Ivat Lab Report. s4g4 (1)

Embed Size (px)

Citation preview

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    1/25

    SEE 4722 (4)

    FACULTY OF ELECTRICAL ENGINEERING

    UNIVERSITI TEKNOLOGI MALAYSIA

    JOHOR BAHRU CAMPUS

    JOHOR

    INSTITUT VOLTAN DAN ARUS TINGGI

    (IVAT)

    TITLE: EFFECT OF CONTAMINATION TO THE

    CAPACITANCE PROPERTIES FOR MEASURING

    BREAKDOWN VOLTAGE OF GLASS INSULATOR

    DSUPERVISOR: DR. ZURAIMY BIN ADZIS

    MEMBERS:

    SYAHEEDULLAH BIN YAHYA (M1)

    THAAHA BIN ABDULLAH (M2)

    NAIMAH BINTI MOHAMAD (M3)

    CONTENT

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    2/25

    1

    ABSTRACT

    1.0 INTRODUCTION

    1.1 Background 1

    1.2

    Objective ...5

    2.0 METHODOLOGY

    2.1 Procedure and equipment ..... 6

    2.1.1 Part 1 : Sample preparation ......6

    2.1.2

    Part 2 : Testing for capacitance, power factor

    (tan), and leakage Current ...8

    2.1.3 Part 3: Testing for breakdown voltage of each sample .13

    3.0 RESULT AND DISCUSSION

    3.1 Measuring Capacitance, Dissipation/Power Factor

    and Leakage Current (Part 2) ..... 16

    3.2

    Testing for breakdown voltage of each sample (Part 3) ......18

    3.3 Test for ESDD (Equivalent Salt Deposit Density) ......19

    4.0 CONCLUSION ....22

    5.0 REFERENCES ....23

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    3/25

    2

    ABSTRACT

    This report is about the experiment on the glass insulator to determine the effect

    of the contamination to the flash over. The experiment was conducted for 2 days in

    Institute of High Voltage and Current. All the procedure is stated in here was conducted

    successfully. All the data collected are also recorded in this report.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    4/25

    3

    INTRODUCTION

    5.1 Background

    5.1.1 Transmission Tower

    Transmission tower is a tall structure, usually a steel lattice tower, used to

    support anoverhead power line.They are used in high-voltage AC and DC systems,

    and come in a wide variety of shapes and sizes. Typical height ranges from 15 to 55

    metres (49 to 180 ft), though the tallest are the 370 m (1,214 ft)

    towers of a 2700-metre-long. In addition to steel, other

    materials may be used, including concrete and wood.

    There are four major categories of transmission

    towers:suspension,terminal,tension,andtransposition.Some

    transmission towers combine these basic functions.

    Transmission towers and their overhead power lines are often

    considered to be a form ofvisual pollution.

    5.1.2 Flash over

    Flash over is the voltage at which an electric discharge occurs between two

    electrodes that are separated by an insulator; the value depends on whether the insulator

    surface is dry or wet. It is also known as sparkover voltage. Sometimes, when a direct

    lightning stroke occur on a tower, the tower has to carry huge impulse currents. If the

    tower footing resistance is considerable, the potential of the tower rises to a large value,

    steeply with respect to the line and consequently a flashover may take place along the

    insulator string. This is known as back flashover.

    http://en.wikipedia.org/wiki/Structurehttp://en.wikipedia.org/wiki/Lattice_towerhttp://en.wikipedia.org/wiki/Overhead_power_linehttp://en.wikipedia.org/wiki/Suspension_towerhttp://en.wikipedia.org/wiki/Dead-end_towerhttp://en.wikipedia.org/wiki/Transposition_towerhttp://en.wikipedia.org/wiki/Visual_pollutionhttp://en.wikipedia.org/wiki/Visual_pollutionhttp://en.wikipedia.org/wiki/Transposition_towerhttp://en.wikipedia.org/wiki/Dead-end_towerhttp://en.wikipedia.org/wiki/Suspension_towerhttp://en.wikipedia.org/wiki/Overhead_power_linehttp://en.wikipedia.org/wiki/Lattice_towerhttp://en.wikipedia.org/wiki/Structure
  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    5/25

    4

    5.1.3 Leakage Current

    Leakage current is the current flow through the protective ground

    conductor to ground. In the absence of a grounding connection, it is current that

    could flow from any conductive part or the surface of non-conductive parts to

    ground if a conductive path was available (such as a human body). There are

    always extraneous current flowing in the safety ground conductor.

    There are 2 types of leakage current; AC and DC. DC leakage current

    usually applies only to end-product equipment, not to power supplies. AC

    leakage current is caused by a parallel combination ofcapacitance and DC

    resistance between a voltage source (AC line) and the grounded conductive

    parts of the equipment. The leakage caused by theDC resistance usually is

    inigsificant compared to the AC impedence of various parallel capacitances.

