cost savings71Offsite construction techniques decreases onsite labour congestion2233-636216703429300.9993701338Reduces workers8441696703429300.9997200595

    26Limits changes in onsite work4.70769230771113-2424703429300.9999300149Reduces project cost62Offsite/construction techniques limits the ability to make change onsite work3868-193612166703429300.9936838422Transportation restraints limit the use of offsite construction techniques13-2424703429300.9999300149

    6 x 156Limits design options4.707692307712102424703429300.9999300149Increases productivity62Offsite construction techniques increase jobsite management efficiency3284-11121726703429300.9978829499Reduces environmental impact of construction operations44000703429301

    n8Increases safety performance4.630769230813112424703429300.9999300149Reduces environmental impact of construction operations62Offsite construction techniques increases overall cost savings3559-162561536703429300.9955209518Increases labor savings523954703429300.9998425335

    n(n2-1)504Increases overall cost savings4.63076923081416-2424703429300.9999300149Decreases onsite labor congestion62Offsite construction techniques reduces the need for skilled craft workers onsite4445-981486703429300.9985828012Increases jobsite management efficiency58-3954703429300.9998425335

    Increase product quality4.55384615381515000703429301Project planning system the one of the barriers of offsite construction62Offsite construction techniques reduces onsite disruption of other adjacent operations4132-2424703429300.9999300149Increases productivity36-3954703429300.9998425335

    0.3095238095Reduces project cost4.523076923116142424703429300.9999300149Transportation restraints limit the use of offsite construction techniques43Offsite construction techniques reduces negative environmental impact of construction operations4142-3954703429300.9998425335Increases project design efficiency36-3954703429300.9998425335

    0.6904761905Increases design cost4.41718-116703429300.9999825037Computer software for designing offsite construction techniques limits their uses43Transportation restraints (size constraints, transportation cost, and impact on the building structures) limit the use of offsite construction techniques4131-116703429300.9999825037Decreases onsite labor congestion633954703429300.9998425335

    Computer software for designing offsite construction techniques limits their uses4.15384615381819-116703429300.9999825037Increase product quality34Offsite construction techniques increases labour savings4125-41696703429300.9997200595Limits changes in onsite work76116703429300.9999825037

    Project planning system the one of the barriers of offsite construction4.061538461519172424703429300.9999300149Increases design cost34Is the increased complexity of project planning system the one of the barriers of offsite construction410910-256253750703429300.9890648237Project planning system the one of the barriers of offsite construction49-525150703429300.9995625929

    Increases jobsite management efficiency34Complicated computer software for designing offsite construction techniques limits their uses57711-204002400703429300.9930014872Increases safety performance66000703429301

    Increases labor savings34Offsite construction techniques reduces the project construction cost6687-152251350703429300.9960633365Increase product quality25-3954703429300.9998425335

    30Reduces workers25Offsite construction techniques increase product quality6957-152251350703429300.9960633365Limits design options35-2424703429300.9999300149

    6 x 180Limits design options25Offsite construction techniques increases safety performance6967-162561536703429300.9955209518Increases design cost71636216703429300.9993701338

    n70Increases safety performance25Offsite construction techniques increase project design efficiency6365-864384703429300.9988802379Reduces project cost38-525150703429300.9995625929

    n(n2-1)342930Offsite construction techniques limits design options7758-131691014703429300.9970431283Increases overall cost savings65116703429300.9999825037

    0.9994751115Offsite construction techniques increases design cost7615-525150703429300.9995625929Computer software for designing offsite construction techniques limits their uses67-116703429300.9999825037

    2978167

    RankingIndustrialRank6 x 178686 x 1002

    Transportation restraints limit the use of offsite construction techniques5.31Contractors rankingCommercialRankn70n70

    RankingC2RankReduces duration5.31Offsite construction techniques reduces the overall project schedule5.81n(n2-1)342930n(n2-1)342930

    Reduces duration6.31Increase product quality5.22Offsite construction techniques increases overall labour productivity5.810.94789607210.9970781209

    Increases labor savings6.22Reduces project cost53Offsite construction techniques reduces onsite disruption of other adjacent operations5.81