    5.1.4 Dissipation Factor (tan)

    Dissipation factor (tan )or DF is defined as the ratio of the ESR and

    capacitive reactance. Dissipation factor is also known as the tangent of the loss

    angle and is commonly expressed in percent.

    =

    Equivalent Series Resistance or ESR for short is the sum of the ohmic losses of

    the dielectric, materials and connections used in the construction of the

    capacitor.

    = =

    2

    ESR is normally expressed as a maximum value at specified

    frequencies, 120 Hz and 100kHz for aluminum electrolytic and tantalum

    capacitors and 100kHz for film capacitors. Impedance is the total resistance the

    capacitor represents to alternating waveforms. This includes the inductive and

    resistive components.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    6/25

    5

    = + ( + )

    The equivalent circuit is shown below;

    Below is a graphical illustration of how the above parameters change

    with frequency.

    An important observation is the Fr parameter. Fr is the self-resonant

    frequency. Defined as the frequency where Xl and Xc are equal.

    =1

    2

    At this frequency the impedance is equal to the ESR. Below self-

    resonance the Xc component is dominant and the capacitor behaves like a

    capacitor. Above the self-resonant frequency the inductive component is

    dominant and the capacitor behaves more like an inductor.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    7/25

    6

    5.1.5 ESDD

    Equivalent Salt Deposit Density (ESDD) is used to measure the

    pollution based on average density of soluble salt. The amount of salt will affect

    the conductivity resulting from the solution of polluted deposits gathered at the

    surface of the insulator.

    =(5.7 [1 ( 2 0)])/3

    Where,

    = solution temperature, C

    = volume conductivity at temperature C, S/m

    V = volume of the water, cm3

    A = area of the cleaned surface, cm2

    b = factor depending on the temperature

    5.2 Objective

    1. To study dielectric properties of insulator

    2. To identify causes o flashover occurring at insulator

    3. To measure leakage current and calculate value of ESDD that influence

    insulation performance

    4. To study the effect of contamination saturation towards insulation

    properties.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    8/25

    7

    METHODOLOGY

    2.1 Procedure and Equipment

    This section describe the procedure and the step taken to set up the experiment.

    In order to achieve the objective of the experiment, there are three test being conducted

    using four glass insulator samples with different amount of contaminant. First test

    conducted to get leakage current, power factor, and capacitance for each contaminant

    .Second experiment was to get the breakdown voltage value for each contaminantdensity, and the third experiment was to test the ESDD of each samples after undergone

    the first and second test. The glass insulator used, represent the insulating material in

    high voltage transmission. The experiment conducted in a closed room under the

    technician supervision and all safety precaution was taken into serious action.

    2.1.1 Part 1: Sample preparation

    Equipment:

    Four insulating glass

    Salt

    Weight scale

    Distilled water

    Procedure:

    1. Glass insulator are washed using tap water to remove impurities

    2. Glass insulator was classified into four sample which are A(no

    contamination),B(small),C (medium) and D(high)

    3. Sample A was dipped into 5 litre of distilled water with 0g salt

    4.

    Sample B was dipped into 5 litre of distilled water with 110g of salt.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    9/25

    8

    5. Sample C was dipped into 5 litre of distilled water with 220g of salt

    6. Sample D was dipped into 5 litre of distilled water with 330g of salt

    7.

    All sample were kept in a room until it completely dry.

    Figure 3.1 Preparing contamination to the insulator

    Figure 3.2 Insulator dried

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    10/25

    9

    Part 2:Measuring Capacitance, Dissipation/Power Factor and Leakage Current

    1) The sample A to be testes ware connected to the high voltage and ground.

    Fig 1: connect the insulator to the PDF test Set (Bridge)

    2) Switch of the Measuring Bridge INST.PWR.SUPPLY and INST.CONTROL is turned ON.

    Fig 2: Switch of the INST.PWR.SUPPLY and INST.CONTROL

    PinHigh Voltage

    Connection

    CapGround

    Connection

    Power Button

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    11/25

    10

    3) The operating cycle and the injection voltage (5kV) were set

    Fig 3: Step to set up the setting

    4) The temperature also need to be set up and updated if the temperature changes.

    Fig 4: Room temperature

    1. Test Mode

    2. UST A/

    UST B 3. IdentityInput

    6. Run5. Enter

    4. Fill the

    number

    Temperature

    25

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    12/25

    11

    Fig 5: Step to set up the temperature

    5) The safety button is pushed before turning ON the High Voltage source and always

    being pushed throughout the experiment.

    Fig 6: The safety button was kept pressed throughout the voltage injection

    2. Fill in the

    temperature

    1. PF/tan

    2. Enter

    Safety

    Button

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    13/25

    12

    6) The test voltage is increased until 5kV.

    Fig 7: the test voltage is increased slowly until reach 5kV

    7) The RUN button is pushed to inject the high voltage.

    Fig 8: Run button

    Test

    Voltage

    6. Run

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    14/25

    13

    8) The readings are taken when the counter finished the counts until 10.

    Fig 9: The reading were taken after the counter counted until 10

    9)

    After all readings have been taken, the test voltage is decreased until reach zero.

    10)

    The INST.CONTROLis pushed to turn off. Then, the safety button is released.

    11)After ensuring that no high voltage source is being injected, the high voltage

    connection is discharged by using a discharger rod before the sample were replaced.

    Fig 10: Discharger rod discharged the high voltage

    CapacitanceDissipation/

    Power FactorTest

    Voltage

    CounterLeakage

    Current

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    15/25

    14

    12)The connections on the insulator are disconnected.

    13)Step 3 until step 12 is repeated for other samples, insulator B, insulator C and

    insulator D.

    14)After finishing the experiment, the switch of the machine is turned OFF.

    Part 3: Testing for breakdown voltage of each sample

    1) The circuit to be used has been set up by the technicians.

    Fig 11: Circuit to be used for breakdown test

    2) The sample was connected to high voltage and ground source

    Fig 12: Sample was connect to high voltage and ground source

    Tools used for insulation

    outboardTransformer

    Capacitor

    Cap Ground

    connection

    Pin High Voltage

    connection

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    16/25

    15

    3) The machine is turn ON and the high voltage were inject, the sequence is follow.

    Fig 13: Digital Measuring Instrument DMI 551 used to measure the voltage

    breakdown

    1 SE

    2 SI

    3 SB1

    4 SB2

    5

    SB3

    6 S/UP

    7 S/DOWN

    Sequence to increase voltage : 1 2 3 4 6

    Sequence to decrease voltage : 6 5 2 1

    1

    2

    3

    4 56 7

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    17/25

    16

    4) The voltage is increased until flashover occur on the insulator.

    Fig 14: Flashover occur

    5)

    After the flashover occur, the voltage is decreased immediately until reach zero volt.

    6) The value of voltage during the flashover occur were record.

    7) After ensuring that no high voltage source is being injected, the high voltage

    connection is discharged by using a discharger rod before the sample were replaced.

    Fig 15: Discharger rod discharged the high voltage

    8)

    The connections on the insulator are disconnected.

    9) Step 2 until step 8 is repeated for other samples, insulator B, insulator C and

    insulator D.

    10)

    After the experiment finished, the machine is turned OFF.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    18/25

    17

    RESULT AND DISCUSSION

    3.1Measuring Capacitance, Dissipation/Power Factor and Leakage

    Current (Part 2)

    Dissipation Power Factor

    Insulator

    Contamination

    Clean Light Medium High

    * Dissipation

    Factor, tan

    0.0459(2.6) 0.272(15.22) 0.348(19.19) 0.420(22.78)

    * Power Factor 0.0461(87.36) 0.261(74.87) 0.327(70.91) 0.390(67.05)

    * Capacitance,

    pF

    48.78

    54.92

    55.57

    59.51

    * Leakage

    Current, mA

    0.076mA 0.086mA 0.087mA 0.093mA

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    19/25

    18

    Fig 16: Relationship between Leakage Current and Dissipation Factor

    From the relationship, it is shown that the higher the dissipation factor which is

    the higher leakage current in the insulator. That will causes flashover occur faster.

    0

    0.01

    0.02

    0.03

    0.04

    0.05

    0.06

    0.07

    0.080.09

    0.1

    0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45

    leakagecurrent,mA

    dissipation factor

    Relationship Between Leakage Current and

    Dissipation Factor

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    20/25

    19

    3.2Testing for breakdown voltage of each sample (Part 3)

    Breakdown Voltage:

    Condition Clean Light Medium High

    test 1 2 1 2 1 2 1 2

    *Breakdown 67.61kV 68.57kV 63.47kV 65.22kV 62.65kV 63.88kV 58.43kV 59.07kV

    Fig 17: Relationship between Breakdown Voltage and Dissipation Factor

    From the relationship, it is shown that the higher the losses in the insulator

    which is the higher the dissipation factor, the lower the breakdown voltage value.

    Breakdown will occur in shorter period for those with higher dissipation factor than

    that with lower dissipation factor. Due to flashover occur at test 1, the contamination

    were reduced. And there is a difference between test 1 and test 2. Are available for test

    2 breakdown voltage is higher than test 1.