    Reduces onsite disruption of other adjacent operations63Increases productivity53Offsite construction techniques reduces negative environmental impact of construction operations5.81

    Increases overall cost savings63Limits design options53Transportation restraints (size constraints, transportation cost, and impact on the building structures) limit the use of offsite construction techniques5.81

    Reduces environmental impact of construction operations5.74Reduces onsite disruption of other adjacent operations53Offsite construction techniques increases labour savings5.81

    Reduces project cost5.25Increases project design efficiency53Offsite construction techniques increase jobsite management efficiency5.52

    Increase product quality5.25Reduces environmental impact of construction operations4.84Offsite construction techniques decreases onsite labour congestion5.52

    Transportation restraints limit the use of offsite construction techniques5.25Project planning system the one of the barriers of offsite construction4.84Offsite construction techniques increase project design efficiency5.13

    Increases project design efficiency5.25Increases jobsite management efficiency4.75Offsite construction techniques reduces the need for skilled craft workers onsite54

    Increases productivity56Increases labor savings4.75Offsite construction techniques increases overall cost savings4.95

    Limits design options4.77Increases safety performance4.56Offsite construction techniques reduces the project construction cost4.66

    Increases safety performance4.77Computer software for designing offsite construction techniques limits their uses4.56Offsite construction techniques increases design cost4.66

    Decreases onsite labor congestion4.77Decreases onsite labor congestion4.56Offsite construction techniques limits design options4.57

    Limits changes in onsite work4.58Increases overall cost savings4.56Complicated computer software for designing offsite construction techniques limits their uses4.57

    Reduces workers4.58Limits changes in onsite work4.37Offsite/construction techniques limits the ability to make change onsite work4.48

    Computer software for designing offsite construction techniques limits their uses4.58Increases design cost4.37Offsite construction techniques increase product quality4.39

    Increases design cost4.29Reduces workers3.88Offsite construction techniques increases safety performance4.39

    Increases jobsite management efficiency4.29Is the increased complexity of project planning system the one of the barriers of offsite construction3.610

    Project planning system the one of the barriers of offsite construction3.710

    RankingInfrastructureRank

    Reduces duration61Contractors rankingIndustrialRank

    Transportation restraints limit the use of offsite construction techniques61Offsite construction techniques increases design cost6.71

    Reduces project cost5.72Offsite construction techniques reduces the overall project schedule6.71

    Limits design options5.72Offsite construction techniques increases labour savings6.32

    Reduces environmental impact of construction operations5.72Offsite construction techniques reduces onsite disruption of other adjacent operations63

    Increases productivity5.33Transportation restraints (size constraints, transportation cost, and impact on the building structures) limit the use of offsite construction techniques63

    RankingC3RankReduces onsite disruption of other adjacent operations5.33Offsite construction techniques decreases onsite labour congestion63

    Reduces duration6.21Increases overall cost savings5.33Offsite construction techniques reduces the need for skilled craft workers onsite5.74

    Reduces workers6.21Limits changes in onsite work54Offsite construction techniques reduces negative environmental impact of construction operations5.74

    Transportation restraints limit the use of offsite construction techniques62Decreases onsite labor congestion54Offsite construction techniques increase product quality5.35

    Increases labor savings62Increases labor savings54Offsite construction techniques limits design options5.35

    Reduces onsite disruption of other adjacent operations5.73Increase product quality4.75Offsite construction techniques increases overall cost savings5.35

    Reduces environmental impact of construction operations5.73Increases project design efficiency4.56Offsite/construction techniques limits the ability to make change onsite work56

    Increases productivity5.54Increases safety performance4.37Offsite construction techniques increases overall labour productivity56

    Increases project design efficiency5.54Increases design cost4.37Offsite construction techniques increases safety performance56

    Decreases onsite labor congestion5.54Computer software for designing offsite construction techniques limits their uses4.37Offsite construction techniques increase project design efficiency56

    Increases design cost5.25Increases jobsite management efficiency48Complicated computer software for designing offsite construction techniques limits their uses4.77