    56

    58

    60

    62

    64

    66

    68

    70

    0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45

    BREAKDOWNVOLTAGE,

    kV

    DISSIPATION FACTOR

    Relationship Between Breakdown Voltage and

    Dissipation Factor

    test 1 test 2

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    21/25

    20

    3.3Test for ESDD (Equivalent Salt Deposit Density)

    Equipment:

    Sample A,B,C and D

    ESDD tester

    600 ml distilled water

    Pail

    Procedure:

    1. Each sample are washed with 600ml of distilled water and being pour into a pail

    2.

    Conductivity of contaminated sample was measured in room temperature.

    3. Result was recorded in table 3.3

    Result and Discussion:

    In order to get the value of ESDD, first we have to get the value of resistivity (),

    from the equation of:

    =

    = resistivity

    = resistance

    (Area of insulator) = 510.7052 cm2

    (Length of the test cell) =80.1106 cm

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    22/25

    21

    Therefore, we can get the value of ESDD from equation:

    =

    _.43

    65650 /.

    (Area of testing insulator)

    SAMPLE ADMITANCE(s) Resistivity () ESDD ( mg/cm2)

    A 107 9345.79 0.012B 359 2785.52 0.041

    C 590 1694.92 0.068

    D 756 1322.75 0.088

    Table 3.3

    Table 3.3 above shows the value of ESDD as compared to each sample with

    different level of contaminant. The value of ESDD increased as the number ofcontaminant is higher and the value varies between the range of 0.012 mg/cm2 and

    0.088 mg/cm2.

    As the objective of the experiment was to study the effect of contaminant

    saturation towards insulation properties, the graph of ESDD versus capacitance was

    plotted as shown in figure 3.2 below.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    23/25

    22

    Figure 3.4 Relationship between ESDD and capacitance

    From the graph, the result clearly shows that the value of capacitance increase

    as the number of ESDD increased. The capacitance value of the sample become

    bigger as the existence of contaminant is more.

    0

    0.01

    0.02

    0.03

    0.04

    0.05

    0.06

    0.07

    0.08

    0.09

    0.1

    48 50 52 54 56 58 60

    ESDD(mg/cm2)

    Capacitance (F)

    Relationship Between ESDD and capacitance

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    24/25

    23

    CONCLUSION

    In this experiment it is clearly shown that the contamination on the glass

    insulator did effect the flash over voltage. The lower the contamination, the higher the

    breakdown voltage. The dissipation factor are also effecting the efficiency of the

    insulator. The higher the dissipation factor, the higher the leakage current. But, the

    breakdown voltage will be lower. We cant avoid the contamination to be occurred

    since its caused by nature, but we can actually have another alternative such as clean

    the insulator especially at the sea area frequently which contain high contamination. An

    automatic or controlled cleaner can be invented. Or we can also produce a better

    insulator that can withstand a higher voltage such as ceramic insulator.

  • 8/11/2019 Ivat Lab Report. s4g4 (1)

    25/25

    REFERENCES

    http://composite.about.com/library/glossary/d/bldef-d1727.htm

    http://en.wikipedia.org/wiki/Breakdown_voltage

    http://scienceworld.wolfram.com/physics/Capacitance.html

    http://www.princeton.edu/~achaney/tmve/wiki100k/docs/Transmission_line.html

    http://www.thefreedictionary.com/flashover

    http://www.wima.com/EN/dissipation.htm

    http://www.wowhead.com/spell=137596/capacitance

    http://composite.about.com/library/glossary/d/bldef-d1727.htmhttp://composite.about.com/library/glossary/d/bldef-d1727.htmhttp://en.wikipedia.org/wiki/Breakdown_voltagehttp://en.wikipedia.org/wiki/Breakdown_voltagehttp://scienceworld.wolfram.com/physics/Capacitance.htmlhttp://scienceworld.wolfram.com/physics/Capacitance.htmlhttp://www.princeton.edu/~achaney/tmve/wiki100k/docs/Transmission_line.htmlhttp://www.princeton.edu/~achaney/tmve/wiki100k/docs/Transmission_line.htmlhttp://www.thefreedictionary.com/flashoverhttp://www.thefreedictionary.com/flashoverhttp://www.wima.com/EN/dissipation.htmhttp://www.wima.com/EN/dissipation.htmhttp://www.wowhead.com/spell=137596/capacitancehttp://www.wowhead.com/spell=137596/capacitancehttp://www.wowhead.com/spell=137596/capacitancehttp://www.wima.com/EN/dissipation.htmhttp://www.thefreedictionary.com/flashoverhttp://www.princeton.edu/~achaney/tmve/wiki100k/docs/Transmission_line.htmlhttp://scienceworld.wolfram.com/physics/Capacitance.htmlhttp://en.wikipedia.org/wiki/Breakdown_voltagehttp://composite.about.com/library/glossary/d/bldef-d1727.htm