    Limits design options56Project planning system the one of the barriers of offsite construction48Offsite construction techniques reduces the project construction cost2.78

    Computer software for designing offsite construction techniques limits their uses56Reduces workers3.79Offsite construction techniques increase jobsite management efficiency2.78

    Increases jobsite management efficiency56Is the increased complexity of project planning system the one of the barriers of offsite construction1.39

    Limits changes in onsite work4.77

    Increases safety performance4.77Contractors sectorsInfrastrucureRank

    Reduces project cost4.58Transportation restraints (size constraints, transportation cost, and impact on the building structures) limit the use of offsite construction techniques61

    Increase product quality4.29Offsite construction techniques reduces the overall project schedule61

    Increases overall cost savings410Offsite construction techniques reduces onsite disruption of other adjacent operations5.82

    Project planning system the one of the barriers of offsite construction3.2511Offsite construction techniques reduces negative environmental impact of construction operations5.82

    Offsite construction techniques decreases onsite labour congestion5.53

    Offsite construction techniques increase jobsite management efficiency5.34

    Offsite construction techniques reduces the need for skilled craft workers onsite55

    Offsite construction techniques increases overall labour productivity55

    RankingC4RankOffsite construction techniques increase project design efficiency55

    Reduces duration6.21Offsite construction techniques increases design cost55

    Limits changes in onsite work62Offsite construction techniques increases labour savings55

    Reduces environmental impact of construction operations5.83Offsite construction techniques increase product quality4.86

    Decreases onsite labor congestion5.83Offsite construction techniques reduces the project construction cost4.57

    Increases productivity5.64Offsite construction techniques increases safety performance4.57

    Reduces onsite disruption of other adjacent operations5.64Offsite/construction techniques limits the ability to make change onsite work4.38

    Transportation restraints limit the use of offsite construction techniques5.64Offsite construction techniques limits design options4.38

    Increases project design efficiency5.45Offsite construction techniques increases overall cost savings4.29

    Increases jobsite management efficiency5.45Is the increased complexity of project planning system the one of the barriers of offsite construction3.810

    Increases design cost56Complicated computer software for designing offsite construction techniques limits their uses3.511

    Project planning system the one of the barriers of offsite construction56

    Increase product quality4.87

    Increases safety performance4.87

    Increases overall cost savings4.87

    Reduces workers4.68

    Increases labor savings4.68

    Computer software for designing offsite construction techniques limits their uses4.49

    Reduces project cost3.810

    Limits design options3.411

    RankingC5Rank

    Reduces duration6.31

    Reduces onsite disruption of other adjacent operations6.31

    Increases productivity62

    Reduces environmental impact of construction operations5.63

    Transportation restraints limit the use of offsite construction techniques5.34

    Increases jobsite management efficiency5.34

    Increase product quality55

    Increases project design efficiency55

    Decreases onsite labor congestion55

    Reduces workers4.76

    Increases design cost4.76

    Increases labor savings4.76

    Reduces project cost4.37

    Increases overall cost savings48

    Limits changes in onsite work3.79

    Project planning system the one of the barriers of offsite construction3.79

    Limits design options3.310

    Increases safety performance3.310

    Computer software for designing offsite construction techniques limits their uses2.711

    RankingC6Rank

    Reduces duration6.61

    Reduces workers6.52

    Increases overall cost savings6.52

    Reduces project cost63

    Increases productivity63

    Transportation restraints limit the use of offsite construction techniques63

    Increases labor savings63

    Reduces onsite disruption of other adjacent operations5.54

    Decreases onsite labor congestion5.54

    Increases safety performance55

    Increases project design efficiency55

    Limits changes in onsite work4.56

    Increase product quality4.56

    Reduces environmental impact of construction operations4.56

    Computer software for designing offsite construction techniques limits their uses4.56

    Increases jobsite management efficiency4.56

    Increases design cost47

    Limits design options3.58

    Project planning system the one of the barriers of offsite construction3.58

    RISK IDENTIFICATION Techniques

    GlobalLocal

    Documentation Review19341t-Test: Paired Two Sample for Means

    Brainstorming16716

    Delphi Technique160Variable 1Variable 2

    Interviewing8914Mean72.35714285718.4285714286

    Root Cause Identification9411Variance3535.0164835165118.8791208791

    SWOT Analysis898Observations1414

    Checklist Analysis12812Pearson Correlation0.8910087636

    Assumptions Analysis667Hypothesized Mean Difference0

    Pareto Chart150df13

    Cause And Effect Diagram644t Stat4.7852331763

    System Or Process Flow Chart603P(T

  • */33Case studyIntroduction & Literature ReviewOverall Spearmans ranking correlation factor = 0.947896

    Spearmans ranking correlation of contractor sectors

    Spearmans correlationOffsite construction techniques reduces the overall project schedule0.99993Offsite construction techniques increases overall labour productivity0.99825Offsite construction techniques decreases onsite labour congestion0.99937Offsite/construction techniques limits the ability to make change onsite work0.993684Offsite construction techniques increase jobsite management efficiency0.997883Offsite construction techniques increases overall cost savings0.995521Offsite construction techniques reduces the need for skilled craft workers onsite0.998583Offsite construction techniques reduces onsite disruption of other adjacent operations0.99993Offsite construction techniques reduces negative environmental impact of construction operations0.999843Transportation restraints (size constraints, transportation cost, and impact on the building structures) limit the use of offsite construction techniques0.999983Offsite construction techniques increases labour savings0.99972Is the increased complexity of project planning system the one of the barriers of offsite construction0.989065Complicated computer software for designing offsite construction techniques limits their uses0.993001Offsite construction techniques reduces the project construction cost0.996063Offsite construction techniques increase product quality0.996063Offsite construction techniques increases safety performance0.995521Offsite construction techniques increase project design efficiency0.99888Offsite construction techniques limits design options0.997043Offsite construction techniques increases design cost0.999563

  • */33

    Commercial (R2 =0%)Infrastructure (R2 =14.7%)Industrial (R2 =1.2%)Residential (R2 =20.9%)Case studyIntroduction & Literature ReviewResults of Regression Analysis

    Sector wise linear relationship of contractors and consultants about offsite construction

  • */33

    Case studyIntroduction & Literature Review

    Spearmans ranking correlation between contractors and consultants

    Construction sectorsSpearmans ranking correlation factorResidential0.994454

    Commercial 0.995923Industrial 0.997078Infrastructure0.996676

  • Name of Project = Furniture houseNo of floors = 4 floor (Lower floor + ground floor + 1st floor + 2nd floor)Country = PakistanCity = Multan*Case studyIntroduction & Literature Review

  • Drawings of project:*Case studyIntroduction & Literature Review

  • Cost comparison of onsite traditional construction and offsite traditional construction:Onsite Traditional cost estimateOffsite cost estimate

    *Case studyIntroduction & Literature Review

  • *Case studyIntroduction & Literature Review

  • Schedule comparison of onsite traditional construction and offsite traditional construction:*Case studyIntroduction & Literature Review

  • */33Almost 50% consultants and contractors say that 6 - 20% offsite construction is implemented in Pakistan. The prefabrication and precast construction techniques are commonly used in PakistanPossible benefits of offsite construction as compared to traditional onsite construction are:-

    1)Reduction in project duration2)Reduction in skilled workers demand3)Increase labor productivity4)Increase safety performance5)Reduction in onsite disruption6)Reduction in negative impact of other operations7)Increase product design efficiency8)Increase management efficiency9)Increase overall savings in cost10)Reduction in labor congestion in site11)Less workers are required in site

    Both consultants and contractors agreed that possible challenges of offsite construction as compared to traditional onsite construction are:-

    1)Transportation feasibility 2)Limited options for designBoth consultants and contractors disagreed that

    1)Project planning is barrier for offsite construction2)Computer software for designing is barrier for offsite construction

    Case studyIntroduction & Literature Review

  • */33

    Case studyIntroduction & Literature Review

    Less duration is the single most factor that is driving the use of offsite construction techniques. And second important factor is cost. From case study, it is verified that offsite construction strategy results in duration and cost reduction as compared to onsite traditional construction.

    There is no relationship of consultants and co